21128.10_Attachment 5 - Construction Spec.pdf

PDF 637 KB Posted

Attached to
OceanSpray Project
Solicitation number
BD-21-1296-02346-MGED1-69671
Issued by
Plymouth County, Massachusetts

About this file

This document is a Construction Specification for the Ocean Spray project in Middleborough, Massachusetts. Cornerstone Energy Services, Inc. has been retained by Middleborough Gas and Electric (MGED) to perform engineering services and oversee the fabrication and installation of additional overpressure and backflow protection to the existing MGED meter assembly located within the Ocean Spray campus. The work will conform to applicable federal and state pipeline safety regulations. The contractor must be qualified to perform the covered tasks, minimize damage to surrounding infrastructure, and properly dispose of all debris and excess materials.

The specification outlines detailed requirements for materials, installation, concrete work, pipe welding, coating, pressure testing, and bolting procedures. It includes specific torque tables and values for various pipe sizes and flange classes. The contractor will be responsible for providing concrete testing, welding inspection, and a final report with torque values. The project appears to be funded by MGED, but the document does not mention pricing, set asides, incumbents, or funding sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION

SPECIFICATION

Page: 1 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

Revision (By): A (RRG) Date: 12/16/21

Cornerstone Energy Services: Company Specifications - Construction Specification (CS)

Successful projects start with the Cornerstone

1. SCOPE/GENERAL

This document outlines methods and procedures for the fabrication and installation of additional overpressure and backflow protection to the existing Middleborough Gas and Electric (MGED) meter assembly located within the Ocean Spray campus at 152 Bridge St., Middleborough, MA.

Cornerstone Energy Services, Inc. (Cornerstone) has been retained by MGED to perform Owner’s engineering services.

All procedures will conform to CFR 49 Part 192 and Massachusetts Natural Gas Pipeline Safety Code 220 CMR 101.00, where applicable.

All materials used must be identical to that listed on the bill of materials as supplied unless prior written approval has been received from Cornerstone.

2. SPECIFICATION COMPLIANCE

The equipment shall comply with any drawings, data sheets, standards, codes and specifications incorporated by the Standards listed in Section 1. Any applicable national, state, or local codes or regulations shall be considered as part of this specification.

3. CONTRACTOR

The contractor shall ensure that all rules and regulations applicable are met. This includes, but is not limited to, Federal, State and Local rules/regulations.

Contractor will conduct work as to minimize damage to any of the following: sidewalks, roadways, underground utilities and structures.

Contractor shall remove all excess material and debris in a timely manner at his/her expense.

At all times during the work, Contractor shall keep, or cause to be kept, the premises clean and orderly and free from accumulation of waste material or rubbish created in the work. Upon completion of the work, Contractor shall repair all damage caused by equipment and leave the project free of rubbish or excess materials of any kind.

The Contractor shall be solely and directly responsible to the Owner and owners of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of any injuries or damage which may result from the construction operations under this Contract.

Prior to commencing work, Contractor shall be responsible for enacting the appropriate “one‐ call” system in order to acquire locates of existing utilities within, or adjacent to, all pipeline alignment(s).

Operator qualifications requirements as defined in the Scope of Work shall be strictly adhered to.

4. RESPONSIBILITY FOR MATERIAL

Contractor shall ensure all materials are transported, loaded/unloaded and stored in such a manner as to protect the integrity of the materials. Any materials damaged or suspect of damage will be replaced with new.

Contractor shall verify compliance with the provided Bill of Material. Any discrepancies shall be brought to the attention of MGED and Cornerstone.

Page: 2 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

The Contractor shall inspect all products or equipment delivered to the site prior to their unloading and shall reject all products or equipment that are damaged, used, or in any other way unsatisfactory for use on project.

Pipe Storage and Handling

i. All pipe, tubing and fittings will be kept clean and stored in original packaging until ready for use.

ii. Store products or equipment off ground and protected from weather. Handle products or equipment in accord with manufacturer's recommendations and instructions.

iii. While storing, take care to avoid creating a humidity chamber by venting the area.

iv. Store products or equipment in location to avoid physical damage to items while in storage, and to facilitate prompt inspection.

v. Delicate instruments and materials subject to vandalism shall be placed under locked cover, and if necessary, provided with temperature control as recommended by manufacturer.

All hazardous and/or toxic materials shall be stored in conformance with Federal, State and local regulations.

5. OPERATOR QUALIFICATIONS

Any contractor performing a covered task as indicated in the attached Covered Task List must be qualified in accordance with Northeast Gas Association (NGA) and within the stated expiration window.

6. INSTALLATION

During the progress of construction, it is expected that minor relocations of the work will be necessary. Such relocations shall be made only by direction of the Owner. If existing structures are encountered that prevent the construction, and that are not properly shown on the Drawings (if applicable), Contractor shall notify the Owner’s Engineer or on‐site representative before continuing with the construction in order that the Owner may make such field revision as necessary to avoid conflict with the existing structures. If the Contractor shall fail to so notify the Owner’s Engineer or on‐site representative when an existing structure is encountered, and shall proceed with the construction despite the interference, he shall do so at his own risk.

7. EXCAVATION PREPARATION

Contractor shall notify applicable One Call Systems or governing authorities, and any other private companies or municipalities having utilities in the vicinity of construction prior to the commencement of any activities in the work area, including hand excavation to verify top-of-utility elevations.

Copies of all applicable permits are to be kept at the trenching and excavating sites during these activities.

Excavation must be performed using hydro-vac methods in the area of the meter assembly.

8. BACKFILL

Section deleted. Not applicable.

Page: 3 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

9. PLAIN AND REINFORCED CONCRETE

Prior to placing concrete, the Contractor shall provide the Company with concrete mix design(s).

Codes and Standards: All activities related to concrete proportioning, mixing, placing, testing and curing shall comply with the latest edition of the codes and standards outlined below, as appropriate:

i. American Concrete Institute (ACI)

ii. ACI SP-066 ACI Detailing Manual

iii. ACI 117 Tolerances for Concrete Construction and Materials

iv. ACI 211.1 Selecting Proportions for Normal, Heavyweight, and Mass Concrete

v. ACI 211.2 Selecting Proportions for Structural Lightweight Concrete

vi. ACI 301 Structural Concrete

vii. ACI 302.1R Concrete Floor and Slab Construction

viii. ACI 304R Measuring, Mixing, Transporting, and Placing Concrete

ix. ACI 304.2R Placing Concrete by Pumping Methods

x. ACI 305R Hot Weather Concreting

xi. ACI 306R Cold Weather Concreting

xii. ACI 306.1 Cold Weather Concreting

xiii. ACI 308 Curing Concrete

xiv. ACI 318 Building Code Requirements for Reinforced Concrete

xv. ACI 347R Formwork for Concrete

xvi. ACI 504R Joint Sealants for Concrete Structures

xvii. American Society for Testing and Materials (ASTM)

xviii. ASTM A185 Standard Specification for Steel Welded Wire Fabric, Plain, for Concrete Reinforcement

xix. ASTM A615/A615M Standard Specification for Deformed and Plain Billet-Steel Bars for Concrete Reinforcement

xx. ASTM C33 Standard Specification for Concrete Aggregates

xxi. ASTM C39 Standard Test Method for Compressive Strength of Cylindrical Concrete

Specimens

xxii. ASTM C494 Standard Admixtures for Concrete

xxiii. ASTM C94/C94M Standard Specification for Ready Mixed Concrete

xxiv. ASTM C150 Standard Specification for Portland Cement

xxv. ASTM C618 Standard Specification for Fly Ash/Natural Pozzolan

xxvi. ASTM C4832 Standard Test Method for preparation and testing of controlled low strength material (CLSM) Test Cylinders

xxvii. ASTM D1557 Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort xxviii. National Ready Mixed Concrete Association (NRMCA)

xxix. Checklist for Ready Mixed Concrete Production Facilities, Sixth Edition

xxx. The concrete production facilities shall be currently certified by the National Ready

Mixed Concrete Association, and Contractors, if requested by the Company, shall submit a copy of that certificate to the Company Representative prior to the start of concrete work. The Company reserves the right to inspect and approve or reject the batch plant.

Page: 4 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

10. FORMWORK

Formwork shall be compliant with ACI 347R and ACI 117.

Exposed corners shall have 45-degree, ¾ in. (19 mm) chamfers.

Sonotube concrete tube forms or compatible shall be utilized. Contractor to follow manufacturer installation instructions.

11. REINFORCING STEEL AND EMBEDMENTS

Reinforcing bars shall conform to ASTM A615/A615M Grade 60 unless noted otherwise in the Contract Documents.

Welded wire fabric shall conform to ASTM A185.

Tie wire shall be 16 gauge or heavier.

Reinforcement placing and bending detail drawings shall be prepared in accordance with ACI SP-

066.

Crossing bars shall not be welded.

Direct embedment (precast) of piping support into concrete pillars is utilized as defined in the foundation drawings. There are no anchor bolts.

12. CONCRETE MATERIALS

Portland cement shall conform to ASTM C150 Type I, unless otherwise specified in the Contract Documents.

Fly ash used in accordance with ACI 301 shall conform to ASTM C618, Class F.

Mixing water and water used to make ice shall be potable or otherwise tested for suitability in accordance with ASTM C94/C94M.

Aggregate shall conform to ASTM C33 and shall be obtained from a single source.

13. PLACING CONCRETE

Concrete shall not be placed during rain or reasonable threat of rain unless provisions have been made to tent or cover the formwork and prevent stormwater runoff from entering the excavation.

The Contractor shall provide a copy of all concrete delivery tickets to the Company.

Concrete that has achieved initial set or has been contaminated by foreign matter shall not be utilized.

Concrete shall not be retempered and water shall not be added after the concrete is first mixed on site.

The addition of ice at the construction site shall only occur if it is included in the mix design. The concrete manufacturer shall provide written instructions on the required amount of ice and the mixing procedure as part of the concrete mix design.

Before any concrete is placed, all ice, snow, mud, and frost shall be completely removed, and the temperature of all surfaces that the concrete shall be raised above the freezing point. Concrete shall not be placed on frozen subgrade or on a surface that contains frozen materials

Prior to placing concrete, the sub-base material shall be mechanically compacted adjacent to foundations and within the limits of the proposed foundation to a minimum of 95% Standard Proctor Maximum Dry Density as determined by ASTM D1557, unless otherwise specified in the Contract Documents.

Page: 5 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

Concrete shall be placed as quickly as possible to avoid exposure of footing bottoms to wetting and drying. If possible, the foundation and concrete shall be placed on the same day the excavation is made. If required to be left open for more than one day, excavations shall be protected to prevent evaporation or entry of moisture. Surface runoff shall be drained away from excavations and not be allowed to pond.

Concrete shall be deposited as near as practicable to its final position to prevent segregation due to handling and flowing and to prevent splashing the forms or reinforcement with concrete. The concreting shall be carried on at such a rate that the concrete shall at all times be plastic and work readily into the spaces between the bars. No concrete that has partially hardened or has been contaminated by foreign materials shall be deposited, nor shall retempered concrete be used

14. CURING AND PROTECTION

Concrete shall be cured and protected in accordance with ACI 301.

Moisture shall be preserved as provided in ACI 301 for concrete not in contact with forms.

Ponding sprayed water or wet sand shall not be used for interior concrete slabs.

Liquid membrane curing compounds shall not be used on surfaces receiving bonded treatment, tile, paint or other adhered finishes, epoxy toppings or additional concrete.

Concrete shall be cured for a period of seven (7) days in weather above 70°F. Concrete shall be cured for a period of fourteen (14) days in weather below 70°F. The concrete temperature shall be maintained above 55°F and in moist conditions for at least the first seven (7) days after placing.

Any concrete, proven by tests to be frozen prior to curing, shall be completely removed from the structure and replaced at no additional cost to the Company

During the entire curing period, concrete shall be kept wet and covered with materials such as a polyethylene film or other suitable moisture barrier conforming to ASTM C 171 and approved by the Company Representative. The curing material shall be securely fastened to the concrete. Hot weather may necessitate water cooling of concrete in addition to membrane curing

Concrete to be exposed to the weather shall have an entrained air content of four percent (4%) to six percent (6%). Concrete to be exposed to the weather with less than four percent (4%) entrained air content shall be rejected.

15. SURFACE FINISHING

The specified surface finish shall be completed within the tolerances as defined in ACI 117.

Exposed concrete surfaces shall be professionally finished within 24 hours of the removal of the formwork to a smooth and uniform finish. Such finish shall be effected either by rubbing or by grinding with a carborundum stone. If plastering is required, a uniform color and appearance must be achieved. The sand-cement grout shall have a minimum seven (7) day compressive strength of three thousand pounds per square inch (3,000 psi). All form work ties shall be broken back one inch (1") from the surface of the concrete and the cavity patched with grout materials prior to finishing.

All exposed edges of concrete shall have a 45-degree chamfer.

Should any honeycombed concrete be discovered upon removal of forms, repairs shall be made within 24 hours after form removal. The Contractor shall chip the honeycombed portions back to solid concrete and shall fill the opening with grout or concrete of the same proportions as that specified for the section in which the fault occurs. Non-destructive or destructive testing to

Page: 6 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

determine the presence of internal honeycombs shall be performed, if required by the Company Representative. If it is determined by the Company Representative that the honeycombing is too extensive to repair, the foundation shall be removed and replaced at no additional cost to the Company.

16. TEMPERATURE CONCERNS

During hot and cold weather, concrete supply and construction shall be in accordance with ACI 305R and ACI 306.1.

Concrete Testing Requirements Company reserves the right to request concrete sampling and testing. If requested, concrete samples shall be obtained by a certified independent third party and tested by a certified independent laboratory in accordance with ACI 301. Testing shall be completed in accordance with the requirements of the Contract Documents. The rate of sampling shall be per ACI 301 and the following:

At least one sample shall be obtained per supplier per day that concrete is poured, unless the amount of concrete poured is less than 15 cubic yards (11 cubic meters).

For structures and foundations, at least one sample shall be obtained per supplier for each cumulative 65 cubic yards (50 cubic meters) of concrete poured.

For paving and slabs on grade, at least one sample shall be obtained per supplier for each cumulative 50 cubic yards (38 cubic meters) of concrete poured.

For all other applications, the rate of sampling shall be specified in the Contract Documents. For large pours (50 yds. or greater) when the concrete will be exposed to the weather, one (1) volumetric measurement of entrained air content shall be preformed for each truckload of concrete. Contractor shall be responsible for the performing air tests. Samples with less than four (4%) entrained air shall be rejected.

During placement of the concrete, representative samples of fresh concrete shall be cast in six inch (6”) diameter by twelve inch (12”) tall cylinders according to ASTM C 31 in order to determine the quality and strength of the hydrated concrete. The Contractor shall provide, prepare, and transport the concrete test cylinders. The Contractor shall be responsible for the selection of samples, storage of specimens, and protection of specimens against injury or loss throughout the operations. The Contractor shall furnish all concrete for testing.

Any group of compressive test samples taken shall consist of two (2) each of seven (7) day strength and two twenty-eight (28) day strength cylinders.

For other applications, the frequency of test samples required shall be one of the following; not less than three (3) samples for every fifty (50) yards (or fraction thereof) of placed concrete, not less than one (1) sample for each one thousand (1000) square feet of surface area placed (or fraction thereof), or as designated by the Company Representative.

At the discretion of the Company Representative, the Contractor may be directed to take additional test samples at no additional cost to the Company.

Test samples shall remain at the site exposed to the same conditions as the placed concrete for the first twenty-four (24) hours. Following the twenty-four (24) hours field cure period, the cylinders shall be immediately transported to a laboratory for controlled curing and testing. During periods of cold weather, the cylinders shall be transported in a temperature-controlled environmental (60- 80°F) or shall otherwise be insulated to protect against freezing.

Page: 7 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

No vehicular traffic, construction equipment, or materials shall be placed or permitted on foundations or floor slabs for at least three (3) days after placement and only if the concrete has achieved at least seventy-five percent (75%) of its specified twenty-eight (28) day compressive strength.

Prior to the end of the seven (7) day and/or fourteen (14) day cure period, the Company Representative may elect to qualify the concrete for loading based on testing cylinders to determine that the required concrete strength has been achieved. Upon approval by Company of alternative concrete mixture, Contractor may use high-early strength concrete. Contractor shall provide the Company adequate opportunity to place thermo-couples in completed formwork prior to placement of concrete.

The Company Representative and chief inspector will review concrete mixes, pours and curing times and work with the Contractor to minimize the curing time with Company design department approval. Each instance should be documented by the Contractor with a “request for information” (RFI).

If the Contractor elects to place equipment, materials, or traffic on concrete prior to the seven (7) day compressive test results, additional test cylinders shall be required to verify three (3) day compressive strength at no additional cost to the Company.

Strength of concrete shall be considered satisfactory if the average of two (2) twenty-eight (28) day tests in each set of cylinders equals or exceeds the specified twenty-eight (28) day strength and neither of the twenty-eight (28) day tests is five hundred (500) psi or more below the specified twenty-eight (28) day strength.

17. CARBON STEEL PIPE

Carbon steel pipe shall be manufactured and tested by the pipe manufacturer in accordance with the CFR 49 Part 192.

18. PIPE WELDING

Steel pipe jointing shall be performed by personnel trained and certified in the methods of such in Welding procedures shall be in accordance with 49 CFR Part 192.225 Welding procedures must be recorded in detail including the results of qualifying tests Welds will undergo 100% nondestructive inspection by a certified welding inspector to be provided by the Contractor.

19. COATING

All carbon steel piping, buried and above ground, shall be coated to protect from corrosion.

Contractor shall submit a two-part epoxy coating selection and color to match existing assembly for approval.

In addition to the requirements of this specification, all above ground coating application shall meet the requirements of the Steel Structures Painting Council (SSPC) and the Coating Manufacturer’s recommendations.

The Contractor/Applicator will follow the Company or coating manufacturer's recommendations for application and for curing time.

During application of coatings nearby structures or property shall be protected to avoid damage by overspray and/or drips.

Page: 8 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

If damage occurs, Applicator shall cease coating application until effective measures are taken to prevent further damage.

All damage will be reported to the Company immediately.

Any damages are repaired at the Applicator’s expense.

The Contractor takes sufficient WFT readings, using an approved instrument or measuring device, to allow an accurate estimation of the final Dry Film Thickness (DFT) of each coat.

DFT information will be recorded for record keeping purposed.

20. PRESSURE TESTING

All piping shall be tested by the contractor in accordance with CFR 49 Part 192 Subpart J.

Test requirements will be provided by Owner in accordance with CFR 49 Part 192 Subpart J and the Massachusetts Natural Gas Pipeline Safety Code.

Contractor is responsible for conducting the test in accordance with the provide procedures including provision of temporary blinds, fittings, hoses, nitrogen, air, recorders, and other equipment that may be necessary.

21. BOLTING

MATERIALS

i. Studs in this specification shall conform to ASTM A193.

ii. Nuts & washers in this specification shall conform to ASTM A194.

iii. Studs and nuts shall be Grade B7, Teflon coated.

iv. Nuts shall be 2H heavy hex.

LUBRICANTS

i. Studs shall be lubricated using Loctite Nickel Anti-Seize or equivalent if approved by Engineering.

ii. All threaded fasteners shall be lubricated immediately prior to installation. Lubricant shall be applied liberally to both ends of the stud bolt prior to the installation of the nuts.

WASHERS

i. A single 1/8 thick washer shall be installed between the nut that is to be turned and the flange.

ii. If desired, contractor may use washers on both side of flange for simplicity.

DOCUMENTATION

i. All studs nuts and washers shall be provided with Material Test Reports (MTRs) or

Certificates of Conformance (CFCs) identifying the material and treatment of the hardware.

PRIOR TO INSTALLATION

i. Contractor shall provide its torqueing plan, equipment conversion tables and calibration certifications (good within the last 12 months) to Cornerstone prior to commencement of the work. Contractor shall not use striking wrenches.

Page: 9 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ii. The number, diameter, and length of studs for various flange sizes and ratings shall meet the requirements of Section 9- Torque Tables

iii. All gaskets shall be CGI type, with a 304SS or 316SS inner ring and a carbon steel outer ring.

iv. Nuts shall be hand tightened first, ensuring both full engagement of the nut threads as well as an equal division of excess bolt length between both ends.

v. Contractor is responsible for the integrity of all installed threaded fasteners. This includes proper storage to prevent corrosion or damage. Fasteners shall be stored out of the weather and kept out of the dirt when the flange is being fit up.

vi. Studs and nuts shall be inspected for thread damage and fit. Contractor shall replace any studs and nuts where difficult engagement is encountered or too loose when threaded by hand. Studs and nuts with damaged threads are not to be used.

INSTALLATION

i. Torquing shall be required on all applications and not as a substitute for the equipment manufacturer's specifications and/or standards.

ii. Studs and nuts shall be replaced if studs have been torqued to a load that exceeds the applicable value specified by more than 30%. Contractor shall replace, at no additional cost to others, any studs that are over-torqued.

iii. Pneumatic or adjustable torque wrenches shall be used for tightening studs to the zero-tension point, which is commonly known as “snugging up”.

iv. Contractor shall submit calibration certificates for all torqueing equipment used.

v. Properly calibrated pneumatic, hydraulic or manual torqueing equipment may be used.

The Contractor is responsible for selecting the appropriate torqueing equipment.

vi. Torque wrenches may be used on flange connections, however in applications larger than

24” Engineering should be consulted prior to doing so.

vii. Studs shall be centered in torqued flange connections (approximately equivalent bolt protrusion beyond the nut faces on either side after tightening). Bolt threads shall fully engage the nut threads on both sides of the connection prior to tightening. Studs shall have a minimum engagement of .5 exposed threads and a maximum of 4.

viii. Studs shall be torqued to the values given in Torque Tables

ix. When torqueing, studs shall be tightened in 25% increments of final torque following the sequential order shown on torque forms. When 100% of the final torque value is reached all studs shall be rechecked in a ring pattern until no studs move to ensure the 100% torque value is maintained.

x. Contractor shall submit a report with final torque values for every flange, with the appropriate signoffs and a map indicating where each flange is located. Report templates can be found in Section 8. Torque maps shall be submitted on engineering drawings unless approved by Engineering to do otherwise.

LEAK TIGHTENING

i. Repair of leaking flanges during pressure testing of a newly constructed pipe system shall meet the following requirements.

Page: 10 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ii. The determination of whether to tighten leaking flanges while under pressure or to depressurize prior to retightening shall be mutually agreed upon between the Contractor and the Inspector. Inspector approval is required prior to tightening of leaking flanges and the pressure must be lowered to 0 PSIG, or as close as possible.

iii. Extreme caution shall be exercised when it is deemed prudent to tighten leaking flanges or threaded fittings while under pressure.

iv. Studs shall be retightened by increasing the specified torque value by 15%.

v. Continued leakage shall be eliminated by depressurizing the system, disassembling and inspecting the flange, checking the alignment, cleaning and inspecting the gasket seal area on the flange face, or replacing damaged or improper flanges, reassembling with a new gasket, and re-tightening.

vi. Contractor shall be responsible for ensuring that all flanged connections are properly tightened prior to pipelines and appurtenances being placed in service.

Page: 11 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

22. TORQUE TABLES

ANSI CLASS 150 RAISED FACE FLANGES

Application: B8 studs and nuts, with washer

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 1/2" 7/8” 3-1/4” 4 42 11, 21, 32 49

1-1/2” 1/2" 7/8” 3-1/4” 4 60 15, 30, 45 69

2" 5/8" 1-1/16” 3-3/4” 4 85 22, 43, 64 98

2 1/2" 5/8" 1-1/16” 4” 4 85 22, 43, 64 98

3" 5/8" 1-1/16” 4-1/4" 4 85 22, 43, 64 98

3 1/2" 5/8" 1-1/16” 4-1/4" 8 85 22, 43, 64 98

4" 5/8" 1-1/16” 4-1/4" 8 85 22, 43, 64 98

6" 3/4" 1-1/4” 4-1/2" 8 153 39, 77, 115 176

8" 3/4" 1-1/4” 4-3/4" 8 153 39, 77, 115 176

10" 7/8" 1-7/16” 5-1/2" 12 248 62, 124, 186 286

12" 7/8" 1-7/16” 5-1/2" 12 248 62, 124, 186 286

16" 1" 1-5/8” 6-1/4" 16 372 93, 186, 279 428

18" 1-1/8" 1-13/16” 6-3/4" 16 553 139, 277, 415 636

20" 1-1/8" 1-13/16” 7” 20 553 139, 277, 415 636

24" 1-1/4" 2” 7-3/4” 20 784 196, 392, 588 902

26" 1-1/4" 2” 9-1/2” 24 784 196, 392, 588 902

30" 1-1/4" 2” 10” 28 784 196, 392, 588 902

36" 1-1/2" 2-3/8” 11-1/2” 32 1424 356, 712, 1,068 1,638

Page: 12 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ANSI CLASS 300 RAISED FACE FLANGES

Application: B8 studs and nuts, with washer

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 5/8" 1-1/16” 3-3/4” 4 85 22, 43, 64 98

2" 5/8" 1-1/16” 4” 8 85 22, 43, 64 98

2 1/2" 3/4" 1-1/4” 4-1/2” 8 153 39, 77, 115 176

3" 3/4" 1-1/4” 4-3/4” 8 153 39, 77, 115 176

3 1/2" 3/4" 1-1/4” 5” 8 153 39, 77, 115 176

4" 3/4" 1-1/4” 5” 8 153 39, 77, 115 176

6" 3/4" 1-1/4” 5-1/2” 12 153 39, 77, 115 176

8" 7/8" 1-7/16” 6-1/4” 12 248 62, 124, 186 286

10" 1" 1-5/8” 7” 16 372 93, 186, 279 428

12" 1-1/8" 1-13/16” 7-1/2” 16 553 139, 277, 415 636

16" 1-1/4" 2” 8-1/4” 20 784 196, 392, 588 902

18" 1-1/4" 2” 8-1/2” 24 784 196, 392, 588 902

20" 1-1/4" 2” 9” 24 784 196, 392, 588 902

24" 1-1/2" 2-3/8” 10” 24 1424 356, 712, 1,068 1,638

26" 1-5/8" 2-9/16” 11” 28 1844 461, 922, 1,383 2,121

30" 1-3/4" 2-3/4” 12-1/4” 28 2339 585, 1,170, 1,755 2,690

36" 2" 3-1/8” 13-3/4” 32 3582 896, 1,791, 2,687 4,120

Page: 13 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ANSI CLASS 600 RAISED FACE FLANGES

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 5/8" 1-1/16” 4-1/4” 4 85 22, 43, 64 98

2" 5/8" 1-1/16” 4-3/4” 8 85 22, 43, 64 98

2-1/2" 3/4" 1-1/4” 5-1/4” 8 153 39, 77, 115 176

3" 3/4" 1-1/4” 5-1/2” 8 153 39, 77, 115 176

4" 7/8" 1-7/16” 6-1/2” 8 248 62, 124, 186 286

6" 1" 1-5/8” 7-1/2” 12 372 93, 186, 279 428

8" 1-1/8" 1-13/16” 8-1/2” 12 553 139, 277, 415 636

10" 1-1/4" 2” 9-1/4” 16 784 196, 392, 588 902

12" 1-1/4" 2” 9-1/2” 20 784 196, 392, 588 902

16" 1-1/2" 2-3/8” 10-3/4” 20 1424 356, 712, 1,068 1,638

18" 1-5/8" 2-9/16” 11-1/2” 20 1844 461, 922, 1,383 2,121

20" 1-5/8" 2-9/16” 12-1/4” 24 1844 461, 922, 1,383 2,121

24" 1-7/8" 2-15/16” 13-3/4” 24 2917 730, 1,459, 2,188 3,355

26" 1-7/8" 2-15/16” 14-1/4” 28 2917 730, 1,459, 2,188 3,355

30" 2" 3-1/8” 15” 28 3582 896, 1,791, 2,687 4,120

36" 2-1/2" 3-7/8” 16-3/4” 28 7245 1,812, 3,623, 5,434 8,332

Page: 14 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ANSI CLASS 900 RAISED FACE FLANGES

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 7/8" 1-7/16” 5-3/4” 4 248 62, 124, 186 285

2" 7/8" 1-7/16” 6-1/2" 8 248 62, 124, 186 285

2-1/2" 1" 1-5/8” 7” 8 372 93, 186, 279 428

3" 7/8" 1-7/16” 6-1/2" 8 372 93, 186, 279 428

4" 1-1/8" 1-13/16” 7-1/2" 8 248 62, 124, 186 285

6" 1-1/8" 1-13/16” 8-1/2" 12 553 138, 276, 414 636

8" 1-3/8" 2-3/16” 9-1/2" 12 553 138, 276, 414 636

10" 1-3/8" 2-3/16” 10” 16 1073 268, 536, 804 1234

12" 1-3/8" 2-3/16” 10-3/4" 20 1073 268, 536, 804 1234

16" 1-5/8" 2-9/16” 12” 20 1844 461, 922, 1383 2121

18" 1-7/8" 2-15/16” 13-1/2" 20 2917 729, 1458, 2187 3355

20" 2" 3-1/8” 14-1/2" 20 3582 896, 1792, 2688 4119

24" 2-1/2" 3-7/8” 18” 20 7245 1811, 3622, 5433 8332

26" 2-3/4" 4-1/4” 18-1/2" 20 9764 2441, 4882, 7323 11229

30" 3" 4-5/8” 19-3/4" 20 12809 3202, 6404, 9606 14730

36" 3-1/2" 5-3/8” 22-1/2" 20 20674 5169, 10338, 15507 23775

Page: 15 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ANSI CLASS 1500 RAISED FACE FLANGES

Flange Size

Bolt Dia.

2H Nut Size

Bolt Length s

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 7/8" 1-7/16” 5-3/4” 4 248 62, 124, 186 285

2" 7/8" 1-7/16” 6-1/2” 8 248 62, 124, 186 285

2-1/2" 1" 1-5/8” 7” 8 372 93, 186, 279 428

3" 1-1/8” 1-13/16” 7-3/4” 8 553 138, 276, 414 636

4” 1-1/4” 2” 8-1/2” 8 784 196, 392, 588 902

ANSI CLASS 2500 RAISED FACE FLANGES

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 7/8” 1-7/16” 6-1/4” 4 248 62, 124, 186 285

2" 1” 1-5/8” 7-3/4” 8 372 93, 186, 279 428

2-1/2" 1-1/8” 1-13/16” 8-1/2” 8 553 138, 276, 414 636

3" 1-1/4” 2” 9-1/2” 8 784 196, 392, 588 902

4” 1-1/2” 2-3/8” 10-3/4” 8 1424 356, 712, 1068 1638

Page: 16 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT

ANSI CLASS 150 FLAT FACE FLANGES

Flange Size

Bolt Dia.

2H Nut Size

Bolt Lengths

Number of Studs

Final Torque (ft-lb)

Torque Increments (ft-lbs)

15% Over Value (ft-lbs)

1" 1/2" 7/8” 3-1/4” 4 60 15, 30, 45 69

1-1/2” 1/2" 7/8” 3-1/4” 4 90 23, 46, 69 104

2" 5/8" 1-1/16” 3-3/4” 4 120 30, 60, 90 138

2 1/2" 5/8" 1-1/16” 4” 4 120 30, 60, 90 138

3" 5/8" 1-1/16” 4-1/4" 4 120 30, 60, 90 138

3 1/2" 5/8" 1-1/16” 4-1/4" 8 120 30, 60, 90 138

4" 5/8" 1-1/16” 4-1/4" 8 120 30, 60, 90 138

6" 3/4" 1-1/4” 4-1/2" 8 200 50, 100, 150 230

8" 3/4" 1-1/4” 4-3/4" 8 200 50, 100, 150 230

10" 7/8" 1-7/16” 5-1/2" 12 320 80, 160, 240 368

12" 7/8" 1-7/16” 5-1/2" 12 320 80, 160, 240 368

16" 1" 1-5/8” 6-1/4" 16 490 123, 246, 369 564

18" 1-1/8" 1-13/16” 6-3/4" 16 710 178, 356, 534 817

20" 1-1/8" 1-13/16” 7” 20 710 178, 356, 534 817

24" 1-1/4" 2” 7-3/4” 20 1000 250, 500, 750 1150

26" 1-1/4" 2” 9-1/2” 24 1000 250, 500, 750 1150

30" 1-1/4" 2” 10” 28 1000 250, 500, 750 1150

36" 1-1/2" 2-3/8” 11-1/2” 32 1800 450, 900, 1350 2070

Page: 17 of 17

Specification Number: CS-21128

MGED: OCEAN SPRAY PROJECT