20261110014proposal.pdf

PDF 4 MB Posted

Attached to
C Milwaukee, W National Ave 27th St to 1st St STH 59
Solicitation number
20261110014​
Issued by
Milwaukee County, Mattoon Village, Wisconsin

About this file

Summary

This is a proposal document for a construction contract issued by the Wisconsin Department of Transportation (WisDOT) for improvements to State Highway 59 (STH 59) in Milwaukee, Wisconsin, spanning West National Avenue from 27th Street to 1st Street in Milwaukee County. The project encompasses pavement removal, excavation, contaminated soil removal, storm sewer installation, underground conduit work, base aggregate placement, concrete curb and gutter construction, concrete and asphalt pavement work, concrete sidewalk installation, signing, pavement marking, street lighting, traffic signals, traffic control, erosion control, and restoration activities. The work is divided into four construction stages occurring over multiple years, with Stage 1 and Stage 2 scheduled for 2027, Stages 3 and 4 for 2028, and completion of ancillary work in 2029. Contractors must begin work within 10 calendar days of written notice to proceed. The contract includes multiple interim completion deadlines with specific liquidated damages ranging from $3,000 to $7,000 per calendar day for delays, including reopening of STH 59 to one through lane in each direction by October 24, 2027, and October 25, 2028.

Bidders must submit proposals electronically via the Bid ExpressTM system or on paper with accompanying diskette/CD-ROM, with an administrative fee of $75 per proposal for paper submissions. A proposal guaranty bond must be submitted with all bids. The contractor must provide a performance bond and payment bond for the full contract amount and maintain an annual bid bond on file with WisDOT. The special provisions document includes extensive traffic control requirements, utility coordination procedures, environmental protections including federally protected bat habitat considerations, holiday and special event work restrictions, and driveway access maintenance protocols for 68 properties along the project corridor. Significant utility relocations by AT&T Local Network and AT&T Wisconsin, We Energies, and other service providers must be coordinated prior to and during construction, with preliminary utility work anticipated to commence 125 working days before construction begins.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

!#��$�%��!����#�#��!"%�&�'���('�'����)**)�+��,-.����)�/#�#��0�01��2 3121�����2 ���4150�21�5���0��6 ������� 5�760�'���8��8-� �9/:��'�'-�*� :�;��<�

>'-#A�/#�#����#�/# /%B��&+ ;��<�

%A����������>� C�D#A !C ���E!

C��CC

�#�#A !#�$%��!����#�#��!>���!� ��C�!

<�#A#A �C@ C� F

�#$�����������)%A

��CC

�!��A�!CC

�����>�!C#�� �$������<��=$��#A !#�$#A C ��E!�# C���G #��!�#A C>��!�� ��C�!

�<�#A�#A !C C����������H F !#���!C�:�!C�#��!�)���������I ���!#D�H F C���D��� !#��$�%��!����#�#��!J*K�>���)�� ?##� A����������I

���!#D��!��� =��$�#A����?IL)M�C�/

�,N� ���%�� ;�D��&>�'�'+?���E!

C�"���C@�!#�E C�M ���L!# �I��� �O P���� ��

>�?CC�

��>�:�#D>�/#�# >�Q���:�C %A��� �!#�� #���� R C

���EA#)%A��

�#A�##A !C ���E!

C��CC

�>C �D�<��!>���!� #A���S C� �$#A C���@ T#A�##A

��CC

�A�� R���!

C�!C �� ��D�� C#A ��C$���#A

���!�>B�EA<�D���=��������>�!C����CC

!C�>�!CA�� A

C#A �!C

���##�!E#A��������������CT�!C#A�##A

��CC

����E ����D

�A�@ �#A �C�� #�D���!C�� #�D> C�!#��!D�E�

C�!�!D ��� ���!>���#A !�!D� #��!�!�

��CC�!E�! �!!

#��!<�#A#A��������������C)2U�VUW�XYZV[�VUW\]Ŷ_[�U]�X̀abYW�WcYX��YZcd\e��U]f��]UgUX\h�dc_V�X̀abYWWYVZ�\V�_h_iW]UVYi�aYj�UV�Wc_��VW_]V_Wk/ C��!C��<��!�#��� �#A���C�# �lllllllllllllll,/�E!�# >� �#��D�� ��$���� �!��!.,���!#����%D�

���
>��#��D��

�:��������!�LR���

�. ,M�CC

��/�E!�# .,���!#����%D�

�M�CC

.,M�CC

.3U]�2_g\]Wb_VW�7X_��Vhe0eg_�Um��U]fn �#� ��$�?<��C�"�# C "�# �I ���!#D�H C �#��D�/

��o��16�0�3���p�22�6���7����1�

H

��@���>�I��C�!E>�?EE�

E�# !#>�?��A��#���@ ����!C�I �/�C �>�L�����!:�!#���>�� !#�/�E!�!E>�%��$$� �:�!#���>���@

!#�;��=�!E>�N�EA#�!E>�%��$$� �/�E!���>�9%/>�H

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

2410-10-71 1 of 144

Special Provision Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Prosecution and Progress

4. Traffic

5. Holiday and Special Event Work Restrictions

6. Utilities

7. Other Contracts

8. Railroad Insurance and Coordination - Soo Line Railroad Company (CP)

9. Hauling Restrictions

10. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

11. Erosion Control

12. Archaeological and Historical Sites

13. Notice to Contractor – Field Office

14. Notice to Contractor – S 4th Street Pedestrian Tunnel

15. Notice to Contractor – Hollow Sidewalks

16. Notice to Contractor – City of Milwaukee Forestry

17. Notice to Contractor – Work By Others

18. Notice to Contractor – Milwaukee County Transit System

19. Notice to Contractor – Creosote Lumber

20. Notice to Contractor, Native American Tribal Coordination

21. Notice to Contractor, City of Milwaukee Street Lighting Coordination

22. Municipality Acceptance of Water Main Construction and Electrical Construction

23. Referenced Construction Specifications

24. Coordination with Businesses and Residents

25. Public Convenience and Safety

26. Abandoning Sewer, Item 204.0291.S

27. Removing Traffic Signals W National Ave & S 21st St, Item 204.9060.S.201; Removing Traffic

Signals W National Ave & S 19th St, Item 204.9060.S.202; Removing Traffic Signals W National Ave & S 16th St, Item 204.9060.S.203; Removing Traffic Signals W National Ave & S 11th St, Item 204.9060.S.204; Removing Traffic Signals W National Ave & S 9th St, Item 204.9060.S.205;

Removing Traffic Signals W National Ave & S 6th St, Item 204.9060.S.206; Removing Traffic Signals W National Ave & S 5th St, Item 204.9060.S.207; Removing Traffic Signals W National Ave & S 2nd St, Item 204.9060.S.208; Removing Traffic Signals W National Ave & S 1st St, Item 204.9060.S.209

28. Removing Poles, Item 204.9060.S.310

29. Removing Traffic Channelizing Curb Systems, Item 204.9090.S.001

30. Removing Aerial Cable, Item 204.9090.S.314

31. QMP Base Aggregate Dense 1 1/4-Inch Compaction, Item 371.2000.S

2410-10-71 2 of 144

32. Coloring Concrete Custom, Item 405.0200

33. QMP HMA Pavement Nuclear Density

34. Concrete Sidewalk 5-Inch, Item 602.0410

35. Storm Sewer Pipe Composite 12-Inch, Item 608.6012

36. Topsoil

37. Landscape Planting Surveillance and Care Cycles

38. Signs Type II

39. Traffic Control Channelizing Curb System, Item 643.0650

40. Temporary Audible Message Devices, Item 644.1900.S

41. Marking Line MMA 4-Inch, Item 646.1060.S; Marking Arrow MMA, Item 646.5060.S; Marking

Symbol MMA, Item 646.5260.S

42. Marking Bike Lane MMA. Item 646.7760.S

43. Electrical, General

44. Traffic Signals, General

45. Electrical Service Meter Breaker Pedestal W National Ave & S 24th St, Item 656.0201.001;

Electrical Service Meter Breaker Pedestal W National Ave & S 21st St, Item 656.0201.002;

Electrical Service Meter Breaker Pedestal W National Ave & S 19th St, Item 656.0201.003;

Electrical Service Meter Breaker Pedestal W National Ave & S 16th St, Item 656.0201.004;

Electrical Service Meter Breaker Pedestal W National Ave & S 11th St, Item 656.0201.005;

Electrical Service Meter Breaker Pedestal W National Ave & S 9th St, Item 656.0201.006;

Electrical Service Meter Breaker Pedestal W National Ave & S 6th St, Item 656.0201.007;

Electrical Service Meter Breaker Pedestal W National Ave & S 5th St, Item 656.0201.008;

Electrical Service Meter Breaker Pedestal W National Ave & S 4th St, Item 656.0201.009;

Electrical Service Meter Breaker Pedestal W National Ave & S 2nd St, Item 656.0201.010;

Electrical Service Meter Breaker Pedestal W National Ave & S 1st St, Item 656.0201.011

46. Pedestal Bases, Item 657.0100; Poles Type 3, Item 657.0310; Poles Type 9, Item 657.0345;

Poles Type 9 Special, Item 657.0347 Poles Type 10, Item 657.0350; Poles Type 10 Special, Item 657.0352; Traffic Signal Standards Aluminum 3.5-FT, Item 657.0405; Traffic Signal Standards Aluminum 13-FT, Item 657.0420; Traffic Signal Standards Aluminum 15-FT, Item 657.0425;

Monotube Arms 20-FT, Item 657.0520; Monotube Arms 25-FT, Item 657.0525; Monotube Arms 30-FT, Item 657.0530; Monotube Arms 35-FT Special, Item 657.0536; Monotube Arms 40-FT Special, Item 657.0541; Monotube Arms 45-FT Special, Item 657.0546; Luminaire Arms Single Member 4-Inch Clamp 6-FT, Item 657.0609

47. Signal Housings

48. Signal Mounting Hardware W National Ave & S 21st St, Item 658.5070.001; Signal Mounting

Hardware W National Ave & S 19th St, Item 658.5070.002; Signal Mounting Hardware W National Ave & S 16th St, Item 658.5070.003; Signal Mounting Hardware W National Ave & S 11th St, Item 658.5070.004; Signal Mounting Hardware W National Ave & S 9th St, Item 658.5070.005; Signal Mounting Hardware W National Ave & S 6th St, Item 658.5070.006; Signal Mounting Hardware W National Ave & S 5th St, Item 658.5070.007; Signal Mounting Hardware W National Ave & S 2nd St, Item 658.5070.008; Signal Mounting Hardware W National Ave & S 1st St, Item 658.5070.009

49. Lamp, Ballast, LED, Switch Disposal by Contractor, Item 659.5000.S

50. Temporary Traffic Signals for Intersections W National Ave & S 19th St, Item 661.0201.001;

Temporary Traffic Signals for Intersections W National Ave & S 16th St, Item 661.0201.002;

Temporary Traffic Signals for Intersections W National Ave & S 11th St, Item 661.0201.003;

Temporary Traffic Signals for Intersections W National Ave & S 9th St, Item 661.0201.004;

Temporary Traffic Signals for Intersections W National Ave & S 6th St, Item 661.0201.005;

Temporary Traffic Signals for Intersections W National Ave & S 1st St, Item 661.0201.006

51. Removing Concrete Pavement Modified, Item SPV.0035.001; Removing Asphaltic Surface Modified, Item SPV.0035.002

52. Utility Line Opening (ULO), Item SPV.0060.001

2410-10-71 3 of 144

53. Salvaging and Reinstalling Brick Pavers, Item SPV.0060.002

54. Adjusting Water Valve Boxes, Item SPV.0060.003

55. Water Main Protection, Item SPV.0060.004

56. Removing City-Owned Signs and Posts, Item SPV.0060.005

57. Moving City-Owned Signs, Item SPV.0060.006

58. Round Aluminum Sign Post System in Soft Surface 7-FT, Item SPV.0060.007; Round Aluminum

Sign Post System in Soft Surface 10-FT, Item SPV.0060.008; Round Aluminum Sign Post System in Soft Surface 11-FT, Item SPV.0060.009; Round Aluminum Sign Post System in Soft Surface 12-FT, Item SPV.0060.010

59. Round Aluminum Sign Post System in Concrete Surface 7-FT, Item SPV.0060.011; Round Aluminum Sign Post System in Concrete Surface 10-FT, Item SPV.0060.012; Round Aluminum Sign Post System in Concrete Surface 11-FT, Item SPV.0060.013; Round Aluminum Sign Post System in Concrete Surface 12-FT, Item SPV.0060.014

60. Pipe Bollards, Item SPV.0060.015

61. Marking Speed Table Chevron Contrast Epoxy, Item SPV.0060.016

62. Marking Bike Lane Two-Stage Turning Queue Box MMA, Item SPV.0060.017

63. Marking Yield Line MMA 18-Inch, Item SPV.0060.018; Marking Crosswalk MMA Block Style 12-

Inch, Item SPV.0090.007; Marking Bike Lane Crosswalk MMA Block Style 24-Inch, Item

SPV.0090.008

64. Inlet Covers Type MS 57, Item SPV.0060.102; Manhole Covers Type MS 58-A, Item SPV.0060.103; Catch Basins Type 44A, Item SPV.0060.110; Curb Inlets Type 70A, Item

SPV.0060.120

65. Storm Inlet Type 45A, Item SPV.0060.112

66. Pipe Connection to Existing Structure, Item SPV.0060.115

67. Traffic Signal Cabinet & Controller W National Ave & S 21st St, Item SPV.0060.201; Traffic Signal

Cabinet & Controller W National Ave & S 19th St, Item SPV.0060.202; Traffic Signal Cabinet & Controller W National Ave & S 16th St, Item SPV.0060.203; Traffic Signal Cabinet & Controller W National Ave & S 11th St, Item SPV.0060.204; Traffic Signal Cabinet & Controller W National Ave & S 9th St, Item SPV.0060.205; Traffic Signal Cabinet & Controller W National Ave & S 6th St, Item SPV.0060.206; Traffic Signal Cabinet & Controller W National Ave & S 5th St, Item SPV.0060.207; Traffic Signal Cabinet & Controller W National Ave & S 2nd St, Item SPV.0060.208; Traffic Signal Cabinet & Controller W National Ave & S 1st St, Item

SPV.0060.209

68. Emergency Vehicle Preemption System W National Ave & S 21st St, Item SPV.0060.210;

Emergency Vehicle Preemption System W National Ave & S 19th St, Item SPV.0060.211;

Emergency Vehicle Preemption System W National Ave & S 16th St, Item SPV.0060.212;

Emergency Vehicle Preemption System W National Ave & S 11th St, Item SPV.0060.213;

Emergency Vehicle Preemption System W National Ave & S 9th St, Item SPV.0060.214;

Emergency Vehicle Preemption System W National Ave & S 6th St, Item SPV.0060.215;

Emergency Vehicle Preemption System W National Ave & S 5th St, Item SPV.0060.216;

Emergency Vehicle Preemption System W National Ave & S 2nd St, Item SPV.0060.217;

Emergency Vehicle Preemption System W National Ave & S 1st St, Item SPV.0060.218

69. Video Detection System W National Ave & S 21st St, Item SPV.0060.219; Video Detection System W National Ave & S 19th St, Item SPV.0060.220; Video Detection System W National Ave & S 16th St, Item SPV.0060.221; Video Detection System W National Ave & S 11th St, Item SPV.0060.222; Video Detection System W National Ave & S 9th St, Item SPV.0060.223; Video Detection System W National Ave & S 6th St, Item SPV.0060.224; Video Detection System W National Ave & S 5th St, Item SPV.0060.225; Video Detection System W National Ave & S 2nd St, Item SPV.0060.226; Video Detection System W National Ave & S 1st St, Item SPV.0060.227

70. Accessible Pedestrian Push Button System W National Ave & S 21st St, Item SPV.0060.228;

Accessible Pedestrian Push Button System W National Ave & S 19th St, Item SPV.0060.229;

Accessible Pedestrian Push Button System W National Ave & S 16th St, Item SPV.0060.230;

Accessible Pedestrian Push Button System W National Ave & S 11th St, Item SPV.0060.231;

2410-10-71 4 of 144

Accessible Pedestrian Push Button System W National Ave & S 9th St, Item SPV.0060.232;

Accessible Pedestrian Push Button System W National Ave & S 6th St, Item SPV.0060.233;

Accessible Pedestrian Push Button System W National Ave & S 5th St, Item SPV.0060.234;

Accessible Pedestrian Push Button System W National Ave & S 2nd St, Item SPV.0060.235;

Accessible Pedestrian Push Button System W National Ave & S 1st St, Item SPV.0060.236

71. Rectangular Rapid Flashing Beacon System W National Ave & S 24th St, Item SPV.0060.237;

Rectangular Rapid Flashing Beacon System W National Ave & S 4th St, Item SPV.0060.238

72. Installing Precast Controller Base, Item SPV.0060.239

73. Traffic Signal LED No Left Turn Blank Out Signs, Item SPV.0060.240

74. Temporary Infrared EVP System W National Ave & S 19th St, Item SPV.0060.241; Temporary

Infrared EVP System W National Ave & S 16th St, Item SPV.0060.242; Temporary Infrared EVP System W National Ave & S 11th St, Item SPV.0060.243; Temporary Infrared EVP System W National Ave & S 9th St, Item SPV.0060.244; Temporary Infrared EVP System W National Ave & S 6th St, Item SPV.0060.245; Temporary Infrared EVP System W National Ave & S 1st St, Item

SPV.0060.246

75. Pull Boxes 13-Inch x 24-Inch x 24-Inch (Fiberglass Polymer Concrete), Item SPV.0060.302; Pull Boxes 17-Inch x 30-Inch x 24-Inch (Fiberglass Polymer Concrete), Item SPV.0060.303

76. Poles MKE 30 Black (30-FT Aluminum, Black, Bolt-Down), Item SPV.0060.321

77. 40-FT Wood Pole, Item SPV.0060.324

78. Submersible Multitap 3-Port Pre-Insulated Connector, Item SPV.0060.342; Submersible Multitap

4-Port Pre-Insulated Connector, Item SPV.0060.343

79. Luminaire Arms Single Member 6-FT WP Mount, Item SPV.0060.346

80. Luminaire Arms Truss Member 12-FT (WP Mount), Item SPV.0060.348

81. Installing Equipment Grounding Electrode, Item SPV.0060.353

82. Removing Bracket Arms and Luminaires, Item SPV.0060.354

83. Luminaire Utility 1LED2, Item SPV.0060.374

84. Luminaire Utility 2LED2, Item SPV.0060.375

85. Concrete Base Type 2 (Milwaukee), Item SPV.0060.388; Concrete Base Type 5 (Milwaukee), Item SPV.0060.389

86. Transformer Bases Breakaway 11 ½-Inch Bolt Circle Black, Item SPV.0060.399

87. 4’ Diameter Manhole Type CUC, Item SPV.0060.401

88. 4’ Diameter Doghouse Manhole Type CUC, Item SPV.0060.410

89. 4’ Diameter Doghouse Manhole Type CUC Installed Over Conduit, Item SPV.0060.411

90. Removing CUC Manhole, Item SPV.0060.420

91. Sawing Concrete-Encased Duct Package, Item SPV.0060.426

92. Adjusting CUC Manhole Cover Using EPP System, Item SPV.0060.430

93. Poles Type 15’-6” Black Aluminum Harp Pole and Shroud, Item SPV.0060.821

94. Luminaire Historic Black Milwaukee Harp LED Screw-In Lamp, Item SPV.0060.865

95. Luminaire Historic Black Milwaukee Lantern LED 3 Screw-In Lamp, Item SPV.0060.867

96. Fuse System On the Lighting Riser Cable In the Pole, Item SPV.0060.881

97. Concrete Curb & Gutter HES 19-Inch, Item SPV.0090.001; Concrete Curb & Gutter HES 31-Inch, Item SPV.0090.002

98. Concrete Curb & Gutter 31-Inch Type MCTS, Item SPV.0090.004; Concrete Curb Type D

Special, Item SPV.0090.005

99. Marking Stop Line Epoxy 24-Inch, Item SPV.0090.006; Marking Crosswalk Epoxy Transverse

Line 12-Inch, Item SPV.0090.009; Marking Crosswalk Epoxy Block Style 12-Inch, Item

SPV.0090.010

2410-10-71 5 of 144

100. City Furnished Electrical Cable 1#8 AWG 5kV Concentric, Item SPV.0090.300

101. Electrical Cable Type 2#2/1#4 AL, Item SPV.0090.304

102. Electrical Cable Type 3#12 UF With Ground, Item SPV.0090.309

103. Liquidtight Flexible Nonmetallic Conduit 1 ½-Inch, Item SPV.0090.319

104. Electrical Cable Type 4#2/1#8 XLP, Item SPV.0090.324

105. Conduit 3-Inch HDPE Schedule 40, Item SPV.0090.325; Conduit 3-Inch HDPE Schedule 80, Item

SPV.0090.326

106. 1-Duct Sand Encased Conduit, HDPE, 4-Inch, Item SPV.0090.451; 2-Duct Sand Encased

Conduit, HDPE, 4-Inch, Item SPV.0090.452; 3-Duct Sand Encased Conduit, HDPE, 4-Inch, Item SPV.0090.453; 4-Duct Sand Encased Conduit, HDPE, 4-Inch, Item SPV.0090.454; 6-Duct Sand Encased Conduit, HDPE, 4-Inch, Item SPV.0090.456

107. Fiber Optic Cable Outdoor Plant 72-Count, Item SPV.0090.601; Fiber Optic Cable Outdoor Plant 12-Count, Item SPV.0090.602

108. Detectable Edge Tiles, Item SPV.0165.001

109. Concrete Raised Median, Item SPV.0165.002

110. Track Zone Removal, Item SPV.0180.001

111. Excavation, Hauling, and Disposal of Metals Contaminated Soil, Item SPV.0195.001

112. Excavation, Hauling, and Disposal of PAH Contaminated Soil, Item SPV.0195.002

113. Excavation, Hauling, and Disposal of VOC Contaminated Soil, Item SPV.0195.003

114. Possible Management of Solid Waste, Item SPV.0195.004

2410-10-71 6 of 144

STSP’S Revised July 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

2410-10-71 C Milwaukee, W National Ave 27th St to 1st St

STH 59

Milwaukee County

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260701)

2. Scope of Work.

The work under this contract consists of pavement removal, excavation common, contaminated soil removal, storm sewer, city underground conduit, select crushed material, base aggregate dense, concrete curb and gutter, concrete pavement, asphalt pavement, concrete sidewalk, signing, pavement marking, street lighting, traffic signals, traffic control, erosion control, restoration, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notice to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

The contract time for completion is based on an expedited work schedule and may require extraordinary forces and equipment.

Protection of Endangered Bats Federally protected bats have the potential to inhabit the project limits because they roost in trees, bridges, culverts, and other structures. Roosts may not have been observed on this project, but conditions to support the species exist. The species and all active roosts are protected by the federal Endangered Species Act. If an individual bat or active roost is encountered during construction operations, stop work, and notify the engineer and the WisDOT Regional Environmental Coordinator

(REC).

Ensure all operators, employees, and subcontractors working in areas of known or presumed bat habitat are aware of environmental commitments and avoidance and minimization measures (AMMs) to protect both bats and their habitat.

Direct temporary lighting, if used, away from wooded areas during the bat active season April 15 to October 31, both dates inclusive.

2410-10-71 7 of 144

Tree Clearing/Trimming:

To avoid adverse impacts upon protected bats, do not perform tree clearing/trimming between April 15 and October 31, both dates inclusive. If the required tree clearing/trimming is not completed by April 14, the department will suspend all tree clearing/trimming and associated work directly impacted by clearing/trimming.Tree clearing/trimming is limited to that which is specified in the plans. Contractor means and methods to remove additional trees/branches will not be allowed. If it is determined that additional trees with a 3-inch or greater diameter at breast height (dbh), or branches of any size on those sized trees, need to be removed beyond contractor means and methods, notify the engineer to coordinate with the WisDOT REC to determine if consultation with United States Fish and Wildlife Service (USFWS) is required. The contractor must be aware that the WisDOT REC and/or USFWS may not permit modifications.

Due to potential for erosion, do not perform grubbing operations at the time of tree clearing unless grading activities will commence in those areas immediately following the tree clearing, or as otherwise approved by the engineer. Provide information for the grubbing and grading activities, including the schedule of operations, in the Erosion Control Implementation Plan (ECIP).

Submit a schedule and description of clearing operations with the ECIP 14 days prior to any clearing operations. The department will determine, based on schedule and scope of work, what additional erosion control measures shall be implemented prior to the start of clearing operations, and list those additional measures in the ECIP.

Branch trimming is incidental to other work if no other tree clearing work is necessary.

Schedule of Operations During roadway removals the existing curbs, terraces, and sidewalks shall remain unless they conflict with construction of the proposed roadway curb. When existing curb must be removed provide temporary pedestrian barricades between the existing sidewalk and the resulting dropoff from the removed curb.

Notify the engineer 14 calendar days before closures.

Close the outside lanes or shoulders for the installation of temporary traffic signals or temporary street lighting.

Staging sequence references shown on the temporary lighting plans are separate from and do not necessarily coincide with the traffic control staging references. Staging denoted below is traffic control staging.

Stage 1

Construct the eastbound lanes of STH 59 from S. 11th Street to S. 1st Street. The south legs of the intersections of S. 10th Street, S. 9th Street, S. 7th Street, S. 6th Street, S. 4th Street and S. 1st Street shall remain fully open to traffic at all times with the following exceptions. The south legs of the intersections of S. 10th Street and S. 9th Street shall be constructed one side at a time to maintain a minimum of one 11 foot lane. The south legs of the intersections of S. 6th Street and S. 4th Street may be closed for up to 21 consecutive calendar days to construct the intersections. The south leg of the 4th Street intersection shall not be closed until after June 15th. The S. 6th Street and S. 4th Street intersections shall not be closed at the same time unless S. 5th Street is open.

Construct temporary street lighting stage 1. The temporary street lighting stage reference numbers are separate from the traffic control stage reference numbers.

Stage 2

Construct the westbound lanes of STH 59 from S. 11th Street to S. 1st Street. The north legs of the intersections of S. 10th Street, S. 9th Street, S. 6th Street, S. 4th Street, S. 3rd Street and S. 1st Street shall remain open to traffic at all times with the following exceptions. The north legs of the intersections of S.

10th Street and S. 9th Street shall be constructed one side at a time to maintain a minimum of one 11-foot lane. The north legs of the intersections of S. 6th Street, S. 4th Street and S. 3rd Street may be closed for up to 21 consecutive calendar days to construct the intersections. Eastbound STH 59 from S. 2nd Street to S. 1st Street may be closed for up to 21 consecutive calendar days to construct the west side of the S.

1st Street intersection. The intersection of S. 1st Street may be reduced to one lane in each direction for up to 42 consecutive calendar days to construct the intersection. The S. 6th Street and S. 4th Street intersections shall not be closed at the same time unless S. 5th Street is open. The S. 6th Street intersection shall not be closed while S. 1st Street is reduced to one lane in each direction.

2410-10-71 8 of 144

Construct temporary street lighting stages 2 and 3. The temporary street lighting stage reference numbers are separate from the traffic control stage reference numbers.

Stage 3

Construct the eastbound lanes of STH 59 from S. Layton Boulevard to S. 11th Street. The south legs of the intersections of S. 17th Street, S. 16th Street, and S. 11th Street shall remain open to traffic at all times with the following exceptions. The south legs of the intersections of S. 16th Street and S. 11th Street may be closed for up to 21 consecutive calendar days to construct the intersections. The S. 16th Street and S.

11th Street intersections shall not be closed at the same time.

Construct temporary street lighting stage 4. The temporary street lighting stage reference numbers are separate from the traffic control stage reference numbers.

Stage 4

Construct the westbound lanes of STH 59 from S. Layton Boulevard to S. 11th Street. The north legs of the intersections of S. 16th Street and S. 11th Street shall remain open to traffic at all times with the following exceptions. The south legs of the intersections of S. 16th Street and S. 11th Street may be closed for up to 21 consecutive calendar days to construct the intersections. The S. 16th Street and S.

11th Street intersections shall not be closed at the same time.

Construct temporary street lighting stages 5 and 6. The temporary street lighting stage reference numbers are separate from the traffic control stage reference numbers.

W. Greenfield Avenue

Construct the railroad crossing on W. Greenfield Avenue by closing eastbound and westbound traffic on Greenfeld Avenue from Miller Park Way to S. 42nd Street. W. Greenfield Avenue shall not be closed until after July 6, 2027.

Winter Shutdowns

Winter shutdowns will commence with the completion of Stage 2 in the Fall of 2027 and the completion of stage 4 in the Fall of 2028.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .