This is an Invitation to Bid issued by the City of Elberton, Georgia for water system improvements involving the 2026 Galvanized Main Replacement project. The work encompasses the installation of approximately 15,000 linear feet of water main, reconnection and relocation of existing meters, and all related appurtenances. Sealed bids will be received until 10:00 AM local time on July 30, 2026, at the City of Elberton offices located at 203 Elbert Street, Elberton, GA 30635. An optional pre-bid conference will be held on July 15, 2026 at 10:00 AM at the same location to address right-of-way concerns and project sensitivity. Contract documents are available for examination at the City of Elberton and the engineer's office (DCCM, 6059 Boylston Drive, NE, Sandy Springs, GA 30328) and may be obtained for $200 per non-refundable set until 48 hours before bid opening.
Bids must include a Bid Bond of not less than five percent of the total amount bid, with all bonds countersigned by a Georgia Resident Agent. The successful bidder must provide both a Performance Bond and Payment Bond each in the amount of one hundred percent of the bid amount. The project is federally funded through the Georgia Environmental Facilities Authority (GEFA) Revolving Loan Fund and requires compliance with Davis-Bacon and Related Acts, wage rate determinations, DBE and EEO requirements, American Iron and Steel provisions, and Build America, Buy America (BABA) Act requirements. Additional compliance obligations include Executive Order No. 11246 (Equal Employment Opportunity), the Copeland Anti-Kickback Act, the Georgia Security and Immigration Compliance Act of 2007, and submission of completed Federal Work Authorization Forms. The Owner reserves the right to delay contract award for up to sixty days from the bid opening date and to reject any or all bids.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
448-01G SECTION AM
SECTION AM
INVITATION TO BID
Sealed bids will be received by CITY OF ELBERTON, GA for the construction of WATER SYSTEM IMPROVEMENTS – 2026 GALVANIZED MAIN REPLACEMENT at 203 Elbert Street, Elberton, GA 30635 until 10:00 AM local time, on July 30, 2026 and then at said time and place publicly opened and read aloud.
The Work includes installing approximately 15,000 LF of water main, reconnecting and relocating existing meters and all related appurtenances.
Payment for the Work will be made periodically on the basis of Contractor's Applications for Payment processed by the Engineer.
The CONTRACT DOCUMENTS may be examined at the following locations:
City of Elberton, GA 203 Elbert Street, Elberton, GA 30635-0070 (Owner) DCCM, 6059 Boylston Drive, NE, Sandy Springs, GA 30328 (Engineer)
Copies of the Contract Documents may be obtained at the office of DCCM, 6059 Boylston Drive, NE, Sandy Springs, GA 30328, (404) 255-2650, until 48 hours before the bid opening for $200 per set, which is nonrefundable.
An optional Pre-Bid Conference will be held at 203 Elbert Street, Elberton, GA 30635 on July 15, 2026 at 10:00 AM local time. The purpose of the Pre-Bid Conference is to provide information regarding right-of-way concerns and the sensitivity of the project, as well as address any questions.
Bids must include a Bid Bond in an amount of not less than five percent (5%) of the total amount bid. All bonds must be countersigned by a Georgia Resident Agent. A Performance Bond in the amount of one hundred percent (100%) of the amount of the bid and a Payment Bond in the amount of one hundred percent (100%) of the amount of the bid must be furnished by the successful bidder.
Bidders must comply with Executive Order No. 11246 as amended, entitled "Equal Employment Opportunity" and with the Copeland Anti-Kickback Act (18 U.S.C. 874) as supplemented in Department of Labor Regulations (29 CFR, Part 3).
Bidders must comply with all provisions of the “Georgia Security and Immigration Compliance Act” of 2007.
Bids must include completed Federal Work Authorization Forms as shown in Section CM1.
This is a GEFA project using the Federally Assisted State Revolving Loan Fund. The Successful Bidder must comply with DBE & EEO requirements; Davis Bacon and Related Acts; Wage Rate Determinations; and EPA Consolidated Appropriations Act 2014 that includes an American Iron & Steel requirement; and Build America, Buy America (BABA) Act requirements.
The right is reserved by the Owner to delay the award of the Contract for a period not to exceed sixty (60) days from the date of opening of the bids, during which time bids shall remain open and not subject to withdrawal.
The right is also reserved to reject any and all bids and to waive any and all technicalities or informalities.
CITY OF ELBERTON, GA
Kevin Eavenson, City Manager June 30, 2026