MT 2453 QAs.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
Main Treasury Demo Build Out 2453
Solicitation number
2032H326R00020
Issued by

About this file

This file is a Questions and Answers (Q&A) document for the Main Treasury Demo Build Out 2453 project, addressing 74 contractor inquiries regarding scope, specifications, site logistics, and project requirements.

Project Scope and Site Requirements: The project involves demolition and build-out of office space in Room 2453 of the Main Treasury building. Work hours are 7:00 AM to 3:30 PM, Monday through Friday, excluding government holidays, with work commencing within one calendar day of Notice to Proceed. All contractor personnel must be U.S. citizens and will display driver's licenses daily for site access; no PIV badges will be issued. Material laydown and storage occur within the work space under construction. A dumpster may be staged in the Main Treasury moat during construction, and the freight elevator is available for material transport. No on-site parking is available for contractors.

Scope of Work Details: The contractor is responsible for erecting temporary Zip Walls or equivalent to contain the construction area, demolishing non-original partitions and clerestory windows per demolition drawings, repairing plaster ceiling damage in Room 2453 only, removing and disposing of existing carpet and replacing it with Shaw Sculpt Clay carpet tiles (83761), installing new wall partitions to the underside of the existing ceiling, painting walls per the paint schedule (A-601), installing new casing and hardware for door 2453-E per specifications A-503 and A-602, and installing one new fire alarm combination speaker/ADA strobe device. Existing crown molding (plaster), baseboard, windows, and door casings require painting but not replacement. The government will clear furniture before construction and provide site visits to identify plaster repair requirements. Out-of-Scope Work: Power and data floor box relocation and installation, electrical work, HVAC, plumbing, sprinkler relocation, and fire alarm system modifications beyond the single new device installation are performed by the government's in-house team and are excluded from contractor scope. Bonding and Staffing: Performance and payment bonds are not required as the project cost is below FAR simplified acquisition thresholds. Staffing requirements include a Project Manager, Superintendent, and Site Safety and Health Officer (SSHO), with the Superintendent potentially serving dual roles as SSHO if qualified; the Project Manager and Superintendent must be separate individuals. No Buy American exceptions apply to construction materials.

View the file

Other files

File Type Posted
A001.pdf PDF
Wage Determination.pdf PDF
Schedule MT2453.docx DOCX document
APU No. 26-01 - Attachment 1 - Fillable.pdf PDF
2032H326R00020.pdf PDF
Main Treasury 2453 New Office Drawings.pdf PDF
Corporate Experience Worksheet.docx DOCX document
APU No. 26-01 - Attachment 2 - Fillable.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

1Badging / Site Access: What is the process, lead time, and point of contact for submitting contractor personnel for PIV-1/PIV-2 vetting and OSP approval? Given the requirement that work commence within 1 calendar day of Notice to Proceed, we want to ensure our mobilization schedule accounts for the actual vetting timeline.
ANSWERNo PIV badges will be issued. All workers must be US Citizens. You will show your Drivers License everyday as you enter the building and receive a contractor's badge.
2Laydown / Material Storage: Is a specific laydown or material storage area available for this project? If so, please provide its location, size, and access schedule. If none is pre-identified, please confirm the process and timing for requesting one through the COR.
ANSWERThe laydown/ material storage area is the work space under construction.
3Dumpster / Debris Removal: Is there an approved location or process for staging a construction debris dumpster or roll-off container on site? If a dumpster is not permitted, please confirm whether all C&D debris should be bagged/carted and removed via the shared loading dock, and any associated scheduling requirements
ANSWERYou can bring a dumpster into the Main Treasury moat during construction.
4Can a dumpster be placed on site for the construction?
ANSWERYou can bring a dumpster into the Main Treasury moat during construction.
5Where can items that have been removed and are to remain be stored?
ANSWERThe storage area is in the work space under construction.
6Will the elevator be able to be used for moving materials?
ANSWERThe freight elevator will be used for moving materials.
7Any molding that needs to be restored or reproduced, can it be made of composite material?
ANSWERNo.
8What is the existing moldings material made of?
ANSWERThe existing moldings are plaster.
9The base molding that was used on the existing added walls does not match the original base. Can the newer base molding be used on the new walls?
ANSWERReference drawing A-301 Key Note 12 for base molding requirements on new walls.
10Will attic stock materials be required?
ANSWERNo attic stock materials are required.
11Will the Government clear the furniture and belongings from the work area before construction begins?
ANSWERYes the government will clear the furniture from the work area before the contractor begins.
12Can contractors leave and return during work hours?
ANSWERYes.
13Will a systems furniture floor plan with dimensions be provided?
ANSWERThe telecom/ data work will be performed by Treasury's in-house team. Not included in this scope of work; therefore, no system furniture floors plan will be necessary to provide for the floor box layouts.
14Are we adding data conduit back to the data rooms for the new floor boxes or are there cable trays already installed?
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
15If we are adding conduit or wire where is the data room located?
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
16Are we to provide data wiring and devices?
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
17What is the manufacturer of the current fire alarm system installed?
ANSWERConvergent.
18Are we to provide fire alarm drawings and load calculations for the addition of the one new speaker/strobe device?
ANSWERNo.
19The Demolition drawings show that there are 17ea. existing floor boxes, but the new work drawings show 18ea. Please confirm the correct quantities.
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
20Are we adding 4 or 5 new floor boxes?
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
21Please provide the specification information What type of floor box specked for this?
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
22Where can Contractor park vehicles?
ANSWERThere is no parking on site.
23Where can Contractor stage materials and tools?
ANSWERThe laydown/ material storage area is the work space under construction.
24Where can Contractor stage dumpster?
ANSWERYou can bring a dumpster into the Main Treasury moat during construction.
25Please confirm that the Working hours will be 7am to 3:30pm Monday through Friday except for Government Holidays?
ANSWERCorrect.
26Will performance and payment bonds be required for this project?
ANSWERNo. The cost of this project is below the FAR simplified threshold requirements for bonds.
27Please provide the specifications, including wood species of the existing crown molding?
ANSWERReference Key Note 1 on A102. Historic existing crown molding and rib molding to remain. New partitions should be build as per the wall sections to avoid damaging the historic elements.
28Is it known why there is plaster damage? As per drawings sheet number AD102?
ANSWERIt is not necessary for you to determine why the plaster was damaged. The contractor's responsibility is simply to repair or replace the damaged plaster.
29Please provide specifications of new carpet tiles to install?
ANSWERShaw / Sculpt / Clay – 83761
30Does the existing door need to be replaced with new?
ANSWERVoid note AD-201/AD-202 to reuse the existing door assembly. Provide a new door/frame/hardware per A-503 & A-602 for door 2453 - E.
31Does the existing baseboard need to be replaced with new?
ANSWERNo. Reference Note 12 on Drawing AD201. Existing baseboard to remain unaltered.
32Please confirm that the constructing of new wall partition are to go up to existing ceiling vault or above existing ceiling?
ANSWERNew partition wall goes to underside of existing ceiling. Reference Key Note 1.c on drawings A2-201.
33If need to go above existing ceiling with new wall partition, then repairs to ceiling would have to be conducted, please confirm?
ANSWERNot applicable. New partition wall goes to underside of existing ceiling. Reference Key Note 1.c on drawings A2-201.
34Please confirm that there is no electrical work, including light fixtures for this project, except to PROTECT DURING CONSTRUCTION AND CLEAN AT ITS CONCLUSION?
ANSWERThere is no electrical work in this scope of work for the contractor.
35Please confirm that there is no fire alarm, fire sprinklers, fire suppression work, for this project, except to PROTECT DURING CONSTRUCTION AND CLEAN AT ITS CONCLUSION?
ANSWERReference Key Note 16 on drawings A-101 for one fire alarm device. There is no sprinkler work included in this contract.
36What is the height from the subfloor to floor deck?
ANSWERApproximately 8".
37Please confirm that all walls are to receive new painting?
ANSWERReference Key Note 12 on drawing A-101. Also reference the paint schedule on A601.
38Please confirm that the is to receive new painting?
ANSWERReference Key Note 12 on drawing A-101. Also reference the paint schedule on A601.
39Please confirm that the room is to receive new install carpet tiles?
ANSWERYes the entire space will receive new carpet tiles, reference drawing A101 Key Note 6.
40Please confirm that the quantity one (1) existing door is to receive new casing from inside the room and from hallway side?
ANSWERVoid note AD-201/AD-202 to reuse the existing door assembly. Provide a new door/frame/hardware per A-503 & A-602 for door 2453 - E.
41Please provide specifications on the new baseboard installed at the new wall partitions?
ANSWERReference drawing A-302 Key Note 12.
42What paint color is to be on the new baseboard installed at the new wall partitions?
ANSWERMatch existing baseboard color.
43Please confirm that the following are to be painted, existing CROWN MOLDING, existing BASEBOARD, existing FCU CABINETS, existing WINDOWS, existing DOORS AND existing NICHE)?
ANSWERReference Key Note 12 on drawing A-101. Also reference the paint schedule on A601.
44Please confirm that the Contractor is to install new INSTALL A FIRE ALARM DEVICE COMBINATION SPEAKER AND ADA STROBE DEVICE. WALL MOUNTED CD= CANDELA RATING?
ANSWERYes reference Key Note 16 on drawing A101. Existing fire alarm contractor is Convergent.
45As per Drawings sheet number A-103, states “THE ARCHITECT WILL SURVEY THE FLOOR ONCE CARPET HAS BEEN REMOVE” – if there turns out to be more floor panels to remove and re-install – will this be a change order for additional cost?
ANSWERAny unforeseen or hidden conditions encountered after award will be evaluated by the Contracting Officer. If the condition qualifies under the applicable contract clauses, it will be addressed through a contract modification.
4613 Power/Data boxes relocated per drawing AD101
4 new Power/Data boxes per drawing on A-103
18 total Power/Data boxes per drawing on A-103
Please confirm the total amount of Power/Data boxes that was needed
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
47Please confirm the existing fire alarm system manufacturer and model serving the project area, including the existing fire alarm control panel.
ANSWERThe building fire alarm contractor is Convergent. Install one new fire alarm device combination speaker and ADA strobe wall mounted CD= Candela Rating which can be reviewed and approved in the submittal process.
48Please confirm if bid bond is required with bid submission.
ANSWERNo. The cost of this project is below the FAR simplified threshold requirements for bonds.
49Please provide cable quantities, source locations, termination requirements, testing, and agency standards for pricing.
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
50Please provide electrical scope of work and drawings of existing, demo, and new work.
ANSWERThere is no electrical work in this scope of work for the contractor.
51Please provide FA scope of work and drawings of existing, demo, and new work.
ANSWERThere is no fire alarm demo work. The building fire alarm contractor is Convergent. Install new fire alarm device combination speaker and ADA strobe wall mounted CD= Candela Rating which can be reviewed and approved in the submittal process.
52Drawings indicate existing sprinkler heads are existing to remain. Please confirm if the existing configuration will work with the new room layout and will meet the coverage requirements. new room layout and will meet the coverage requirements.
ANSWERNo sprinkler work is included in this scope of work.
53Please provide HVAC scope of work and drawings of existing, demo, and new work.
ANSWERNo HVAC work is included in this scope of work.
54Please confirm exact quantity of existing power/data boxes to be relocated and new boxes to be provided.
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
55Please confirm if the door hardware is to be ML 2053/Citation CSN or ML 2051 and provide final specifications.
ANSWERReference hardware schedule Type 1 on drawing A-602. The lever entrance set is ML 2053/Citation CSN.
56Please provide the Building Standard paint colors to match.
ANSWERPaint colors are listed on A-601 - Room Finish Schedule.
57Please confirm if new wall is required to be fire rated and identify applicable tested assembly.
ANSWERReference A-302 for Wall Construction Notes and Key Notes.
58What positions are required to submit on Attachment 1 Staffing Plan?
ANSWERProject Manager, Superintendent and SSHO.
59Can any positions dual hat? Such as can the Superintendent also be the QCM / SSHO?
ANSWERYes. The Superintendent may also serve as the Site Safety and Health Officer (SSHO), provided they meet all applicable qualifications for both roles. However, the Project Manager and Superintendent must be separate individuals.
60Can we please have an extension for proposal submission?
ANSWERNo because we need time to proper review all the proposals and award before 9/30.
61Plaster ceiling repair extent is not quantified. AD-102 Key Note 2 and A-102 Key Note 3 both state "plaster damage to be repaired as indicated," but only one location (Vault 5) is documented/photographed. A-201/A-202 Key Note 16 further limits refinishing to areas "where the existing finish is failing" — a qualitative, not measured, criterion. Please provide a plaster condition survey/quantity takeoff, or a unit price / allowance for plaster patching, so this item can be priced consistently.
ANSWERVoid the Vault 5 location. The plaster ceiling repairs are only in Room 2453. The Architect just used the photo since it showed the typical ceiling conditions. The site visit showed the space and the repairs required.
62Door 2453-E instructions conflict between sheets. AD-201/AD-202 note the existing door assembly may be reused "if in good condition and approved by Treasury's COR," while A-503 provides full fabrication details for a new wood door/frame (Frame Type F-1, Leaf Type A) built to match door "2453-B." Please confirm whether door 2453-E is (a) the existing door salvaged and reinstalled, or (b) new fabrication per A-503, and clarify the COR approval timeline given procurement lead time.
ANSWERVoid note AD-201/AD-202 to reuse the existing door assembly. Provide a new door/frame/hardware per A-503 & A-602 for door 2453 - E.
63Existing carpet disposition appears to conflict between sheets. AD-101 General/Demolition Notes direct removal and disposal of existing carpet, with new carpet tile (C-1) installed per the A-601 finish schedule, while other demolition notes reference storing floor panels/carpet on site for reinstallation after wall construction. Please confirm existing carpet throughout Suite 2453 is fully removed and disposed of (not salvaged/reinstalled), with new C-1 carpet tile installed suite-wide.
ANSWERProvide new carpet tiles in the entire space. Building standard is Shaw / Sculpt / Clay – 83761.
64Please confirm the scope of window blind work at the clerestory windows referenced in the AD-201 Key Notes ("reinstall window blinds if they were removed"). Specifically, confirm whether existing blinds are to be reused/reinstalled as-is at all affected windows, or whether new blinds are required at any location (e.g., at the new partition location or where clerestory windows are being demolished).
ANSWERExisting window blinds are to remain. Protect in place.
65Can the government confirm if it would like contractors to provide temporary partitions to contain and secure the construction area in room 2453, including a locking door secured by keypad?
ANSWERPer Key Note 1 on AD101 erect Zip Walls or equivalent.
66Per drawing sheet A-101, Key Note 16, please provide the specifications for the fire alarm device combination speaker and ADA strobe device.
ANSWERThe building fire alarm contractor is Convergent. Install new fire alarm device combination speaker and ADA strobe wall mounted CD= Candela Rating which can be reviewed and approved in the submittal process.
67Per drawing sheet A-1-3, Key Note 4, please provide the specifications for the new power and data boxes.
ANSWERThe power and data floor boxes (relocation and new boxes) will be performed by Treasury's in-house team; therefore, not in the contractor's scope of work.
68FAR 52.225-9(b)(2) and 52.225-11(b)(3) both leave the "excepted materials" blank ("Contracting Officer to list applicable excepted materials or indicate 'none'"). Please confirm whether any construction materials (e.g., specialty fire-rated glazing, historic-match hardware, access floor components) are excepted from the Buy American domestic content requirement, or whether "none" applies.
ANSWERNo exceptions to the Buy American Act.
69Sheets AD101, A-103, and A-502 note repeatedly: "Due to the presence of carpet, the floor panel system has not been surveyed... adjustments will be necessary. The architect will survey the floor once carpet has been removed." Given the LPTA/lump-sum pricing structure, please confirm: (a) will a post-demo floor system survey be issued as a design bulletin/RFI response prior to bid, or (b) should offerors carry a contingency allowance, and if so, is a specific allowance amount to be included in the price schedule?
ANSWERAny unforeseen or hidden conditions encountered after award will be evaluated by the Contracting Officer. If the condition qualifies under the applicable contract clauses, it will be addressed through a contract modification.
70Sheets AD101, AD201, A-201–A-204 all include the note: "NOTE: If door assembly (door leaf + frame) is in good condition and it is approved by Treasury's COR, keep the assembly on site door to be reused at new office location." This creates a contingent scope item (reuse existing door/frame vs. new Frame Type F-1/Door Type A per A-503/A-602) that cannot be priced with certainty. Please confirm whether the Government will make this determination prior to proposal due date, or advise how offerors should price this contingency (e.g., unit price alternate, allowance).
ANSWERVoid note AD-201/AD-202 to reuse the existing door assembly. Provide a new per A-503 for door 2453-E.
71General Note 4 on multiple sheets states "protect all historic fabric... do not remove historic fabric unless specifically noted." Note 1 (AD101/AD201/AD202) separately calls for demolition of "non-original" partitions, baseboards, and clerestory windows. Please confirm the Government's/SHPO's determination of which specific existing elements (e.g., partition at Grid B/2453-E, clerestory windows) are classified as non-original and cleared for removal, versus historic fabric requiring COR sign-off before disturbance, since misclassification carries schedule/cost risk under the historic preservation clauses.
ANSWERFollow the Demolition and Protection notes on AD101.
72The drawings state existing sprinkler heads are to "remain unaltered" and be protected during construction, but new full-height partitions (Wall Type A/B) are being constructed under an existing open sprinkler layout (see AD102 RCP, A-102). Please confirm whether the Government's fire protection engineer has verified that existing sprinkler head spacing/coverage remains code-compliant (NFPA 13) once new partitions divide the space, or whether relocation/additional heads are anticipated — this scope is not shown on any drawing (no FP drawings were issued).
ANSWERNo sprinkler work is included in this scope of work.
73The drawing index (G-001) lists only General and Architectural disciplines (21 sheets total); no Mechanical, Electrical, Plumbing, or Fire Protection drawings were issued, despite: (a) a new fire alarm device requiring circuit connection, (b) existing FCUs to remain but requiring protection/covering, and (c) new floor boxes (power/data) shown on A-103. Please confirm whether MEP scope is: (a) not part of this contract (NIC), (b) design-build/performance-spec based on offeror's approach, or (c) missing drawings that will be issued via amendment.
ANSWERThere is no mechanical, electrical or plumbing work in this scope of work only one fire alarm device. The building fire alarm contractor is Convergent. Install new fire alarm device combination speaker and ADA strobe wall mounted CD= Candela Rating can be reviewed and approved in the submittal process
74SOW states normal work hours are 7:00 AM–3:30 PM, Monday–Friday, and that "all building systems outside the immediate construction area shall be kept fully operational during normal working hours," while the suite is located within an occupied historic office building. Please confirm whether any noise/vibration-generating activities (e.g., anchor drilling into ceiling, demolition) must be scheduled outside normal business hours or on weekends with COR approval, given proximity to occupied adjacent offices (2449, 2457, Electrical Closet
ANSWERThe working hours are 7am to 3:30pm for all work.