This file is a sidewalk spray location list prepared by the Ada County Highway District (ACHD) in Idaho for the 2027 Roadside, Sidewalk, and Basin Herbicide Application Services contract opportunity. The document details 34 specific roadside and sidewalk locations throughout the ACHD service area where herbicide application services will be required. The locations are organized by east/west roads and north/south roads, with measurements provided in linear feet and lane miles for each designated area. The total project scope encompasses 1,460,384 linear feet across 276.59 lane miles of sidewalks and roadsides requiring treatment. The selected contractor will be responsible for furnishing all qualified personnel, equipment, herbicides, traffic control, documentation, and related services necessary to control noxious and nuisance vegetation in compliance with all applicable federal, state, and local regulations. A voluntary pre-submission meeting and proposal workshop is scheduled for November 10, 2026, from 10:00 a.m. to 11:00 a.m. at ACHD Headquarters in Boise, Idaho.
Proposals will be evaluated based on cost, qualifications, experience, and the respondent's demonstrated ability to safely and effectively perform the required herbicide application services. The document does not specify pricing terms, set-asides, funding sources, or contract duration details. Attendance at the voluntary pre-submission meeting is not a condition of proposal responsiveness, though prospective respondents are strongly encouraged to participate to gain guidance on preparation and submission requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sidewalk Spray Locations
East/West Roads Feet Lane Miles
Floating Feather Between Pimlico Rd to Eagle Rd 12,088.00 2.29
Hill Rd between Horseshoe Bend Rd to Bogus Basin Rd 68,476.00 12.97
McMillan Rd between Black Cat and Maple Grove 84,474.00 16.00
Cherry Lane/Fairview between McDermott and N Bluff 118,246.00 22.40
Pine/Executive/Emerald between Ten Mile to Latah 88,550.00 16.77
Franklin between Black Cat and Vista 128,140.00 24.27
Overland between Ten Mile and Federal Way 124,562.00 23.59
Victory between Linder and Orchard St 90,080.00 17.06
Lake Hazel between Locust Grove and Eagle Rd 10,820.00 2.05
Parkcenter between Bown St to Warm Springs 8,062.00 1.53
Federal Way between Bergeson to Gowen 24,668.00 4.67
W Boise between Linder and Ten Mile 10,456.00 1.98
Ustick Rd from Curtis Rd to Black Cat 86,092.00 16.31
E Porter between Linder and Kaye 5,114.00 0.97
North/South Roads
Black Cat between Victory and Chinden 63,384.00 12.00
Ten Mile between Victory and Chinden 63,384.00 12.00
Linder between Franklin and Chinden 50,032.00 9.48
Locust Grove between Victory and Chinden 64,974.00 12.31
Eagle Rd between Amity and Overland 21,350.00 4.04
Cloverdale between Victory and Chinden 52,732.00 9.99
Five Mile between Victory and Chinden 62,646.00 11.86
Maple Grove between Victory and Chinden 59,752.00 11.32
Cole Rd between Lake Hazel and Mountain View 73,250.00 13.87
Orchard between Victory and Chinden 32,474.00 6.15
Vista between Wright St and Rose Hill 23,780.00 4.50
Meridian Road between from Pine Rd to Chinden Blvd 29,834.00 5.65
Protest Hill between Federal Way and Boise Ave 2,964.00 0.56
Total: 1,460,384.00 276.59