2026 JWP_Switches_RFP.pdf
PDF 513 KB Posted
- Attached to
- Network Switches - Jones Wheat Primary School
- Solicitation number
- PE-55240-NONST-2026-000000008
- Issued by
- Dade County, Georgia
About this file
This is a Request for Proposals (RFP) issued by the Decatur County School System in Georgia for the upgrade of network switches and battery backup units at Jones-Wheat Primary School located at 1401 E. Shotwell Street, Bainbridge, Georgia. The project scope includes replacing existing Alcatel-Lucent Enterprise network switches with new equipment across multiple distribution frames: two main distribution frames (MDFs) and four intermediate distribution frames (IDFs). The RFP specifies procurement of seven 48-port network switches with advanced capabilities including PoE support, 10Gbit/s SFP+ ports, and stacking functionality, along with direct attached stacking cables, SFP+ transceivers, CAT6 patch cables, and nine 1500VA uninterruptible power supplies. The RFP was released on February 13, 2026, with proposals due by March 16, 2026, at 2:00 PM EST. Vendors are welcome to schedule site visits by contacting Jason Logue, Director of Technology, at jlogue@dcboe.com. No formal bidders' conference is mentioned. Award notification will follow evaluation, with final payment contingent upon completion and extensive final walk-through testing.
Pricing represents 40 percent of the evaluation criteria, with technical qualifications weighted at 30 percent, in-area engineer capability at 20 percent, and prior E-Rate experience with DCBOE at 10 percent. The project is funded entirely through the E-Rate program for the 2026-27 funding year, contingent upon receipt of a Funding Commitment Decision Letter from the Schools and Libraries Division (SLD). The vendor must submit a SPIN number with the bid and accept Service Provider Invoice (SPI) billing methodology, whereby the vendor bills DCBOE only for the local matching funds portion and invoices the SLD for the non-discount amount. All vendors must meet specific certification requirements including debarment certification, E-Rate service provider certification, and federal work authorization compliance under Georgia law. The vendor must perform all installation and configuration work with in-house licensed personnel, provide perpetual management licenses without cloud-based service requirements, offer manufacturer warranty coverage during the funding year, provide on-site warranty service, and maintain an engineer within four hours of Bainbridge for service calls.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Decatur County School System
REQUEST FOR PROPOSALS
Network Switches
For Jones-Wheat Primary School
E-Rate Funding Year 2026-27
Released on:
February 13, 2026
Proposals Deadline:
March 16, 2026 at 2:00 PM EST
For all questions about this RFP contact:
Jason Logue, Director of Technology jlogue@dcboe.com
All correspondence must be in writing.
mailto:jlogue@dcboe.com
Project Objectives:
1.0 Objective
The Decatur County School System intends to upgrade the network switches and battery backup units at
Jones-Wheat Primary School, 1401 E. Shotwell St, Bainbridge, GA 39819.
1.1 Evaluation Methodology
Each proposal will be evaluated based on criteria and priorities defined by the Decatur County Schools
Board of Education and SLD requirements. The BOE will decide on the best submissions that are in the best interest of the long-term technology plan, not necessarily the lowest price. Proposals will first be evaluated based upon the base requirements. The evaluation criteria include, but are not limited to, the following:
1. Vendors overall performance record based on available references, reliability, and meeting of the requirements as described in this RFP.
2. Vendor’s ability to meet all the requirements detailed in the RFP.
3. Vendor’s proposed hardware meets the specifications requested in this RFP.
4. Ability to have an engineer for warranty service within four (4) hours of Bainbridge.
5. Best overall value and in the best interest of the Decatur County Schools Board of Education
6. Vendor agrees to provide a completed Category Two – Internal Connections (V21.0 or greater)
USAC approved template for uploading to EPIC. Template and directions can be found at https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates
7. New equipment will be installed and configured by vendor’s licensed engineer according to
Decatur County Schools’ Technology Department specifications. Subcontractors will not be allowed.
8. Decatur County Schools will only accept discounted billing. Vendor agrees to bill Decatur County
School System for the “non-discount amount”.
https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates
TERMS AND CONDITIONS OF REQUEST FOR PROPOSAL (RFP)
Response Submission
Responses to this RFP must be submitted and delivered to the Decatur County School Board of
Education by no later than 2:00 pm on March 16, 2026. It is the sole responsibility of the respondents to ensure that their responses arrive in a timely manner. The Customer reserves the right to reject all late arrivals. Envelopes containing RFPs shall be so marked as to be easily identified as containing RFP proposals. The outside of the envelope shall be identified as follows:
RFP ERATE 2026 JWP Network Switches Mr. Jason Logue, Technology Director
Decatur County Schools Board of Education
1417 Dothan Road
Bainbridge, Georgia 39817
NOTE:
Envelopes/packages incorrectly labeled may be rejected.
Each package submitted must include BOTH a hard copy of the proposal and an electronic copy of the proposal and a completed Category Two – Internal Connections (V21.0 or greater) USAC approved template for uploading to EPIC. The electronic media must be stored on either a CD/DVD or USB drive.
The package must also include the following completed forms:
• Certificate Regarding Debarment, Suspension, Ineligibility (Appendix A)
• E-Rate Certification (Appendix B)
• Vendor Affidavit (Appendix C)
Oral, telephone, email, or fax bids shall not be considered, nor will modifications of proposals by such communication be considered. Delivery of the proposals will be considered authorized by The Vendor to supply SLD approved contract (s) for 471 use, if awarded. Vendor agrees to supply the BOE with all required 471 paperwork in approved format to meet filing deadlines.
2.1 Bidders’ Conference/Site Visit
Vendors are welcome to view the school location(s) as necessary for equipment planning. Appointments may be made by contacting Jason Logue at the email address jlogue@dcboe.com. Vendors who schedule appointments must be qualified as per vendor qualifications listed in this RFP.
mailto:jlogue@dcboe.com
2.2 Subcontractors
Subcontractor work is not acceptable by the Decatur County BOE for technology projects. We expect
The Vendor to perform all services with in-house personnel. Appropriate switch channel partners and licenses, Microsoft Engineers, RCDD and Ga. Low Voltage holders must be full-time employees. Each vendor must be contractor certified in their respective hardware (i.e., cable, patch panels, fiber, etc.). All employees must be insured. Borrowed certifications will result in bid rejection and certification proof will be checked by the Decatur County BOE.
2.3 Addenda
Any interpretation, correction, or change of the RFP will be made by updating the RFP on the DCBOE
Request for Bids/Proposals web site. It is the responsibility of vendors to check for changes made to the
RFP.
2.4 Financing
After notification of award, The Vendor will receive purchase order(s) for the products and services for which The Vendor will be responsible as a result of the RFP. This project is projected to be funded through ERATE. The actual installation of this project is totally contingent on ERATE approval. Each vendor must supply a SPIN number on your bid response. Purchase order(s) will show the amount that is the responsibility of the local school system. The final payment of this project will be made only after an extensive final walk-through at the completion of the installation. The Decatur County BOE will strictly enforce the bid guidelines and the quality of the installation. Final testing will take place in the presence of a designated technology staff member. The Decatur County Schools Technology Staff will have total discretion to request any needed changes to meet current national, state, or industry standards.
2.7 Warranty
The Vendor shall fully warrant with the manufacturer’s warranty all items provided under this RFP against defects in material and workmanship for the ERATE funding year. The primary warranty response is to come from the awarded vendor and should be on a per equipment basis on the RFP and detailed in the Bid Proposal. The vendor will also be expected to provide on-site service in addition to the manufacture warranty, so please list this service in detail.
2.8 Right to Reject
The BOE reserves the right to accept or reject all proposals or sections thereof and when the rejection is in the best interest of the Decatur County School District. The Customer reserves the right to award without further discussion. Therefore, responses should be submitted initially with the most favorable terms that The Vendor can propose.
The BOE reserves the right to reject the proposal of a Vendor whom in the opinion of the Technology
Department cannot adequately perform the contract.
Contracts will be awarded to the highest ranked Vendor using an ERATE formula where it is in the best interest of the Decatur County School System.
2.9 Discount Billing
Decatur County Schools will only accept discounted billing. This method is known in the ERATE program as “Service Provider Invoicing” (SPI). Vendor agrees to bill Decatur County School System for the “non-discount amount”.
3.0 Vendor Certification
Included within Vendor’s Bid Packages, vendors must submit a declaration of Vendor’s ability to meet all the requirements detailed in the RFP and submit certification requirements as listed in session 2.2
Subcontractors.
4.0 Bid Scale
In addition to meeting the specifications described in this RFP, evaluation of all proposals will be based on the following grid criteria:
Factor Weight Price 40% Technical Qualifications 30% In-Area Engineer 20% Prior E-Rate experience with DCBOE 10% Total 100%
SCOPE OF PROJECTED WORK
Jones-Wheat Primary School
The scope of this project is to upgrade the network switches and battery backup units throughout Jones-
Wheat Primary School.
A detailed parts list and pricing of ALL items to be installed must be included with the bid. This detailed parts list must be submitted using an approved USAC “Bulk Upload Template” Excel spreadsheet Attachment. Information can be found at https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates
Below are the hardware requirements for this project along with the individual specifications for the
MDF and each IDF. All proposed equipment must meet the capabilities described in this section. All equipment bids must be submitted as complete. Any additional components or licenses that are required to use and manage the listed equipment must be included in the bid.
NETWORK SWITCHES
DCBOE currently uses Alcatel-Lucent Enterprise network switches. If a different brand is proposed, vendor must provide a temporary demo unit for DCBOE to confirm its compatibility and functionality.
The school’s existing network switches are to be replaced with new network switches by vendor’s licensed engineer (no subcontractors). Vendor is to configure and test the new network switches.
All proposed network switches must support all the following requirements as well as the individual requirements listed on pages 8-10. These features and the ability to manage these features must not require the use of cloud-based services. Any required license to use and manage these features must be perpetual.
• Command-based management through a local console port
• Command-based management through a remote SSH connection
• Switch stacking
• VLAN port assignments
• VLAN trunking (802.1q)
• Spanning Tree Protocol (STP) support
• Port teaming (LACP and static teaming)
• QoS
• 802.1X port authentication with VLAN assignment through a remote RADIUS server
• MAC-based port authentication with VLAN assignment through a remote RADIUS server
• The compatibility of any included SFP or SFP+ ports must not be locked to only work with modules from the switch manufacturer.
• Manufacturer-provided firmware for security updates and bug fixes during the duration of the warranty https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates https://www.usac.org/e-rate/applicant-process/applying-for-discounts/fcc-form-471-filing/#bulk-upload-templates
UNINTERRUPTIBLE POWER SUPPLIES
All proposed uninterruptable power supplies must meet the requirements that are listed below, as well as the individual requirements specified on pages 8-10.
• 120-volt NEMA 5-15 for input and output
• Rack mountable
• Replaceable batteries
• Automatic voltage regulation (AVR)
• Output power as pure sine wave
• Equipped with a network management card which provides the following capabilities:
o Complete local network management with no requirement of cloud services o Ability to send all alerts including power events and battery replacement notices through an SMTP email server, SNMP traps, and remote syslog events.
MDF Rack 1
Item Qty
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• Redundant power supplies supporting the switch’s full PoE capacity
Direct attached stacking cable (for stacking between each switch)
• Minimum speed 20Gbit
• Minimum cable length 40cm
Direct attached stacking cable (for redundant stacking from top switch to bottom switch)
• Minimum speed 20Gbit
• Minimum cable length 100cm
10G SFP+ Multimode Transceiver 10
1ft CAT6 patch cable (the existing switches are part of a chassis unit and use longer cables) 336
Uninterruptable power supply
• 1500VA
• 120-volt input/output (NEMA 5-15)
MDF Rack 2
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• 1RU size
Direct attached stacking cable (for stacking between each switch)
• Minimum speed 20Gbit
• Minimum cable length 40cm
Direct attached stacking cable (for redundant stacking from top switch to bottom switch)
• Minimum speed 20Gbit
• Minimum cable length 100cm
10G SFP+ Multimode Transceiver 2
Uninterruptable power supply
• 1500VA
IDF-1 (Hall 311)
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• 1RU size
Direct attached stacking cable (for stacking between each switch)
• Minimum speed 20Gbit
• Minimum cable length 40cm
Direct attached stacking cable (for redundant stacking from top switch to bottom switch)
• Minimum speed 20Gbit
• Minimum cable length 100cm
10G SFP+ Multimode Transceiver 2
1ft CAT6 patch cable (the existing switches are part of a chassis unit and use longer cables) 192
Uninterruptable power supply
• 1500VA
IDF-2 (Hall 414)
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• 1RU size
Direct attached stacking cable (for stacking between each switch)
• Minimum speed 20Gbit
• Minimum cable length 40cm
Direct attached stacking cable (for redundant stacking from top switch to bottom switch)
• Minimum speed 20Gbit
• Minimum cable length 100cm
10G SFP+ Multimode Transceiver 2
Uninterruptable power supply
• 1500VA
IDF-3 (Gym 130C)
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• 1RU size
10G SFP+ Multimode Transceiver 2
Uninterruptable power supply
• 1500VA
IDF-4 (Lunchroom 116B)
Network switch
• 48 total RJ-45 ports o All 48 ports should support 1000BASE-T and IEEE 802.3at PoE o Minimum of 16 ports should support 2.5GBASE-T and IEEE 802.3bt PoE
• 4 SFP+ ports supporting a speed of 10Gbit/s
• 2 QSFP+ stacking ports supporting a minimum speed of 20Gbit/s
• Capable of stacking with all other switches on this rack
• 1RU size
10G SFP+ Multimode Transceiver 2
Uninterruptable power supply
• 1500VA
NOTE: DCBOE reserves the right to adjust the quantity of products according to individual product cost. This adjustment will be based upon USAC’s Allocated Pre-Discount amount.
Appendix A
Certificate Regarding Debarment, Suspension, Ineligibility
The Decatur County School District is a recipient of Federal monies. As such we require that participating vendors not be debarred, suspended, ineligible or excluded from doing business with the Federal government or any agency thereof.
The prospective participant certifies, by submission of the proposal, that neither it, nor its principals, is presently debarred, suspended, proposed for debarment, declared ineligible, or excluded from participation in this transaction by any Federal department or agency.
Organization Name
Name(s) and Title(s) of Authorized
Representative(s)
Signature(s)
Date
Notary
Date
Appendix B
E-RATE CERTIFICATION
I, __________________________________, certify that ________________________________, is a
(Print or Type Name) (Company Name)
Service Provider as defined by the E-Rate Program and has not been suspended or disbarred from participating by the Federal Communications Commission. Our SPIN # is __________________, and
(Type Service Provider ID) we have operated under this SPIN for ______years.
(number)
I also certify to the acceptance of the following:
1. All information necessary to respond to any PIA (Program Integrity Assurance), Item 25 Selective
Review, or Audit performed by the FCC, the SLD, or their designated authority, will be furnished completely and in a timely manner sufficient to meet the any response deadlines;
2. In the event an appeal is necessary, all the information necessary to complete the appeal will be furnished completely and in a timely manner to the Decatur County School System, it’s attorney(s) or authorized agent;
3. Any contract awarded based upon this RFP in contingent upon the receipt of a Funding
Commitment Decision Letter (FCDL) from the SLD that awards the requested discounts in full. In the event that partial funding or no funding is granted, the Decatur County School System reserves the right to cancel the contract in whole or in part;
4. The Decatur County School System will be invoiced for the only the matching funds portion, and it our responsibility, as the E-Rate Service Provider, to invoice the SLD for the remaining “non-discount” portion. This billing method is known as the SPI (Service Provider Invoice) method;
5. In the event the Decatur County School System wishes to perform a SPIN change, as afforded by the COPAN decision, permission will be granted within the contracted terms, provided 14 days prior written notice is given.
(Original Signature in Blue or Black Ink)
(Today’s Date)
(Print or Type Name)
(Title)
Appendix C Vendor Affidavit under O.C.G.A. § 13-10-91(b)(1)
By executing this affidavit, the undersigned Vendor verifies its compliance with O.C.G.A. § 13- 10-91, stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services on behalf of Decatur County School District has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned Vendor will continue to use the federal work authorization program throughout the contract period and the undersigned Vendor will contract for services in satisfaction of such contract only with sub- Vendors who present an affidavit to the Vendor with the information required by O.C.G.A. § 13- 10-91(b). Vendor hereby attests that its federal work authorization user identification number and date of authorization are as follows:
Federal Work Authorization
User Identification Number
Date of Authorization
Name of Vendor
Name of Project
Decatur County School District________ Name of Public Employer
I hereby declare under penalty of perjury that the foregoing is true and correct.
Executed on ______, ___, 2026 in ____________________(city), ______(state).
Signature of Authorized Officer or Agent
Printed Name and Title of Authorized Officer or Agent
SUBSCRIBED AND SWORN BEFORE ME ON THIS THE ______ DAY OF ______________,2026.
NOTARY PUBLIC
My Commission Expires:________________________________
File details come from the government source that posted it. Updated .