21-253 Addendum #1

172 KB Posted

Attached to
On Call Stormwater Repair Services
Solicitation number
21-253
Issued by
Fulton County, Georgia

About this file

This is Addendum #1 to an Invitation to Bid (ITB #21-253) for On Call Stormwater Repair Services issued by the City of Johns Creek, Georgia, Purchasing Division. The addendum addresses 32 questions and answers submitted by prospective bidders prior to the August 26, 2021, 5:00 PM question deadline. The scope of work encompasses a comprehensive range of stormwater infrastructure repair and maintenance services, including pipe replacement at various diameters, closed-circuit television (CCTV) inspection work, catch basin and junction box repair and replacement, headwall repair, sidewalk replacement, asphalt patching, channel and ditch excavation, geotextile fabric installation, landscape restoration, and miscellaneous items such as riser installation and pipe collar replacement. All work shall be constructed in accordance with Georgia Department of Transportation (GDOT) standards and specifications. Sealed bids are due electronically through BidNet no later than 2:00 PM Eastern Time on September 10, 2021. The contract is structured as an on-call arrangement with work issued through individual task orders on a project-by-project basis, with a typical ten-calendar-day startup period from the Notice to Proceed following a preconstruction meeting.

The City anticipates an annual budget of $500,000 to $800,000 for stormwater repair projects under this on-call contract. Task orders are not anticipated to exceed $100,000 individually, and therefore performance and payment bonds will not be required under Georgia law; however, the City reserves the right to require bonds if a task order reaches $100,000. The work will consist of a mixture of pipe replacement and general maintenance activities, with project scope and requirements to be determined during individual task order phases. All line items on the rate sheet must be completed with estimated unit costs, even for pipe sizes that may be rarely used. Contractors are responsible for all hauling, disposal, and site restoration costs, which must be incorporated into unit pricing. No General Contractor or Utility Contractor license is required. The City reserves the right to reject any or all bids and award the contract in its best interest, and all bidders must comply with Title VI of the Civil Rights Act and disadvantaged business enterprise provisions.

Text of this file

Purchasing Division

11360 Lakefield Drive | Johns Creek, GA 30097 | JohnsCreekGA.gov | 678-512-3200 | Fax: 678-512-3244

ADDENDUM #1

Invitation to Bid (ITB)

Bid #21-253 On Call Stormwater Repair Services

To All Prospective Offerors:

To follow is Addendum Number 1 for the above solicitation.

1. Answers from questions asked in BidNet prior to the Q&A deadline 8/26/21 5:00 PM

REMINDER, BIDS ARE DUE ELECTRONICALLY IN BIDNET NO LATER THAN 2:00 PM ET

SEPTEMBER 10, 2021.

All addendums are electronically acknowledged at submission of bid within BidNet. Firms shall include this acknowledgement of receiving RFP 21‐253 addendum #1 in your proposal package with your forms and documents.

Firm: ______________________________________

Signature: __________________________________

Date:__________________

Questions & Answers - 1

Project 21-253 - On Call Stormwater Repair Services

Buying Organization The City of Johns Creek

No Question/Answer Question Date

Q1 Question: CCTV Work to be done

Will each project require CCTV work for pipe replacement and once complete?

Answer: Typically so, but the need for CCTV will be determined during the scoping phase of individual task orders.

08/24/2021

Q2 Question: CCTV Work to be done

Will each project require CCTV along with cleaning work order

Answer: Typically so, but the need for CCTV will be determined during the scoping phase of the individual task orders.

08/24/2021

Q3 Question: Cut and Replace Section

Can you clarify bedding standards for each type of pipe.

Answer: Pipe installation will be constructed to GDOT standards and specifications.

08/24/2021

Q4 Question: Cut and Replace Section

Can you add section for additional depth of pipe as each location different.

Example > than 10 deep installation, 15 and or > 20

Answer: No changes to these line items will be made.

08/24/2021

Q5 Question: Headwall Repair

Can you explain the scope of work needed in this section. There are many types of headwalls.

Answer: Repair work will be for minor concrete damage. Major damages to headwall will require a headwall replacement.

08/24/2021

Q6 Question: Demo and Replace Catch Basin

Is this understood as throat and top to be done? A line item for throat and top separated may be needed.

Answer: This line item is understood as throat and top.

08/24/2021

Q7 Question: Catch Basin/Junction Box Grouting

Can you explain the scope of work for this item? Linear feet or Square feet would help for estimating purposes.

Answer: The line items are specified by their depths. A range of depths are provided in each line item and a lump sum price is requested for each range.

08/24/2021

Q8 Question: Demo and Replace Sidewalk

Can you tell us if all projects unless noted are assumed 3000 psi concrete?

Answer: All sidewalk projects shall use Class B concrete.

08/24/2021

No Question/Answer Question Date

Q9 Question: Miscellaneous Items

Pipe Collar Replacement

Do you have a detail or are we to follow GDOT

Answer: Pipe collar replacements will be to GDOT standards and specifications.

08/24/2021

Q10 Question: Asphalt Patching and Paving (roadway)

Do you have a detail showing thickness to determine the square footage allowance?

Answer: Asphalt patching and paving shall be constructed to GDOT standards and specifications.

08/24/2021

Q11 Question: Miscellaneous Items

Can you explain the 4000 psi concrete line item? How it will be used and or in place of 3000psi for payment

Answer: The 4000 psi concrete line item will be used separate from other line items as necessary dependent upon project needs.

08/24/2021

Q12 Question: Riser Install

Can you add diameters to be used for estimating accuracy.

Answer: No changes to this line item will be made.

08/24/2021

Q13 Question: Geotextile Fabric

Can you detail Woven or Nonwoven and grade?

Answer: Geotextile type and grade will be determined as necessary in each task order. No changes to the rate sheet will be made.

08/24/2021

Q14 Question: Channel/Ditch Excavation

Can this line item be changed to Cubic yards for measurement ?

Answer: The line item will remain in linear feet.

08/24/2021

Q15 Question: Fill Dirt on project

Is this Borrow or Haul off in conjunction with pipe or can you explain this work scope.

Answer: The fill dirt in the miscellaneous category will be separate from any of the other line items and treated as a stand alone cost as needed. Any fill associated with the other line items shall be included in their unit prices.

08/24/2021

Q16 Question: Pipe Laying Conditions

When pipe laying occurs there is assumed soil left over especially when changing diameters, soil conditions or pipe materials.

How will leftover soil be paid for to be removed from the site as conditions change from site to site

Answer: All hauling and disposal should be built into your unit price.

08/24/2021

Q17 Question: Pipe Laying Conditions

How will unsuitable soil from excavated pipe that cannot be used be handled for payment on line items

Answer: All hauling and disposal should be built into your unit price.

Q18 Question: Pipe Laying Conditions

Who will be performing testing of any of the contract work

Answer: The contractor will responsible for all work associated with the stormwater repair scope of work.

08/24/2021

Q19 Question: Survey Work

Will survey need to be done by the contractor for each project? Maybe payment by the hour or some other way would be easier to estimate as the size of the project and trips will determine contractor cost.

Answer: Survey work will be determined on a project by project basis.

08/24/2021

Q20 Question: Licensing Requrement

Is no Utility Contractor license or General Contractor required for this work

Answer: That is correct.

08/24/2021

Q21 Question: Grassing Complete

Will trees, shrubs or any plants need to be replaced. Transplanting depending on the season may not allow it to placed back and flower bulbs will not be visible.

Answer: This item is included in the "Landscape Restoration" line item and will be determined on a project by project basis.

08/24/2021

Q22 Question: Irrigation

How will irrigation in yard be paid for when crossing.

Answer: Any damage to surrounding public/private infrastructure will be the responsibility of the contractor.

08/24/2021

Q23 Question: Pipe replacement

Some pipes are not available as they have not been made in several years. Is it ok to leave these line items $0.00?

Answer: All line items should be filled in with estimated costs to repair/replace these specific sized pipes.

08/24/2021

Q24 Question: Connecting to a structure

Some structures can be reused. Can a line item be added - Connect to existing Structure

Answer: Connecting to existing structure should be included in material cost.

08/24/2021

Q25 Question: Pipe removal

Can a line item be added for Pipe Removal

Answer: All hauling and disposal should be built into your unit price.

08/24/2021

Q26 Question: Invert Installation

Will all structures being added and connected to need a invert installed in the manhole?

Answer: Typically so, but invert installation will be determined during the scoping phase of the individual task order.

Q27 Question: Estimation

Can you state the annual budget to be used for this RFP

Answer: We intend to spend between $500-$800K per year on stormwater repair projects.

08/24/2021

Q28 Question: Insurance Requirement

Will a performance and payment bond be required?

Answer: State law defined in O.C.G.A. title 36 does not require Performance and payment bonds for contracts (Task Order Agreements) under $100,000.00. The City does not anticipate any Task Order exceeding $100,000.00 however, a governmental entity can require bonds for projects $100,000.00 & should the agency determine bonds are required which would be included with the Task Order Request for Quote.

08/24/2021

Q29 Question: Project Management

How many days does the contractor have when given a project to start?

Answer: Typically Ten (10) calendar days from the issuance of the Notice to Proceed for the Task

Order. The NTP will be issued after the On Call Contractor and City Staff have a Task Order project preconstruction meeting. Emergency repair situations will be discussed at contract negotiation.

08/24/2021

Q30 Question: Work Orders

Will these project be primarily pipe replacement or will the contractor get separate work orders such as :

1. Just reset a Headwall or 2. Replace curb, 3. Replace catch basin lid

We are just trying to justify labor cost to do minor items within the bid

Answer: The task orders will be a mixture of pipe replacement as well as general maintenance.

08/24/2021

Q31 Question: Manholes and Catch basins

Can brick boxes be used lieu of Precast as certain situation allow better replacement methods as long as they meet GDOT. If so will line item be added

Answer: Yes, brick boxes can be used when precast is not suitable if they meet GDOT Standards and

Specifications.

08/24/2021

Q32 Question: Demo and Replace Catch Basin

Can line items be added for diameters as size will have to be assumed for the largest diameters of pipe for line items #87-91. Example 72 pipe in and out will not fit in a 6 foot diameter manhole

Answer: No diameters will be provided.

21-244 Q&A Document 1 (30).pdf
Questions & Answers - 1

Other files

File Type Posted
21-253 Terminated Bid —
21-253 Communication 1 —
21-253 Bid Packet —
21-253 Received Bids —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .