2026 Installation of SDR35 PVC Gravity Sewer Pipe and Replacement of Two Manholes Daniels Ct.pdf

PDF 2 MB Posted

Attached to
City of Havelock, 2026 Installation of SDR35 PVC Gravity Sewer Pipe and Replacement of Two Manholes Daniels Court
Solicitation number
294-294-09282026
Issued by
Cumberland County, North Carolina

About this file

Summary

This is an Invitation to Bid issued by the City of Havelock, North Carolina for the installation of approximately 40 feet of 8-inch PVC SDR35 gravity sewer pipe and replacement of two manholes located at Daniels Court. The project scope includes excavation and removal of two existing brick manhole structures at locations P45 and P47, each approximately 5 feet deep, and installation of two new precast concrete manholes with 6-inch ballast rings. The contractor must replace approximately 20 feet of terracotta pipe at both the influent and effluent sides of each manhole with new PVC SDR35 pipe, install two 4-inch schedule 40 PVC cleanout pipes, and restore surface conditions including driveway, garden beds, mailbox, and asphalt pavement on Daniels Road. Bids must be submitted by 2:00 PM EST on Wednesday, October 28, 2026, addressed to Kimberly Walters, Finance Director, City of Havelock. The performance period is 30 calendar days from the Notice to Proceed, with work hours limited to 8:00 AM to 5:00 PM Monday through Friday. A site visit is recommended but not mandatory. Bids remain valid for 75 days after opening, and the contractor must submit an itemized schedule by quantity, unit price, and total for each work element.

Bidders must provide an E-Verify Affidavit with their bid submission, and bids lacking this documentation will be deemed non-responsive. For projects over $30,000, a general contractor's license is required. Out-of-state vendors must maintain a Certificate of Authority to Transact Business in North Carolina. The contractor is responsible for all costs associated with labor, materials, equipment, excavation disposal, dewatering, bypass pumping, shoring, restoration, and traffic control. Liquidated damages are assessed at $300 per day for each day beyond the 30-day performance period. The contractor must comply with OSHA standards, NC DEQ erosion and sediment control requirements, and all applicable federal, state, and municipal regulations. Materials and workmanship are warranted for one year from the time equipment is placed back into service. The City reserves the right to reject any or all proposals.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF HAVELOCK

Post Office Box 368

Havelock, NC 28532

INVITATION TO BID

Pursuant to North Carolina General Statutes §143-131, the City of Havelock invites informal bids on the following:

Bids must be submitted in accordance with the attached specifications. Bids must include an itemized schedule (including quantity, unit price and total) for each work element. Bids can be submitted by mail, email, fax or hand delivered. Cover sheets, envelopes, etc. should be clearly marked with the words:

“City of Havelock, 2026 Installation of SDR35 PVC Gravity Sewer Pipe and Replacement of Two Manholes

Daniels Court”

Address Bids to: Kimberly Walters, Finance Director City of Havelock P.O. Box 368 1 Governmental Ave.

Havelock, NC 28532 Fax: 252-447-0126 Email: Bids@havelocknc.us

Bids will be accepted until 2:00 PM (EST) on Wednesday, October 28, 2026 at which time they will be reviewed in the office of the City Finance Officer. Quotes are not subject to public inspection until the contract is awarded.

The bids are good for 75 days after opening. The winning bidder will be issued a Notice To Proceed (NTP) along with a Purchase Order. The performance period is 30 calendar days from the NTP.

Bidders are cautioned not to submit bids until the proposed requirements and specifications have been carefully examined. It will be considered that bidders will have satisfied themselves as to the accuracy of the specifications. No proposal will be considered unless prices are submitted for all items requested in any section. The City reserves the right to change the amount of quantities.

All bids submitted should be to the desired specifications. Any exceptions to the specifications will be evaluated based on the best interest of the City. Any deviation from specifications indicated herein must be clearly pointed out; otherwise, it will be considered that items offered are in strict compliance with these specifications, and bidder will be held responsible therefore. Deviations shall be explained in detail.

The bidder shall not construe this paragraph as inviting deviation or implying that any deviation will be acceptable.

The names of certain brands or makes denote quality standard in the article desired, but do not restrict bidders to the specific brand, make or manufacturer named. They are meant to convey to prospective bidders the general style, type, character and quality of the article desired.

The successful bidder on all construction contracts will be required to conduct the operation in accordance with all Federal, State, and Municipal health and safety rules, regulations and laws applicable to the operation. The successful bidder may be asked to provide the City with a copy of the company's safety plan prior to commencing work. For all projects over $30,000, a general contractor’s license must be furnished to the City if applicable.

Certificate to Transact Business in North Carolina: As a condition of contract award, each out-of-State Vendor that is a corporation, limited-liability company or limited-liability partnership shall have received, and shall maintain throughout the term of The Contract, a Certificate of Authority to Transact Business in North Carolina from the North Carolina Secretary of State, as required by North Carolina law. A contract requiring only an isolated transaction completed within a period of six months, and not in the course of a number of repeated transactions of like nature, shall not be considered as transacting business in North Carolina and shall not require a Certificate of Authority to Transact Business.

The City will not sell bid packages. Plans, specifications, and addenda may be viewed and obtained online at www.havelocknc.us. Click on: “Bid on a Contract”; “Current Bids”. The Bidder’s List is maintained by Vendor Registry. Registration for the Bidder’s List is made online at www.havelocknc.us. Click on: “Bid on a Contract”; “Vendor login/Registration”.

N.C.G.S. (North Carolina General Statutes), specifically §160A-20.1(b), prohibit the City from entering into contracts with contractors and subcontractors who have not complied with the requirement of Article 2 or Chapter 64. The Contractor shall submit the E-Verify Affidavit, located in the Bid Proposal section, with their bid. Bids that do not include this Affidavit will be considered non-responsive.

N.C.G.S 147-86.42-84 requires that contractors with a North Carolina Local Government must not utilize any subcontractor found on the State Treasurer’s Iran Divestment list or Companies Boycotting Israel list. The referenced lists can be found on the State Treasurer’s website at the address www.nctreasurers.com and will be updated every 180 days.

The City of Havelock reserves the right to reject any or all proposals and to purchase items from the state contract in the efforts to award the contract to the bidder it deems to be for the best interest of the City.

MODIFICATION AND WITHDRAWAL OF BIDS. Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. A request to withdraw a bid may be made to the Owner within 72 hours after Bids are opened in accordance with NCGS § 143-129.1 Requests to withdraw a Bid will be subject to the requirements of NCGS §143-129.1 and in the sole discretion of the City of Havelock Finance Officer.

This institution is an equal opportunity provider, and employer.

Contact person(s) for information on this bid:

For questions in regards to the bid specifications, the City requires and only responds to questions submitted in writing and sent via email to: Bids@havelocknc.us

Questions must be received by 2:00 PM (EST) on Wednesday, October 14, 2026. If questions are received, the City will respond no later than 2:00 PM (EST) on Wednesday, October 21, 2026.

This is the 28th day of September 2026

Published: DemandStar September 28, 2026

Kimberly Walters Finance Director http://www.havelocknc.us/ http://www.havelocknc.us/

STATE OF NORTH CAROLINA

AFFIDAVIT

I, ___________________________ (the individual attesting below), being duly authorized by and on behalf of __________________________________ (the entity hereinafter “Employer”) after first being duly sworn hereby swears or affirms as follows:

1. Employer understands that E-Verify is the federal E-Verify program operated by the United States Department of Homeland Security and other federal agencies, or any successor or equivalent program used to verify the work authorization of newly hired employees pursuant to federal law in accordance with

NCGS §64-25(5).

2. Employer understands that Employers Must Use E-Verify. Each employer, after hiring an employee to work in the United States, shall verify the work authorization of employee through E-Verify in accordance with NCGS §64-26(a).

3. Employer is a person, business entity, or other organization that transacts business in the State and that employs 25 or more employees in this State. (mark Yes or No)

a. YES_____, or

b. NO_____

4. Employer’s subcontractors comply with E-Verify, and if Employer is the winning bidder on this project, Employer will ensure compliance with E-Verify by any subcontractors subsequently hired by Employer.

This _________ day of ________________________, 20________.

Signature of Affiant: _______________________________________

Print or Type Name: _______________________________________

State of North Carolina County of ____________________________

Signed and sworn to (or affirmed) before me, this the

_________ day of _____________________________, 20________.

Signature of Notary Printed Name of Notary

Bid Sheet

Base Bid: _____________________________

NC Sales Tax: _____________________________

Delivery Cost (if applicable): _____________________________

Total Cost to City: _____________________________

Bids must include an itemized schedule by quantity, unit price and total for each work element.

Company Name: ______________________________________________

Company Address: ______________________________________________

Contact Person: ______________________________________________

Telephone Number: ______________________________________________

Email Address: ______________________________________________

NC Contractor’s License Type and Number: ______________________________________________

Number of Addendums Acknowledged (circle one): N/A 1 2 3 4

As of the date listed below, the vendor or bidder listed above is compliant with N.C.G.S. 147-86.42-84, the

Iran Divestment Act and the Companies Boycotting Israel Act.

Authorized Signature: ____________________________________________________

Print Name of Authorized Signature: ____________________________________________________

Title: ____________________________________________________

Address Bid to: Kimberly Walters, Finance Director City of Havelock P.O. Drawer 368 1 Governmental Avenue Havelock, NC 28532

Bids@Havelocknc.us Please indicate the Bid name on the outside of the envelope.

2026 Installation of SDR35 PVC Gravity Sewer Pipe and Replacement of Two Manholes

Daniels Court Havelock, NC 28532

Objective:

Installation of approximately a total of 40 feet of 8-inch PVC SDR35 Gravity Sewer Pipe, remove the two old manhole structures, and install two new manhole structures.

Scope:

Manhole P45 and manhole P47 located at Daniels Court, Havelock, NC 28532 (Figure 1) shall be replaced in addition to approximately 20 feet of 8-inch PVC SDR35 Gravity Sewer Pipe for both manholes; each approximately 5 feet deep. Contractor shall remove and dispose of the current brick manhole and structure and replace the manhole with a precast concrete manhole constructed with a 6-inch ballast ring. The terracotta pipe is to be replaced at the influent side and the effluent side of both manholes; approximately 10 feet. Contractor shall use PVC SDR35 for the influent and effluent piping.

Contractor shall be responsible for dewatering the excavation, and bypassing sewer if bypassing becomes necessary. Contractor shall install approximately 100 cubic feet of #57 stone bedding for each new manhole structure (Section 6). After the structure is properly placed the contractor shall install the new SDR35 piping from the manhole out approximately 10’ feet from both the influent and the effluent sides. Manhole P45 has two additional influent pipes that are used for cleanouts on Daniels Court. Contractor shall replace the current terracotta pipe up the end of the excavation using 4-inch schedule 40 PVC. Contractor shall install an accessible property line cleanout for 109 and 111 Daniels Court within the city easement. Manhole P47 has one additional influent pipe that is used for cleanout. Contractor shall replace the current cleanout pipe with 4-inch schedule 40 PVC at the length of the excavation. Once installation is complete contractor shall backfill with select fill material to the surface of the manhole cover.

Under no circumstance shall the contractor use excavated material. All excavated material is the contractor’s responsibility and shall be disposed of and hauled off daily in accordance with all local, state, and federal regulations.

The project will require having to excavate through a gravel driveway at 111 Daniels Court, and a flower bed and a mailbox at 109 Daniels Court. Contractor shall restore the driveway to its current condition, see Section 8. Contractor shall restore the flowers in the garden bed and mailbox in its current location and replace in a equal or better condition. Contractor shall remove and dispose of any impedances and replace in an equal to or better condition. Contractor must maintain resident access to property. Contractor shall provide a copy of the contractor’s bypass and dewatering plan to a representative of the City of Havelock. If contractor is to excavate into the ditch near the manholes, disturb the ditch structure, or damage the ditch, the contractor shall be responsible for restoring the ditch to its current condition or better. The ditch shall follow the current flow direction and grade.

Contractor is responsible for contacting 811 for locating all existing utility lines and verifying all existing site conditions, including but not limited to existing pipe diameter, invert elevations, and existing pipe material prior to beginning repair. Manhole invert elevation is to be found between the upstream and he downstream manholes. The effluent side must be site cored after. Manhole channeling must be installed with grout after coring. Damage to existing utilities will be the responsibility of the contractor. Contractor shall perform a vacuum test on the newly installed manhole following Section 2 specifications. Excavation for the project will require excavating into the asphalt of Daniels road. Contractor shall restore pavement in accordance to Section 9 of this scope of work. Contractor shall issue a traffic control plan to a representative of the City of Havelock.

A site visit is highly recommended but not mandatory. All measurements are approximate contractor to verify. Contractor is to supply all labor, materials, and equipment to complete this project, unless otherwise specified in writing. The City of Havelock shall not be held responsible for omissions or errors in description.

City of Havelock Responsibilities

A representative of the City of Havelock will track progress daily. Work hours shall be 8am to 5pm Monday through Friday. No work shall be performed on City holidays. Work outside established work hours must be scheduled with the City of Havelock, 48 hours in advance and is subject to approval.

1. Excavating and Installing New Manhole and PVC SDR35 Gravity Sewer Pipe:

a. Install a bypass system, see Section 10.

b. Excavate and remove the existing manhole. Excavated spoils cannot be used for any purpose other than for disposal. Excavated spoils will become the responsibility of the contractor to remove from the site daily.

c. The rim elevation of the manhole shall be 2-inches taller than the ground elevation.

d. Excavate a minimum of 100 square feet (10’X10’) of base soil underneath the manhole base by a minimum of 24-inches deep and replace with 57 stone. The 57 stone must be compacted to 98% standard proctor in no more than 8” lifts. Stone shall be wrapped in geotextile fabric on all sides.

e. The existing Gravity Sanitary Sewer Line is approximately five (5) feet deep.

Excavate the existing ten (10) feet of Gravity Sanitary Sewer Line on each influent and effluent line utilizing a trench box per OSHA standards. The excavated and removed pipe will become the property of the contractor. It will be the responsibility of the contractor to dispose of the excavated and removed pipe.

f. The bedding for the new PVC SDR35 Gravity Sewer Pipe is to be 8-inches of 57 stone compacted to 95% standard proctor. ABC Stone is to be utilized from the base of the pipe to the top elevation of the pipe and backfill that is compacted to 95% standard proctor in 8-inch lifts to the ground elevation.

g. Install the influent and effluent pipe at manhole using mechanically installed flexible rubber boot seals to create a watertight connection.

2. Manhole Vacuum Testing

a. Excavated material shall not be stockpiled; excavated material shall be hauled and disposed of daily and is the responsibility of the contractor. In no manner shall excavated material be used for compacted material.

b. All excavations shall be protected from cave in by use of shoring, the contractor shall be responsible for remediation created by any and all excavation growth. All excavations shall be protected by use of fabric fencing, and shall be designed to stop trespassing into the work area.

c. The contractor shall excavate a minimum of 100 square feet (10’X10’) of base soil underneath the manhole base by a minimum of twenty-four inches deep and replace with 57 stone. All 57 stone within the base stone shall be wrapped on all sides, top, and bottom with geo-textile fabric. The 57 stone shall be compacted to 98% standard proctor in no more than eight-inch lifts.

d. The assembly of the manhole shall include a CS-102 Butyl Rubber sealant and shall create a durable and watertight seal.

e. Before any backfilling, the manhole shall be inspected and vacuum tested by a third-party inspector for structural integrity and watertightness. All testing shall be scheduled between the contractor and a representative of the City of Havelock. The representative from the City of Havelock shall be given a 24-hour notice prior to the testing taking place.

f. Criteria for the manhole testing shall follow ASTM C1244 and shall be as follows:

1. Utilizing 8” plugs and manhole testing head, seal the manhole.

2. Draw a vacuum on the manhole equal to 10 inches of Mercury.

3. Allow the drawn vacuum to stabilize to 9 inches of Mercury, noting the time for the stabilization to occur.

4. The manhole will fail the vacuum testing if the stabilization from 10 to 9 inches of mercury happens within a time span of 30 seconds. The manhole will pass the vacuum testing if the stabilization from 10 to 9 inches of mercury happens outside of a 30 second timeframe.

5. Upon failing the ASTM C1244 manhole vacuum testing; the manhole shall be resealed and retested.

3. Gravity Sewer Materials:

a. PVC SDR35 Gravity Sewer Pipe: Pipe shall conform to all requirements of

AWWA and shall be capable of withstanding the overburden pressures determined by the depth of burial in the field.

b. Non-pressure-type Pipe Couplings: Couplings for joining new PVC pipe to existing pipe shall be solid sleeve type suitable for all types of pipe. When applicable, material shall be ductile iron with gaskets suitable for sewer service.

Coupling shall be Maxadaptor coupling or equal, per AWWA C605.

c. Solid Wall Plastic Pipe Cutting: Cutting of pipe lengths shall be performed using tools and or equipment that will provide a neat, perpendicular cut without damage to the plastic. All burrs shall be removed using a file, knife or abrasive paper. Ends on the cut pipe shall be beveled to prevent gasket damage.

4. Dewatering:

a. The contractor shall dewater until completion of work. Excavation shall be kept free of water at all times during pipe removal, pipe replacement, and backfill operation.

b. A dewatering plan shall be submitted to the City of Havelock for approval prior to the beginning of the project.

c. All dewatering shall flow through a sediment filter bag. Sediment filter bags shall be of Polypropylene non-woven geotextile fabric with a sewn-in sleeve of sufficient size to accept a 4-inch diameter discharge hose. The discharge hose shall be extended into the sleeve a minimum of six (6) inches and be tightly secured with a hose clamp or other suitable device to prevent leakage. Contractor shall size sediment filter bags as necessary to dewater excavations. Effluent to be directed to adjacent stormwater conveyance areas and Contractor shall remove any accumulation of sediment from such areas following dewatering operations.

d. Upon removal of any dewatering header pipe system the contractor shall be responsible for filling the header pipe hole with filter sand to 50% of the depth of the hole while compacting to 95% standard proctor in 8” lifts. Grout shall be utilized to fill to 90% of the depth of the hole and the remaining 10% shall be topsoil, or select fill.

e. The usage of water from a hydrant will only be accomplished by use of a Hydrant Meter which will be issued from Customer Service at City Hall within the City of Havelock.

f. Upon submission of the Hydrant Meter Application there will be a refundable security deposit of $1,500 due. The Hydrant Meter shall be installed, removed operated, relocated, maintained, and or repaired by authorized City personnel only. Installation and removal of the Hydrant Meter shall occur during normal business hours unless otherwise approved.

g. Contractors shall notify the City at least two (2) business days before requesting removal. The City may assess late fees or remove unused equipment at its discretion.

h. For monthly hydrant meter rental, the meter will be read and billed monthly for usage and then a final bill will be issued after meter is returned.

i. For daily hydrant meter rental, the meter will be read and billed when the meter is returned.

j. Upon return of the Hydrant Meter, final usage will be read and metered charges applied. The refundable deposit will be applied to your final bill, and a refund check will be issued for any remaining funds after all charges have been applied per the Hydrant Meter policy. If no funds are remaining and a balance is still due an invoice will be mailed for final payment.

5. Excavation and Shoring:

a. Contractor is responsible for the design and protection of all excavation and shoring. Standard shoring practices including trench boxes, which can be used if certified/stamped by manufacturer. If required, shoring shall be designed and sealed by a professional engineer registered in the State of North Carolina, as required by OSHA, CFR1926.

b. Contractor shall notify NC 811 for utility locations prior to any excavations.

c. In no case shall excavations exceed that which cannot be backfilled by the end of the work day.

6. Backfill and Compaction:

a. All excavations shall be backfilled with select fill or ABC stone material.

Contractor shall be responsible for removal and disposal of all excavation material and construction debris in accordance with all local, state, and federal regulations.

b. Compaction in embankment shall be to 85% standard proctor.

c. Compaction in roadways, driveways, and sidewalks shall be to 98% standard proctor.

7. Pipe and Manhole Bedding:

a. Pipe bedding shall consist of an eight-inch (8”) depth of # 57 stone under pipe and

#57 or ABC stone to top of pipe (Figure 2).

8. Gravel Driveway Restoration

a. Any material removed from the driveway will be the responsibility of the contractor to remove and dispose of in accordance with all local, state, and federal regulations.

b. Material to be used shall be #57 Stone 3 inches thick.

c. Backfill material shall be used to fill the excavated area up to 3 inches from surface elevation.

d. #57 Stone shall be compacted to 95% standard proctor.

9. Concrete Restoration

a. Any concrete rubble from removal of the driveway aprons will be the responsibility of the contractor to remove and dispose of in accordance with all local, state, and federal regulations.

b. Concrete is to be 3500-psi fiber reinforced concrete mix.

c. The foundation for the concrete shall be compacted to 95% standard proctor in no more than 8” lifts before the concrete is poured.

d. The concrete driveway aprons and sidewalks shall be no less than four inches thick.

e. The concrete driveway aprons and sidewalks will require no wire mesh or rebar.

f. The seams where the new concrete meets the old concrete will be tolled to a ½” radius.

g. The seams where the new concrete meets the existing concrete shall have a ½” expansion joint between the existing and newly poured concrete.

h. Until completely cured the contractor will supply signage “No Walking, Wet

Concrete”.

10. Pavement Restoration

a. Replacement of asphalt roadway and/or concrete driveways/sidewalks are the responsibility of the contractor and shall be returned to original condition or better before the end of the project.

b. The contractor shall utilize a 12” bedding of 57 stone for both the newly installed 8” sanitary sewer line and 4” lateral services and fill the excavation with 57 or ABC stone to 12” above the top of the sanitary sewer lines. Engineered select fill shall complete the backfill of the remainder of the excavation to 3.5” from the top of the existing asphalt.

See figure 4.

c. The contractor shall be responsible for square cutting the utility cut back to undisturbed asphalt before the Pavement Restoration portion of this project can begin.

d. Engineered select fill shall be utilized from the top of the 57 or ABC stone above the top of the newly installed sanitary sewer lines. The Engineered select fill shall be compacted to 95% standard proctor in a maximum of eight-inch lifts.

e. Asphalt base course shall be a minimum of two inches thick and meet the requirements of B25.OB per NCDOT Standards for Roads and Structures.

The asphalt base will remain one and a half inches (1.5”) below the elevation of the existing asphalt.

f. Asphalt tack coat shall be sprayed or brushed on the existing asphalt to be tied into and shall be in accordance with section 605 asphalt tack coat of the NCDOT Standard Specifications for Roads and Structures.

g. The asphalt surface course shall be S9.5B at one and a half inches thick per NCDOT Standards for Roads and Structures. Prior to placement of the asphalt surface course, the base course shall be inspected for damage or defects and repaired to the satisfaction to the representative of the City of Havelock.

h. Asphalt stripping shall be restored to an as was condition. Stripping which is done on a DOT roadway will meet all DOT specifications.

i. Access to residents’ driveways must remain as accessible as possible during the course of this project.

11. Erosion and Sediment Control and Restoration:

a. The contractor shall be responsible for the installation and maintenance of all erosion and sediment control in accordance with the NC DEQ Erosion and Sediment Control Manual.

b. Construction activities shall be completed in such a manner that erosion of disturbed areas and off-site sedimentation is absolutely minimized.

c. All disturbed areas shall be restored as soon as construction is complete. Seed or sod type shall match existing grass in maintained areas. Follow the NC DEQ Erosion and Sediment Control Manual for type or as directed by City of Havelock representative.

12. Bypass Pumping:

a. Sewage bypass pumping shall be required for completion of repairs. If required, contractor shall design and furnish all material, labor, equipment, power, fuel, fuel storage, maintenance, etc. to implement a temporary bypass arrangement for the purpose of diverting flow around the work area on a daily basis for the duration of the repair. The bypass system shall meet the requirements of all codes and regulatory agencies having jurisdiction. Contractor shall be held liable for any and all fines imposed by local, State, and/or Federal agencies for failure to maintain flows or contain spills and/or overflows.

13. Traffic Control

a. Contractor shall submit a Traffic Control Plan for any operations affecting traffic including but not limited to lane closures. City must approve the traffic plan prior to implementation, particularly 24-hour notice prior to any lane closure.

b. Access to residences for local traffic shall be maintained throughout contract. Contractor shall provide a minimum of 24-hour notice to City of Havelock for any road closure.

14. Performance Period

a. It will be the contractor’s responsibility to set a start date with a representative from the City of Havelock to begin a project within thirty

(30) days from the issuance of a Notice of Award - Proceed.

b. The performance period is 30 days from the listed date on the Notice to Proceed.

c. The contractor shall work diligently to complete the project from the arranged start date. Work hours shall be 8am to 5pm, Monday through Friday. No work shall be performed on City holidays. Work outside established work hours must be scheduled with the City, 48 hours in advance and is subject to approval.

d. The contractor will be responsible for contacting a representative of the City of Havelock in the event that a project will be extended outside of the arranged performance period. Contact must be in the form of an email and acceptance of the extension of the performance period from a representative of the City of Havelock must also be in the form of an email.

15. Access:

a. Access to project site is within existing City of Havelock right of way.

16. Termination Clause:

a. Any agreement and issuance of purchase orders shall be terminated upon the expiration of (90) ninety days without work commencing. At the end of ninety days the City of Havelock will give written notice to the other party of its intention to terminate.

b. Any intent to begin a project thirty (30) days or more after a purchase order has been issued must be submitted in writing and approved by a representative of the City of Havelock.

17. Warranty:

a. Contractor will be held responsible for the materials and workmanship utilized within this project for a term of one year from the time that the equipment is put back into service.

b. The City of Havelock will be responsible for the warranty of any materials that are supplied to the contractor by the City of Havelock during the course of this project.

General Provisions:

a. Contractor shall comply with all requirements of OSHA 1926.

b. Work hours shall be 8am to 5pm, Monday through Friday. No work shall be performed on City holidays. Work outside established work hours must be scheduled with the City, 48 hours in advance and is subject to approval.

c. Contractor will obtain all necessary permits.

d. Roadway repair is the responsibility of the contractor.

e. Contractor shall control erosion and sediment release while this project is under construction.

f. The contractor is to clean and remove all debris at the end of each work day.

g. All underground utilities are to be 811 located, prior to work being started.

h. Contractor is responsible for all damage to existing roads, driveways, drainage, or utilities that occur as a result of the construction project.

i. Contractor is responsible for all damage to City property that occurs as a result of the construction of the project.

j. Contractor shall provide safety measures during the entire length of the project.

k. Contractor is responsible for the storage and safety of materials and equipment on jobsite.

l. Submittals must be approved by the City of Havelock prior to any work starting.

m. The performance period is 30 days from the Notice to Proceed.

Liquidated Damages:

a. The Contractor agrees to pay the owner $300 per day in liquidated damages for each day beyond the period of performance.

Figure 1: Area of Work

Figure 2: Pipe Bedding

Engineered

Existing

Figure 3: Driveway Area

Figure 4: Garden Bed & Mailbox

CITY OF HAVELOCK
INVITATION TO BID