This is a proposal and bidding document for a highway construction project issued by the Wisconsin Department of Transportation (WisDOT) in Waukesha County. The project, designated as V Lisbon (Proposal 2450-06-71), involves the reconstruction of the intersection of Redford Boulevard (CTH F) and Lisbon Road (CTH K) in Lisbon, Wisconsin. The scope of work includes common excavation, base aggregate, concrete and HMA pavement, concrete curb and gutter, storm sewer, culvert pipes, traffic signal installation, signing, pavement marking, and traffic control measures. The project is structured in five construction stages and includes provisions for interim completion milestones with associated liquidated damages. Contractors must submit bids electronically or on paper (with waiver) prior to 11:45 AM on the last business day preceding the letting. The contract requires a proposal guaranty bond, and selected contractors must execute a contract agreement and performance bond within 14 days of award notification. Work must commence within 10 calendar days after written notice from the engineer.

The contract includes a lane rental fee assessment structure charging $2,000 per lane per direction of travel per hour (in 15-minute increments) for closures outside allowable times. Interim liquidated damages of $2,000 per calendar day are assessed if Stage 2 and Stage 4 pavement replacement work (each limited to 10 calendar days) is not completed on schedule. All bidders must comply with non-discrimination employment requirements per Wisconsin statutes, maintain traffic on CTH F and CTH K with no flagging allowed, and adhere to holiday and special event work restrictions. The contract requires submission of an Erosion Control Implementation Plan (ECIP) 14 days prior to the preconstruction meeting and coverage under the Wisconsin Pollutant Discharge Elimination System Transportation Construction General Permit due to 2.52 acres of land-disturbing activity. The project involves coordination with multiple utility companies including We Energies, AT&T, Spectrum, American Transmission Company, and Bluebird Communications for facility relocations prior to construction. Waukesha County will provide final acceptance of traffic signal cabinet and controller installations. The bidding document specifies detailed requirements for traffic signal equipment conforming to NEMA TS2 Type 2 standards, including controller specifications, malfunction management units, and comprehensive documentation requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"��#�$�� ����"�"�� !$%&����%'�������())(�*�%+,-����(�."�"��/�/0��1 2010�����1 ���304/�10�4���/��5 ������� 4�65/��7&�8�)8,% �9.:�����,�,& ;�<���� =�> ?#��?�@�A?=9 " �"�� ���"B�<���� �>? :$C�D �� E �B� $B����������=� ?�F"B ���G �"�"B H�"B"B �?A I

�"#�����������($B � ��B� ??

��A �#������H��E#��"B �����A "�#"B ��G �" ?���J �"�� �"B �H�"B�"B I "��� ?�:� ?�"�� �(���������K ��� "F�> I ?���F��� "��#�$�� ����"�"�� L,&=���(�� M""��B����������K

��� "F�� ����E��#�"B����MKN(@�?�.

��O=����)%%������:� "���"�:���� P�"�� ��Q%=����,M���G ?�!���?A� "�G ���N " �K��� �R D���� �� =�M??� ��=�:�"F=�."�" =�S���:�?

$B����� "���"���� T �����A

���GB"($B���

�"B�""B ���G �F�H�� =��� � "B���U "�"�A �#"B ?���A V"B�""B �B�� T��� ��F�� ?"B ��?#���"B

��� �=C�GBH�F���E��������=� ?����??

?�=� ?B���B �E ?"B ���""� G"B��������������?V� ?"B�""B ����G ����F

�B�A �"B �"�F��� ?�� �"�F= ?� "�� F�G�

?� � F���� ��� =���"B �H�� "�E � F��"�� � �

"�"�A ��??� G� �� �"�� H�"B"B��������������?(1W�XWY�Z[\X]�XWŶ_[̀a]�W_�Zbcd[Y�Ye[Z��[\ef̂ g��W_h��_WiWẐj�feaX�Zbcd[YY[X\�̂X�ajakY_WX[k�c[l�WX�Yea��XYa_XaYm.

?�� ?��H�� �"��� �"B���?�" �nnnnnnnnnnnnnnn+.�G �" =� �"��F�� ��#������ �� -+��� "����$F�

���
=��"��F��

�:�������� �NT���

��.�G �" -+��� "����$F� -2W_�1aî_YdaXY�6Za��Xjg/gia�Wo��W_hp �"��

��#�MH��?�!�"

�K ��� "F�> ? �"��F�.

��q��05�/�2���r�11�5���6����0�

��A���=�K��?� G=�MGG�

G�" ���A "=�M��B��"���A �A ���� ?�K H��E=�."���.

H �=�N����� �:� "���=�� "�.�G � G=�$��##���:� "���=���A "�s��E� G=�<�GB"� G=�$��##���.�G ���=�>

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

2450-06-71 1 of 23

Special Provisions Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Prosecution and Progress

4. Lane Rental Fee Assessment

5. Traffic

6. Holiday and Special Event Work Restrictions

7. Utilities

8. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

9. Erosion Control

10. Nighttime Work Lighting-Stationary

11. Removing Traffic Signals – CTH F & CTH K, Item 204.9060.S.01

12. Lamp, Ballast, LED, Switch Disposal by Contractor, Item 659.5000.S

13. Waukesha County Acceptance of Traffic Signal Cabinet and Controller (CTH F & CTH K)

14. Traffic Signal Cabinet and Controller (CTH F & CTH K), Item SPV.0060.01

15. Retroreflective Backplates 3S, Item SPV.0060.02; Retroreflective Backplates 4S, Item

SPV.0060.03

16. Furnish and Install Video Detection System (CTH F & CTH K), Item SPV.0060.04

17. Furnish and Install Emergency Vehicle Preemption (EVP); Item SPV.0060.05

2450-06-71 2 of 23

STSP’S Revised July 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

2450-06-71 V Lisbon, Redford Blvd Intersection with Lisbon Rd

CTH F

Waukesha County

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260401)

2. Scope of Work.

The work under this contract consists of common excavation, base aggregate, concrete pavement, HMA pavement, concrete curb & gutter, storm sewer, culvert pipes, traffic signals, signing, pavement marking, traffic control and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notice to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

Protection of Endangered Bats Federally protected bats have the potential to inhabit the project limits because they roost in trees, bridges, culverts, and other structures. Roosts may not have been observed on this project, but conditions to support the species exist. The species and all active roosts are protected by the federal Endangered Species Act. If an individual bat or active roost is encountered during construction operations, stop work, and notify the engineer and the WisDOT Regional Environmental Coordinator

(REC).

Ensure all operators, employees, and subcontractors working in areas of known or presumed bat habitat are aware of environmental commitments and avoidance and minimization measures (AMMs) to protect both bats and their habitat.

Direct temporary lighting, if used, away from wooded areas during the bat active season April 15 to October 31, both dates inclusive.

Tree Clearing:

Contractor means and methods to remove trees will not be allowed. If it is determined that trees with a 3-inch or greater diameter at breast height (dbh) need to be removed beyond contractor means and methods, notify the engineer to coordinate with the WisDOT REC to determine if consultation with United

2450-06-71 3 of 23

States Fish and Wildlife Service (USFWS) is required. The contractor must be aware that the WisDOT REC and/or USFWS may not permit modifications.

Interim Completion and Liquidated Damages – Stage 2 - CTH F Lane 1 Pavement Replacement: 10 Calendar Days During Stage 2, close CTH F lane 1 to through traffic for a maximum of 10 calendar days. Do not reopen until completing the following work: Sawcutting, existing pavement removal, and pavement replacement.

If the contractor fails to complete the work necessary to reopen CTH F lane 1 to traffic within 10 calendar days, the department will assess the contractor $2,000 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 10 calendar days. An entire calendar day will be charged for any period of time within a calendar day that the road remains closed beyond 12:01 AM.

If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

Interim Completion and Liquidated Damages – Stage 4 - CTH F Lane 2 Pavement Replacement: 10 Calendar Days During Stage 4, close CTH F lane 2 to through traffic for a maximum of 10 calendar days. Do not reopen until completing the following work: Sawcutting, existing pavement removal, and pavement replacement.

If the contractor fails to complete the necessary work to reopen CTH F lane 2 to traffic within 10 calendar days, the department will assess the contractor $2,000 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 10 calendar days. An entire calendar day will be charged for any period of time within a calendar day that the road remains closed beyond 12:01 AM.

If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

4. Lane Rental Fee Assessment.

A General The contract designates some lane closures to perform the work. The contractor will not incur a Lane Rental Fee Assessment for closing lanes during the allowable lane closure times. The contractor will incur a Lane Rental Fee Assessment for each lane closure outside of the allowable lane closure times. If a lane is obstructed at any time due to contractor operations, it is considered a closure. The purpose of lane rental is to enforce compliance of lane restrictions and discourage unnecessary closures.

The allowable lane closure times are shown in the Traffic article.

Submit the dates of the proposed lane, ramp, and roadway restrictions to the engineer as part of the progress schedule.

B Lane Rental Fee Assessment The Lane Rental Fee Assessment incurred for each lane closure, each ramp closure, and each full closure of a roadway, per direction of travel, is as follows:

- Night time- $2,000 per lane, per direction of travel, per hour broken into 15-minute increments

- Off Peak- $2,000 per lane, per direction of travel, per hour broken into 15-minute increments

- On Peak- $2,000 per lane, per direction of travel, per hour broken into 15-minute increments

The Lane Rental Fee Assessment represents a portion of the cost of the interference and inconvenience to the road users for each closure. All lane, roadway, or ramp closure event increments 15 minutes and less will be assessed as a 15-minute increment.

The engineer, or designated representative, will be the sole authority in determining time period length for the Lane Rental Fee Assessment.

Lane Rental Fee Assessments will not be assessed for closures due to crashes, accidents or emergencies not initiated by the contractor.

The department will assess Lane Rental Fee Assessment by the dollar under the administrative item Failing to Open Road to Traffic. The total dollar amount of Lane Rental Fee Assessment will be computed by multiplying the Lane Rental Assessment Rate by the number of 15-minute increments of each lane closure event as described above.

2450-06-71 4 of 23

Lane Rental Fee Assessment will be in effect from the time of the Notice to Proceed until the department issues final acceptance. If interim completion time or contract time expires before the completion of specified work in the contract, additional liquidated damages will be assessed as specified in standard spec 108.11 or as specified within this contract.

stp-108-070 (20161130)

5. Traffic.

Keep CTH F and CTH K open to traffic. No flagging is allowed.

Notify project staff and emergency officials of any changes in the traffic patterns at least 3 days prior to any changing traffic conditions. List of officials is listed below:

• Waukesha County Sheriff’s Office: Eric Severson – sheriff@waukeshacounty.gov

• Sussex Police Services: Lisa Panas – Police@sussexwi.gov (262) 246-0939

• Pewaukee Fire Department: Sandi DeByl – debyl@pewaukee.wi.us (262) 522-2500

• Waukesha County DPW: Ethan Moser - emoser@waukeshacounty.gov (262) 548-7746

Provide PCMS message boards as shown in the plan at least 7 days prior to and during construction.

Maintain emergency vehicle access to all properties at all times.

Allowable Lane Closure Turn lane and shoulder closures are allowed during the following days and times:

Sunday through Thursday – 9:00pm to 5:30am

Friday through Saturday – 11:00pm to 8:00am

Temporarily close CTH F northbound left turn lane (existing lane 1) is allowed for up to 10 days during Stage 2. The CTH F northbound left turn lane must remain open at the intersection north of the pavement repair location.

Temporarily close CTH F northbound through/right turn lane (existing lane 2) is allowed for up to 10 days during Stage 4. The CTH F northbound through/right lane must remain open at the intersection north of the pavement repair location.

Traffic Operations During Construction Stage 1 Close CTH F & CTH K right turn lane and shoulder closures to accommodate splitter island removals and temporary asphalt placement.

Stage 2 Close the existing CTH F northbound and southbound lane 1 into a temporary left turn lane for both directions during reconstruction of the existing left turn lanes.

A short term CTH F northbound left turn lane (existing lane 1) closure will be required for pavement replacement work. Close CTH F northbound left turn lane for no longer than 10 days for pavement replacement. Keep CTH K traffic in existing condition. Allowable lane closure restrictions are waived for this closure.

Stage 3 CTH F northbound traffic will be in the existing configuration.

CTH F southbound lane 2 and existing CTH K through lanes into a temporary through/right configuration during reconstruction of the existing right turn lanes.

Stage 4 CTH F southbound and CTH K eastbound traffic will be in the existing configuration.

Northbound traffic will use a temporary through/right lane on existing CTH F northbound lane 2 during the reconstruction of the existing CTH F northbound right turn lane. CTH K westbound traffic will shift north mailto:sheriff@waukeshacounty.gov mailto:Police@sussexwi.gov mailto:debyl@pewaukee.wi.us mailto:emoser@waukeshacounty.gov

2450-06-71 5 of 23 approximately 12-ft as the plans show to accommodate truck turning movements from CTH F northbound to CTH K eastbound.

A short term CTH F northbound through/right turn lane (existing lane 2) closure will be required for pavement replacement work. Limit closures for pavement replacement on CTH F to 10 days. Allowable lane closure restrictions are waived for this closure.

Stage 5 CTH F and CTH K traffic will be in the final configuration.

Traffic control shall consist of CTH F & CTH K right turn lane and shoulder closures to accommodate splitter island construction and permanent signal installation.

Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).

TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION

Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION

Lane and shoulder closures 7 calendar days

Full roadway closures 7 calendar days

Ramp closures 7 calendar days

Detours 7 calendar days

Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION

Shoulder Closures 3 calendar days

Lane closures 3 business days

Ramp closures 3 business days

Modifying all closure types 3 business days

Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.

Temporary Regulatory Speed Limit Reduction (35 mph) During engineer-approved regulatory speed limit reductions, install temporary speed limit signs on the inside and outside shoulders of divided roadways to enhance visibility. On two-lane, two-way roadways, install temporary speed limit signs on shoulders. When construction activities impede the location of a post-mounted regulatory speed limit sign, relocate the sign for maximum visibility to motorists. If work lasts less than seven days, mount the regulatory speed limit sign on a portable sign support.

Post temporary regulatory speed limit signs in the work zone only during continuous worker activity.

During periods of no work activity or when the traffic controls are removed from the roadway, cover or remove the temporary speed limit signs.

6. Holiday and Special Event Work Restrictions.

Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying CTH F or CTH K traffic, and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following holiday and special event periods:

2450-06-71 6 of 23

- From noon Friday, May 28th, 2027 to 6:00 AM Tuesday, June 1st, 2027 for Memorial Day;

- From noon Friday, July 2nd, 2027 to 6:00 AM Monday, July 5th, 2027 for Independence Day;

- From noon Friday, September 3rd, 2027 to 6:00 AM Tuesday, September 7th, 2027 for Labor Day.

stp-107-005 (20210113)

7. Utilities.

This contract does not come under the provision of Administrative Rule Trans 220.

stp-107-066 (20240703)

Any utility facility locations (stations, offsets, elevations, depths) listed in this article are approximate.

American Transmission Company (Transmission) Overhead transmissions line running north and south on the east side of CTH F that crosses CTH K at approximately Station 11K+00. No conflicts anticipated.

AT&T Wisconsin (Communications) Underground communication line crossing at approximately Station 6K+85 that transitions to run north along CTH F. No conflicts anticipated.

Spectrum (Communications) Underground communication lines running north and east through the CTH F & CTH K intersection and overhead communication lines attached to We Energies poles on the south side of CTH K.

Overhead communication line conflict from approximately Station 13K+50 – Station 15K+00 with We Energies poles holding overhead communication lines within the CTH K clear zone. Prior to construction, the We Energies wood poles in conflict will be relocated south per the accepted We Energies electric work plan. Spectrum overhead facilities will be transferred to newly placed We Energies wood poles after the We Energies relocations.

Bluebird (Communications) Underground fiber lines running east and west on the south side of CTH K. Shallow fiber in conflict with proposed pavement sections on CTH F from approximately Station 9K+25 – Station 11K+00. Prior to construction, fiber lines in conflict will be relocated to depth of 5-ft.

We Energies (Electric) Underground electrical line running north, east, and west through the CTH F & CTH K intersection and overhead electric distribution lines on the south side of CTH K. Prior to construction, electrical lines in conflict will be relocated as follows per the accepted We Energies electric work plan:

Overhead facilities west of CTH F will be relocated underground near approximately Station 4K+00 – 7K+00 to 60-ft RT to maintain clear zone requirements.

Overhead facilities east of CTH F will also be relocated further south near approximately Station 13K+00

– 14K+50 to 54-ft RT to maintain clear zone requirements.

We Energies (Gas) Underground gas lines running east and west under CTH K throughout the project area. Gas lines from approximately Station 4K+00 – Station 17K+00 is in conflict with proposed roadway construction. Prior to construction, gas lines in conflict will be relocated as follows per the accepted We Energies work plan:

Gas facilities will be relocated from approximately Station 4K+00 – Station 8K+50 to an offset of 55-ft LT approximately 3-ft from the edge of R/W to avoid roadway conflicts.

Gas facilities will be relocated from approximately Station 8K+50 – Station 13K+50 to an offset ranging from 55-ft LT to 110-ft LT approximately 3-ft from the edge of R/W from Station 11K+50 – Station 13K+50 to avoid roadway conflicts.

Gas facilities will be relocated from approximately Station 13K+50 – Station 17K+00 to an offset of 40-ft LT approximately 3-ft from the edge of R/W to avoid roadway conflicts.

2450-06-71 7 of 23

8. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm Water Discharges.

The following Project IDs have one acre or more of land disturbing construction activity and are required to obtain coverage under the TCGP. The permit requirements are part of the contract:

Project ID Design Calculated Amount of Land Disturbing Construction Activity (acres)

2450-06-71 2.52 Acres

This permit is the Wisconsin Pollutant Discharge Elimination System, Transportation Construction General Permit, (WPDES Permit No. WI-S066796-2) and is located at:

https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp

The department will apply for coverage under the TCGP upon submittal of the complete ECIP from the contractor, and concurrent with the department providing the ECIP to the Department of Natural Resources (DNR). The DNR will convey permit coverage upon the department’s approval of the ECIP and DNR concurrence that the project has met the requirements for coverage under the TCGP.

Do not begin land disturbing construction activity until the ECIP is approved and the DNR conveys TCGP coverage for the project.

A “Certificate of Permit Coverage” will be provided by the DNR upon conveyance of coverage under the permit. Post the “Certificate of Permit Coverage” in a conspicuous place at the construction site.

Stormwater discharge permit coverage for additional land disturbing construction activities related to contractor means and methods, including temporary support activity sites, will be considered as part of the ECIP review and approval process. Coverage under the TCGP for additional land disturbance areas will be considered if the areas meet all of the following:

• Must meet the TCGP applicability criteria.

• Must be for the exclusive use of WisDOT projects.

• Land disturbance first commences after the ECIP approval, and the areas are fully restored to meet the final stabilization criteria of the TCGP upon completion of the work.

Obtain any permits for areas that are not approved by the department for coverage under the TCGP.

stp-107-056 (20260701)

9. Erosion Control.

Add to standard spec 107.20 with the following:

Erosion control best management practices (BMP’s) shown on the plans are at suggested locations. The actual locations will be determined by the contractor’s ECIP and by the engineer. Include dust control and each dewatering or by-pass (mechanical pumping) operation in the ECIP submittal. The ECIP will supplement information shown on the plans and not reproduce it. The ECIP will identify how to implement the project’s erosion control plan. ECIP will demonstrate timely and diligently staged operations, continuing all construction operations methodically from the initial removals and topsoil stripping operations through the subsequent grading, paving, re-application of top soil, and restoration of permanent vegetation to minimize the period of exposure to possible erosion.

Provide the ECIP 14 days prior to the pre-construction meeting. Provide 1 copy of the ECIP to the department and 1 copy of the ECIP to the WDNR Liaison Craig Webster at Craig.Webster@wi.gov. Do not implement the ECIP without department approval and perform all work conforming to the approved

ECIP.

Maintain Erosion Control BMP’s until permanent vegetation is established or until the engineer determines that the BMP is no longer required.

Stockpile excess materials or spoils on upland areas away from wetlands, floodplains, and waterways.

Prevent the discharge of sediment eroding from soil stockpiles. If soil stockpiles will be left for more than 14 days, install temporary stabilization measures as the engineer orders and as identified in the approved

ECIP.

https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp mailto:Craig.Webster@wi.gov

2450-06-71 8 of 23

Any and all disturbed areas, not permanently restored in 14 or less days, must be temporary seeded and mulched within 5 days of any or repeated disturbances.

When land disturbing construction activities have temporarily ceased and will not resume for a period exceeding 14 calendar days, install temporary stabilization measures as the engineer orders and as identified in the approved ECIP.

As the ECIP is developed, remember all select sites for waste and/or borrow must be an adequate distance from and not within any waterway, wetland, or floodplain. Select sites must have erosion control measures installed to prevent offsite sediment runoff, both temporary and/or permanent. Additional environmental review must be conducted on select sites that are not permitted (commercial) facilities.

Non-permitted selected sites must be identified in the ECIP and will be subject to additional DNR review and coordination.

Final stabilization activity shall commence when land disturbing activities cease, and final grade has been reached on any portion of the site.

10. Nighttime Work Lighting-Stationary.

A Description

This special provision describes furnishing portable lighting as necessary to complete nighttime work.

Nighttime operations consist of work specifically scheduled to occur after sunset and before sunrise.

B (Vacant) C Construction

C.1 General This provision shall apply when providing, maintaining, moving, and removing portable light towers and equipment-mounted lighting fixtures for nighttime stationary work operations, for the duration of nighttime work on the contract.

At least 14 days before the nighttime work, furnish a lighting plan to the engineer for review and acceptance. Address the following in the plan:

1. Layout, including location of portable lighting – lateral placement, height, and spacing. Clearly show on the layout the location of all lights necessary for every aspect of work to be done at night.

2. Specifications, brochures, and technical data of all lighting equipment to be used.

3. The details on how the luminaires will be attached.

4. Electrical power source information.

5. Details on the louvers, shields, or methods to be employed to reduce glare.

6. Lighting calculations. Provide illumination with average to minimum uniformity ratio of 5:1 or less throughout the work area.

7. Detail information on any other auxiliary equipment.

C.2 Portable Lighting

Provide portable lighting that is sturdy and free standing and does not require any guy wires, braces, or any other attachments. Furnish portable lighting capable of being moved as necessary to keep up with the construction project. Position the portable lighting and trailers to minimize the risk of being impacted by traffic on the roadway or by construction traffic or equipment. Provide lightning protection for the portable lighting.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .