This is a Bid Schedule (pricing template) for FY26 Boiler Inspections at Hanscom Air Force Base, Massachusetts. The schedule outlines Contract Line Items (CLINs) for a one-year base period (September 18, 2026 to September 17, 2027) plus four one-year option periods extending through September 17, 2031. The contractor shall provide inspection and testing services for four boiler units, one Heat Recovery Steam Generator (HRSG), and associated systems including condensate receiver tanks, compressors, compressed air tanks, deaerator tanks, pumps, economizers, fans, fuel train components, turbines, and safety valves.
The base year and option years include recurring CLINs for biannual Type "A" External/Internal Inspections and Type "C" External/Operational Inspections of boilers #1 and #2 (CLIN 0001/1001/2001/3001/4001); biannual inspections of boilers #3 and #4 (CLIN 0002/1002/2002/3002/4002); annual testing of 13 safety valves (CLIN 0003/1003/2003/3003/4003); and annual inspection of the HRSG (CLIN 0004/1004/2004/3004/4004). Option Year 1 includes an additional CLIN 1005 for a Deaerator Condition Assessment for all four boilers occurring every five years beginning in Option Year 1. All unit costs and totals are shown as $0.00 in this template, indicating pricing shall be provided by offerors. Questions were due August 26, 2026, with answers provided by August 28, 2026, and offers due September 2, 2026 at 11:00 AM EST. A mandatory site visit was scheduled for August 25, 2026 from 9:00-11:00 AM at Hanscom AFB Visitor Center.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Year
| CONTRACT LINE | ||||||
| ITEM NO. (CLIN) | SUPPLIES/SERVICE | QTY | UNIT | COST | TOTAL | |
| NON-PERSONAL SERVICES: | ||||||
| 0001 | Inspection of boilers #1 and #2 and all assocciated elements to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 0002 | Inspection of boilers #3 and #4 and all associated element to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 0003 | Test Safety Valves Annually | 13 | EA | $0.00 | ||
| 0004 | Inspection of Heat Recovery Steam Generator and all assocciated elements Annually | 1 | EA | $0.00 | ||
| September 18 2026 to September 17 2027 TOTAL CLINs 0001 through 0004 | $0.00 |
Option YR 1
| CONTRACT LINE | ||||||
| ITEM NO. (CLIN) | SUPPLIES/SERVICE | QTY | UNIT | COST | TOTAL | |
| NON-PERSONAL SERVICES: | ||||||
| 1001 | Inspection of boilers #1 and #2 and all assocciated elements to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 1002 | Inspection of boilers #3 and #4 and all associated element to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 1003 | Test Safety Valves Annually | 13 | EA | $0.00 | ||
| 1004 | Inspection of Heat Recovery Steam Generator and all assocciated elements Annually | 1 | EA | $0.00 | ||
| 1005 | Dearator Condition Assessment for #1 Boiler, #2 Boiler, #3 Boiler, and #4 Boiler Every 5th year beginning in Option Year 1 | 1 | EA | $0.00 | ||
| September 18 2027 to September 17 2028 TOTAL CLINs 1001 through 1005 | $0.00 |
Option YR 2
| CONTRACT LINE | ||||||
| ITEM NO. (CLIN) | SUPPLIES/SERVICE | QTY | UNIT | COST | TOTAL | |
| NON-PERSONAL SERVICES: | ||||||
| 2001 | Inspection of boilers #1 and #2 and all assocciated elements to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 2002 | Inspection of boilers #3 and #4 and all associated element to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 2003 | Test Safety Valves Annually | 13 | EA | $0.00 | ||
| 2004 | Inspection of Heat Recovery Steam Generator and all assocciated elements Annually | 1 | EA | $0.00 | ||
| September 18 2028 to September 17 2029 TOTAL CLINs 2001 through 2004 | $0.00 |
Option YR 3
| CONTRACT LINE | ||||||
| ITEM NO. (CLIN) | SUPPLIES/SERVICE | QTY | UNIT | COST | TOTAL | |
| NON-PERSONAL SERVICES: | ||||||
| 3001 | Inspection of boilers #1 and #2 and all assocciated elements to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 3002 | Inspection of boilers #3 and #4 and all associated element to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 3003 | Test Safety Valves Annually | 13 | EA | $0.00 | ||
| 3004 | Inspection of Heat Recovery Steam Generator and all assocciated elements Annually | 1 | EA | $0.00 | ||
| September 18 2029 to September 17 2030 TOTAL CLINs 3001 through 3004 | $0.00 |
Option YR 4
| CONTRACT LINE | ||||||
| ITEM NO. (CLIN) | SUPPLIES/SERVICE | QTY | UNIT | COST | TOTAL | |
| NON-PERSONAL SERVICES: | ||||||
| 4001 | Inspection of boilers #1 and #2 and all assocciated elements to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 4002 | Inspection of boilers #3 and #4 and all associated element to include a Type "A" External/Internal Inspection and Type "C" External/Operational inspections Biannually | 2 | EA | $0.00 | ||
| 4003 | Test Safety Valves Annually | 13 | EA | $0.00 | ||
| 4004 | Inspection of Heat Recovery Steam Generator and all assocciated elements Annually | 1 | EA | $0.00 | ||
| September 18 2030 to September 17 2031 TOTAL CLINs 4001 through 4004 | $0.00 |