22 - Atch D - Submittal Log.pdf

PDF 132 KB Posted

Attached to
Pinnacle Peak Substation – Series Capacitor Breaker Replacement
Solicitation number
89503121BWA000032
Issued by

About this file

This submittal log and federal contract opportunity document outline requirements for a series capacitor breaker replacement project at the Pinnacle Peak Substation. The project involves installing new 345-kV circuit breakers, modifying electrical equipment foundations, providing galvanized steel structures, and relocating circuit breaker cables. The estimated value is between $500,000 and $800,000. The performance location is in Maricopa County, Arizona. As a 100% small business set-aside, the NAICS code is 237130 with a size standard of $36.5 million. The solicitation was issued by the Department of Energy Western Area Power Administration. The submittal log specifies over 200 items required prior to or during contract performance relating to schedules, safety plans, material testing, drawings, reports and records.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Included Contract Title: Pinnacle Peak Series Capacitor Breaker Replacement Award Date: Not included Contract No.: NTP:

Contractor: Completion Date:

Western Location Location Submittal In In

# Standards Project Specifications

STANDARD 1 STANDARD 1

1 Construction Schedule 1.1.4.1. (see project spec)

6 Breakdown of Contract Prices 1.1.6.1. NLT 30 days after NTP

10 Safety and Health Program 1.4.1.5.

NLT 10 days prior to start of construction

11 Copies of Certifications, Test Records & Technical Data 1.4.1.10. Prior to use

16 Material Safety Data Sheets 1.4.1.10.(5) Prior to use

21 Assurance of Competency in Equipment Operation 1.4.3.4. Prior to use

22 Respiratory Protection Program 1.4.4.8 Prior to work requiring resp.

protection

STANDARD 2 STANDARD 2

32 Earth Material Testing Laboratory 2.1.1.2.(1) & 2.7.1.2.(1) 20 days prior to compacting

33 Earth Material Compaction Test Reports 2.1.1.2.(2)& 2.7.1. Immed. after test complete

35 Gravel Surfacing Material Gradation 2.1.1.4 Prior to placing

36 Gravel Surfacing Density & Compaction Test Results 2.1.1.4 NLT 7 days after test complete

46 Aggregate for Paving Courses 2.1.1.7.(4) NLT 20 days prior to paving

47 Gravel Base Certification 2.1.1.7.(5) NLT 20 days prior to paving

48 Batch Certification 2.1.1.7.(6) NLT 20 days prior to paving

49 Earth Backfill Material 2.3.1.3. & 2.8.1.2.(1) Prior to refill

STANDARD 3 STANDARD 3

51 Concrete Testing Laboratory 3.1.1.2.(1) & 3.1.1.3.

NLT 20 days prior to concrete placement

52 Concrete Mix Design 3.1.1.2.(2) & 3.1.1.5. NLT 10 days prior to use

53 Fly Ash For Concrete 3.1.1.2.(5) & 3.1.1.4. NLT 20 days prior to use

54 Admixtures and Curing Compound 3.1.1.2.(6) & 3.1.1.4. NLT 10 days prior to use

55 Batch Certificates 3.1.1.2.(7) Provide at delivery

STANDARD 4 STANDARD 4 Included

63 Approval Drawings For Steel Structures & Steel Modifications 4.1.1.2. Prior to fabrication

64 Approval Drawings & Data For Oil Storage Tanks 4.1.1.3. Prior to fabrication

65 Final Drawings For Steel Structures & Oil Storage Tanks 4.1.1.4. Prior to material shipment

66 Weld Procedures 4.1.1.5.(1) & 4.1.7.4. Prior to fabrication

67 Partial Penetration Weld - Test & Evaluation Procedure 4.1.1.5.(2) & 4.1.7.4. Prior to fabrication

68 Nondestructive & Metallographic Test Reports 4.1.1.5.(3) & 4.1.7.4. NLT 20 days after test

69 Connection Bolts 4.1.1.6. Prior to fabrication

70 Mill Test Reports 4.1.1.7. Prior to fabrication

71 Dulling Surface Treatment For Galvanizing 4.1.1.8. Prior to use

72 Tower Test Procedures 4.1.1.9.(1) Prior to testing

73 Calibration of Load Testing Devices 4.1.1.9.(2) NLT 5 days prior to testing

74 Tower Test Report 4.1.1.9.(3) NLT 4 weeks after testing

75 Certified Mill Test Reports 4.1.5.3. Prior to shipping material

76 Magnetic Particle and Dye Penetrant Weld Test (if required by COR) 4.1.7.5. Upon test completion

77 Master List of Bundles - Steel Structure & Tower Material 4.1.13 Upon completion of material bundling

STANDARD 9 STANDARD 9 Included

115 Contractor On-site Test Personnel 9.1.2.2.(2) Prior to working on-site

116 Electrical Test Reports & Documents 9.1.2.2.(3) NLT 7 days after testing

117 Continuity & Megohmmeter Testing Personnel 9.1.2.2.(7) Prior to testing

118 Infrared Inspection Tape 9.1.2.2.(15) NLT 48 hours after testing

119 Equipment Installation Drawings Including Seismic Qualification Report Table 9-1 & 9.1.3.2. NLT 60 days after NTP

120 Equipment Informational Drawings & Data Table 9-1 & 9.1.3.3. NLT 60 days after NTP

121 Equipment Final Drawings Table 9-1 & 9.1.3.4.(1) NLT 21 days prior to equip.

installation

122 Equipment Parts Identification Lists & Bills of Materials Table 9-1 & 9.1.3.4.(2) NLT 21 days prior to equip.

installation

Included or not included (Dropdowns)

SUBMITTAL LOG

*Submittal required if item is used in the performance of the contract.

"T"= Submit transmittal sheet only.

"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable

Submittal Item Date Due

Included Contract Title: Pinnacle Peak Series Capacitor Breaker Replacement Award Date: Not included

SUBMITTAL LOG

*Submittal required if item is used in the performance of the contract.

"T"= Submit transmittal sheet only.

"NLT"= No Later Than "NTP"= Notice To Proceed "ASAP"= As Soon As Practicable

123 Manufacturer's Operation & Maintenance Instructions Table 9-1 & 9.1.3.4.(3) NLT 21 days prior to equip.

installation

124 Equipment & Oil Test Reports Table 9-1 & 9.1.3.5. Prior to shipping equipment

125 Equipment Insulating Liquid PCB Certification Table 9-1 & 9.1.3.6. Prior to delivery of oil or equip.

126 Insulated Conductor Data Table 9-1 & 9.1.3.7. NLT 60 days after NTP

127 Revised Wiring Diagrams Table 9-1 & 9.1.3.9.

NLT 60 days after receipt of drawings

128 Contractor's As-Built Equipment Drawings Table 9-1 & 9.1.3.10.(1) NLT 60 days after equip.

checkout

129 As-built Western Drawings Table 9-1 & 9.1.3.10.(2) NLT 60 days after equip.

checkout

130 Test Reports For Ground Tests 9.2.1.3.

NLT 15 days after completion of testing

STANDARD 12 STANDARD 12

178 Manufacturer's Data 12.1.1.2.

STANDARD 13 STANDARD 13 Included 179 Recycled Materials Quantity Report 13.2.1. & 13.7.2.

180 Products Containing Recovered Materials Report 13.2.2. & 13.8.3.

182 Spill Prevention Notification & Cleanup Plan 13.2.5. & 13.11.2.

188 Water Pollution Permits 13.2.12. & 13.17.2.

STANDARD 15 STANDARD 15

193 As-Built Drawings 15.2.6.

CUSTOM ENTRIES BELOW

Submittal List