This is a Request for Proposal (RFP) issued by the Ada County Highway District (ACHD) in Boise, Idaho, for 2027 Roadside, Sidewalk, and Basin Herbicide Application Services. ACHD seeks qualified firms to provide herbicide application services for vegetation control within ACHD-owned or maintained public rights-of-way and stormwater facilities, including initial and follow-up treatments along roadsides, sidewalks, stormwater basin perimeters, upland areas, basin side slopes, and access roads. Respondents must furnish all qualified personnel, equipment, herbicides, traffic control, and documentation in compliance with federal, state, and local regulations and safety and environmental standards. The solicitation includes six cost schedule line items covering roadside initial applications (1,522 lane miles), sidewalk initial applications (277 lane miles), basin initial applications (1,034,918 square feet across 53 locations), and corresponding follow-up/breakout services for each category, plus authorized additional spot applications on a crew-hour basis. A voluntary pre-submission meeting and proposal workshop is scheduled for November 10, 2026, at 10:00 a.m. at ACHD Headquarters. Sealed proposals must be submitted electronically through ACHD's eProcurement Portal by 3:00 p.m. (local time) on Wednesday, November 18, 2026, at which time proposals will be publicly opened via Zoom. The question submission deadline is November 11, 2026, at 4:00 p.m., with responses due November 12, 2026, at 4:00 p.m. Contract award is anticipated following proposal evaluation, with the successful bidder required to execute the agreement within 15 days of award.

Pricing is to be submitted as firm costs with unit prices and total costs for each line item in the cost schedule; no cash discounts are permitted. The quantities listed in the cost schedule are approximate and prepared for proposal comparison purposes; ACHD reserves the right to increase, decrease, or omit scheduled quantities and may place multiple orders throughout the agreement duration and elect to extend the contract term. No specific set-asides are designated in this solicitation. Upon award, the successful bidder may be required to furnish supply, material, payment, and performance bonds, each in an amount equal to 100 percent of the total contract value; however, no bonds are required at the time of bid submission. Proposals are evaluated using a weighted scoring methodology (0-5 points) across five criteria: Proposal Cost (30 percent weight), Firm History, Experience and References (15 percent weight), Firm Qualifications and Key Personnel (20 percent weight), Project Approach and Understanding (30 percent weight), and Disputes, Claims with ACHD or Notices of Insufficient Work (5 percent weight). The contract will be awarded to the highest-ranked responsive firm that best meets the specifications. Respondents must acknowledge their DBE status and comply with ACHD Policy for Equal Employment Opportunity and Title 49 CFR Part 21 Non-Discrimination Statement requirements. ACHD assumes no responsibility for costs incurred by respondents prior to purchase order or agreement execution and reserves the right to reject any or all proposals or waive informalities in its best interest.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ada County Highway District

5800 North Meeker Avenue – Boise, ID 83713 Phone (208) 387-6100 - FAX (208) 345-7650

Website: www.achdidaho.org

2027 Roadside, Sidewalk, and Basin Herbicide Application

Services

MO27-13

Contract Documents November 3, 2026

Miranda Gold, President Alexis Pickering, Vice-President Kent Goldthorpe, Commissioner http://www.achdidaho.org/

Request For Proposal #MO27-13 Title: 2027 Roadside, Sidewalk, and Basin Herbicide Application Services

Dave McKinney, Commissioner Patricia Nillson, Commissioner Ryan Head, Director

Ada County Highway District

REQUEST FOR PROPOSAL

MO27-13

2027 Roadside, Sidewalk, and Basin Herbicide Application

Services

I. NOTICE

II. INTRODUCTION

III. INSTRUCTIONS TO RESPONDENTS

IV. ADDITIONAL RESPONDENT INFORMATION

V. SCOPE OF WORK

VI. EVALUATION PHASES

VII. VENDOR QUESTIONNAIRE

VIII. COST SCHEDULE

Attachments:

A - SCOPE OF WORK

B - Sidewalk Spray Location Map C - 2027 Sidewalk Spray Location List D - 2027 Storm Basin List E - Pesticide Application Record - Sample - For Viewing Purposes Only F - Sample Agreement

NOTICE

Ada County Highway District

REQUEST FOR PROPOSAL

2027 Roadside, Sidewalk, and Basin Herbicide Application Services

MO27-13

Sealed proposals for 2027 Roadside, Sidewalk, and Basin Herbicide Application Services will be received within the Ada County Highway District (ACHD) eProcurement portal, https://procurement.opengov.com/portal/achdidaho, until 3:00 pm (local time), Wednesday, November 18, 2026, at which time the proposals will be publicly opened via Zoom. ACHD will conduct the bid openings scheduled for that date and time individually and in an order established solely by ACHD that best suits its business needs. All proposals must be electronically sealed and submitted via ACHD's eProcurement portal https://procurement.opengov.com/portal/achdidaho. Manual/Paper bids will be deemed non-responsive.

The Ada County Highway District (ACHD) seeks competitive Requests for Proposals (RFP) from qualified Firms to provide Herbicide application services within ACHD-owned or maintained public rights-of-way and stormwater facilities. Services shall include initial and follow-up treatments to control noxious and nuisance vegetation along roadsides, sidewalks, stormwater basin perimeters, upland areas, designated basin side slopes, access roads, and other ACHD-authorized locations. The selected Firm shall furnish all qualified personnel, equipment, herbicides, traffic control, documentation, and related services necessary to perform the work in compliance with all applicable federal, state, and local regulations, safety and environmental standards, and ACHD requirements.

Voluntary Pre-Submission Meeting and Proposal Workshop Prospective Respondents are strongly encouraged, but not required, to attend the Voluntary Pre-Submission Meeting and Proposal Workshop. ACHD will provide general guidance regarding the preparation, submission requirements, and the solicitation process.

Location: ACHD Headquarters – Sawtooth Boardroom 5800 N. Meeker Avenue Boise, Idaho 83713 Date: Tuesday, November 10, 2026, and Time: 10:00 am (Mountain Standard Time) Attendance is voluntary and is not a condition for submitting a Proposal.

All questions or requests for clarification regarding this Request for Proposal (RFP), including the content and requirements of the RFP and Documents, must be submitted in writing through the "Question and Answer" section of the ACHD eProcurement Portal no later than 4:00 pm on Wednesday, November 11, 2026. Questions submitted by any other method, including phone calls, manual delivery or email, will not be accepted, nor will questions be accepted after the designated Question and Answer deadline. Respondents are strongly advised to observe the stated deadline for submitting inquiries. To ensure timely receipt of updates, respondents are encouraged to select “Follow” on this Proposal within the eProcurement Portal to receive automated email notifications when responses are posted.

Notwithstanding such notifications, it remains the sole responsibility of each bidder to monitor the eProcurement Portal for updates and responses regularly. Any interpretation, clarification, or modification of the RFP that may affect its substance will be issued only in writing in the form of an Addendum and will be made available through the eProcurement Portal. It is the Respondent's responsibility to review and acknowledge all Addenda before submitting a Proposal. The Final Addendum will be issued to all registered Respondent Holders no later than 4:00 pm on Thursday, November 12, 2026.

The successful Bidder may be required, upon issuance of the Notice of Award, to furnish supply, material, payment, and performance bonds, each in an amount equal to one hundred percent (100%) of the total Contract value. No such bonds shall be required at the time of bid submission.

https://procurement.opengov.com/portal/achdidaho

ACHD has prepared the RFP Documents, and copies must be obtained from the eProcurement Portal.

ACHD reserves the right to reject all proposals or reject any proposal not conforming to the intent and purpose of the Contract Documents whenever such action appears to be in the best interest of ACHD. Award of a contract pursuant to this procurement may be delayed, without penalty, for up to sixty (60) calendar days after the date of submission.

Dated Tuesday, November 3, 2026

ADA COUNTY HIGHWAY DISTRICT

Dates of Publication: November 3 and 10, 2026

INTRODUCTION

Summary The Ada County Highway District (ACHD) seeks competitive proposals from qualified Firms to provide herbicide application services within ACHD-owned or maintained public rights-of-way and stormwater facilities. Services shall include initial and follow-up treatments to control noxious and nuisance vegetation along roadsides, sidewalks, stormwater basin perimeters, upland areas, designated basin side slopes, access roads, and other ACHD-authorized locations.

The selected Firm shall furnish all qualified personnel, equipment, herbicides, traffic control, documentation, and related services necessary to perform the work in compliance with all applicable federal, state, and local regulations, safety, and environmental standards, and ACHD requirements.

Proposal Evaluation Proposals will be evaluated based on established criteria, including cost, qualifications, experience, and the Respondent's demonstrated ability to safely, lawfully, and effectively perform the required herbicide application services in accordance with the RFP Scope of Work/Specifications.

Voluntary Pre-Submission Meeting and Proposal Workshop Prospective Respondents are strongly encouraged, but not required, to attend the Voluntary Pre-Submission Meeting and Proposal Workshop. ACHD will provide general guidance regarding the preparation, submission requirements, and the solicitation process.

Location: ACHD Headquarters – Sawtooth Boardroom 5800 N. Meeker Avenue Boise, Idaho 83713 Date: November 10, 2026 Time: 10:00 a.m. to 11:00 a.m.

Attendance is voluntary and is not a condition of proposal responsiveness.

Background As written in the Legal Notice, including deadline dates: All questions or requests for clarification regarding this Request for Proposal (RFP), including the content and requirements of the RFP and Documents, must be submitted in writing through the "Question and Answer" section of the ACHD eProcurement Portal.

Questions submitted by any other method, including phone call, manual delivery, or email, will not be accepted, nor will questions be accepted after the designated Question and Answer deadline.

NOTE: Bid Opening Zoom Meeting Link: (The Date and Time are stated in the Legal Notice) Join Zoom Meeting:

BID ZOOM MEETING LINK

Meeting ID: 853 4920 0922 Passcode: 028768

Contact Information Mike Fagerness

Procurement & Contracting Administrator

5800 N Meeker Ave

Boise, ID 83713

Email: mfagerness@achdidaho.org

Phone: (208) 387-6316 Department:

Maintenance Operations

Timeline

Release Project Date November 3, 2026

Dates of Publication November 3 and 10, 2026

Pre-Proposal Meeting (Non- Mandatory)

November 10, 2026, 10:00am Prospective Respondents are strongly encouraged, but not required, to attend the Voluntary Pre-Submission Meeting and Proposal Workshop.

ACHD will provide general guidance regarding the preparation and submission of Proposals.

Location: ACHD Headquarters – Sawtooth Boardroom

5800 N. Meeker Avenue

Boise, Idaho 83713

Date: November 10, 2026

Time: 10:00 a.m. to 11:00 a.m.

Question Submission Deadline November 11, 2026, 4:00pm

Question Response Deadline November 12, 2026, 4:00pm

Proposal Submission Deadline November 18, 2026, 3:00pm https://achdidaho-org.zoom.us/j/85349200922?pwd=dtq8xszPhoE9Sg6Zw9WxR0KcaLRxgM.1 mailto:mfagerness@achdidaho.org tel:(208)387-6316

INSTRUCTIONS TO RESPONDENTS

MULTIPLE DOCUMENTS TO MAKE UP ENTIRE AGREEMENT

All Sections as well as the notice, taken together, shall make up the entire Agreement between the Ada County Highway District (ACHD) and the successful Respondent. The Respondent should carefully read and understand all these documents. By signing and submitting the Authorized Representative Signature Form, the successful respondent does herein agree to abide by the terms and conditions of the entire Agreement.

COMPLIANCE

The proposal submitted must comply with the Specifications and the General Terms and Conditions included herein, and any addendum issued. Failure to comply will result in rejection of the proposal as void and non-responsive.

PROPOSAL SUBMITTAL

Sealed proposals will be received for 2027 Roadside, Sidewalk, and Basin Herbicide Application Services through the Ada County Highway District’s eProcurement Portal located at https://procurement.opengov.com/portal/achdidaho The Ada County Highway District's (ACHD) e-Procurement Portal Clock is the official clock for the determination of all deadline dates and times.

Responses will not be accepted after the submission deadline regardless of any technical difficulties, such as internet connectivity issues. Submissions will not be considered, even if attempted within the final thirty (30) minutes, nor will exceptions be made for calls made to procurement close to the deadline. The Ada County Highway District strongly recommends that all respondents complete and submit their Request for Proposals (RFP) well in advance of the specified deadline.

Respondents are solely responsible for ensuring that their RFP's are timely submitted to ACHD via the eProcurement Portal.

ACHD assumes no responsibility for any failures of computer systems or equipment that may result in partial or incomplete submissions, nor for failure to meet the required deadline as outlined in the solicitation.

Should any technical issues arise during the submission of the Request for Proposals within OpenGov (ACHD e-Procurement Portal), please utilize the "chat" feature of the "contact us" section under OpenGov Support for assistance.

Neither OpenGov nor ACHD guarantees uninterrupted access to the OpenGov website or error-free services. Furthermore, neither party will be held liable for any inadvertent disclosure of repository information or unauthorized access by third parties.

"Disruption to electronic communications" or "service loss" refers to unplanned events that significantly hinder or entirely prevent the normal functionality of electronic communications systems, such as cyberattacks, intentional disruptions (e.g., government shutdowns), power outages, or natural disasters. It does not apply to other technical issues, including operator errors or internet connectivity problems.

In the event of a disruption to electronic communications or service loss by OpenGov within four (4) hours of submission deadline, ACHD will investigate the reported incident in coordination with OpenGov. If the disruption is confirmed, ACHD will work to provide the best possible resolution to ensure respondents have the opportunity to submit their responses.

ACHD will notify all affected parties via email through OpenGov regarding any incidents and the resolutions.

PROPOSAL FORMS

Respondents must provide all information required in the Proposal and submit the Proposal by the date and time specified. If supporting documentation is required, such documentation must be submitted with the response to this solicitation. If addenda have been issued in relation to the solicitation, respondents must acknowledge all addenda. Failure to submit these required documents will be a basis for rejecting the submission as non-responsive.

The respondent shall sign the Authorized Representative Signature Form. If the respondent is a corporation, the legal name of the corporation shall be entered together with the original signature of an agent authorized to sign contracts on behalf of the corporation. If the respondent is a partnership, the true name of the firm shall be entered together with the original signature of the partner(s) authorized to sign contracts on behalf of the partnership

All blank spaces in the proposal form must be filled in. No changes may be made in the phraseology of the forms nor may the respondent add any phraseology conditioning the acceptance of the award. In case of a discrepancy between unit and total prices, unit prices shall govern.

A proposal will be deemed unresponsive if it contains omissions, erasures, or alterations not initialed by the firm signatory, additions of any kind, prices not called for, prices which are obviously unbalanced, or items which fail to conform to the conditions of the Request for Proposal.

INTERPRETATIONS OF QUANTITIES IN COST SCHEDULE

The quantities appearing in the cost schedule are approximate and are prepared for the comparison of proposal. The scheduled quantities may be increased, decreased, or omitted.

ACHD retains the right to place multiple orders throughout the duration of the agreement.

Furthermore, ACHD may elect to extend the duration of the agreement.

PROPOSAL OPENING

Proposals will be opened at the date, time, and place specified in the Introduction. No person will be denied the right to be present during the proposal opening process. Proposals may be received up to but not later than Wednesday, November 18, 2026 at 3:00 pm via the eProcurement Portal. The ACHD eProcurement Portal Clock is the official clock for the determination of all deadline dates and times. Without exception, responses will not be accepted after the submission deadline regardless of any technical difficulties such as poor internet connections. ACHD strongly recommends completing your response well ahead of the deadline.

MODIFICATION OF PROPOSAL

In all instances, a Respondent may modify their Proposal at any time prior to the scheduled closing date and time for the receipt of proposals.

WITHDRAWAL OF PROPOSAL

Any proposal may be withdrawn prior to the scheduled date and time set for proposal opening by clicking un-submit within the eProcurement portal by the respondent or their authorized agent. No proposal may be withdrawn after the date and/or time set for the submission deadline.

BID SECURITY

If Bid Security is required, proposals must be accompanied by an original certified check, cashier's check, or a bid bond (collectively referred to hereafter as “Bid Security”) issued by a surety authorized to issue such bonds in the State of Idaho, in the amount of ten percent (10%) of the total amount of the proposal submitted. Failure to include an original Bid Security as required with the bid, and/or submission of photocopies or electronic versions, e.g. PDF, FAX, etc. of the Bid Security, will, if not waived per Item 26, render said proposal void and non-responsive.

Special Note: Bid Security: If required by this solicitation, each bid shall be accompanied by the bid security specified in the solicitation documents. If Bid security is required, it will be listed https://secure.procurenow.com/portal/achdidaho/projects/304294/document?section=2920794 under the "Vendor Questionnaire" section. If the Bid Security is not being requested under the Vendor Questionnaire Section, then please disregard.

RETURN OF BID SECURITY

If Bid Security is required, within 15-calendar days after award of the contract, ACHD will return Bid Securities, other than bid bonds, to all Bidders whose proposals are not to be further considered in awarding the contract. The Bid Security, including bid bond if applicable, of the Successful Bidder shall be retained until the contract has been fully executed and the Successful Bidder has furnished all required contract security and met all other conditions of the Notice of Award. Any guarantees which have been forfeited shall be retained.

ADDENDA

Prior to the proposal opening, any interpretation or change in the RFP Documents will be made only in writing in the form of addenda. Addenda, if any, will be furnished to all respondents receiving a set of the documents from ACHD through the eProcurement Portal.

It is the responsibility of all respondents to check the eProcurement portal for all addenda.

ACHD will not be responsible for any other explanation or interpretation of the RFP Documents. Any oral explanations, instructions, and interpretations given to respondents prior to the proposal opening will not be binding on ACHD unless supplemented by written addenda.

BURDEN OF PROOF

It is the respondent's responsibility to furnish ACHD with sufficient data to determine whether or not the product(s), service(s), and/or supplies offered conform to the specified requirements.

ACHD is not liable for any costs incurred by respondents prior to issuance of a purchase order or execution of the Agreement.

FIRM COSTS

Prices submitted are to be considered firm. No cash discounts can be accepted or used in determining a low cost.

DATA TO BE FURNSHISED WITH PROPOSALS

The following submittal shall be provided with the proposal:

• List of additions, deletion or variation from the specification

• Description of service availability.

• Complete statements of all applicable warranties.

SERVICE REQUIRED

The successful respondent shall be able to provide service to ACHD, where applicable, for the items bid and delivered.

EXECUTION OF AGREEMENT

The successful respondent must execute an Agreement with ACHD within 15 days after award by ACHD.

FOREIGN ENTITIES

If respondent is an entity not organized and existing under the laws of the State of Idaho, that it will be appropriately authorized, registered, qualified, certified or otherwise in compliances with the laws of the State of Idaho relating to doing business in Idaho as a foreign entity prior to any award of a contract under this RFP. At any time after the proposal opening, at the request of ACHD, the respondent will provide ACHD with proof of compliances within five (5) business days following the request. The proposal may be rejected if respondent does not provide such proof prior to the date scheduled for the award.

PROTESTS FROM THE RESPONDENT

Any protests concerning the specifications, procurement procedures or method of evaluation must be made in writing and received by ACHD at least three (3) business days before the date and time upon which proposals are scheduled to be opened. Failure to timely raise such protest in writing shall be deemed to operate as a waiver as to any objections that may have been raised on the part of the respondent.

PROPOSAL ANALYSIS AND AWARD

The Purchase or Service Agreement contract will be awarded to the highest ranked respondent submitting complying with the procurement procedures and best meeting the specifications for the goods or services sought to be procured.

ACCEPTABILITY

Acceptability of the item shall be judged solely by ACHD. Decisions shall be final and in the best interests of the ACHD.

MATERIALS

Materials shall be free from defects and shall be those ordinarily used for the intended service, unless otherwise specified herein. It is the intent of the Specifications to permit the respondent to supply any item(s) specified or offer an equivalent. Whenever any particular item is indicated by patent, proprietary or brand name, or by name of manufacturer, such wording is for the purpose of facilitating its description and shall be deemed to be followed by the words “or approved equivalent.” The respondent shall, at its own expense, furnish with its proposal, data concerning items offered as being equivalent to those specified. ACHD shall determine whether the material offered is equivalent to that specified.

RESERVATION OF RIGHTS

ACHD reserves the right to reject any or all proposals, to waive informalities, and to contract in the best interest of ACHD.

WAIVERS

Specifications and manufacturer’s models noted in this bid are those that are acceptable to ACHD. All deviations from these specifications must be listed. Failure to list all deviations from the specifications is an informality and irregularity which shall be a basis for ACHD to deem the proposal void and non-responsive, unless such deviations are waived by ACHD.

ADDITIONAL UNITS

ACHD may order additional units as budget restrains allow within 180 days of awarding. All terms and conditions and prices of proposal shall apply to additional units ordered.

NON-RESPONSIVE CRITERIA

All proposals submitted that fail to meet the following criteria (if applicable) shall be deemed void and non-responsive:

• Provide proof of licensure. (If Applicable)

• Submit their proposal to ACHD eProcurement Portal by the date and time stated in the Request for Proposal or other solicitation.

INFORMALTIES AND IRREGULARITIES

Informalities and irregularities may be waived by the ACHD Director following notification by ACHD staff managing the procurement and upon the Director’s findings that: (1) the subject cost amount is lower than the ACHD estimate; (2) the informality and irregularity has no substantive impact on any substantial or material requirements of the procurement; (3) waiver of the informality and irregularity will not create an advantage for the subject respondent; and

(4) the informality and irregularity can be corrected by the subject respondent within 48 hours of the waiver being granted by the ACHD Director. In all other circumstances, waiver of informalities and irregularities can only be considered by the ACHD Commission as part of the award process and at the request of the affected respondent. If not waived, these informalities and irregularities shall result in a proposal being deemed void and non-responsive.

Based upon the foregoing, the informalities and irregularities that may be waived include, but are not limited to, the following:

• Failure to list all deviations from the specifications.

• Failure by the Respondent to meet the specifications contained in the Request for Proposal or other solicitation.

• Failure to timely provide the required Bid Security.

• Failure to comply with any other procurement procedures.

• Failure to provide all other required Bid Security documentation.

• Failure by the Respondent to sign their proposal.

• Failure by the Respondent to obtain from ACHD and submit official Ada County Highway District Documents, Plans, and/or Addenda.

• Minor mathematical errors.

• Omissions, erasures, or alterations, not initialed by an authorized representative of the Respondent.

• Additions of any kind or prices which are uncalled for in the Request for Proposal.

ADDITIONAL RESPONDENT INFORMATION

DOCUMENT INTERPRETATION

All Respondents submitting a response shall have thoroughly examined all the content contained in the Request for Proposal (RFP) Documents. Should there be any doubt as to any meaning or intent of any RFP statement or provision, the Respondent should submit their inquiries in writing as prescribed in the RFP NOTICE. Any interpretation that may alter or change the RFP Documents will be in writing, in the form of an Addendum, which will be furnished to all respondents receiving the RFP Documents. ACHD will not be responsible for any other explanation or interpretation of the RFP Documents. Respondents shall acknowledge all Addenda or be deemed non-responsive.

RESPONDENT UNDERSTANDING

Each respondent must adequately inspect the RFP Documents and make themselves thoroughly familiar with the content of the RFP Documents. It shall be the Respondent's obligation to verify, to their complete satisfaction, all information contained in the RFP Documents.

The submission of a Proposal Document will constitute an incontrovertible representation by the Respondent that they have been given adequate opportunity to be acquainted with the RFP Documents. Further the Respondent has, to their satisfaction, resolved any questions regarding any perceived conflicts, ambiguities, errors, and discrepancies contained within the RFP Documents.

EVALUATION AND SELECTION PROCESSES

The selection of Respondent Firms for the proposed project will be based on the Evaluation https://secure.procurenow.com/portal/achdidaho/projects/304294/document?section=undefined

Criteria.

A. The Selection Committee will evaluate the qualifications and other information presented in each Firm’s response to the RFP. To complete these tasks, the Selection Committee will use the Evaluation Criteria provided.

B. ACHD reserves the right to reject any or all Proposal Documents not conforming to the intent and purpose of this RFP whenever such action appears to be in the best interest of ACHD.

C. Once evaluated and selected, The contract will be awarded to the firm who, in the sole opinion of ACHD, is best qualified and available to perform the work.

Evaluation Phase Methodology

Scoring Method: 0 - 5 Points

Rating Guidelines:

Score

Points

EXCEPTIONAL / EXCELLENT 5

GOOD 4

SATISFACTORY 3

POOR 2

UNSATISFACTORY 1

NON-RESPONSIVE / NO VALUE 0

DISADVANTAGED BUSINESS ENTERPRISE

Acknowledgement requirement to list the consideration as to whether the Firm is certified by the Idaho Transportation Department and listed in the Idaho Disadvantaged Business Enterprise (DBE) Directory or other comparable state registries. Including of DBE-certified firms endures maintenance of compliance and meets the goals of Federally assisted projects and ACHD policy.

PROPERTY OF ACHD

All information and material submitted in response to this RFP shall become the property of ACHD and will not be returned. At its sole discretion, ACHD reserves the right to use any and all information submitted.

COST OF SUBMITTING

ACHD is not responsible for any cost incurred by any respondent in the preparation of Proposal Documents.

SCOPE OF WORK

Scope of Work Please refer to the "Attachments" section for the Scope of Work and other pertinent supporting documents.

EVALUATION PHASES

Evaluation Phase Methodology

Scoring Method: 0 - 5 Points https://procurement.opengov.com/portal/achdidaho/projects/304294/document?section=2920797

Rating Guidelines:

Score

Points

EXCEPTIONAL / EXCELLENT 5

GOOD 4

SATISFACTORY 3

POOR 2

UNSATISFACTORY 1

NON-RESPONSIVE / NO VALUE 0

No. Evaluation Criteria Scoring Method Weight (Points)

1. PROPOSAL COST

• First Low Cost = 5,

• Second Low Cost = 4

• Third Low Cost = 3

• All Other Cost = 2

0-5 Points 30 (30% of Total)

2. FIRM HISTORY,

EXPERIENCE AND

REFERENCES:

A. Quality Work and Satisfactory Project Completion

B. Positive Customer Service, Communication, and Responsiveness

C. Relevant Experience and Comparable Projects with Government Agencies and with ACHD, if applicable

0-5 Points 15 (15% of Total)

3. FIRM QUALIFICATIONS and

KEY PERSONNEL:

A. Firm Qualifications and Organizational Capacity

B. Qualifications and Key Personnel.

C. Staffing, Equipment, and Resources Available to Perform the Services.

0-5 Points 20 (20% of Total)

4. PROJECT APPROACH AND

UNDERSTANDING:

A. Understanding the Scope of Work and Specifications.

B. Project Approach, Methodology, and Scheduling

C. Quality Control, Environmental Protection, and Performance Management.

0-5 Points 30 (30% of Total)

5. DISPUTES, CLAIMS WITH

ACHD OR ANY NOTICES OF

INSUFICIENT WORK BY

ACHD

PER ACHD POLICY SECTION

2009.2.6:

A. No Past or Pending disputes or claims with ACHD or any notices of insufficient work by ACHD = 5 Exceptional / Excellent (No deduction from total score.)

B. Past or Present disputes or claims with ACHD or any notices of insufficient work by ACHD = 0 Non- Responsive / No Value (5-point deduction from total score.)

0-5 Points 5 (5% of Total)

VENDOR QUESTIONNAIRE

Authorized Representative Signature* Once you start your proposal you will be asked to complete a DocuSign form.

Click here to go to the form *Response required Firm's Name* Please provide the Firm's Name Example: ABC Contractor *Response required Firm's Address* Must provide Firm's "Full Address" (Number, Street and any Suite, City, State and Zip Code) *Response required Firm's Individual Contact Name and Title* Must provide the "Full Name" and "Title" of the individual responsible for overseeing this contract.

*Response required Firm's Individual Contact Phone Number* Must provide the contact phone number of the individual overseeing this contract.

*Response required Firm's Fax Number* Please provide the firm's fax number.

Note: If the firm no longer utilizes a fax line, you may indicate "N/A."

*Response required Individual Contact E-Mail Address* Must provide the email address of the individual overseeing this contract.

*Response required ACHD Policy for Equal Employment Opportunity* The Firm does not and will not discriminate against any person, employee, or applicant for employment because of these protected classes on the bases of race, color, religion, sex, sexual orientation, gender identity, national origin, age, disability, military status, genetic information, or any other status protected by federal, state or local law in accordance with ACHD Policy for Equal Employment Opportunity Please confirm ☐ Please confirm *Response required Title 49 CFR Part 21 Non-Discrimination Statement* The Firm does not and will not discriminate against any person, employee, or applicant for employment because of race, color, religion, gender, national origin, age or disability in accordance with Title 49 CFR Part 21.

Please Confirm ☐ Please confirm *Response required Disadvantaged Business Enterprise (DBE) Status* Is the Respondent Firm a Disadvantaged Business Enterprise (DBE)?

☐ Yes ☐ No *Response required https://na4.docusign.net/Member/PowerFormSigning.aspx?PowerFormId=53c06061-04af-4876-a1d0-fe9f9f703133&env=na4&acct=94a6fb97-f6a3-406b-8ab2-8282d73a5796&v=2

PROPOSAL NARRATIVES

Proposers shall provide a clear, complete, and concise Proposal Narrative demonstrating the Firm's ability to successfully perform the Services in accordance with the requirements of this RFP and the Scope of Work (SoW).

The Proposal Narrative shall be organized in the order identified below and shall provide sufficient information for ACHD to evaluate the Firm in accordance with the Evaluation Criteria and to perform the required services:

• 11.1 Firm History

• 11.2 Firm Experience

• 11.3, 11.4, 11.5 References

• 11.6 Firm Qualifications

• 11.7 Staffing, Equipment, and Resources

• 11.8 Key Personnel

• 11.9 Project Approach and Understanding

• 11.10 Other Information

• 11.11 Prior ACHD Disputes, Claims, or Notices of Insufficient Work

• 11.12 Explanation of Prior ACHD Disputes, Claims, or Notices of Insufficient Work

• 11.13 Confirming Certification and Acknowledgment

FIRM HISTORY*

Respondents shall provide a clear, complete, and concise narrative describing the Firm’s history and organizational background, including:

• The year established and number of years in business;

• Ownership and business Structure; and

• Significant organizational changes, if any, relevant to the Firm's ability to perform the Services

Maximum response length: 3500 characters *Response required

FIRM EXPERIENCE AND REFERENCES*

Respondents shall describe the Firm's relevant experience performing herbicide application and vegetation-control services of similar size, scope, and complexity.

The response shall identify relevant experience with:

• Roadside, sidewalk, and public right-of-way applications;

• Stormwater Basin and Stormwater Facility Vegetation Management;

• Work performed within or adjacent to active roadways and public facilities;

• Environmental protection and No-Spray Requirements; and

• Identify relevant experience with Governmental or other public-sector agencies of comparable scope and complexity.

• Shall demonstrate the Firm's History of quality work and satisfactory completion of comparable projects.

Firm References shall be provided separately in Sections 11.3, 11.4, and 11.5 below.

Maximum response length: 5500 characters *Response required

REFERENCE ONE (1)*

Provide Company/Firm Name, Contact Person Name, Firm Address, Firm Phone Number, Contact Number, and E-mail Address.

*Response required

REFERENCE TWO (2)*

Provide Company/Firm Name, Contact Person Name, Firm Address, Firm Phone Number, Contact Number, and E-mail Address.

*Response required

REFERENCE THREE (3)*

Provide Company/Firm Name, Contact Person Name, Firm Address, Firm Phone Number, Contact Number, and E-mail Address.

*Response required

FIRM QUALIFICATIONS*

Respondents shall provide a concise description of the Firm’s qualifications, organizational capacity, and resources available to successfully perform the services within the required treatment periods and requirements of this RFP and Scope of Work.

Licenses, certifications, product information, labels, Safety Data Sheets (SDS), insurance documentation, and other information required elsewhere in the RFP need not be duplicated in this narrative.

The response shall demonstrate the Firm's ability to comply with applicable safety, environmental, regulatory, and contractual requirements.

*Response required

STAFFING, EQUIPMENT, AND RESOURCES*

Respondents shall describe the staffing, equipment, and resources available to successfully perform the Services, including:

• Proposed staffing and supervision;

• Availability of qualified applicators and backup personnel;

• Vehicles, spray systems, and application equipment;

• Backup equipment and resources;

• Traffic-control resources necessary for safe operations; and

• Contingency resources for equipment failures, weather delays, staffing shortages, or other schedule disruptions.

*Response required

KEY PERSONNEL*

Respondents shall identify the Key Personnel proposed to perform or supervise the Services, including the primary point of contact, supervisor(s), and applicator personnel, as applicable.

For each individual identified as Key Personnel, provide a written summary résumé not to exceed one-half (½) page that includes:

• Proposed role and responsibilities;

• Relevant Experience;

• Applicable Qualifications and Certifications; and

• Experience performing comparable herbicide application services.

Hyperlinks or external references shall not be accepted in lieu of the required information.

*Response required

PROJECT APPROACH AND UNDERSTANDING*

Respondents shall provide a clear and concise narrative demonstrating the Firm’s understanding of the Scope of Work and proposed approach to successfully performing the Services.

A. Understanding of the Scope of Work Describe the Firm’s understanding of the project objectives, required Services, treatment areas, performance requirements, treatment periods, environmental restrictions, and required deliverables.

The Response shall demonstrate an understanding of the requirements applicable to roadside, sidewalk, public right-of-way, stormwater basin, access road, follow-up, and spot-treatment work.

B. Project Approach, Methodology, and Scheduling Describe the Firm's proposed approach to performing the Services, including:

• Work sequencing and scheduling;

• Initial, follow-up, and spot-treatment applications;

• Methods for addressing site conditions and constraints;

• Weather-related limitations and schedule disruptions; and

• Corrective work and ACHD-requested retreatment.

C. Quality Control, Environmental Protection, and Performance Management.

Describe the Firm's approach to quality control, environmental protection, documentation, and performance management, including:

• Pre-application inspections and identification of No-Spray areas;

• Protection of water, drainage features, desirable vegetation, and environmentally sensitive areas;

• Prevention of drift, overspray, runoff, and off-target application;

• Verification of herbicide mixtures and application rates;

• Application records and documentation of treatment areas;

• Quality-control inspections and corrective work; and

• Communication with ACHD regarding scheduling, field conditions, weather delays, complaints, and other performance-related matters.

The response shall provide sufficient information for ACHD to evaluate whether the Firm demonstrates a practical and effective approach to successfully performing the Services.

*Response required

OTHER INFORMATION

Respondents may provide other information directly relevant to ACHD's evaluation of the Firm's experience, qualifications, or ability to perform Services.

Respondents should not duplicate information or documentation required elsewhere in the Proposal.

Maximum response length: 5000 characters

PRIOR ACHD DISPUTES, CLAIMS OR NOTICES OF INSUFFICIENT WORK*

Respondents shall disclose whether the Firm has been involved in any disputes, claims, or notices of insufficient work arising from or relating to a prior or current contract, agreement, or project with the Ada County Highway District (ACHD).

☐ Yes ☐ No *Response required

EXPLANATION OF PRIOR ACHD DISPUTES, CLAIMS, OR NOTICES OF

INSUFFICIENT WORK

If the response to Section 11.11 is "Yes," the Respondent shall provide a brief explanation of each applicable dispute, claim, or notice of insufficient work. At a minimum, the response shall include:

A. The contract, agreement, or project associated with the dispute, claim, or notice of insufficient work;

B. The general nature and circumstances of the dispute, claim, or notice of insufficient work;

C. The resolution of the current status of the matter; and D. Any other information the Respondent considers relevant to ACHD's evaluation.

If the response to Section 11.11 is "No," no response to this Section is required.

CONFIRMING CERTIFICATION AND ACKNOWLEDGMENT*

By submitting a Proposal, the Respondent certifies that the information provided in Section 11.11, Prior ACHD Disputes, Claims, or Notices of Insufficient Work, and Section 11.12, Explanation of Prior ACHD Disputes, Claims, or Notices of Insufficient Work, is complete and accurate to the best of the Respondent's knowledge.

The Respondent further acknowledges and understands that the information disclosed will be considered by ACHD as part of its evaluation of the Proposal, in accordance with the evaluation criteria established in this RFP.

The Respondent acknowledges and confirms the certification above.

☐ Please confirm *Response required

COST SCHEDULE

COST SCHEDULE 1, FY27 ROADSIDE, SIDEWALK, AND BASIN HERBICIDE APPLICATION

SERVICES

Line Item Description Quantity Unit of Measure

Unit Cost Total

1 Roadside - Initial Pre- Emergent, January 1 - March 15, 2027; Target 10-foot Spray Width

1,522 LANE

MILE

2 Sidewalk - Initial - May 10 - June 7, 2027; Cracks, Joints, Crevices, Curbs, and Seams.

277 LANE

3 Basin - Initial - April 15 - May 15, 2027; approved perimeter, upland, inspected side slopes, access roads, and maintenance pads; basin bottoms excluded.

(53 Locations)

1,034,918 SQFT

4 Roadside - Follow-Up / Breakout - March 16 - September 30, 2027, as directed by ACHD

1,522 LANE

5 Sidewalk - Follow-Up / Breakout - June 7 - September 30, 2027, as directed by ACHD

277 LANE

6 Basin - Follow-Up / Breakout - May 15 - July 15, 2027, as directed by ACHD

1,034,918 SQFT

TOTAL

COST SCHEDULE 2, FY27 ROADSIDE, SIDEWALK, AND BASIN HERBICIDE APPLICATION

SERVICES

Line Item Description Quantity Unit of Measure

Unit Cost Total

1 Authorized Additional / Spot Application - Scattered sites or added locations only upon ACHD writeen authorization;

includes on fully equipped application crew.

1 CREW

HOUR

TOTAL

NOTICE
INTRODUCTION
Summary
Background
Contact Information
Timeline
INSTRUCTIONS TO RESPONDENTS
MULTIPLE DOCUMENTS TO MAKE UP ENTIRE AGREEMENT
COMPLIANCE
PROPOSAL SUBMITTAL
PROPOSAL FORMS
INTERPRETATIONS OF QUANTITIES IN COST SCHEDULE
PROPOSAL OPENING
MODIFICATION OF PROPOSAL
WITHDRAWAL OF PROPOSAL
BID SECURITY
RETURN OF BID SECURITY
ADDENDA
BURDEN OF PROOF
FIRM COSTS
DATA TO BE FURNSHISED WITH PROPOSALS
SERVICE REQUIRED
EXECUTION OF AGREEMENT
FOREIGN ENTITIES
PROTESTS FROM THE RESPONDENT
PROPOSAL ANALYSIS AND AWARD
ACCEPTABILITY
MATERIALS
RESERVATION OF RIGHTS
WAIVERS
ADDITIONAL UNITS
NON-RESPONSIVE CRITERIA
INFORMALTIES AND IRREGULARITIES
ADDITIONAL RESPONDENT INFORMATION
DOCUMENT INTERPRETATION
RESPONDENT UNDERSTANDING
EVALUATION AND SELECTION PROCESSES
DISADVANTAGED BUSINESS ENTERPRISE
PROPERTY OF ACHD
COST OF SUBMITTING
SCOPE OF WORK
Scope of Work
EVALUATION PHASES
VENDOR QUESTIONNAIRE
Authorized Representative Signature*
Firm's Name*
Firm's Address*
Firm's Individual Contact Name and Title*
Firm's Individual Contact Phone Number*
Firm's Fax Number*
Individual Contact E-Mail Address*
ACHD Policy for Equal Employment Opportunity*
Title 49 CFR Part 21 Non-Discrimination Statement*
Disadvantaged Business Enterprise (DBE) Status*
PROPOSAL NARRATIVES
FIRM HISTORY*
FIRM EXPERIENCE AND REFERENCES*
REFERENCE ONE (1)*
REFERENCE TWO (2)*
REFERENCE THREE (3)*
FIRM QUALIFICATIONS*
STAFFING, EQUIPMENT, AND RESOURCES*
KEY PERSONNEL*
PROJECT APPROACH AND UNDERSTANDING*
OTHER INFORMATION
PRIOR ACHD DISPUTES, CLAIMS OR NOTICES OF INSUFFICIENT WORK*
EXPLANATION OF PRIOR ACHD DISPUTES, CLAIMS, OR NOTICES OF INSUFFICIENT WORK
CONFIRMING CERTIFICATION AND ACKNOWLEDGMENT*