2026 Dust Off Schedule Summary
This is a dust suppressant application schedule prepared by the County of Solano's Department of Resource Management, Public Works Division for the supply, delivery, and application of Cargill Dust-Off or approved equal dust suppressant to graveled and unimproved roads throughout the county. The project spans six application dates from May 7 through May 22, 2026, covering 24 to 28 distinct road segments organized across four geographic zones. The schedule details specific road locations, zone assignments, application rates of $0.50 per gallon, road lengths and widths in feet, and calculated gallon quantities for each segment. Daily application volumes range from 12,972 gallons on May 14, 2026, to 19,810 gallons on May 15, 2026, with a total project requirement of 93,371 gallons. Questions regarding the solicitation must be submitted by March 23, 2026, with responses provided by March 26, 2026. Proposal submissions are due no later than April 17, 2026, at 5:00 p.m., with contractor selection scheduled for April 20, 2026. The contract period shall extend within eighteen calendar days from the project start date or until project completion, with the County reserving the right to award a one-year contract renewable for two additional one-year terms without competitive rebidding, contingent upon contractor performance and continued funding.
The total project cost is approximately $46,685.50, calculated at the uniform rate of $0.50 per gallon for all 93,371 gallons scheduled. The County maintains a local vendor preference policy that allows qualified local businesses within five percent of the lowest responsible bid an opportunity to match that bid. Bidders may submit up to two bids, including a base bid and one alternate bid proposing alternative environmentally sensitive or "Green" dust suppressant products if deemed equal to the specified Cargill product. No incumbent vendors or current contractors are identified in the documentation. All bidders must submit detailed product specifications, complete literature, descriptions of trucks and dispensing apparatus, proof of prevailing wage compliance, non-collusion declarations, and certifications including drug-free workplace compliance and debarment status through the County's OpenGov eProcurement Portal. Contractors must maintain appropriate insurance coverage including Workers' Compensation and Commercial General Liability, comply with all applicable federal, state, and local laws, and submit Material Safety Data Sheets for hazardous materials as applicable. The County reserves the right to periodically test material concentrations using a Refractometer and refuse any material not meeting specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DUST_SUPPRESSANT_APPLICATION_W_CARGILL_DUST_OFF_OR_EQUAL.pdf | ||
| Solano_County_-_Zone_Map.pdf | ||
| PO_TERMS_CONDITIONS.pdf | ||
| 2026_Dust_Off_Schedule.pdf | ||
| ZONE_MAP.pdf | ||
| 2026_Dust_Off_Schedule_for_IFB.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 Dust Off Schedule
Proposed Application Date
Road Zone Rate per gallon Length/feet Width/feet Gallons
5/7/2026 Race Course 1 0.5 2,016 10 1,120 McNiel 1 0.5 3,806 10 2,114 Sparks Ranch 1 0.5 8,745 10 4,858 Thissell 1 0.5 15,840 12 10,560
Daily Total: 18,653
5/8/2026 McCune 1 0.5 3,168 10 1,760 Herst 1 0.5 2,640 10 1,467 Timm 1 0.5 2,243 14 1,745 Esquivel 1 0.5 4,752 10 2,640 Robinson 1 0.5 6,647 10 3,693 Kataleba 2 0.5 1,500 10 833 Meredian 2 0.5 1,056 12 704 Cantelow 2 0.5 870 14 677
Daily Total: 13,518
5/14/2026 King 2 0.5 5,434 12 3,623 Levee@King 2 0.5 792 12 528 Levee@Mills 2 0.5 792 12 528 Levee@North 1 0.5 2,582 12 1,721 Etzel 2 0.5 1,320 10 733 Delhi W 2 0.5 1,056 10 587 Delhi E 2 0.5 1,056 10 587 Sikes 2 0.5 528 12 352 Swan 2 0.5 300 10 167 Bunkerstation 2 0.5 2,112 12 1,408 Robben 2 0.5 2,112 14 1,643 Cook 2 0.5 984 12 656 Mills 2 0.5 792 10 440
Daily Total: 12,972
5/15/2026 Grizzly Island 3 0.5 15,000 14 11,667 Scally 3 0.5 3,053 10 1,696 Creed, Peterson 4 0.5 1,056 12 704 Creed, Shop 4 0.5 792 12 528 Creed, Goose 4 0.5 3,423 12 2,282 Van Sickle 3 0.5 5,280 10 2,933
Daily Total: 19,810
5/21/2026 Dinkelspiel 4 0.5 2,755 12 1,837 Birdslanding 4 0.5 6,079 12 4,053 Olsen 4 0.5 6,336 12 4,224 Liberty RV 4 0.5 2,212 14 1,720 McCormack 4 0.5 2,904 12 1,936 Flannery 4 0.5 1,320 10 733 mailto:Levee@Mills
2026 Dust Off Schedule
Proposed Application Date
Road Zone Rate per gallon Length/feet Width/feet Gallons
McCloskey 4 0.5 792 12 528 Daily Total: 15,031
5/22/2026 Elevator 4 0.5 9,504 10 5,280 Holland 4 0.5 14,593 10 8,107
Daily Total: 13,387 Project Total: 93,371