2026_Dust_Off_Schedule.pdf

PDF 93 KB Posted

Attached to
DUST SUPPRESSANT APPLICATION W/CARGILL DUST OFF OR EQUAL
Solicitation number
968-0316-26
Issued by
Trinity County, California

About this file

This document is a 2026 Dust Off Schedule prepared by the County of Solano, California, Department of Resource Management, Public Works Division, detailing the planned application of dust suppressant to county roads. The schedule spans five application dates from May 7 through May 22, 2026, covering dust suppressant applications to twenty-eight distinct road segments across four zones. The project encompasses a total of 93,371 gallons of dust suppressant to be applied at a uniform rate of $0.50 per gallon. Daily application quantities vary from approximately 12,972 to 19,810 gallons, with individual road segments ranging from 167 to 11,667 gallons depending on road length and width specifications. Road widths range from 10 to 14 feet, with lengths spanning from 300 to 15,840 feet.

The schedule establishes specific application dates and road-by-road allocations for contractors to follow in delivering and applying Cargill Dust-Off or approved equivalent dust suppressant products for soil stabilization and dust mitigation. All roads are assigned to one of four zones, with zone designations potentially affecting application scheduling or logistics. The fixed pricing structure of $0.50 per gallon across all applications provides cost predictability for the overall project budget, with the total project cost calculable at approximately $46,685.50 based on the 93,371-gallon allocation.

View the file

Other files

File Type Posted
DUST_SUPPRESSANT_APPLICATION_W_CARGILL_DUST_OFF_OR_EQUAL.pdf PDF
Solano_County_-_Zone_Map.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
ZONE_MAP.pdf PDF
2026_Dust_Off_Schedule_for_IFB.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Dust Off Schedule

Proposed Application Date

Road Zone Rate per gallon Length/feet Width/feet Gallons

5/7/2026 Race Course 1 0.5 2,016 10 1,120 McNiel 1 0.5 3,806 10 2,114 Sparks Ranch 1 0.5 8,745 10 4,858 Thissell 1 0.5 15,840 12 10,560

Daily Total: 18,653

5/8/2026 McCune 1 0.5 3,168 10 1,760 Herst 1 0.5 2,640 10 1,467 Timm 1 0.5 2,243 14 1,745 Esquivel 1 0.5 4,752 10 2,640 Robinson 1 0.5 6,647 10 3,693 Kataleba 2 0.5 1,500 10 833 Meredian 2 0.5 1,056 12 704 Cantelow 2 0.5 870 14 677

Daily Total: 13,518

5/14/2026 King 2 0.5 5,434 12 3,623 Levee@King 2 0.5 792 12 528 Levee@Mills 2 0.5 792 12 528 Levee@North 1 0.5 2,582 12 1,721 Etzel 2 0.5 1,320 10 733 Delhi W 2 0.5 1,056 10 587 Delhi E 2 0.5 1,056 10 587 Sikes 2 0.5 528 12 352 Swan 2 0.5 300 10 167 Bunkerstation 2 0.5 2,112 12 1,408 Robben 2 0.5 2,112 14 1,643 Cook 2 0.5 984 12 656 Mills 2 0.5 792 10 440

Daily Total: 12,972

5/15/2026 Grizzly Island 3 0.5 15,000 14 11,667 Scally 3 0.5 3,053 10 1,696 Creed, Peterson 4 0.5 1,056 12 704 Creed, Shop 4 0.5 792 12 528 Creed, Goose 4 0.5 3,423 12 2,282 Van Sickle 3 0.5 5,280 10 2,933

Daily Total: 19,810

5/21/2026 Dinkelspiel 4 0.5 2,755 12 1,837 Birdslanding 4 0.5 6,079 12 4,053 Olsen 4 0.5 6,336 12 4,224 Liberty RV 4 0.5 2,212 14 1,720 McCormack 4 0.5 2,904 12 1,936 Flannery 4 0.5 1,320 10 733 mailto:Levee@Mills

2026 Dust Off Schedule

Proposed Application Date

Road Zone Rate per gallon Length/feet Width/feet Gallons

McCloskey 4 0.5 792 12 528 Daily Total: 15,031

5/22/2026 Elevator 4 0.5 9,504 10 5,280 Holland 4 0.5 14,593 10 8,107

Daily Total: 13,387 Project Total: 93,371