22. Revised Bid Schedule AMD 0001.pdf
PDF 258 KB Posted
- Attached to
- Boysen Peak Generator Site & Cody Office Remodel
- Solicitation number
- 89503222BWA000053_AMD0001
About this file
This bid schedule document outlines pricing requirements for two federal construction projects under Solicitation Number 89503222BWA000053_AMD0001. The projects include overhauling the generator site at Boysen Peak and remodeling the office at the Cody Service Center for the Department of Energy Western Area Power Administration. Contractors must provide lump sum pricing for mobilization, site work, utilities, concrete, doors and frames, mechanical, electrical, painting, and other work items for each project. The bid schedule also includes abbreviations for common measurement units. Pricing is to be submitted using this form to allow for ease of tabulation and evaluation by the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN Work or Material Quantity Unit Unit Price Amount
LS $
LS $
LS $
LS $
LS $
LS $
LS $
LS $
LS $
LS $
0001 Mobilization & Preparatory Work (Not to exceed 5% of SUBTOTAL. See Section H.)
0002 Demolition
0003 Sitework
0004 Site Utilities
0005 Precast Concrete
0006 Thermal Protection
0007 Steel Doors and Frames
0008 Mechanical
0009 Electrical
0010 Paint
0011 Grounding System LS $
TOTAL $
ABBREVIATIONS
CLIN = Contract Line Item Number
CY = cubic yards EA = each LF = linear feet LS = for the lump sum of LB = pounds
SECTION B
SUPPLIES OR SERVICES AND PRICES
BIDDING SCHEDULE
BOYSEN PEAK ACDC OVERHAUL
siltman Highlight
CLIN Work or Material Quantity Unit Unit Price Amount
LS $
LS $
LS $
LS $
LS $
LS $
0001 Mobilization & Preparatory Work (Not to exceed 5% of SUBTOTAL. See Section H.)
0002 Thermal Protection
0003 Metals
0004 Steel Door and Frames
0005 Finishes
0006 Electrical
0007 Painting LS $
SUBTOTAL $
ABBREVIATIONS
CLIN = Contract Line Item Number
CY = cubic yards EA = each LF = linear feet LS = for the lump sum of LB = pounds
SECTION B
SUPPLIES OR SERVICES AND PRICES
BIDDING SCHEDULE
CODY SERVICE CENTER OFFICE REMODEL
siltman Highlight
SECTION B
SUPPLIES OR SERVICES AND PRICES
BIDDING SCHEDULE
BOYSEN PEAK ACDC OVERHAUL CODY
SERVICE CENTER OFFICE REMODEL
Substation Unit Amount
SUBTOTAL $
SUBTOTAL$
TOTAL $
BOYSEN PEAK ACDC OVERHAUL
CODY SERVICE CENTER OFFICE REMODEL
ABBREVIATIONS
CLIN = Contract Line Item Number
CY = cubic yards EA = eachh L = linear feet LS = for the lump sum of LB = pounds
| BPK_BPK ACDC OVERHAUL_BID SCHEDULE.pdf |
| Bid Schedule |
File details come from the government source that posted it. Updated .