This document is an Amendment of Solicitation/Modification of Contract for canine detection services issued by the Bureau of Engraving and Printing. The amendment extends the questions due date to November 17, 2025, and the solicitation due date to November 21, 2025. Key changes include increasing the number of site visits from 244-312 to 260-328 per performance period, and modifying the hours calculation from 46 weeks at 4 hours per week to 52 weeks at 10 hours per week, totaling 520 hours. The solicitation specifies that a site visit consists of a minimum of two hours of detection services, with pricing to be submitted based on 12 months and a quantity of 12 months in Section B of the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF CHANGES:

1. Extend the questions due date to November 17, 2025 at 4:00 PM Central Standard Time.

2. Extend the solicitation due date to November 21, 2025 at 4:00 PM Central Standard Time.

3. Update section 1.6.5.A of the Performance Work Statement as follows:

From: Canine detection services will consist of 244 to 312 site visits per period of performance.

To: Canine detection services will consist of 260 to 328 site visits per period of performance.

From: Total: 244 Days Usage Estimation: 232 Days = 46 Weeks / 46 Weeks @ 4Hours per Week (184 Hours) /*12 Days @ 6Hours per Day (72 Hours)/ (*Visitor Center Special Events) To: Total: 260 Days Usage Estimation: 260 Days = 52 Weeks / 52 Weeks @ 10 Hours per Week (520 Hours).

Questions and Answers

1. Please confirm the number of hours I should use when I submit the price sheet (Section B of the solicitation)?

Government response: See SF 1449 Section B - Supplies or Services and Prices/Costs lists quantity of 12 and Unit of Measure as Month.

2. Do I multiply by 250 hours/annually?

Government response: See SF 1449 Section B - Supplies or Services and Prices/Costs with quantity of 12 and Unit of Measure as Month. See section 1.6.5.A “Total: 260 Days Usage Estimation: 260 Days = 52 Weeks / 52 Weeks @ 10 Hours per Week (520 Hours).”

3. Is it at least a minimum of 4 hours per site visit?

Government response: See Performance Work Statement section 1.6.5.A, “A site visit shall consist of a minimum of Two (2) hours detection services when team is deployed.”

END OF DOCUMENT

2031ZA26R00003 0003
Summary of Changes 0003