This document is a Government Response to Industry Questions for the Modernization of Scientific and Technical Intelligence (S&TI) Prototype Effort, issued by the Air Force Life Cycle Management Center (AFLCMC) at Wright-Patterson Air Force Base on 30 September 2026. The memorandum addresses a clarification question regarding the period of performance and rough order of magnitude (ROM) pricing structure for the prototype effort.

The Government clarifies that the overall projected total period of performance is 48 months. In response to industry confusion about whether the effort would extend to 60 months, the Government specifies that it requests two separate ROMs: one covering the initial 12-month period and a second ROM for the remaining 36 months (months 13-48). This structure allows the Government to evaluate prototype feasibility and costs in two distinct phases within the consolidated 48-month performance window. No specific response deadline, contract vehicle type, or award date is identified in this clarification document.

View the file

Other files

File Type Posted
20261001_Question_Answer_2026SandTIPrototype.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS AIR FORCE LIFE CYCLE MANAGEMENT CENTER

WRIGHT-PATTERSON AIR FORCE BASE

30 September 2026

MEMORANDUM FOR: Modernization of Scientific and Technical Intelligence (S&TI) Prototype Effort Interested Parties

FROM: AFLCMC/PZIEC

Building 2, Room 11 2000 Allbrook Dr.

WPAFB, OH 45433

SUBJECT: Government Response to the Question from Industry on the S&TI Prototype Sources

Sought Posting

1. In response to the subject effort, please see below Government response:

A. Regarding Item 5: Prototype Feasibility, Ballpark ROM & Relevant IP, please confirm if the total period of the ROM is 12 Months +13-48 Months = a projected total of 48 Months Total OR is the intention that the effort is projected at 12 Months + another 13- 48 Months = Upward to 60 Months Total?

Government Response: The overall projected total period of performance is 48 months.

The Government requests two separate ROMs:

One for the initial 12 months, and One for the remaining 36 months (months 13–48).

File details come from the government source that posted it. Updated .