2026 Ridgeview Park Improvements _ Project Ma.pdf

PDF 1 MB Posted

Attached to
27-010 Ridgeview Park Improvements
Solicitation number
PE-66098-NONST-2027-000000151
Issued by
Fulton County, Georgia

About this file

Ridgeview Park Improvements Project Summary

This is a project manual and scope of work document for the Ridgeview Park Improvements project managed by the City of Sandy Springs Recreation & Parks Department, located at 15 Simpson St. NW Atlanta, Georgia (Project No. 24148). The project encompasses site preparation, demolition, clearing, earthwork, and erosion control measures across multiple construction phases. Work includes site clearing and grubbing; demolition of existing structures, curbs, gutters, and concrete elements; excavation and grading to specified elevations; utility relocation and protection; installation of erosion and sedimentation controls; and final site stabilization with topsoil and vegetative cover. The project maintains phased operations to accommodate existing site users including tennis courts, playgrounds, and trails. Key specifications require compliance with Georgia Department of Transportation standards, ASTM testing procedures, and the Georgia Manual for Erosion and Sediment Control (2016 Edition). A designated erosion control superintendent with Level 1A certification from the Georgia Soil & Water Conservation Commission must remain on-site during all land disturbance activities, with daily inspection logs and weekly documentation of erosion control devices.

The project requires the contractor to obtain NPDES Phase II permit coverage and file Notice of Intent (NOI) documentation with Georgia's Environmental Protection Division 14 days prior to land disturbance. All materials, including fill, backfill, geotextiles, and erosion control blankets, must meet specified quality standards with independent testing agency verification. The contractor bears responsibility for all water damage, sediment control, and dewatering operations, including costs for unsuitable soil removal and replacement with approved materials. Construction scheduling must allow permanent erosion controls to be established within the same construction season, with temporary grassing applied within 14 calendar days of soil exposure and final grassing within 7 calendar days of reaching finished grades. The contractor is responsible for all site cleanup, debris removal, and restoration of adjacent properties affected by construction activities.

View the file

Other files

File Type Posted
ITB 27_010 Ridgeview Park Improvements.pdf PDF
Vendor Responsibility Questionnaire (VRQ).docx DOCX document
Site Work Construction Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ridgeview Park Improvements City of Sandy Springs

FOR

SANDY SPRINGS RECREATION & PARKS

15 Simpson St. NW Atlanta, GA 30308

Project No. 24148

Ridgeview Park Improvements TOC-1 BLP-24148 Table of Contents

TABLE OF CONTENTS

SECTION TITLE

31 0001 Site Preparation and General Site Work 31 0002 Site Demolition 31 1000 Site Clearing 31 2200 Earthwork 31 2500 Erosion and Sedimentation Controls 32 0500 Common Works for Exterior Improvements 32 0115 Flexible Paving and Rigid Paving Repair 32 1200 Flexible Paving 32 1301 Rigid Paving and Site Concrete 32 1413 Permeable Pavers 32 3113 Chain Link Fences and Gates 32 9200 Turf & Grasses 33 1100 Water Utility Distribution Piping 33 3000 Sanitary Utility Sewerage

Sandy Springs Recreation & Parks SITE PREPARATION AND GENERAL SITE WORK

BLP-24148 31 00 01 -1

09-08-2026

SECTION 31 00 01 – SITE PREPARATION AND GENERAL SITE WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Site work layout and construction survey.

2. Protecting existing vegetation to remain.

3. Protecting existing site improvements to remain.

4. Utility locates.

5. Disposition of utilities.

6. Maintain existing utility services.

7. Recycling and waste management for site materials.

8. Spill prevention

9. Final Cleanup

B. Related Sections:

1. 31 00 02 “SITE DEMOLITION” for removal of site improvements including utilities.

1.2 REFERENCE SPECIFICATIONS AND DOCUMENTS

A. Manual for Erosion and Sediment Control in Georgia, 2016 Edition, by the

Georgia Soil and Water Conservation Commission, “Best Management

Practices”. Apply to all land disturbing activities for all phases of Work.

B. American Society of Civil Engineers (ASCE)

1. ASCE CI 38-2: Standard Guideline for the Collection and Depiction of

Existing Subsurface Utility Data.

1.3 SUBMITTALS

A. Record Drawings: Record active, inactive, relocated, and abandoned utilities encountered.

1. Survey the horizontal and vertical positions, and depths to ground surface, for utilities capped, utilities uncovered during project operations and for utilities relocated. Survey shall be from established project control.

1.4 QUALITY ASSURANCE

A. Qualifications: The person in responsible charge of construction survey and survey of asbuilt/record drawing items shall be a Professional Land Surveyor licensed in the state of Georgia.

BLP-24148 31 00 01 -2

1.5 SITE CONDITIONS

A. Safety: Provide all safety fence barricades guards, lights and other installations required to protect persons and property during the work. This is in addition to such protection required elsewhere in the Contract documents.

At a minimum, secure all work areas and staging/storage areas with temporary construction safety fencing. Maintain such safety fencing to assure a complete boundary throughout construction.

B. Locate storage sheds, temporary office, and stockpiled material to best advance the progress of work, as approved by the Design Professional or in areas otherwise designated for Contractor’s use.

C. Existing conditions are shown on the drawings. Contractor shall visit the site, familiarize himself/herself with existing conditions in the field.

D. Contractor shall strictly adhere to the “Land Disturbance Construction Activity

Sequence” As defined in the Phase I Erosion and Sedimentation Control Plan only upon completion of applicable items in the sequence, shall the contractor expand clearing and grubbing operations to the entire site.

E. Items of historic or archaeological value discovered during construction operations shall remain the property of the Owner. Notify Design Professional immediately of any such type finding for instructions.

1.6 RECYCLING AND REFUSE COLLECTION CENTERS (WASTE MATERIALS)

A. The contractor shall provide appropriate refuse collection centers, which allow for glass, paper, and plastic separation. Said refuse collection centers shall be maintained on a weekly basis and transferred to an Owner-approved recycling and refuse center. The contractor shall also provide appropriate refuse containers for construction debris. Construction debris shall be recycled as possible and practical, especially in demolition and renovation situations (i.e., copper pipe, steel, concrete, glass, etc.). Illegal disposal of said materials (including littering) is subject to fines and penalties. The Contractor shall establish construction site policy and educate all construction personnel.

B. All waste materials shall be collected and stored in a securely lidded, metal dumpster. The dumpster shall be rented from and emptied by a Georgia licensed solid waste management company. The dumpster shall meet all County and State

Solid Waste Management regulations and ordinances. The dumpster shall be emptied as necessary, and the material shall be hauled to a State licensed landfill.

No construction debris shall be buried on the construction site. All personnel shall be informed and instructed regarding the correct procedure for waste disposal.

Notices stating these procedures shall be posted in the construction office and the construction superintendent shall be responsible for ensuring that these procedures shall be followed.

BLP-24148 31 00 01 -3

1.7 HAZARDOUS WASTE

A. All hazardous waste materials shall be disposed of in a manner specified by Georgia

State Solid Management regulations. All personnel shall be informed and instructed regarding the correct procedure for waste disposal. Notices stating these procedures shall be posted in the construction office, and the construction superintendent shall be responsible for ensuring that these procedures shall be followed.

1.8 SANITARY WASTE

A. All sanitary waste shall be collected from the portable units, as necessary, by a

Georgia State licensed sanitary waste management contractor, or as required by local regulations.

1.9 TEMPORARY FUELING TANK AREA

A. Temporary fueling tanks shall have a Georgia E.P.D. approved secondary containment (liner system) basin to prevent and/or minimize site contamination.

Temporary fueling tank locations shall be located remotely from drainage ways, drainage systems, and state waters (streams, springheads, etc.).

1.10 EQUIPMENT MAINTENANCE AREA

A. Equipment maintenance areas shall be clearly identified with signage. Said signage shall read as follows:

B. Sign shall be weatherproof and have a minimum size of 36” X 36”.

C. Equipment Maintenance Area(s) shall be located remotely from drainage ways, drainage systems, and state waters (streams, springheads, etc.).

PART 2 - PRODUCTS

2.1 CONSTRUCTION SURVEY AND LAYOUT EQUIPMENT

A. Surveyor's transit and measuring devices properly calibrated to accurately layout the work shall be used.

B. Provide stakes and batter boards of size and quality commensurate with function. Use wire or non-stretching cord to establish reference lines for site clearing and grading.

Equipment Maintenance Area

Discharge of new or used oil, fuel, lubricants, etc. is prohibited. Utilize containment/capture systems. Recycle used oils, contaminated fuels and lubricants. Illegal discharges are subject to fines and penalties.

BLP-24148 31 00 01 -4

2.2 PROTECTION MATERIALS

A. Materials for protection of existing work remaining shall be of the size, strength, and extent to provide adequate protection of existing work remaining.

2.3 REPAIR MATERIALS

A. Repair materials shall be of the same or better quality and performance as materials that are to be restored. Where possible, reuse existing materials that are removed.

PART 3 - EXECUTION

3.1 SITE WORK LAYOUT AND CONSTRUCTION SURVEY

A. Bench Marks and Monuments: Before commencing work verify bench marks and all reference points. If found at variance with the drawings, notify the

Design Professional immediately and prior to continuing with construction activities in that area.

B. Plainly mark all bench marks, and property corners and property lines as follows:

1. Mark all project bench marks and mark all property corners within 100 feet of construction limits by driving a 4 foot lath with appropriate offset (not to exceed 5 feet) from property pin or monument. Paint at least the upper 8” of the lath a bright yellow and clearly label the label the lath with the bench mark number and elevation, or label “property corner” as applicable.

2. Install 2’ lath, label “property line”, and tie a red ribbon to the lath every 50’ along property lines when project work coincides within 50 feet of property boundaries.

C. Carefully maintain all benchmarks, monuments and other reference points. If disturbed or destroyed, replace as directed, at no additional cost to the owner. Establish and maintain stakes as required for drives, parking, walks, underground vaults and structures, and other site improvements.

D. Flag or stake limits of construction and tree protection areas and install tree protection fencing to protect existing trees to remain.

E. As work progresses provide construction staking for grading (including subgrade, gravel courses, finish grade), points of curvature, points of tangency, grade changes, and for structures and miscellaneous site elements.

If discrepancies between actual lines, grades, and elevations exist, notify

Design professional before proceeding with layout of structure.

BLP-24148 31 00 01 -5

3.2 PROTECTING EXISTING VEGETATION TO REMAIN

A. All trees and vegetation marked to be saved or relocated shall be protected by temporary barricades, be watered and maintained where necessary, and replaced if damaged by construction. Root systems cut or damaged within work area during construction shall be pruned and protected from additional damage and covered with soil as soon as possible.

B. Under no circumstance, do not remove vegetation shown on the drawings to be saved, or marked by the Design Professional or Owner to be saved.

3.3 PROTECTING EXISTING SITE IMPROVEMENTS TO REMAIN.

A. Protect all existing curbs, sidewalks, buildings, utilities, and paving to remain.

B. If existing site improvements are damaged in performance of this work, restore such improvements without extra cost to the Owner.

3.4 UTILITY LOCATES

A. Utilities Protection Law (Dig Law): Comply with Georgia Utilities Protection

Law. Notice must be given to the Georgia Utilities Protection Center; by dialing 8-1-1 or 800-282-7411 at least 48 hours but no more than 10 days preceding the day mechanized digging is to begin. This notice shall contain

County (where project is located), Town (or closest City or Town), location

(street address), type of work to be done, name of Contractor, company name and address, telephone number, which company/individual the work is being done for, date and time the Contractor is planning to dig. Locates are valid for 30 days. Renew or call for re-mark as necessary.

3.5 DISPOSITION OF UTILITIES

A. Follow rules and regulations of authorities having jurisdiction for the respective utilities in executing work under this section.

B. Carefully locate existing underground utilities by hand excavation, potholing, vacuum excavation, or other methods. If utilities are to remain in place, provide protection from damage during construction operations.

C. Active Utilities Shown on Drawings or that are Visible Onsite: Protect from damage and remove or relocate as indicated or specified. All utilities

(including but not limited to: existing utility poles, guy wires, hydrants, meters, valve boxes) within the construction area that are evident from a visual inspection of the site shall be protected or relocated as necessary.

D. Active Utilities Not Shown on Drawings or Evident from Visual Inspection:

Protect or relocate in accordance with written instructions of the Design

Professional. Contract Sum may be adjusted for additional work in accordance with Contract Conditions.

BLP-24148 31 00 01 -6

E. Inactive and Abandoned Utilities:

1. Fully remove inactive and abandoned utilities only as shown.

2. Plug, cap, abandon in place utilities as shown. In absence of specific requirements, plug or cap such utility lines at least 4 feet outside of existing building walls, excavation limits, or as required by local regulations.

F. Repair damaged utilities to satisfaction of utility owner.

G. Accurately record locations of active and inactive utilities encountered during construction operations on record drawings.

3.6 MAINTAIN EXISTING UTILITY SERVICES

A. Cooperate with Owner and utility companies in keeping respective services and facilities in operation. Do not interrupt existing utility service facilities occupied and used by Owner or others, unless written permission is given by the Design Professional and then only after temporary utility services have been provided. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to governing authorities.

B. Provide not less than 72 hours’ notice to Owner if shutdown of service is required during a changeover.

1. Arrange to shut off indicated utilities with utility companies.

2. Where utility services are required to be removed, relocated, or abandoned, provide bypass connections to maintain continuity of service to other parts of the building before proceeding with selective demolition.

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal the remaining portion of pipe or conduit after bypassing.

3.7 DUST CONTROL

A. Keep airborne dust to a minimum by using water sprinkling or tossing and/or other suitable means to limit dust and dirt from rising and scattering in the air. Water all disturbed earth no later than 5 days from last rain or last watering.

3.8 POLLUTION AND SPILL PREVENTION

A. Control both air and water pollution. No tires, oils, asphalt, paint or coated metals are permitted in combustible waste piles. Pollutants such as fuels, lubricants, bitumens, raw sewage and other harmful materials will not be discharged into or near rivers, streams or man-made channels. Equipment maintenance shall be performed with containment and capture of used oi. Do not pour or drain used lubricants or other necessary mechanical fluids onto the ground. Remove from site and deliver to a recycling center. Utilize a concrete washout area and remove washed out concrete from the site.

B. Material Management Practices

BLP-24148 31 00 01 -7

1. The following material management practices shall be used to reduce the risk of spills or other accidental exposure of materials and substances to storm water runoff. Follow good housekeeping practices onsite during the construction project.

a. An effort shall be made to store only enough product required to do the job.

b. All materials stored onsite shall be stored in a neat, orderly manner in their appropriate containers and, if possible, under a roof or other enclosure.

c. Products shall be kept in their original containers with the original manufacturer’s label.

d. Substances shall not be mixed with one another unless recommended by the manufacturer.

e. Whenever possible, all of a product shall be used up before disposing of the container.

f. Manufacturer’s recommendations for proper use and disposal shall be followed.

g. The site superintendent shall inspect daily to ensure proper use and disposal of materials onsite.

C. Hazardous Products

1. The Contractor shall use the following practices to reduce the risks associated with hazardous materials:

a. Products shall be kept in original containers unless they are not resealable.

b. Original labels and material safety data shall be retained with the product by the General Contractor. They contain important product information.

c. Surplus products shall be disposed of following and in conformance with local and State recommended methods, NPDES permit requirements, and Federal Environmental Regulations.

D. Product Specific Practices

1. The following product specific practices shall be followed for products stored on-site:

a. Petroleum Products:

1) All on-site vehicles shall be monitored for leaks and receive regular preventive maintenance to reduce the chance of leakage.

Petroleum products shall be stored in tightly sealed containers that shall be clearly labeled and stored in a clearly identified area. Any asphalt substances used on-site shall be applied according to the manufacturer’s recommendations.

b. Fertilizers:

1) Fertilizers used shall be applied only in the minimum amounts recommended by the manufacturer. Once applied, fertilizer shall be worked into the soil to limit the exposure to storm water. Any fertilizers that are to be stored on-site shall be stored in a protected, securable enclosure. The contents of any partially used bags of fertilizers shall be transferred to a clearly labeled sealable plastic container to avoid spills.

c. Paints:

1) All containers shall be tightly sealed and stored when not required for use. Excess paint shall not be discharged to the storm sewer

BLP-24148 31 00 01 -8

system but shall be properly disposed of according to local and

State regulations.

d. Concrete:

1) Concrete trucks shall be allowed to wash out, discharge, and drum wash only at the identified equipment maintenance area(s).

Maintenance areas shall be equipped with a discharge containment area (e.g., earth berms surrounding area). The containment area shall be cleaned up and removed from the site upon completion of concrete installation work.

E. Spill Prevention and Cleanup

1. The following practices shall be followed for spill prevention and cleanup:

a. Local, State, NPDES, Federal Environmental, and Manufacturer’s recommended methods for spill cleanup shall be clearly posted and site personnel shall be made aware of the procedures and the location of the information and cleanup supplies.

b. Materials and equipment necessary for spill cleanup shall be kept in the material storage area on-site. Equipment and materials shall include but not be limited to brooms, dustpans, mops, rags, gloves, goggles, respirators, cat litter, sand, sawdust, and plastic and metal trash containers specifically for this purpose.

c. All spills shall be cleaned up immediately upon discovery.

d. The spill area shall be kept well ventilated and personnel shall wear the appropriate protective clothing to prevent injury from contact with a hazardous substance.

e. Spills of toxic or hazardous material shall be reported to the appropriate local or State government agency, regardless of size.

f. A spill prevention plan shall be implemented or adjusted to include measures to prevent this type of spill from reoccurring and how to clean up the spill if there is another one. A description of the spill, what caused it, and the cleanup measures shall also be included.

g. The General Contractor shall be responsible for assigning personnel to be responsible for spill prevention and cleanup coordination. The

General Contractor shall designate, at a minimum, three site personnel to receive spill prevention and cleanup training. These individuals shall each become responsible for a particular phase of prevention and cleanup. The names of responsible spill personnel shall be posted in the material storage area and in the on-site construction office.

3.9 WASTE MANAGEMENT

A. Clean and remove trash and debris on entire site, including trash and debris deposited from previous operations.

B. During construction, maintain a clean and orderly worksite. Do not dump or store debris on any part of the property unless authorized in writing by the

Owner and Design Professional. Debris may include but is not limited to trash, construction material, cleared vegetative matter, and boulders.

BLP-24148 31 00 01 -9

3.10 FINAL CLEAN UP

A. Remove Contractors office trailer, storage shelters, stockpiled materials, and equipment from the site.

B. Remove all remaining debris, or any other extraneous material deposited during construction from the site including all graded areas, and other undisturbed areas. All debris is the property of the Contractor and shall be hauled away from the site and disposed of lawfully.

C. Clean, sweep and wash the entire site, including areas outside of the “limits of disturbance” for final inspection. Provide required lawn maintenance to provide complete and finished appearance. Leave the site in a neat and orderly fashion for use by the Owner.

END OF SECTION 31 00 01

Sandy Springs Recreation & Parks SITE DEMOLITION

BLP-24148 31 00 02 -1

SECTION 31 00 02 – SITE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition of buildings and below grade foundations.

2. Selective demolition of site features.

3. Demolition of existing site elements.

4. Protection of existing site elements to remain.

5. Disposal of demolished materials.

B. Related Sections:

1. 31 00 01 “SITE PREPARATION AND GENERAL SITE WORK” for protection of existing facilities, protection of vegetation, utility locates, and utility protection, and maintenance of active utility service to portions of existing facilities schedule to remain open and in service during construction.

1.2 DEFINITIONS:

A. Remove: Remove and legally dispose of items except those indicated to be salvaged, or to remain the Owner’s property.

B. Remove and Salvage: Items indicated to be removed and salvaged remain the Owner’s property. Remove, clean, and pack or crate items to protect against damage. Identify contents of containers and deliver to Owner’s designated storage area.

C. Existing to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by the Design

Professional, items may be removed to a suitable, protected storage location during selective demolition and then cleaned and reinstalled in the original locations.

1.3 SUBMITTALS:

A. Prior to demolition work, submit the following for information only.

1. Proposed dust control measures.

2. Proposed noise control measures.

B. Schedule Selective Demolitions Activities Indicating the Following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Arrange selective demolition schedule so as not to interfere with Owner’s on-site operations.

2. Interruption of utility services.

BLP-24148 31 00 02 -2

3. Coordination for shutoff, capping, and continuation of utility services.

4. Detailed sequence of selective demolition and removal work to ensure uninterrupted progress of Owner’s on-site operations.

5. Coordination of Owner’s continuing occupancy of portions of existing building and of Owner’s partial occupancy of completed Work.

6. Locations of temporary partitions and means of egress.

C. Inventory of all items to be removed and salvaged.

D. Photographs or videotape, sufficiently detailed, of existing conditions of adjoining construction and site improvements that might be misconstrued as damaged caused by demolition operations.

E. As applicable, records indicating receipt and acceptance of solid waste and hazardous wastes by legal and licensed facilities to accept such wastes.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements:

1. Comply with hauling and disposal regulations of Georgia EPD

(Environmental Protection Division) and other authorities having jurisdiction.

2. Comply with applicable demolition requirements of local jurisdictions and the State of Georgia.

3. Comply with the requirements of NFPA 241, 2013 Edition, Standard for

Safeguarding Construction, Alteration, and Demolition Operations.

1.5 SITE CONDITIONS

A. Cooperation with the Owner in phasing the work to accommodate existing site users is of the essence. The Owner will occupy portions of the site / building adjacent to demolition areas as noted below:

1. Tennis Courts

2. Playground

3. Trails and Open Space

B. Conduct selective demolition so that the Owner’s operations will not be disrupted. Provide not less than 72 hours’ notice to Owner of activities that will affect Owner’s operations.

C. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain the Owner’s property, demolished materials shall become the Contractor’s property and shall be removed from the site with further disposition at the Contractor’s option.

D. Storage or sale of removed items or materials onsite will not be permitted.

E. All existing curb and gutter, paving, structures, utilities and all other existing items that are located where proposed items are to be built but are not shown

BLP-24148 31 00 02 -3

specifically for removal, shall be removed only when approved in writing by the Owner or Design Professional.

PART 2 - PRODUCTS

PART 3 - EXECUTION

3.1 PREPARATION

A. Perform public and private utility locates in accordance with Section 31 00 01

“Site Preparation and General Site Work.” Disconnect and de-activate all existing utilities before proceeding with the work, except as specified herein or otherwise shown on plans.

B. Verify that utilities have been disconnected and capped.

C. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

D. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

E. When unanticipated mechanical, electrical, or structural elements that conflict with the intended function or design are encountered, investigate and measure the nature and extent of the conflict. Promptly submit a written report to the Design Professional.

F. Evaluate the condition of site structures to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of the structure or adjacent structures during selective demolition.

3.2 SAFETY AND PROTECTION

A. Conduct demolition operations and remove debris to ensure minimum interference with roads, streets, walks, and other adjacent occupied and used facilities. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.

B. Conduct demolition operations to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide all barricades, guards, lights and other installations required.

2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

3. Ensure safe passage of people around demolition area

4. Protect existing site improvements, appurtenances, and landscaping to remain.

BLP-24148 31 00 02 -4

3.3 POLLUTION CONTROLS:

A. Use water mist, temporary enclosures, and other suitable methods to limit the spread of dust and dirt.

1. Do not use water to the extent that may result in damage to existing construction or create hazardous or objectionable conditions, such as ice, flooding, and pollution.

B. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before start of selective demolition.

3.4 DEMOLITION:

A. Demolish and remove from site the existing structures, curb & gutter, slabs, walks, paving, steps, and any other item above or below ground that interferes with construction of the project as shown on plans.

B. Remove existing curbs, gutters, slabs, and concrete walkways at the nearest contraction or expansion joint.

C. Provide neat and straight sawcutting as shown on the Plans and as required to provide selective or partial demolition.

D. Where portions of concrete slabs-on-grade are to be removed, first outline the portion with a concrete saw to a depth of at least 1/3 of the thickness.

E. Completely remove below grade construction, including foundations and footings.

F. Contractor is to coordinate the subsurface demolition with any phased utility demolition and construction. The demolition of below grade items shall not interrupt any existing or proposed utility services.

3.5 FILLING BELOW-GRADE AREAS AND VOIDS:

A. Completely fill below-grade areas and voids resulting from demolition of structures.

B. Use only clean, non-frozen, and approved fill material, stone, gravel, or sand that is free from deleterious materials. Refer to Section 31 22 00

“EARTHWORK” for general fill or structural back fill.

C. Grade completed surface to drain and to meet adjacent contours.

BLP-24148 31 00 02 -5

3.6 DISPOSAL OF DEMOLISHED MATERIALS:

A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

B. Send recyclable waste such as asphaltic concrete, Portland cement concrete, plastic, and metals to applicable recycle centers when feasible.

C. Burning: Do not burn demolished materials.

D. Burying: Do not bury materials onsite unless approved or otherwise shown.

E. Disposal of Regulated Materials (in accordance with GDNR, EPD rules):

1. Organic debris such as stumps, limbs, leaves, may be taken to a permitted solid waste landfill or to a permitted inert landfill.

2. Dispose of other non-hazardous trash and debris to a municipal solid waste landfill.

3. Dispose of oils, solvents, fuels, untreated lead paint residue and other solid hazardous wastes in properly licensed hazardous waste disposal facility.

F. Obtain all necessary permits for disposal. Transport demolished materials off

Owner’s property and legally dispose of them. Provide copies of disposal certificates to the Design Professional.

3.7 REPAIRS AND PATCHING:

A. Repair excess demolition.

B. Employ skilled workmen to perform repair work.

C. Where installation of similar new work is included, perform repairs in manner specified for installation of new work.

D. Where similar new work is not included in the project, perform repairs using approved materials that are appropriate to the repair and, where practicable, are identical to the existing materials being repaired.

E. Restore exposed finished patched areas in a manner, which eliminates evidence of repairs.

1. Continuous surfaces: Extend refinish to nearest intersection, with a neat transition to adjacent surfaces.

2. Assemblies: Refinish entire unit.

3. Painted piping, conduit and duct: Clean and repaint.

3.8 CLEANING:

A. Remove tools and equipment. Dispose of scrap.

B. Leave exterior areas free of debris.

BLP-24148 31 00 02 -6

C. Existing structures and site features to remain shall be returned to the condition prior to the commencement of construction.

D. Sweep remaining hard surfaces on completion of selective or partial demolition operations.

END OF SECTION 31 00 02

Sandy Springs Recreation & Parks SITE CLEARING

BLP-24148 31 00 00 -1

SECTION 31 10 00 – SITE CLEARING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Clearing of vegetative matter and debris.

2. Grubbing.

3. Disposal of cleared and grubbed material.

B. Related Sections:

1. 31 00 01 “SITE PREPARATION AND GENERAL SITE WORK” for layout, public safety, protection of existing facilities, protection of vegetation, utility locates, and utility protection.

1.2 SITE CONDITIONS

A. Tree save and protection of existing vegetation: Unless approved in writing by the Design Professional clearing operations and equipment shall be limited to the “Limits Of Work Area”, “Limits Of Disturbance”, and “Tree Protection

Limits” as shown on the drawings.

PART 2 - PRODUCTS (not used)

PART 3 - EXECUTION

3.1 PREPARATION

A. Verify that utilities have been disconnected and capped as necessary for clearing activities and that clearing limits and tree protection areas are plainly marked.

3.2 CLEARING:

A. Strictly adhere to the phased clearing plan as shown on the “Land

Disturbance Construction Activity Sequence” Erosion and Sedimentation

Control Plan. Only upon completion of initial inspection by the Design

Professional shall the contractor expand his clearing and grubbing operations to the entire site.

B. Clear all areas to be graded of remaining debris and extraneous materials.

Sandy Springs Recreation & Parks SITE CLEARING

BLP-24148 31 00 00 -2

C. Remove from the general construction /grading areas and proper disposal of all trees, brush, stumps, logs, grass, weeds, roots, decayed vegetable matter, refuse dumps, and all other objectionable matter resting on the original ground surface or appearing or being placed on these areas at any time before final acceptance of the work, except as provided for elsewhere.

D. Remove and properly dispose of any remaining obstructions not to be salvaged or preserved, such as fences and poles, and incidental structures within the construction area.

3.3 GRUBBING:

A. Grubbing includes the removal and proper disposal of all stumps, roots, and other vegetation or perishable matter that exists below the original ground surface in cleared areas. Grubbing also includes removal of general buried obstructions, trash, and debris not otherwise removed by demolition.

B. Unless otherwise shown, grub to the following depths:

1. All sound, unsound or decayed stumps shall be removed to a depth of

2 feet below the original ground.

2. Under lawn, planting, or sports field areas: Grub to a depth of at least

2 feet below finish grade.

3. Under asphalt, concrete, and gravel pavements: Grub to a depth at least 2 feet below subgrade elevation.

4. Under foundations, slabs, and structures: Grub to a depth of at least

3 feet below the foundation of proposed structures.

5. For other areas: Remove to a depth of at least 1 feet below natural ground surface.

3.4 DISPOSAL OF MATERIALS:

A. The removal and disposal of all cleared and grubbed materials is the responsibility of the Contractor. However, burning of organic waste is not allowed without obtaining a local jurisdiction burn permit.

B. Contractor may utilize a tub grinder for grinding of clearing operation organic debris. Organic mulch produced may be spread and utilized on cut and fill slope upon reaching finished grade for erosion and sedimentation control purposes. All other debris from clearing and grubbing operations shall be disposed of offsite, unless approved otherwise by the Owner and Design

Professional.

C. Comply with all local ordinances and obtain any necessary permits if applicable for disposal of trees, stumps, and other debris. Refer to Section

31 00 02 “Site Demolition” for disposal of debris.

END OF SECTION 31 10 00

Sandy Springs Recreation & Parks EARTHWORK

BLP-24148 31 22 00 -1

SECTION 31 22 00 – EARTHWORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Temporary grading or ditching to protect the site and adjoining property from water and silt damage.

2. Topsoil Stripping.

3. Grading, excavating, rock excavating, and filling to prepare subgrades for foundations (buildings and structures), walks, pavements, grass areas, landscape areas, and general areas.

4. Excavating and backfilling trenches for utilities and pits for buried utility structures.

B. Related Sections:

1. 31 00 01 “SITE PREPARATION AND GENERAL SITE WORK” for layout, protection of existing facilities, protection of vegetation, utility locates, and utility protection.

2. 32 05 00 “Common Works for Exterior Improvements” for import fill, import backfill, geotextile specifications.

1.2 REFERENCE SPECIFICATIONS AND DOCUMENTS

A. Georgia Department of Transportation (GDOT)

1. Department of Transportation, State of Georgia Standard

Specifications, Construction of Roads and Bridges, Current Edition.

Unless otherwise noted, conform with GDOT Standard Specifications where referenced.

2. GDOT Test Procedures (GDT), where referenced.

B. American Society for Testing Materials (ASTM)

1. ASTM D422 - Particle Size Analysis of Soils.

2. ASTM D423 - Test for Liquid Limit of Soils.

3. ASTM D424 - Test for Plastic Limit and Plasticity Index of Soils.

4. ASTM D1556 - Test for Density of Soil In Place Sand Cone Method.

5. ASTM D2487 – Standard Practice for Classification of Soils for

Engineering Purposes (Unified Soil Classification).

6. ASTM D6938 – Standard Test Methods for In-Place Density and Water

Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow

Depth).

7. ASTM D698 - Standard Test Methods For Moisture-Density Relations of

Soil Using Standard Effort.

8. ASTM D1557 - Standard Test Methods for Laboratory Compaction

Characteristics of Soil Using Modified Effort.

9. ASTM D2321 – Standard Practice for Underground Installation of

Thermoplastic Pipe for Sewers and Other Gravity Flow Applications.

BLP-24148 31 22 00 -2

1.3 DEFINITIONS

A. Backfill is defined as fill immediately behind foundation elements or retaining walls.

B. Excavation: Removal of material encountered above subgrade elevations, and to lines and dimensions indicated, or as directed. Excavation may be classified as earth excavation, rock excavation, or subexcavation, or it may be unclassified as described below.

1. Unclassified Excavation: Excavation of all material, including rock, regardless of its nature or the manner in which it is removed. All excavation shall be unclassified unless explicitly and otherwise shown on the Drawings, or if unit pay items are provided for Rock Excavation, Earth Excavation, or Subexcavation.

2. Earth excavation or simply “Excavation”: Excavation of all material is except for active utilities and rock.

3. Rock excavation: Excavation of all hard, compacted, or cemented materials that require the use of drilling, blasting or wedging equipment to remove. It shall consist of un-decomposed stone hard enough to ring under a hammer, and the amount of solid stone shall not be less than one (1) cubic yard in volume. If applicable, rock is further defined as follows:

a. General Excavation (Mass): Any material occupying an original volume of more than one cubic yard which cannot be excavated with a single-tooth ripper drawn by a crawler tractor having a minimum draw bar pull rated at not less than 80,000 pounds

(Caterpillar D-8 or larger).

b. Trench Excavation: Any material occupying an original volume of more than one cubic yard which cannot be excavated with a hydraulic excavator having a minimum flywheel power rating of

123 kW (165 hp); such as a Caterpillar 322C L, John Deere

230C LC, or a Komatsu PC 220LC-7; equipped with a short tip radius bucket not wider than 42 inches.

4. Subexcavation: Authorized additional excavation below subgrade elevations or beyond indicated lines and dimensions as directed by

Design Professional or Testing Agency in writing.

C. Fills: Suitable materials placed to raise existing grades.

1. General area fill: all fill in the general grading area covering banks, hollows, drain ditches, etc.

2. Pavement fill zone: The zone occupied by materials supporting asphalt or concrete paving supporting vehicular traffic or parking and extending for a distance of 4 feet on each side paving area measured at the finished grade (including gutter pans), thereafter tapering away at a 45° angle. Pavement fill zone for asphalt or concrete pedestrian areas are 2 feet on each side of paving area measured at finish grade and tapering down at a 45° angle.

3. Structural fill zone: The zone occupied by materials supporting floor slabs, building foundations or other structures and extending for a distance of 10 feet on each side of said structure measured at the finished grade, thereafter tapering away at a 45° angle.

BLP-24148 31 22 00 -3

D. Neat line: The shown, directed or described line or plane defining the limits of work. Work beyond neat line(s) is not subject to payment when included in a unit pay item.

E. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, drainage fill, drainage course, or topsoil materials.

F. Trenches:

1. Foundation: The area beneath the bedding.

2. Bedding: The area above the foundation and below the bottom of the pipe.

3. Haunching: The area above the bottom of the barrel of the pipe up to a specified height above the bottom of the barrel of the pipe.

4. Initial backfill: The area above the haunching material and below a plane 12 inches above the top of the pipe.

5. Final backfill: The area above a plane 12-inches above the top of the barrel of the pipe.

G. Conserved Topsoil: Excavated soil material, with organics, conserved from grading areas that is suitable for growth of grass, cover crops, or planting areas. Identification and use of all conserved topsoil is subject to approval by the Testing Lab or Design Professional. Refer to 32 05 00 “COMMON

WORKS FOR EXTERIOR IMPROVMENTS” for definition of Furnished Topsoil.

H. Unsuitable Soils:

1. Existing undisturbed soils which are determined by the Testing

Laboratory or Design Professional to be unsuitable for use as fill in a particular application for reasons other than moisture or water content.

a. Water saturated soils, regardless of the source of the water

(rainfall, storm runoff, ground water or other sources) shall not be considered as unsuitable.

b. Dewater or dry out water saturated soils to the extent necessary to satisfy the requirements for fill.

c. The Contractor is solely responsible for the scheduling and sequencing of the work. If necessary, to maintain the

Contractor’s schedule, wet soils shall be removed and replaced with suitable fill to replace water saturated soils. The removal and replacement of water saturated soils shall be performed at the Contractor’s expense.

2. Fill material placed on site by the Contractor, regardless of whether fill is on-site or off-site borrow, cannot by its nature, be classified as unsuitable soils.

a. Materials placed as fill shall not be classified as unsuitable soils regardless of conditions encountered, since only suitable soils shall be used as fill.

b. Fill shall be placed, compacted and tested as required by the

Contract documents.

c. The Contractor shall be responsible for maintaining compacted fill, in condition and at compaction levels required, until improvements (site and/or building) are placed on fill.

BLP-24148 31 22 00 -4

d. Should compacted soil be disturbed or become water saturated the Contractor shall be responsible for conducting whatever work is necessary to restore to the soils to the specified criteria at no cost to the Owner.

3. Water Saturated Soils: Should soils become saturated the Contractor shall, as part of the scope of this Contract, perform activities necessary to mediate and / or replace water saturated soils as required to obtain suitable fill as required by the Testing Agency or

Design Professional.

1.4 SUBMITTALS

A. Product data for materials, including but not limited to: geotextiles, utility line markers, import fill material, control density backfill.

B. Quantities of stripped and stockpiled topsoil. Provide report within 48 hours of stockpiling.

C. Shoring, bracing and shielding plans and calculations by a Professional

Engineer registered in the State of Georgia.

D. Backup for unit cost documentation, that may include:

1. Survey and computed quantities for Rock Excavation.

2. Delivery tickets (tonnage) for import fill incorporated into the Work.

E. Field and laboratory test or quality control results including, but not limited to, the following:

1. Subgrade proctor, compaction, moisture content.

2. Gradation, proctor, compaction, moisture content for fill or backfill material.

3. Proof rolling and other qualitative inspection reports.

1.5 QUALITY ASSURANCE

A. Earthwork Testing and Inspection Services: The Owner will engage a qualified independent Testing/Inspection Agency to perform Earthwork Testing as described in this Section.

1.6 SITE CONDITIONS

A. Protection:

1. Limit grading and filling operations to within the defined clearing limits, work zones, or limits of disturbance. Do not disturb the existing terrain or trees outside these lines.

2. Fill material placed against drainage structures or back-filled around utility pipes shall be placed and compacted by methods which will not cause any damage. Any damage which does occur shall be repaired or replaced by the Contractor at the Contractor’s expense.

BLP-24148 31 22 00 -5

3. Graded Areas: Any settlement or washing that occurs prior to acceptance of the work shall be repaired and grades re-established to the required elevations and slopes. Fill to required subgrade levels any areas where settlement occurs.

B. Hazardous Materials:

1. No soil found on site or transported to the site which is contaminated with material containing asbestos, PCB's, radon, gasoline, fuel oil, or other fossil fuels, shall be used for fill, backfill or landscape topsoil.

2. Notify Design Professional of any contaminated soil found on site. Any contaminated soil found on site shall be removed and disposed of in a lawful manner.

1.7 COORIDINATION AND SCHEDULING

A. Notify the Design Professional a minimum of 48 hours prior to the beginning of any excavation, filling, or grading.

B. The Contractor is solely responsible for the scheduling and sequencing of the work. If necessary, to maintain the contractor’s schedule, removed wet soils dewater and dry out sufficiently for its application, or remove and replace with suitable fill. The dewatering or removal and replacement of water saturated soils shall be performed at the contractor’s expense.

PART 2 - PRODUCTS

2.1 FILL OR BACKFILL MATERIALS

A. The soil used for fill or backfill material shall be free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.

B. Fill or backfill for paving areas or supporting buildings shall have a maximum dry density exceeding 90 pounds per cubic foot (pcf).

C. Where specified use Graded Aggregate Base (GAB) as backfill or structural fill: Refer to 32 05 00 “Common Works for Exterior Improvements” for material properties.

D. Structural Fill: Soil Classification Groups GW, GP, GM, SM, ML, CL; SW, SP, SC, SP-SM, SP-SC. (ASTM D 2487). Additionally Class I or Class II (but excluding Class IIB4) Roadway Materials (GDOT Section 810.01) are also acceptable for Structural Fill.

1. Structural fill material exhibiting a wide variation in consistency and or moisture content shall be blended and/or aerated to stabilize and upgrade the material.

E. Permeable Backfill: Unless shown otherwise, provide a minimum of 2 horizontal feet of permeable backfill material behind retaining structures

BLP-24148 31 22 00 -6

consisting of gravel, crushed rock, natural sands, manufactured sands, or combinations of these materials conforming to the following gradation:

Sieve Size Percent Passing

3/4 inch 100

3/8 inch 0-100

No. 100 0-8

No. 200 0 -3

Those portions of fill material passing a No. 4 sieve shall provide a sand equivalent of at least 60.

F. General Fill: Includes soils suitable for structural fill as well as other onsite non organic and non expansive soils that are approved by the Design

Professional or Testing Agency that will form a stable and dense mass with or without confinement.

2.2 UTILITY EARTHWORK MATERIALS

A. Foundation Material: Unless otherwise specified, Crushed stone meeting

GDOT Standard Specification 800.01, Group 1 (limestone, marble, or dolomite), or Group II (quartzite, granite, or gneiss). Stone size is between

No. 57 and No. 4, inclusive.

B. Utility bedding and backfill: Unless otherwise shown bed pipes from trench bottom to one foot above pipe.

1. Unless otherwise shown pipe bedding and backfill shall consist of:

sand, gravel, crushed aggregate, or native free draining granular material providing a sand equivalent of at least 30 or a coefficient of permeability greater than 1.4 inches per hour.

2. Cement sand slurry shall be provided with 1 sack of concrete per cubic yard of mixture.

3. Imported Fill Material: Imported fill material shall be a granular material with sufficient binder to form a firm and stable unyielding subgrade and shall not have more than 60 percent of fines passing a

200 mesh sieve. Material shall provide a coefficient of expansion of not more than 2 percent from air dry to optimum moisture content and not more than 6 percent from air dry to saturation. Imported materials shall be clean and free of rubbish, debris, and toxic or hazardous contaminants. Adobe or clay soils are not permitted.

2.3 LINE MARKERS

A. 2” width minimum, 5 mil tape thickness with non-ferrous detectable aluminum backing and shall be printed with the description that the relevant

BLP-24148 31 22 00 -7

utility is “buried below”. Line marker colors according to APWA corresponding to the utility type as follows:

1. Gas lines- yellow

2. Power – red

3. Communications - orange

4. Sanitary – green

5. Water - blue

2.4 GEOSYTHETICS

A. Refer to 32 05 00 “Common Works for Exterior Improvements” for material properties of geotextiles for separation and stabilization.

PART 3 - EXECUTION

3.1 PREPARATION

A. Construction Survey: Refer to 31 00 01 “Site Preparation and General Site

Work” for layout and survey requirements. Provide construction staking as required for drives, parking, walks and other site improvements. Protect benchmarks, monuments and other reference points.

B. Clear and grub the area of vegetation and obstructions.

3.2 EROSION CONTROL AND SEDIMENT CONTAINMENT SYSTEMS:

A. Adhere to the “Land Disturbance Construction Activity Sequence” as defined in the Erosion and Sediment Control Plans.

B. Temporary Grading and Drainage: Provide effective drainage for the entire site at all times. Divert watersheds by ditching or embankments to prevent encroachment of surface water in excavations. No impoundment of water will be permitted except as provided. The Contractor is fully responsible for all water damage to the site and to the installed work.

C. Refer to 31 25 00 “EROSION AND SEDIMENT CONTROLS” for additional grading operation requirements and storm drainage system installation requirements.

3.3 CONSERVED TOPSOIL

A. After all demolition, clearing and disposal is completed, strip from the top of the existing ground all topsoil from all areas to be graded.

B. Stockpile topsoil in designated or approved locations with proper drainage and where it will not interfere with the work. After topsoil has been stockpiled, BLP-24148 31 22 00 -8 quantify the stockpiled volumes. Report quantities to the Design Professional, Owner and Site Design Professional within 2 days of completing stockpiles.

C. Refer to Division 32 Sections “TURFS AND GRASSES” and “PLANTING

PREPARATION” for stockpiled topsoil application requirements and additional amendment requirements for turf, lawn, and planting areas.

1. If…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .