This is an Addendum 2 to an Invitation to Bid (ITB) issued by the City of Johns Creek, Georgia, for On Call Professional Services related to Storm Pipe Lining Services. The City is seeking sealed proposals from qualified firms to provide storm pipe lining services that meet or exceed the specifications outlined in the bid documents. The deadline for submission of sealed proposals is 2:00 PM ET on Tuesday, August 24, 2021, through BidNet, Georgia's online bidding and vendor registration system accessible via the City website. The deadline for submitting questions regarding the bid is August 10, 2021, at 5:00 PM ET. All offerors must comply with the general and special requirements contained in the ITB information and instructions.
The City of Johns Creek has established this procurement in accordance with Title VI of the Civil Rights Act of 1964 and applicable non-discrimination regulations, specifically ensuring that disadvantaged business enterprises are afforded full opportunity to submit bids without discrimination based on race, color, national origin, or sex. The City reserves the right to reject any or all bids and to award the contract in its best interest, with the authority to waive technicalities and informalities. Neil Trust, Purchasing & Contracts Manager, is the identified contact for this procurement.
Text of this file
Purchasing Division
11360 Lakefield Drive | Johns Creek, GA 30097 | JohnsCreekGA.gov | 678-512-3200 | Fax: 678-512-3244
ADDENDUM #2
Request for Proposals (RFP)
Bid #21-236
On Call Professional Services- Storm Pipe Lining Services
To All Prospective Offerors:
To follow is Addendum Number 2 for the above solicitation.
1. Transcript from Prebid Zoom teleconference from 8/4/2021 (optional attendance)
2. Answers to Questions asked in BidNet through 8/5/2021
3. Revised cost proposal line 127, 128, 129 in BidNet and revised hard copy of cost proposal
PREBID TELECONFERENCE (Optional Attendance) 8/4/2021 10:00AM ET.
Project Overview:
The City adopted a stormwater utility program with dedicated funding for maintenance and repair work for the City’s stormwater system. A complete conditions assessment has been done on over 32,000 pipes within the City. The City is responsible for 2/3 of the pipes within the City and the assessment has provided what shape, condition, siltation, and what assets need repaired. A handful of pipes will fall within spin casting and CIP repair work and the award
Contractor(s) will work closely with staff on how best to accomplish work at these sites.
Questions during Teleconference:
1. Q: Was the CCTV done in house or subcontracted out?
A: Contracted out with Lowe Engineering.
2. Q: Has the City ever done CIPP lining?
A: Yes
3. Q: Did the City bid out the CIPP lining?
A: Yes
4. Q: Could the City release the bid numbers from the lining as an addendum?
A: Information regarding previous bid award shall be requested as a Public Records
Request through the City’s website, www.johnscreekga.gov http://www.johnscreekga.gov/
Purchasing Division
11360 Lakefield Drive | Johns Creek, GA 30097 | JohnsCreekGA.gov | 678-512-3200 | Fax: 678-512-3244
5. Q: Could the City release the bid numbers from the lining as an addendum?
A: Information regarding previous bid award shall be requested as a Public Records
Request through the City’s website: https://www.johnscreekga.gov/services-resources/forms/city-city-clerk/request-public-records
End of Questions from the teleconference
Electronic Questions Received through BidNet:
*see the attached Q&A document.
Key Dates for Request for Proposal 21-236:
Deadline to submit questions related to this bid is August 10, 2021 5:00 PM ET. All questions must be asked electronically through the City’s bid platform, BidNet. Firms can register for
BidNet free or paid services by visiting our City website, https://www.bidnetdirect.com/georgia/cityofjohnscreek
An addendum shall publish within 3-5 business days with responses to questions received.
Addendums are published at BidNet and the state of Georgia Procurement Registry.
All proposal submissions are due both electronically in BidNet with hard copies to City Hall no later than 2:00 PM ET August 24, 2021. Instructions for proposal organization and submission are in the bid packet. A list of firm names shall publish within 24 hours after the bid closes and proposals will then follow the evaluation schedule outlined in Appendix A of the bid packet.
All addendums are electronically acknowledged at submission of bid within BidNet. Firms shall include this acknowledgement of receiving RFP 21-236 addendum #2 in your proposal package with your forms and documents.
Firm: ______________________________________
Signature: __________________________________
Date:__________________ https://www.johnscreekga.gov/services-resources/forms/city-city-clerk/request-public-records https://www.johnscreekga.gov/services-resources/forms/city-city-clerk/request-public-records https://www.bidnetdirect.com/georgia/cityofjohnscreek
Questions & Answers - 1
Project 21-236 - On Call Professional Services - Storm Pipe Lining Services
Buying Organization The City of Johns Creek
No Question/Answer Question Date
Q1 Question: Offerors Conference
In section 1.2.2 in the documents, a offerors conference is mentioned at City Hall. Is this in addition to the zoom pre-bid meeting or will this be an additional meeting held on August 4 at 10am?
Answer: Addendum 1 addresses this questions. The Pre-bid meeting is only being held via teleconference.
07/29/2021
Q2 Question: Bid Bond Required
Will a bid bond be required for this project? If so, at what percent?
Answer: This Bid will not require a bid bond for the award of On Call services. Contractors are to submit unit pricing for services good for 3 years. At the end of year number 3, the Contractor(s) shall submit unit pricing for years number 4 & 5 option years 4 & 5
08/04/2021
Please include a copy of this price sheet in your hard copy submission envelope #2. Enter unit costs directly into BidNet at Bid Submission
ITEM
Description Unit Unit Price
Lining Requirements Inversion Setup
1 Inversion Setup Charge 15‐36" CIPP EA
2 Inversion Setup Charge 42‐48" CIPP EA
CIPP (12' or less in depth) Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (less than 25% full)
3 12" ‐ 7.5 mm (.2953") LF
4 15" ‐ 7.5mm (.2953") LF
5 18" ‐ 8.0mm (.315") LF
6 21" ‐ 10.0mm (.3937") LF
7 24" ‐ 10.0mm (.3937") LF
8 30" ‐ 12.5mm (.4921") LF
9 36" ‐ 16.0mm (.6299") LF
10 42" ‐ 18.0mm (.7087") LF
11 48" ‐ 21.0mm (.8268") LF
12 Add Thickness Per 1.5mm ‐12" LF
13 Add Thickness Per 1.5mm ‐15" LF
14 Add Thickness Per 1.5mm ‐18" LF
15 Add Thickness Per 1.5mm ‐21" LF
16 Add Thickness Per 1.5mm ‐24" LF
17 Add Thickness Per 1.5mm ‐30" LF
18 Add Thickness Per 1.5mm ‐36" LF
19 Add Thickness Per 1.5mm ‐42" LF
20 Add Thickness Per 1.5mm ‐48" LF
CIPP (12' or less in depth) Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (greater than 25% full)
21 12" ‐ 7.5 mm (.2953") LF
22 15" ‐ 7.5mm (.2953") LF
23 18" ‐ 8.0mm (.315") LF
24 21" ‐ 10.0mm (.3937") LF
25 24" ‐ 10.0mm (.3937") LF
26 30" ‐ 12.5mm (.4921") LF
27 36" ‐ 16.0mm (.6299") LF
28 42" ‐ 18.0mm (.7087") LF
29 48" ‐ 21.0mm (.8268") LF
30 Add Thickness Per 1.5mm ‐12" LF
31 Add Thickness Per 1.5mm ‐15" LF
32 Add Thickness Per 1.5mm ‐18" LF
33 Add Thickness Per 1.5mm ‐21" LF
34 Add Thickness Per 1.5mm ‐24" LF
35 Add Thickness Per 1.5mm ‐30" LF
36 Add Thickness Per 1.5mm ‐36" LF
37 Add Thickness Per 1.5mm ‐42" LF
38 Add Thickness Per 1.5mm ‐48" LF
Styrene Free‐CIPP (12' or less depth) Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (less than 25% full)
39 12" Pipe ‐ 7.5mm LF
40 15" Pipe ‐ 7.5mm LF
CITY OF JOHNS CREEK ON-CALL PIPE LINING RATE SHEET
Bid 21-236 On Call Prefoessional Services-Storm Pipe Lining Service
41 18" Pipe ‐ 8.0mm LF
42 21" Pipe ‐ 10.0mm LF
43 24" Pipe ‐ 12.5mm LF
44 30" Pipe ‐ 12.5mm LF
45 36" Pipe ‐ 16.0mm LF
46 42" Pipe ‐18.0mm LF
47 48" Pipe ‐ 21.0mm LF
48 Additional Cost Per 1.5mm ‐ 12" LF
49 Additional Cost Per 1.5mm ‐ 15" LF
50 Additional Cost Per 1.5mm ‐ 18" LF
51 Additional Cost Per 1.5mm ‐ 21" LF
52 Additional Cost Per 1.5mm ‐ 24" LF
53 Additional Cost Per 1.5mm ‐ 30" LF
54 Additional Cost Per 1.5mm ‐ 36" LF
55 Additional Cost Per 1.5mm ‐ 42" LF
56 Additional Cost Per 1.5mm ‐ 48" LF
Styrene Free‐CIPP (12' or less depth) Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (greater than 25% full)
57 12" Pipe ‐ 7.5mm LF
58 15" Pipe ‐ 7.5mm LF
59 18" Pipe ‐ 8.0mm LF
60 21" Pipe ‐ 10.0mm LF
61 24" Pipe ‐ 12.5mm LF
62 30" Pipe ‐ 12.5mm LF
63 36" Pipe ‐ 16.0mm LF
64 42" Pipe ‐18.0mm LF
65 48" Pipe ‐ 21.0mm LF
66 Additional Cost Per 1.5mm ‐ 12" LF
67 Additional Cost Per 1.5mm ‐ 15" LF
68 Additional Cost Per 1.5mm ‐ 18" LF
69 Additional Cost Per 1.5mm ‐ 21" LF
70 Additional Cost Per 1.5mm ‐ 24" LF
71 Additional Cost Per 1.5mm ‐ 30" LF
72 Additional Cost Per 1.5mm ‐ 36" LF
73 Additional Cost Per 1.5mm ‐ 42" LF
74 Additional Cost Per 1.5mm ‐ 48" LF
Spin Cast Lining Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (less than 25% full)
75 30" Centrifugal Spin‐ 1.5 Thickness LF
76 36" Centrifugal Spin ‐ 1.5 Thickness LF
77 42" Centrifugal Spin ‐ 1.5 Thickness LF
78 48" Centrifugal Spin ‐ 1.5 Thickness LF
79 54" Centrifugal Spin ‐ 1.5 Thickness LF
80 60" Centrifugal Spin ‐ 1.5 Thickness LF
81 66" Centrifugal Spin ‐ 1.5 Thickness LF
82 72" Centrifugal Spin ‐ 1.5 Thickness LF
83 Add Cost Per 0.5 Thickness ‐ 30" LF
84 Add Cost Per 0.5 Thickness ‐ 36" LF
85 Add Cost Per 0.5 Thickness ‐ 42" LF
86 Add Cost Per 0.5 Thickness ‐ 48" LF
87 Add Cost Per 0.5 Thickness ‐ 54" LF
88 Add Cost Per 0.5 Thickness ‐ 60" LF
89 Add Cost Per 0.5 Thickness ‐ 66" LF
90 Add Cost Per 0.5 Thickness ‐ 72" LF
Spin Cast Lining
Includes Pre & Post TV & typical point repairs during lining Includes Cleaning (greater than 25% full)
91 30" Centrifugal Spin‐ 1.5 Thickness LF
92 36" Centrifugal Spin ‐ 1.5 Thickness LF
93 42" Centrifugal Spin ‐ 1.5 Thickness LF
94 48" Centrifugal Spin ‐ 1.5 Thickness LF
95 54" Centrifugal Spin ‐ 1.5 Thickness LF
96 60" Centrifugal Spin ‐ 1.5 Thickness LF
97 66" Centrifugal Spin ‐ 1.5 Thickness LF
98 72" Centrifugal Spin ‐ 1.5 Thickness LF
99 Add Cost Per 0.5 Thickness ‐ 30" LF
100 Add Cost Per 0.5 Thickness ‐ 36" LF
101 Add Cost Per 0.5 Thickness ‐ 42" LF
102 Add Cost Per 0.5 Thickness ‐ 48" LF
103 Add Cost Per 0.5 Thickness ‐ 54" LF
104 Add Cost Per 0.5 Thickness ‐ 60" LF
105 Add Cost Per 0.5 Thickness ‐ 66" LF
106 Add Cost Per 0.5 Thickness ‐ 72" LF
Spin Cast Lining for Drainage Boxes
107 48" Drainage box VF
108 60" Drainage box VF
109 72" Drainage box VF
Precast Headwalls (per GDOT Std ) 110 Precast Headwall for 18" Pipe EA
111 Precast Headwall for 24" Pipe EA
112 Precast Headwall for 30" Pipe EA
113 Precast Headwall for 36" Pipe EA
114 Precast Headwall for 42" Pipe EA
115 Precast Headwall for 48" Pipe EA
Cast‐In Place Concrete Headwall 116 Cast‐n‐Place Conc HW‐GDOT Det 1125 CY
Rubble Masonry HW 117 Rubble Headwall for 18" Pipe EA
118 Rubble Headwall for 24" Pipe EA
119 Rubble Headwall for 30" Pipe EA
120 Rubble Headwall for 36" Pipe EA
Miscellaneous Items 121 Stone #57 Ton
122 Surge Stone Ton
123 No.3's and 4's Stone Ton
124 Reset Existing Headwall EA
125 3000psi Concrete CY
126 Flowable Fill CY
Site Preparation 127 Traffic Control LS project‐by‐project basis
128 Erosion and Sediment Control LS project‐by‐project basis
Landscaping and Restoration 129 Tree Removal LS project‐by‐project basis
130 Clearing and Grubbing SY
131 Sod Restoration SF
Lump sum items will be determined on a project by project basis and include but not be limited to erosion control, landscaping, traffic control, special internal and external point repairs, pumping operations, ground penetrating radar and pressure grouting. These items will be included with proposals prior to each purchase order for lining projects.
NOTES
All unit prices shall include but not be limited to all mobilization, labor, equipment and materials necessary to perform the work. In addition, unit prices for pipe lining shall include typical point repairs, pre and post CCTV, and cleaning (less than
25% full & greater than 25%).
| Q&A Document 1.pdf |
| Questions & Answers - 1 |
| Text1: Pricing shall be valid for 3 years from issuance of the Notice to Proceed. Line 129, 128 and 129 will be on a project-to- |
| Text2: project basis and Contractor shall submit pricing at time of issuance of a Task Order. |
| Text3: Firm Name:_____________________________________________________ Date:__________________ |
| Text4: Authorized Agent:______________________________ Signature__________________________________ |
Other files
| File | Type | Posted |
|---|---|---|
| 21-236 Bid Packet | — | |
| Award Information | — | |
| 21-236 NOIA | — | |
| 21-236 Sample Contract | — | |
| 21-236 Received Proposals List | — | |
| 21-236 Addendum 1 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .