SECTION B

SUPPLIES OR SERVICES AND PRICES

BIDDING SCHEDULE

SPENCE SUBSTATION, STAGE 02

CLIN Work or Material Estimated Quantity Unit Unit Price Amount

0001 Mobilization and preparatory work (Not to exceed 5% of TOTAL. See Section H and M.)

LS $ _

0002 Demolition (see note#1 below) 40 CY $ _

0003 Concrete foundations 43 CY $ $ _

0004 Cable trenches LS $ _

0005 Grounding system LS $ _

0006 Existing outdoor electrical equipment and material

LS $ _

TOTAL $ _

ABBREVIATIONS

Note#1:

CLIN = Contract Line Item Number

CY = cubic yards LS = for the lump sum of LB = pounds

Demolition includes the removal and disposal of concrete foundations, propane tank, the generator building and the generator building contents.

NOTE: the Buy American Act applies to this solicitation. Refer to FAR Clause 52.225-9 (Section I) and FAR Provision 52.225-10 (Section L) if any non-domestic material will be proposed. Bidders must identify any non-domestic materials (not manufactured in United States) included in their bid. Please check with your suppliers and subcontractors to verify whether or not their quotes include non-domestic material.