Attachment 2 - Sole Source Justification.pdf
PDF 383 KB Posted
- Solicitation number
- 2027-LGD-0061
- Issued by
-
Library of Congress
About this file
This is a Justification and Approval for Other than Full and Open Competition document from the Library of Congress (Plan ID: 2027-LGD-0061) supporting a sole-source contract award.
The Library of Congress seeks contractor support for mass deacidification of bound volumes printed on acidic paper to prevent deterioration and brittleness. The contractor will select volumes onsite, inventory them in the Library's integrated library system, pack and ship materials offsite for treatment, and return treated volumes for reshelving. The contract is awarded to Preservation Technologies, LP (PTLP), the sole identified vendor capable of performing this specialized service in the United States. The estimated contract value is $600,000 for a 12-month period of performance from April 1, 2027 through March 31, 2028. The justification cites FAR 6.302-1(b)(1), establishing that only one responsible source exists and no other supplier can satisfy the Library's requirements. Historical evidence supporting sole-source status includes successful PTLP performance since 2001, previous sole-source awards in 2005 and 2016, and multiple market research efforts and competitive solicitations conducted in 2013, 2021, 2022, 2023, 2024, 2025, and 2026 that yielded no competing proposals. While a European company possesses capability, shipping fragile collections internationally presents unacceptable risks and administrative burdens. The Library certified that advance notice will be published on sam.gov for 15 days prior to award, and the Contracting Officer determined pricing is fair and reasonable based on historical prices paid by the Government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Statement of Work (SOW).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval For Other than Full and Open Competition
Plan ID Number: 2027-LGD-0061
Form Updated 4/14/2023
Justification & Approval
As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.
This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.
This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.
1. Contracting Agency and Activity: Library of Congress, LCSG/DPS/PRES/PSD
2. Nature of Action Being Approved
3. Description of Supplies or Services Required to Meet Library Needs Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.
The Library requires the following supplies or services: The Library of Congress requires contractor support for mass deacidification of bound volumes primarily printed on acidic paper. Librarians and archivists have been aware of the worldwide preservation problems that began in the mid- 1800s when acidic wood pulp was substituted for cotton rags in the manufacture of paper. The introduction of wood pulp and chemicals in the manufacturing process resulted in printed volumes produced with acidic paper stock which, without intervention, becomes brittle and unusable over time. The objective of mass deacidification is to neutralize the acid components of paper before the paper become brittle. While the Library of Congress mainly uses cold storage to prevent ongoing acidification, other methods have been employed as well, such as mass deacidification of the collections themselves.
The objective of this contract is to treat volumes that are found to be acidic with a process which will neutralize acid in paper. Volumes will be selected onsite by contractor staff, inventoried in the Library’s ILS for documentation and tracking, packed for shipment offsite, treated offsite, returned and reshelved.
The only known business performing this service in the United States is Preservation Technologies, LP.
Contract (or modification) LoC or Leg Branch Order (or modification) GSA Schedule or GWAC: Identify Schedule/Contract Other: Identify
Plan ID Number: 2027-LGD-0061 Contractor (or Brand Name): Preservation Technologies, LP Estimated Value (Base and all options): $600,000.00 Period of Performance: 04/01/2027 – 03/31/2028, One 12-month period of performance – stand alone contract (not an IDIQ)
Part 1 – Identification
Plan ID Number:
Form Updated 12/10/2025
4. Authority for Contracting Without Competition Over $350,000 For this requirement over $350,000, under FAR part 6, the basis for contracting without providing for full and open competition is:
There is only one responsible source and no other supplies or services will satisfy Library requirements.
41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.
Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).
Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302-
1(b)(2).
Other exception identified in FAR 6.302-1:
There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.
41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.
Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5: LEGISLATIVE BRANCH APPROPRIATIONS 2027 – While the appropriations have not yet been identified, it is assumed that the Library will receive appropriated funds as we have for years. As a result, this is anticipated to be appropriate funding legislation. If it is *not* approved, then the award based off the upcoming funds will not occur. No award will be made without congressionally approved funds.
Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302:
Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
Up to and including $350,000 For this requirement up to $350,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:
Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.
Product or service is reasonably available from only one source.
Source controls copyrights, patents or other exclusive licensing arrangements.
Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.
Source is expressly authorized or required by statute: Identify the authority
Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:
An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.
FAR 8.405-6(a)(1)(i)(A).
Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).
In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).
Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)
Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:
The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).
The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR
16.505(b)(2)(i)(B).
A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).
To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).
Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).
The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41
U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
Part 2 – Program Office Justification & Approval
5. Rationale for Contracting Without Competition In supporting an action not providing for full and open competition, it is not sufficient to demonstrate that the contractor is exceptionally well qualified or even the best qualified, or that the required brand name product is well suited to the Library’s needs. The rationale must demonstrate that no one else, or no other competing product, can satisfactorily fulfill the Library’s requirement. Do not focus on the importance of the requirement; the issue is the rationale for not competing.
In supporting urgency, address the following: What are the unexpected facts or the unpredictable events that led to this situation? When is the required delivery or performance start date? Why this date? What specific harm to the Government will occur if the delivery is not made or performance not begun as scheduled? (Note that expiration of funds is not sufficient harm to justify not competing.) Demonstrate that the contract is only for items and quantities urgently needed until a competitive procurement action can be developed, or that a separate competitive follow-on is not practical.
In supporting a brand name justification, the brand name or feature must be essential to the Library’s requirements, and market research indicates that other company’s similar products or products with similar features cannot meet or be modified to meet the Library’s needs.
We are authorized to limit competition on the basis of the citation in section 4 because:
In accordance with FAR 6.302-1 (b)(1) only one responsible source and no other supplier will satisfy the Agency’s requirements.
The Library has a documented history with this requirement and its sole source nature. Preservation Technologies Limited Partnership (PTLP) has been the sole vendor for mass deacidification services at the Library of Congress since 2001. Historical information is provided below.
• This service was awarded as a sole source in 2005 (LSP20050085) and in 2016 (LSP20150082) to PTLP.
• Market research and RFIs performed in 2013 (LCLSP13R0004) and 2021 (030ADV21R0066), 2023-2024 (LCLGD23C0002) 2024-2025 (LCLGD25C0001), and 2025-2026 (LCLGD26C0002) yielded no other viable sources and no other bids beyond the bids provided by PTLP. There is a European Company with the capability to perform the required work, however, shipment of fragile Library materials to another country would endanger collections and require additional administrative overhead for transport, such as customs declarations, additional shipping costs. PTLP is located in Pennsylvania and can safely and quickly transport and treat materials. In addition, the European business has never actually expressed any interest in performing the work.
• In 2022, the requirement was publicly competed on SAM. No businesses other than PTLP provided a proposal.
• In 2023, the contract was extended by 12 month period. When the J&A was posted for this modification, no businesses other than PTLP provided a proposal.
• In 2024, the contract was again extended by 12 months. When the J&A was posted for this modification, no businesses other than PTLP provided a proposal.
• In 2025, the contract was awarded as sole source (LCLGD25C0001) to PTLP. When the J&A was posted for this modification, no businesses other than PTLP provided a proposal.
• In 2026, the contract was awarded as sole source LCLGD26C0002 April 1, 2026 - March 31, 2027 - services procured for mass deacidification from Preservation Technologies, LP.
PTLP is the only vendor that can provide the requirements needed to continue the program, and the Library will award a sole source award to PTLP under FAR 6.302-1(b)(1). Other than PTLP and the European business, there are no other businesses on Earth that the Library is aware that can fulfill these congressionally mandated requirements. This has been demonstrated many times through the execution of this requirement.
As a result, the Library must sole source the requirement to PTLP.
6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required State what actions, if any, the program office can take to overcome barriers to competition before a contracting for this requirement again, such as:
using action to provide time to develop specifications for a competitive procurement by a certain date; licensing copyrights or patents so other contractors may use the works; or breaking the requirement into parts that may be purchased competitively. If this is a one-time requirement, explain that action to increase future competition is not needed. If the source is expressly required by statute, state “Source is statutory.”
To increase competition, we will: The Library of Congress has encouraged the research and testing of alternative processes for deacidification and has shared research broadly. To date, no company has expressed interest in developing the capability that LOC requires for treatment of collections. No other businesses in the United States performs this work. No actions can be done to increase competition.
7. Program Office Certification I certify that the description of the Government’s minimum needs, schedule requirements, and technical information that provide the basis for this justification are accurate and complete.
Supervisory Program G_ regory Cooper
Name Management Specialist/ COR
Title Signature 9/21/2026
Date
8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.
Advance notice will be published in sam.gov for 15 days before a contract is awarded. FAR 5.203(a).
Advance or concurrent notice will be published in sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).
Advance notice will not be published because the action meets the following FAR exception:
Notice would compromise national security. FAR 5.202(a)(1).
Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).
Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).
Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).
Order will be placed against GSA schedule or other competitively-awarded contract. FAR 5.202(a)(11).
Other:
Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.
We made the following efforts to interest potential sources in this award: N/A – But the public posting of this solicitation will serve as the Library’s public query, as well as serve as the notice of intent to sole source.
9. Listing of Sources That Expressed Interest in Writing The following sources expressed interest in this award: N/A – But the public posting of this solicitation will allow other potential vendors to express an interest in this award.
10. Additional Information The following additional information is relevant to this justification and approval: N/A
11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):
Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other: Prices obtained through competitive proposals
The following analysis (based on attached pricing information) supports my determination:
12. Contracting Officer Determination of Responsibility
Checked System for Award Management (or will check in the case of competitive proposals for a brand name product) – SAM will be checked before an award is made.
13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because: A best-value determination shall be made before an award is executed.
14. Contracting Officer Certification I certify that, to the best of my knowledge and belief, this justification is accurate and complete. For those actions up to $900,000, I approve contracting without competition for this requirement.
James R. Robinson
Name
Signature
Date
0BPART 3 – CONTRACTING OFFICER DETERMINATIONS & CERTIFICATION
| Justification & Approval |
| 2. Nature of Action Being Approved |
| 3. Description of Supplies or Services Required to Meet Library Needs |
| GSA Schedule Order |
| Order Under Multiple Award Indefinite-Delivery Contract or GWAC |
| 5. Rationale for Contracting Without Competition |
| 6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required |
| 7. Program Office Certification |
| 8. Efforts to Solicit from As Many Potential Sources As Practicable |
| 9. Listing of Sources That Expressed Interest in Writing |
| 10. Additional Information |
| 11. Contracting Officer Determination that Price Is Fair and Reasonable |
| 12. Contracting Officer Determination of Responsibility |
| 13. Contracting Officer Determination of Best Value |
| 14. Contracting Officer Certification |
| 2026-11-17T15:06:04-0500 | |
| Robinson, James |
File details come from the government source that posted it. Updated .