22. Revised Bid Schedule AMD 0001.pdf

PDF 372 KB Posted

Attached to
Hoyt and Kiowa Creek 115-kV Breaker Replacement
Solicitation number
89503222BWA000050_AMD0001
Issued by

About this file

This document contains a bid schedule for a federal contract opportunity to replace 115-kV breakers at two substations. The bid schedule lays out contract line items for mobilization, site work, demolition, foundations, steel structures, circuit breakers, electrical equipment, cables, and installation. Quantities and units are provided for estimated work. The contract is to replace breakers at the Hoyt Substation and Kiowa Creek Switching Station for the Department of Energy Western Area Power Administration under solicitation number 89503222BWA000050_AMD0001. Pricing will be evaluated based on the amounts entered into the bid schedule for each contract line item at each substation and an overall total price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION B

SUPPLIES OR SERVICES AND PRICES

BIDDING SCHEDULE

HOYT SUBSTATION 115KV BREAKER REPLACEMENT

CLIN Work or Material Estimated Quantity Unit Unit Price Amount

0001 Mobilization and preparatory work (Not to exceed 5% of TOTAL. See Section H.)

LS $

0002 Miscellaneous sitework LS $

0003 Demolition LS $

0004 Concrete foundations 13.6 CY $ $

0005 Steel structures, welded (galvanized) 3340 LBS. $ $

0006 Power circuit breaker, 115-kV, 3,000 amps (Gov't furnished)

4 EA. $ $

0007 Associated electrical equipment and material LS $

0008 Existing outdoor electrical equipment and material

LS $

0009 Furnishing 5/c No. 10 AWG control cable 5,000 LF $ $

0010 Installing 5/c No. 10 AWG control cable 5,000 LF $ $

0011 Furnishing 12/c No. 10 AWG control cable 2,500 LF $ $

0012 Installing 12/c No. 10 AWG control cable 2,500 LF $ $

SUBTOTAL $

ABBREVIATIONS

CLIN = Contract Line Item Number yards CY = cubic EA = each LBS = pounds LF = linear feet LS = lump sum siltman Highlight

BIDDING SCHEDULE

KIOWA CREEK SWITCHING STATION 115KV BREAKER REPLACEMENT

CLIN Work or Material Estimated Quantity Unit Unit Price Amount

0001 Mobilization and preparatory work (Not to exceed 5% of TOTAL. See Section H.)

LS $

0002 Miscellaneous sitework LS $

0003 Demolition LS $

0004 Concrete foundations 13.6 CY $ $

0005 Steel structures, welded (galvanized) 3340 LBS. $ $

0006 Power circuit breaker, 115-kV, 3,000 amps (Gov't furnished)

4 EA. $ $

0007 Associated electrical equipment and material LS $

0008 Existing outdoor electrical equipment and material

LS $

0009 Furnishing 5/c No. 10 AWG control cable 5,200 LF $ $

0010 Installing 5/c No. 10 AWG control cable 5,200 LF $ $

0011 Furnishing 12/c No. 10 AWG control cable 2,600 LF $ $

0012 Installing 12/c No. 10 AWG control cable 2,600 LF $ $

SUBTOTAL $

ABBREVIATIONS

CLIN = Contract Line Item Number yards CY = cubic EA = each LBS = pounds LF = linear feet LS = lump sum siltman Highlight

BIDDING SCHEDULE

HOYT SUBSTATION KIOWA CREEK SWITCHING

STATION 115-kV BREAKER REPLACEMENT

Substation Unit Amount

SUBTOTAL $ _

SUBTOTAL$ _

TOTAL $ _

Hoyt Substation 115kV Breaker Replacement

Kiowa Creek Switching Substation 115kV Breaker Replacement

ABBREVIATIONS

CLIN = Contract Line Item Number CY = cubic yards EA = each LBS = pounds LF = linear feet LS = lump sum

HT_BkrRplcmnt_2022_SubBiddingSchedule 07.26.22.pdf
Bid Schedule
KIC_BkrRplcmnt_2022_SubBiddingSchedule 07.26.22.pdf
Bid Schedule

File details come from the government source that posted it. Updated .