20261013009proposal.pdf

PDF 2 MB Posted

Attached to
Pavement Repairs & Replacement
Solicitation number
20261013009
Issued by
Fond Du Lac County, Wisconsin

About this file

This proposal package is issued by the Wisconsin Department of Transportation for two pavement repair and replacement projects located in Fond du Lac County along Interstate 41 and US Highway 151. The work consists of concrete pavement repair and replacement, HMA pavement, storm sewer installation, trenchless storm sewer installation, cable barrier installation, pavement marking, and associated incidental items. The projects are designated as 1100-56-70 and 1100-56-71 and are organized into four construction stages: Stage 1 involves storm sewer construction from IH 41 to the Fond du Lac River; Stage 2 addresses IH 41 northbound inside lane pavement repairs and asphalt shoulder resurfacing; Stage 3 covers IH 41 southbound outside lane pavement repairs, asphalt shoulder resurfacing, and ramp work; and Stage 4 includes median work with grading, guardrail replacement, and cable barrier replacement. Interim completion milestones include reopening the IH 41 northbound Hickory Street exit ramp within 19 calendar days and the southbound Hickory Street entrance ramp within 5 calendar days, with liquidated damages of $3,000 and $2,000 per day respectively for delays beyond these periods. Contractors must begin work within 10 calendar days of receiving written notice to proceed and are restricted to three separate nighttime closures of IH 41 northbound and southbound during off-peak hours for storm sewer work.

Lane rental fees are assessed at $1,750 per lane per direction of travel per hour (broken into 15-minute increments) for closures outside designated allowable times, with single lane closures permitted between 7:00 PM and 6:00 AM Monday through Thursday and extended hours on weekends and Friday. Contractors must comply with all Wisconsin Department of Transportation standard specifications for 2025, maintain railroad coordination with Wisconsin Central Ltd, coordinate with multiple utility companies including Alliant Energy, ANR Pipeline, AT&T, and others, and obtain appropriate permits including Section 404 U.S. Army Corps of Engineers permits and WPDES Transportation Construction General Permit coverage for stormwater discharge. The proposal requires submission of a proposal guaranty bond, a list of proposed subcontractors with written bids submitted at least 48 hours before bid closing, and certifications regarding debarment and suspension. Bidders may submit proposals electronically through Bid Express, on printouts with accompanying diskettes or CD-ROMs, or via paper bid under waiver (subject to a $75 administrative fee). All work must comply with Wisconsin non-discrimination employment statutes, fish spawning restrictions prohibiting instream disturbance from March 1 to June 15, and special event work restrictions during Memorial Day, Independence Day, EAA AirVenture, Labor Day, and Lambeau Field events with attendance over 30,000.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"��#�$�� ����"�"�� !$%&�'��%('�'����)**)���%+,-����)�."�"��/�/0��1 2010�����1 ���304/�10�4���/��5 ������� 4�65/�%%��7&*7,� (8 9� :�!

�;���7�<�=>��=?@.A�%&%�7�B$A�! CA��D% 9� :�!

�;��%%��7&*7,% �C.B��'�',�%� 9� :�!

�;���7�<�=>��=?@.A�%&%�7�B$A�! CA��D% 9� :�!

:�E"= ���F G�"="= �:H I

��H �#������G��>#��"= �����H ��F �" :���J �G�"=�"= :����������K I "��� :�B� :�"�� �)���������L ��� "E�K I :���E��� "��#�$�� ����"�"�� M'*�?���)�� 8""��=����������L

��� "E�� ����>��#�"=����8LN)O�:�.

��%P?�'�'*%%������B� "���"�B���� ��'�?�'�',8���F :�!���:H� "�F :�O ���N " �L��� �Q 9���� �� ?�8::� ��?�B�"E?�."�" ?�R���B�:

S �����H ���F=")$=��� ���F �E�G�� ?��� � "=���T "�"�H :���H U"=�""= S��� ��E�� ��� �?A�F=G�E���>��������?� :����::

���""� F"=��������������:U� :"=�""= ����F ����E

�=�H �"�E��� :�� �"�E?

:� "�� E�F�

:� � E���� �G�� � E��"�� � �

"�"�H ��::� F� �� �"�� G�"="=��������������:)1V�WVX�YZ[W\�WVX]̂Z_̀\�V̂�YabcZX�XdZY��Z[de]f��V̂g��̂VhVY]i�ed̀W�YabcZXXZW[�]W�̀ìjX̂VWZj�bZk�VW�Xd̀��WX̀ Ŵ̀Xl.

:�� :��G�� �"��� �mmmmmmmmmmmmmmm+.�F �" ?� �"��E�� ��#������ �� -+��� "����$E�

���
?��"��E��

�B�������� �NS���

�- +O�::

��.�F �" -+��� "����$E� �O�::

-+O�::

-2V̂�1̀ h]̂Xc ẀX�6Ỳ��Wif/fh̀�Vn��V̂go �"�� ��#�8G��:�!�" �L ��� "E�K : �"��E�.

��p��05�/�2���q�11�5���6����0�

K ��H���?�r���� F?�L��:� F?�8FF� F�" ?�B� �� ���H "?�8��=��"���H �K �K =�����"�"�� ?�B �H ?�B ���� :�L �?�B� �� G��>?�."����.

G �?�O ���L ��:?�N����� �B� "���?�� "�.�F � F?�$��##���B� "���?���H "r��>� F?�.� �"��E?���" �?�K

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

1100-56-70, 1100-56-71 1 of 54

Special Provisions Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Prosecution and Progress

4. Lane Rental Fee Assessment

5. Lane Rental Fee Assessment for Lambeau Field Events

6. Traffic

7. Holiday and Special Event Work Restrictions

8. Utilities

9. Railroad Insurance and Coordination - Wisconsin Central Ltd (CN)

10. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit

11. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

12. Environmental Protection, Dewatering

13. Environmental Protection, Aquatic Exotic Species Control

14. Notice to Contractor, Airport Operating Restrictions

15. Notice to Contractor, ANR Pipeline Coordination

16. Notice to Contractor, FlixBus Coordination

17. Coordination with Businesses and Residents

18. Removing Crash Cushion, Item 204.9060.S

19. Sawing Pavement Deck Preparation Areas, Item 509.0310.S

20. Concrete Masonry Deck Repair, Item 509.2100.S

21. Storm Sewer

22. Pipe Grates 36-Inch, Item 611.9850.S.01; Pipe Grates 54-Inch, Item 611.9850.S.02; Pipe Grates

24x38-Inch, Item 611.9850.S.03

23. Cable Barrier Type 1, Item 613.1100.S; Cable Barrier End Terminal Type 1 Item 613.1200.S

24. Nighttime Work Lighting-Stationary

25. Traffic Control

26. Digital Speed Reduction System (DSRS), Item 643.0370.S

27. Basic Traffic Queue Warning System, Item 643.1205.S

28. Temporary Audible Message Devices, Item 644.1900.S

29. Repair Chain Link, Item SPV.0060.01

30. Concrete Barrier Transition, Item SPV.0060.02

31. Connect to Existing Structure, Item SPV.0060.03

32. Geotechnical Instrumentation, Item SPV.0060.04

33. Inclinometer Casing, Item SPV.0060.05

34. Settlement Monitoring Point, Item SPV.0060.06

35. Structure Survey Target, Item SPV.0060.07

1100-56-70, 1100-56-71 2 of 54

36. Utility Line Opening, Item SPV.0060.08

37. Sawing Concrete Barrier Single Faced, Item SPV.0060.09

38. Joint Sealing, Item SPV.0090.01

39. Trenchless Storm Sewer Pipe Reinforced Concrete Class V 54-Inch, Item SPV.0090.02

40. Excavation, Hauling, and Disposal of VOC Contaminated Soil, Item SPV.0195.01

41. Excavation, Hauling, and Disposal of Pesticide Contaminated Soil, Item SPV.0195.02

1100-56-70, 1100-56-71 3 of 54

STSP’S Revised April 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

1100-56-70 Fond du Lac – Oshkosh

USH 151 – CTH D

IH 41

Fond du Lac County

1100-56-71 Fond du Lac – Oshkosh

USH 151 – CTH D

IH 41

Fond du Lac County

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260401)

2. Scope of Work.

The work under this contract consists of concrete pavement repair & replacement, HMA pavement, storm sewer, trenchless installation of storm sewer, cable barrier, pavement marking, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notice to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

IH 41 NB and SB will each be allowed to be fully closed separately for 3 nights each during off-peak hours to complete the storm sewer work crossing IH 41 at 2251+28 to 2252+00, 2257+20 to 2257+27, and 2260+54. Do not close IH 41 NB and IH 41 SB at the same time for this work. See the Traffic article for allowable time periods and Lane Rental Fee Assessment article for assessments charged for closures outside the allowed time periods.

Construction Overview Stage 1

• Storm sewer construction from IH 41 to the Fond du Lac River

Stage 2

• IH 41 inside lane pavement repairs and asphalt shoulder resurfacing Stage 3

• IH 41 outside lane pavement repairs and asphalt shoulder resurfacing

• IH 41 ramp work including pavement repairs, asphalt shoulder resurfacing and storm sewer

1100-56-70, 1100-56-71 4 of 54

Stage 4

• IH 41 median work including grading, guardrail replacement and cable barrier replacement

Interim Completions Interim Completion and Liquidated Damages – IH 41 Northbound/Hickory Street exit ramp: 19 Calendar Days At the beginning of storm sewer work crossing the ramp at 2252+00 to 1253’E’+20, close the IH 41 NB Hickory Street exit ramp to traffic for a maximum of 19 calendar days. Do not reopen until completing the following work: Storm sewer, gore area grading, guardrail, barrier wall, crash cushion, base, pavement, and pavement markings.

If the contractor fails to complete the work necessary to reopen the IH 41 NB Hickory Street exit ramp to traffic within 19 calendar days, the department will assess the contractor $3,000 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 19 calendar days. An entire calendar day will be charged for any period of time within a calendar day that the ramp remains closed beyond 12:01 AM.

Interim Completion and Liquidated Damages – IH 41 Southbound/Hickory Street entrance ramp: 5 Calendar Days At the beginning of storm sewer work crossing the ramp at 2251+09 to 2251+28, close the IH 41 SB Hickory Street entrance ramp to traffic for a maximum of 5 calendar days. Do not reopen until completing the following work: Storm sewer, guardrail, base, pavement, and pavement markings.

If the contractor fails to complete the work necessary to reopen the IH 41 SB Hickory Street entrance ramp to traffic within 5 calendar days, the department will assess the contractor $2,000 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 5 calendar days.

An entire calendar day will be charged for any period of time within a calendar day that the ramp remains closed beyond 12:01 AM.

If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

Fish Spawning There shall be no instream disturbance of East Branch of the Fond du Lac River at Station 141’HS’+50 as a result of construction activity under or for this contract, from March 1 to June 15, both dates inclusive, in order to avoid adverse impacts to fish and other aquatic organisms during sensitive time periods such as spawning and migration.

Any change to this limitation will require submitting a written request by the contractor to the engineer, subsequent review and concurrence by the Department of Natural Resources in the request, and final approval by the engineer. The approval will include all conditions to the request as mutually agreed upon by WisDOT and DNR.

WisDOT Park & Ride lot Once access to the WisDOT Park & Ride lot is closed, maintain sufficient resources, including personnel, equipment, and subcontractors, to proceed with the mill and resurface work with constant attention necessary to promote the progress of the work until the work is complete and the Park & Ride lot is reopened. Do not cease operations or move equipment to work on other areas of the project without prior written approval from the engineer.

Connector Trail to Wild Goose State Trail Once the connector trail to Wild Goose State Trail is closed, maintain sufficient resources, including personnel, equipment, and subcontractors, to proceed with the storm sewer replacement work across the connector trail with constant attention necessary to promote the progress of the work until the work is complete and the connector trail is reopened. Do not cease operations or move equipment to work on other areas of the project without prior written approval from the engineer.

1100-56-70, 1100-56-71 5 of 54

4. Lane Rental Fee Assessment.

A General The contract designates some lane closures to perform the work. The contractor will not incur a Lane Rental Fee Assessment for closing lanes during the allowable lane closure times. The contractor will incur a Lane Rental Fee Assessment for each lane closure outside of the allowable lane closure times. If a lane is obstructed at any time due to contractor operations, it is considered a closure. The purpose of lane rental is to enforce compliance of lane restrictions and discourage unnecessary closures.

The allowable lane closure times are shown in the Traffic article.

Submit the dates of the proposed lane, ramp, and roadway restrictions to the engineer as part of the progress schedule.

B Lane Rental Fee Assessment The Lane Rental Fee Assessment incurred for each lane closure, each ramp closure, and each full closure of a roadway, per direction of travel, is as follows:

- On Peak - $1,750 per lane, per direction of travel, per hour broken into 15-minute increments

The Lane Rental Fee Assessment represents a portion of the cost of the interference and inconvenience to the road users for each closure. All lane, roadway, or ramp closure event increments 15 minutes and less will be assessed as a 15-minute increment.

The engineer, or designated representative, will be the sole authority in determining time period length for the Lane Rental Fee Assessment.

Lane Rental Fee Assessments will not be assessed for closures due to crashes, accidents or emergencies not initiated by the contractor.

The department will assess Lane Rental Fee Assessment by the dollar under the administrative item Failing to Open Road to Traffic. The total dollar amount of Lane Rental Fee Assessment will be computed by multiplying the Lane Rental Assessment Rate by the number of 15-minute increments of each lane closure event as described above.

Lane Rental Fee Assessment will be in effect from the time of the Notice to Proceed until the department issues final acceptance. If interim completion time or contract time expires before the completion of specified work in the contract, additional liquidated damages will be assessed as specified in standard spec 108.11 or as specified within this contract.

stp-108-070 (20161130)

5. Lane Rental Fee Assessment for Lambeau Field Events.

A General This special provision describes lane rental fee assessments associated with Lambeau Field Events with expected attendance over 30,000.

The contract designates some lane closures to perform the work. The contractor will not incur a Lane Rental Fee Assessment for closing lanes during the allowable lane closure times. The contractor will incur a Lane Rental Fee Assessment for each lane closure outside of the allowable lane closure times. If a lane is obstructed at any time due to contractor operations, it is considered a closure. The purpose of lane rental is to enforce compliance of lane restrictions and discourage unnecessary closures.

No lane closures can be in place for events with expected attendance over 30,000 at Lambeau Field, 5 hours before the start of the event and 8 hours after the start of the event regardless of the allowable closures stated elsewhere in the contract.

Submit the dates of the proposed lane, ramp, and roadway restrictions to the engineer as part of the progress schedule.

B Lane Rental Fee Assessment The Lane Rental Fee Assessment incurred for each lane closure, each ramp closure, and each full closure of a roadway, per direction of travel, is as follows:

- $1,250 per lane, per direction of travel, per hour broken into 15-minute increments

1100-56-70, 1100-56-71 6 of 54

The Lane Rental Fee Assessment represents a portion of the cost of the interference and inconvenience to the road users for each closure. All lane, roadway, or ramp closure event increments 15 minutes and less will be assessed as a 15-minute increment.

The engineer, or designated representative, will be the sole authority in determining time period length for the Lane Rental Fee Assessment.

Lane Rental Fee Assessments will not be assessed for closures due to crashes, accidents or emergencies not initiated by the contractor.

The department will assess Lane Rental Fee Assessment by the dollar under the administrative item Failing to Open Road to Traffic. The total dollar amount of Lane Rental Fee Assessment will be computed by multiplying the Lane Rental Assessment Rate by the number of 15-minute increments of each lane closure event as described above.

Lane Rental Fee Assessment will be in effect from the time of the Notice to Proceed until the department issues final acceptance. If interim completion time or contract time expires before the completion of specified work in the contract, additional liquidated damages will be assessed according to standard spec

108.11 or as specified within this contract.

ner-643-020 (20221010)

6. Traffic.

General:

Maintain emergency vehicle access at all times.

Prior to any traffic control being placed, provide engineer, Wisconsin State Patrol, and Fond du Lac County highway department with the name and telephone number of the local person responsible for the emergency maintenance of traffic control.

IH 41:

Keep IH 41 and all ramps open to through traffic at all times for the duration of this project except as noted below and in the Prosecution and Progress article in these special provisions.

Reduce traffic to one lane in the immediate area of work operations with the use of traffic control devices to complete the work. Maintain a minimum of one 12-foot travel lane unless otherwise allowed by the engineer. Restore the roadway to normal two-way traffic operations at the end of each work day. Traffic shall not be allowed on any milled surface.

Lane Closure Restrictions Single lane closures on IH 41 are allowed as follows:

7:00 PM to 6:00 AM Monday night to Thursday morning

8:00 PM Thursday to 6:00 AM Friday

8:00 PM Friday to 7:00 AM Saturday

8:00 PM Saturday to 8:00 AM Sunday

8:00 PM Sunday to 6:00 AM Monday

Auxiliary lane closures are allowed anytime.

No lane or shoulder closures will be permitted during Holiday and Special Events listed in the Holiday and Special Events Restrictions article.

Shoulders may be closed if required by the work operation, but the right and left shoulder may not be closed in the same area at the same time without the approval of the engineer.

Ramp Closures:

Ramp closures are allowed during the single lane closures listed above; however, ramp closures shall not occur at consecutive interchanges and must be reopened when no active work is taking place.

Full Freeway Closure:

Full closure and detouring of freeway roads will be restricted as follows:

1100-56-70, 1100-56-71 7 of 54

10:00 PM to 5:00 AM nightly from Sunday night to Friday morning

10:00 PM to 6:00 AM nightly from Friday night to Sunday morning

The freeway may be closed to facilitate the construction of drainage crossings or other work approved by the engineer. Provide signed detour routes, as shown in the plans, fully open and free of construction during all full roadway closures.

Submit requests for closures 14 calendar days prior to the planned closure events. Notify State Patrol 7 calendar days prior to closures. Notify John Zettler (920) 929-7605 and Mike Born (920) 929-3492 from Fond du Lac County 14 calendar days prior to full freeway closures.

Freight Width Restriction IH 41 is a designated WisDOT Freight Network Route. Maintain a width restriction no less than 16 feet at all times in each direction outside of lane closure hours. Movement of OSOW freight is scheduled to occur during this construction project that will require a minimum of 16 feet of horizontal clearance. During allowed nightly closure timeframes, the effective width will be 10 feet and shall be posted as such prior to the lane closure and at the last exit ramp safe for exiting.

Enter in the correct minimum width restriction in Wisconsin Lane Closure System.

Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).

TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION

Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION

Lane and shoulder closures 7 calendar days

Full roadway closures 7 calendar days

Ramp closures 7 calendar days

Detours 7 calendar days

Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION

Shoulder Closures 3 calendar days

Lane closures 3 business days

Ramp closures 3 business days

Modifying all closure types 3 business days

Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.

Temporary Regulatory Speed Limit Reduction A reduction of the posted regulatory speed limit from 70 or 65 mph to 55 mph is required when any of the following conditions are created within the project limits: 1. Bi-directional traffic separated by tubular markers. 2. Lane(s) closed and workers are present within 12 feet of live traffic without positive protection.

No portion of sign text shall be visible when not in use, regardless if it is temporary or permanent regulatory speed limit sign.

During approved temporary regulatory speed limit reductions, install regulatory speed limit signs on the inside and outside shoulders of the roadway at the beginning of the reduced regulatory speed zone, after all locations where traffic may enter the highway segment or every 1/2 mile within the reduced regulatory speed zone. Signs shall be installed at the end of the temporary regulatory speed zone to designate the end of the temporary regulatory speed zone and inform drivers the posted regulatory speed limit reverts back to the original posted speed limit. To minimize possible confusion to the traveling public and to ensure appropriate speed enforcement, enhanced attention to placement and changing of speed limit signs is required.

During periods of no work activity when devices are pulled back and lanes re-opened, restore speed limit to normal posted speed.

1100-56-70, 1100-56-71 8 of 54

When construction activities impede the location of a post mounted regulatory speed limit sign, mount the regulatory speed limit sign on portable supports that meet the "crashworthy" definition and height criteria in the Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD).

ner-643-055 (20210921)

Removing Guardrail The new guardrail system must be installed within 5 days of removal of the existing guardrail.

Portable Changeable Message Signs – Message Prior Approval After coordinating with department construction field staff, notify the Northeast Region Traffic Section at

(920) 366-8033 (secondary contact number is (920) 360-3107) 3 business days before deploying or changing a message on a PCMS to obtain approval of the proposed message. The Northeast Region Traffic Unit will review the proposed message and either approve the message or make necessary changes.

PCMS boards must be deployed 7 days before any closures.

ner-643-035 (20171213)

Expressway / Freeway Traffic Control Meeting Conduct a traffic control meeting before:

- Initial traffic control set up.

- Intermediate traffic switches.

- Reopening of the highway to traffic.

Notify the Northeast Region Traffic Work Zone Engineer at 920-366-8033 (secondary contact number is 920-360-3107) 7-business days before setting up the meeting.

ner-643-015 (20180529)

Temporary Work Zone Clear Zone Working Restrictions The temporary work zone clear zone for this project is 18-feet from the edge of traveled way. If auxiliary lanes are present, clear zone is from the outside edge of the auxiliary lane.

Do not perform work in the median at any time unless protected by concrete barrier temporary precast in both directions except as allowed during lane closure periods.

Do not perform work within the clear zone unless protected by concrete barrier temporary precast or a lane closure during the allowed closure periods.

Park equipment and store materials, including stockpiles, a minimum of 30-feet from the edge of the traveled way. Equipment may be parked and material stored in the median if it meets the minimum distance requirement from both traveled ways or if it is protected by concrete barrier temporary precast.

If unsure whether an individual work operation will meet the safety requirements for working within the clear zone, review the proposed work operation with the engineer before proceeding with the work.

Replace standard specification 305.3.3.3(2) with the following:

If the roadway remains open to through traffic during construction and a 2-inch or more drop-off occurs within the clear zone, eliminate the drop-off prior to completing that day’s work. Unless the special provisions specify otherwise, provide aggregate shoulder material compacted to a temporary 3:1 or flatter cross slope from the surface of the pavement edge.

ner-104-001 (20181017)

Local Roadways Keep Morris Street open at all times. Single lane closures using flaggers will be allowed during daytime working hours.The project area includes commercial properties that require trucking into and out of the properties on a daily basis. Coordinate with adjacent commercial properties to determine trucking schedules and access requirements.

Horseshoe Lane will be closed east and west of Morris Street. Coordinate with businesses west of Morris Street to provide access to these properties via either Morris Street or temporary roadway along Horseshoe Lane. Milk Specialties located at 1000 Morris Street has loading docks located between Stations 25’HS’+10 and 26’HS’+60 RT. The property owner will construct a temporary gravel access road within their property between the parking lot and loading dock area, allowing their semi-trucks to enter the

1100-56-70, 1100-56-71 9 of 54 property off Morris Street to access the loading docks. However, the semi-trucks will need to traverse into Horseshoe Lane to allow the truck and trailer to align with the dock prior to backing into the loading docks. Provide a 60’ wide area on Horseshoe Lane within the right-of-way limits between Stations 25’HS’+10 and 26’HS’+60 for the trucks to turn and back into the loading docks. Maintain the temporary gravel access road and parking area at 1000 Morri Street. Fill potholes, sags, and depressions within the temporary gravel areas on a weekly basis or as requested by the engineer.

Provide access to properties east of Morris Street with a temporary roadway (minimum base aggregate dense surface) as shown in the plans.

Existing trees, street light poles, hydrants, and other utility poles are to remain in place during construction unless otherwise noted in the plan. Maintain proper clearance between the trees, hydrants, and poles and the construction operations/equipment.

Coordinate with local officials, emergency responders, local residents, postal service, garbage and recycling services and school districts, concerning construction operations and scheduling prior to construction. Provide notification 4 days in advance of the start of work, closures of streets, and prior to traffic control changes.

Provide 24-hour contact information, including current…

This is the start of the file's text. The full file is on GovTribe.