Job Specific Specifications for Rhode Island Department of Transportation (RIDOT) Contract 2026-CB-024

This document comprises job-specific specifications for RIDOT contract 2026-CB-024, a Rhode Island state transportation infrastructure project. The contract encompasses multiple work items including repair of Bridge No. 057821 Providence Viaduct southbound expansion joint, completion of the Dike Street Pedestrian Bridge No. 130201, installation of a temporary protective shield for Amtrak protection, reinforcing steel provisions, overhead sign structure installation, and a shared-use path bicycle counter. The work includes fabrication, transportation, and erection of structural components, with portions of previously fabricated bridge materials stored at the RIDOT Maintenance Facility in Warwick. The contract establishes substantial completion by August 23, 2027, with final acceptance required by May 22, 2028, subject to daily liquidated damages of $1,950.00 per day for delays. Progress payments are made bi-weekly to monthly with a 2 percent retainage applied to invoices.

The specifications establish compliance with Buy America (BABA) requirements under the Infrastructure Investment and Jobs Act, mandating domestic sourcing for all manufactured products and construction materials with federal funding. Contractors may request waivers for foreign materials under public interest, nonavailability, or unreasonable cost (exceeding 25 percent) provisions, subject to Federal Highway Administration approval and public comment periods. Price adjustment provisions are included for asphalt binder ($712.50 per ton as of June 29, 2026), diesel fuel ($3.3513 per gallon as of June 29, 2026), and steel prices established at project award. Force account banking provisions include $10,000.00 for unexpected Amtrak downtime compensation and $10,000.00 for miscellaneous work, with payments authorized at $1.00 per unit. Contractor responsibilities include quality verification of stored fabricated items within 30 days of notice to proceed, graffiti removal, steel re-coating, and coordination with utility providers and Amtrak for construction phasing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS – JOB SPECIFIC

SPECIFICATIONS - JOB SPECIFIC

INDEX

Code Title Page

106.01.1 Buy America Job Specification (BABA) JS-1

108.08 Prosecution and Progress JS-4

109.06 Payment for Work JS-5

800.9901 Bridge No. 057821 South Abutment – Expansion Joint Repairs JS-6

800.9902 Dike St Pedestrian Bridge No. 130201 Structure JS-9

803.9901 Temporary Protective Shield JS-11

817.9901 Reinforcing Steel Bank JS-12

936.9901 Force Account Bank – Unexpected Amtrak Downtime JS-13

938.1000 Price Adjustments JS-14

999.9902 Miscellaneous Work JS-15

T13.9901 Shared Use Path Bicycle Counter JS-16

T17.9901 Overhead Sign Structure 35 foot span - steel JS-17

JS-i

Date: 2/26/2025

RICN: 2026-CB-024

JOB SPECIFIC

CODE 106.01.1

BUY AMERICA JOB SPECIFICATION (BABA)

Remove Section 106.01.1 from the RIDOT Standard Specifications for Road & Bridge

Construction, February 2026 in its entirety and replace with:

106.01.1 Buy America Job Specification (BABA)

Introduction:

While existing Buy America requirements previously applied to iron, steel, and certain manufactured goods, the Infrastructure Investment and Jobs Act (IIJA) expands requirements to include all manufactured products and construction materials in construction contracts that include Federal Aid funding in the construction phase. Additional information available in 23 CFR 635.410 Buy America and it’s Q&A at FHWA's Buy America Q and A for Federal-aid Program - Buy America - Contract Administration - Construction - Federal Highway Administration (dot.gov) [fhwa.dot.gov]

Purpose:

Provide materials from domestic sources when products are permanently incorporated into the work.

Ensure all manufacturing processes, including applications of coatings, occur in the United States. A coating includes all processes required to apply the coating to a product to protect or enhance the value of the product. The requirements of this JS are not applicable to equipment, tools, and temporary items, including materials left in place at the Contractor’s convenience.

Certifications:

All certifications are submitted by the prime Contractor. When submitting certifications for materials that are subject to the requirements of this specification, the certification shall be on Form provided by the Department.

Determination of Material Category:

• Foreign or Uncertified Products.

Buy America does not apply to minimal use of steel/iron materials provided that the total cost of all foreign source items used in the contract, as delivered to the project site, is less than $2500 or one-tenth-of-one percent of the total contract amount, whichever is greater.

The total value is that shown to be the cost of the steel and iron products as delivered to the project site. Contractor to keep a log of foreign source items to ensure that the minimal use threshold is not exceeded during the life of the contract

• Manufactured Products Provide manufactured products produced in the United States.

A manufactured product is acceptable under this provision if:

The manufactured product was manufactured in the United States; and The cost of the components of the manufactured product that are mined, produced, or

JS-1

manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product.

• Construction Materials

The category of construction materials excludes cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.

Construction materials are materials that consist primarily of:

− Non-ferrous metals.

− plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);

− glass (including optic glass);

− lumber; or

− drywall.

Waivers:

The Contractor may submit a waiver request to the department using RIDOT procedures and form provided in the PMP document management folder. The form must reflect a detailed justification for the use of goods, products, or materials mined, produced, or manufactured outside the United States and including copies of all documentation verifying the unavailability of the material or product.

The Department will submit approved waiver requests to FHWA for review. The Contractor shall investigate and respond to any public comments made to the FHWA Office of Program Administration, indicating that a domestic supplier cannot provide the material for which a waiver has been requested. Final approval of the Buy America Waiver request will be made by the Administrator, Federal Highway Administration. The waiver will be effective the date following publication in the

Federal Register.

Contractor fully understands there is no guarantee a waiver request will be approved. Any contract delays caused by this waiver process will be the sole responsibility of the contractor.

The contractor shall be responsible for all cost associated with any of the construction materials that are permanently incorporated into the project that does not meet the requirements of this Special Provision without prior written approval from the Department, up to and including removal and replacement.

The Contractor may submit a waiver request to the department during construction:

1. Determine which type of the three waivers applies.

• Public Interest Waiver: applying the domestic content procurement preference would be inconsistent with the public interest. A waiver in the public interest may be appropriate where the approving federal agency determines that other important policy goals cannot be achieved consistent with the IIJA requirements, and the proposed waiver would not meet the requirements for a nonavailability or unreasonable cost waiver.

• Nonavailability Waiver: for types of iron, steel, manufactured products, or construction materials that are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality.

• Unreasonable cost waiver: the inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the

JS-2

overall project by more than 25 percent. Provide documentation that no domestic alternatives are available within this cost parameter. Document in the waiver a comparison of the cost of the domestic product to the cost of the foreign product or a comparison of the overall cost of the project with domestic products to the overall cost of the project with foreign-origin products.

2. Contractor shall prepare waiver documentation including waiver form provided by RIDOT;

located in the PMP portal and submit to the Department’s Project Manager with a cc: to the

Construction Manager (RE)

3. RIDOT/Project Manager to Submit waiver to Federal Highway Division.

4. Federal Highway Division submits the waiver to the Made in America Office. All waivers have to be submitted by Federal agencies to the Made in America Office. Project specific waivers require a minimum of 15 calendar day public comment period. General applicability waivers are subject to a minimum 30 calendar day public comment period. Federal agencies are responsible for performing due diligence and approving or rejecting waivers.

JS-3

Date: 8/17/2026

CODE 108.08

PROSECUTION AND PROGRESS

Substantial Completion: The following fine/charge for not completing contract work according to Section 101.89 by August 23, 2027, is $1,950.00 per day.

Final Acceptance: All Contract work shall be completed as defined by Section 105.18 by May

22, 2028, or a Daily Charge will be deducted from any money due in the amount of

$1,950.00 per day.

JS-4

8/17/2026

R.I. CONTRACT NO. 2026-CB-024

CODE 109.06

PAYMENT FOR WORK

Remove Section 109.06 b from the RIDOT Standard Specifications for Road & Bridge Construction, February 2026 in its entirety and replace with:

109.06 PAYMENT FOR WORK.

b. Frequency. The Department will make progress payments a minimum of bi-weekly and maximum of monthly based on the Contractor Invoice provided according to established Department procedures. Progress payments will be subject to a 2 percent retainage.

JS-5

Job Specific RIC No. 2026-CB-024

CODE 800.9901

BRIDGE NO. 057821 SOUTH ABUTMENT - EXPANSION JOINT REPAIRS

DESCRIPTION: This work is the complete repair of Bridge No. 057821, Providence Viaduct Southbound, south abutment expansion joint. The work includes removal and in-kind replacement of hot mix asphalt, tack coat, waterproofing membrane, backwall concrete, reinforcing steel, metal edge beam extrusion, fabricated armor angle, box seal, foam joint filler and polyurethane seal components of the joint repair to the limits as shown on the plans. The work also includes bituminous saw cuts and temporary hot mix asphalt.

All work shall be in accordance with the appropriate sections of the February 2026 RIDOT Standard Specifications for Road and Bridge Construction (Standard Specifications).

MATERIALS: The following are the minimum requirements:

Concrete Repair in accordance with Section 817:

• Use rapid set high-performance, containing rapid-hardening hydraulic cement, compressive strength f’c at least 2,000 psi after 1.0 hour, with 7-day compressive strength, f’c, of 5,000 psi (min.) from RIDOT Approved Materials List. Blend with sand and aggregate per manufacturer’s recommendations.

• Use closed cell preformed polyethylene foam: Subsection M.02.10.1c

• Use silicone sealant: The requirements for silicone sealant for bridges is identical to that set forth for highways in Subsection M02.09.4

• Use bonding agent from RIDOT Approved Materials List if the bonding agent is recommended by the rapid concrete repair manufacturer.

Reinforcing Steel in accordance with Section 810:

• Use Deformed reinforcing steel conforming to AASHTO M31 (ASTM designation A615)

• Galvanized and conform to the requirements of Subsection M.05.06.

Expansion Joint in accordance with Section 823:

• Edge channel (edge beam) with loop anchors and neoprene locking seal (box seal) by Watson Boman ACME Corporation, 95 Pineview Drive, Amherst, NY 14228. Phone: (716) 691-7566.

• Exact match to existing edge beam and neoprene box seal (reference WBA Job No. 148099 05/17/2013).

Structural Steel in accordance with Section 824:

• AASHTO M270 Grade 50W (ASTM designation A709) to match the existing expansion joint steel.

• Coating: Hot dipped galvanized in accordance with AASHTO M111(ASTM A-123).

• Welding: Conform to ANSI/AASHTO/AWS D1.5 Bridge Welding Code

• Waston Bowman ACME Corporation shall furnish the armor angle fabrication.

Temporary and Permanent Hot Mix Asphalt in accordance with Section 401:

• HMA Class 9.5.

• Bituminous seal for sawed joint: hot poured rubber compound conforming to AASHTO D6690 in accordance with Section 821 as applicable.

Waterproofing Membrane in accordance with Section 813:

• Use cold-applied liquid membrane, Subsection M12.01.2 must be compatible with the existing GCP Eliminator membrane.

• Use tack coat compatible with GCP Eliminator membrane.

JS-6

CONSTRUCTION METHODS: Field verify the deck and barrier geometry to ensure that the joint will fit from end to end and within up-bends in the barriers. Ensure the joint material length achieves the proper fit.

Shop Drawings - Submit detailed shop drawings for the box seal, edge beam, armor angle fabrication, concrete repair, reinforcing steel, waterproofing membrane in sufficient time to allow for review and approval by the Engineer prior to fabrication. It is expressly understood and agreed that approval by the Engineer will not relieve the Contractor of any or all responsibility resulting from improper fabrication and installation of the deck joint system. The shop drawing submission shall include, but not be limited to, the following:

1. Details showing joint size, joint dimensions, material strengths, connection details, etc. as required for fabrication and installation. Provide sufficient extra length of the edge beam-loop anchor assembly to allow field adjustment of the edge beam so loop anchors are not in conflict with existing bent U- Bar reinforcing steel of the concrete backwall. Similarly, provide sufficient extra length of the armor angle with anchor assembly to allow field adjustment of the armor angle so its anchorage is not in conflict with existing bent U-Bar reinforcing steel of the concrete backwall.

2. Details showing the proposed deck joint system installation.

3. Obtain acceptance of shop drawings before beginning manufacture.

Manufacturer’s Representative -Install in strict accordance with the manufacturer’s instructions. An experienced technical representative employed by the manufacturer shall be present during all phases of preparation and installation. Manufacturer's Representative shall be there to advise the Engineer and the Contractor in the proper techniques to be followed. The Engineer may release the technical representative at his discretion with the allowance to recall if needed to the project.

Where Standard Specification Sections are listed in MATERIALS, refer to those Specification Sections for applicable construction methods.

Demolition – Saw cut bituminous concrete; remove and dispose bituminous concrete; saw cut and remove and dispose existing concrete; cut and remove and dispose steel armor angle and steel edge beam to limits shown on the plans in accordance with applicable specifications of Section 803.

Preparation - Prepare the backwall concrete removing any materials present and cleaning the opening with sandblasting or grinding to the satisfaction of the Engineer.

Installation – Field trim edge beam and armor angles to proper length so anchorages are not in conflict with existing bent U-Bar reinforcing steel. Temporarily support edge beam and armor angle to match the longitudinal grade and cross slopes of the road surface. Match the existing edge beams for proper fit of the seal. Match seal opening dimension of the existing joint. Complete welding of the proposed edge beam to existing edge beam.

Install reinforcing steel, forms and joint fillers. Place rapid set concrete in accordance with manufacturers written instructions. Match the longitudinal grade and cross slopes of the road surface. Cure rapid set concrete for 60 minutes before installing temporary pavement adjacent to the concrete repair. Cure concrete repair 2 hours before opening work zone to traffic.

Complete the demolition, preparation, installation and temporary paving operations (Stage 1 shown on the plans) listed above in an accelerated manner, in one continuous operation, until the work is complete in accordance with requirements of the Traffic Management Plan.

JS-7

Allow the concrete to be cured for 28 days or cured for duration recommended by the waterproofing membrane manufacturer. Complete Stage 2 (shown on the plans). Remove pavement, install polyurethane sealant, and waterproofing membrane. Install tack coat and final pavement and install bituminous seal in pavement at back of armor angle.

Install continuous box seal in the existing joint. Field splicing is not permitted. The seal shall be bonded to the seal frame with an approved lubricant-adhesive in accordance with the Manufacturer’s recommendations.

Additional steps shall be according to the Manufacturer’s installation materials details.

The expansion joint shall be installed to provide a watertight seal from end to end per the manufacturer’s written instructions and as directed by the manufacturer’s representative.

Remove and dispose damaged pavement in Span 1 at right lane at the location shown on the plans. Existing waterproofing membrane (GCP Eliminator) shall remain and shall not be damaged by contractor’s operations. If waterproofing membrane has pre-existing damage, repair the cold-applied liquid membrane in accordance with Manufacture’s written recommendations. Clean and prepare existing membrane waterproofing for tack coat and paving in accordance with Manufacturer’s recommendations.

METHOD OF MEASUREMENT: This item will not be measured for payment.

BASIS OF PAYMENT: The Department will pay for the completed and accepted quantities at the Contract unit prices as follows.

Pay Item Pay Unit

BRIDGE NO. 057821 SOUTH ABUTMENT - EXPANSION

JOINT REPAIRS LS

The price constitutes full compensation for all labor, materials, and equipment including disposal replacement and incidentals to complete the work

JS-8

Date: 7/07/2026

CODE 800.9902

DIKE ST PEDESTRIAN BRIDGE NO. 130201 STRUCTURE

DESCRIPTION: The work under this item shall consist of furnishing, fabricating, transporting, and erecting the Dike St Pedestrian Bridge No. 130201, in its entirety, in accordance with Section

800 of the RI Standard Specifications and these special provisions. During a previous contract, portions of the bridge and staircase towers were constructed, but the project is currently unfinished.

The steel structural components that were previously fabricated are stored at the RIDOT

Maintenance Facility at 360 Lincoln Avenue, Warwick, RI 02886, except as noted in this specification. The Contractor is responsible for checking the fabricated items compared to the approved shop drawings to ensure no items are missing before initiating any work within thirty

(30) calendar days from NTP. The checking of the fabricated items will require the use of lifting equipment and coordination with RIDOT Maintenance. It shall be noted that the stored bolts, nuts, washers, and connectors for this project have been deemed unusable, and all new connectors will need to be furnished by the Contractor. The Contractor is responsible for furnishing, fabricating, transporting, and erecting, including bearings, joints, and any missing components.

Graffiti Removal: The Contractor is responsible for removing graffiti from the existing structure, stored materials, and existing retaining walls at the project site. All work shall be performed by a qualified cleaning contractor with demonstrated proficiency and experience in the removal of graffiti. Documentation of at least five successfully completed graffiti removal projects of a similar type to the work to be performed shall be submitted to the Engineer for approval. Any chemical removers shall be specifically formulated for graffiti removal and approved by the Engineer. The

Contractor shall submit the MSDS Sheet, Manufacturer’s Technical Data Sheet, and written procedure for application of remover and removal of graffiti, including any proposed equipment being used. The proposed graffiti removal methods shall be tested on a 1 square foot area of the existing material. The proposed methods shall be approved for testing by the Engineer prior to full implementation.

Steel Re-Coating: The Contractor is responsible for cleaning and re-coating any components with damaged coating, missing coating, and corrosion/rusting, including the installed project components and the stored project components. All work shall be performed by a qualified contractor with demonstrated proficiency and experience with re-coating galvanized steel.

Documentation of at least five successfully completed re-coating projects of a similar type to the work to be performed shall be submitted to the Engineer for approval. The proposed cleaning and re-coating methods shall be tested on a 1 square foot area of the existing material. The proposed methods shall be approved for testing by the Engineer prior to full implementation. All methods shall adhere to AASHTO M11 (ASTM A123) and RIDOT Standard Specifications Section 827 and M.05.07.

The approximate quantities shown on the plans for this item are intended for estimating purposes only, and RIDOT assumes no responsibility for their accuracy. Any increase or decrease in the quantities listed shall in no way relieve the Contractor of his responsibility under the Contract.

JS-9

Date: 7/07/2026

This item shall comprise all work pertaining to the construction of all project components, including deck, wearing surfaces, landing pads, connection to shared use path on the east side and

Dike Street on the west side, staircases, bearings, joints, and all attached components. All of the above work shall be complete in place and accepted in accordance with the Contract Documents, except that the Method of Measurement and the Basis of Payment will be in accordance with these

Special Provisions.

Excluded Items of Work: The work pertaining to the following items of work is excluded from this lump sum item and instead will be measured and paid for separately under their own appropriate unit bid or lump sum items as listed in the proposal: Rip rap installation.

METHOD OF MEASUREMENT: This item does not require a measurement for payment.

BASIS OF PAYMENT: Item Code 800.9902 “DIKE ST PEDESTRIAN BRIDGE NO. 130201

BRIDGE STRUCTURE” will be paid for at the contract lump sum price as listed in the Proposal.

The price so-stated shall constitute full and complete compensation for all labor, materials, transportation, tools, equipment and all other incidentals required to complete the construction of the Dike St Bridge No. 130201 as described above under “DESCRIPTION”, and elsewhere in the

Contract Documents, complete in place and accepted by the Engineer. Any fabricated items that are missing, except for the connectors (bolts, nuts, washers, etc.) at the stored site shall be paid under the separate Item Code 999.9902 “MISCELLANEOUS WORK”.

JS-10

CODE 803.9901

TEMPORARY PROTECTIVE SHIELD

DESCRIPTION: This item of work shall consist of designing, furnishing, fabricating, erecting, maintaining, removing and disposing a temporary protective shield to protect trains and tracks, etc. from demolition or construction debris. The temporary protective shield shall also be provided per Amtrak’s request as directed by the

Engineer. The protective shielding shall comply with Amtrak Specification EP3014-01520A- “Requirements for

Temporary Protective Shields for Demolition and Construction of Overhead Bridges and Other Structures”.

METHOD OF MEASUREMENT: TEMPORAY PROTECTIVE SHIELD will be measured for payment by the square foot of protective shield installed in accordance with the plans and/or as directed by the Engineer.

BASIS OF PAYMENT: The Department will pay for the completed and accepted quantities at the

Contract unit prices as follows.

TEMPORARY PROTECTIVE SHIELD SF

The price constitutes full compensation for all labor, materials, and equipment including disposal replacement and incidentals to complete the work

JS-11

CODE 817.9901

REINFORCING STEEL BANK

DESCRIPTION: This item of work shall consist of establishing a bank for unanticipated but necessary reinforcing steel, wire mesh and anchors, when applicable, as separate payment of concrete patch repairs. The concrete repairs and supplemental steel reinforcing and anchors shall be in accordance with Section 817.03.2 Placement of

Reinforcement of the Standard Specifications and as directed by the Engineer or as shown on the contract drawings.

METHOD OF MEASUREMENT: REINFORCING STEEL BANK will be measured per the unit “EACH” of in accordance with the plans and/or as directed by the engineer. will be measured for payment by the unit each in accordance with the plans and/or as directed by the Engineer.

BASIS OF PAYMENT: The Department will pay for the completed and accepted quantities at the

Contract unit prices as follows.

REINFORCING STEEL BANK EACH

Once Section 817 force account billing for concrete repairs reinforcing has been approved, the Contractor will be paid from this item.

JS-12

Date: 5/11/2026

CODE 936.9901

FORCE ACCOUNT BANK – UNEXPECTED AMTRAK DOWNTIME

DESCRIPTION: The intent of this item is to cover Contractor costs associated with AMTRAK cancellations of scheduled track outages for which the Contractor’s forces are mobilized prior to being informed of AMTRAK’s notice of cancellation. Compensation shall be limited to actual hours lost that were scheduled with AMTRAK and were cancelled by AMTRAK at 9:00 PM or later on the same working day. Reimbursement shall be limited to the hourly rate of wage as shown by certified payroll for labor hours lost (up to two hours) and the standby rate for leased or rented equipment (up to two hours) that was mobilized for use on the project. Minor tools, expendable accessories and equipment, project trailers, storage boxes and personnel facilities shall not be eligible for reimbursement under this item. The Contractor shall make every effort to reassign the idled workforce to other work activities not requiring track outages.

No payment will be made for any Contractor owned equipment.

MATERIALS: Not applicable.

CONSTRUCTION METHODS: Not applicable.

METHOD OF MEASUREMENT: “Force Account Bank-Unexpected Amtrak Downtime” will not be measured for payment. This item will be documented and paid for on the Force Account

Basis as set forth below under “Basis of Payment”.

BASIS OF PAYMENT: The Department will pay “Force Account Bank-Unexpected Amtrak

Downtime” on a force account basis in accordance with Subsection 109.04 of the Rhode Island

Standard Specifications for Road and Bridge Construction, February, 2026 Edition, with all revisions.

The Department has established an estimated dollar amount of $10,000.00 for this work and is an authorized amount from which said Force Account payments will be made. Compensation will be determined as described herein and will be paid in units of “Each” with a price of $1.00/Each.

JS-13

8/16/2026

CODE 938.1000

PRICE ADJUSTMENTS

DESCRIPTION:

a. Asphalt Binder. The Base Price of Asphalt Binder as required to implement Subsection

938.03.1 of the Standard Specifications is $712.50 per ton as of June 29, 2026.

b. Diesel Fuel. The Base Price of Diesel Fuel as required to implement Subsection 938.03.2 of the Standard Specifications is $3.3513 per gallon as of June 29, 2026.

c. Steel. The Base Price of Steel as required to implement Subsection 938.03.3 of the Standard

Specifications shall be the price posted as of the project award date. The steel base prices are posted at RIDOT PMP start page, Documents, “Price Adjustment” link.

JS-14

5/11/2026

CODE 999.9902

MISCELLANEOUS WORK

DESCRIPTION: This work shall consist of furnishing all labor, equipment, tools and materials to perform various supplemental items of work as directed by the Engineer.

MATERIALS and CONSTRUCTION METHODS: Materials and Methods of Construction shall conform to the applicable sections of the Rhode Island Standard Specifications for Road and Bridge

Construction.

METHODS OF MEASUREMENT: Item Code 999.9902 "MISCELLANEOUS WORK" shall be measured for payment by the actual cost, as approved by the Engineer for the cost of performing the work as directed by the Engineer.

BASIS OF PAYMENT: Item Code 999.9902 "MISCELLANEOUS WORK" will be paid for at the actual dollar amount. The estimated dollar figure for this item of work established by Department at

10,000 each at a fixed price of $1.00 per each and is inserted in the proposal as an authorized amount from which the payments shall be drawn.

JS-15

Date: 5/11/2026

CODE T13.9901

SHARED USE PATH BICYCLE COUNTER

DESCRIPTION. The work under this Section shall consist of furnishing and installing a shared use path bicycle counter as shown on the Plans or as directed by the Engineer. The counter shall be a ZELT® Bicycle Counter manufactured by Eco-Counter. No equal will be accepted.

CONSTRUCTION METHODS. All work performed under this item shall be done in accordance with the manufacturer’s instructions. The counter shall be installed in an HD configuration.

• All loops are to be centered on the bike lane or expected travel path of cyclists

• All loops are to be diamond-shaped with the same dimension. Loop height is always 40 cm (16”). Loop width can range from 110 cm (43”) to 150 cm (60”). Consult an Eco-

Counter representative for bike lanes or trails outside this with range.

• Equipment; logger, sensor, and battery disks, are to be stored in a Rainbird® manhole.

Manhole location is to be approved by the Engineer.

• Manhole is to be provided by the manufacturer to allow for remote access to the logger without the need to remove the lid.

METHOD OF MEASUREMENT. This item does not require a measurement for payment.

BASIS OF PAYMENT. “Shared Use Path Bicycle Counter” will be paid for at the contract lump sum price as listing in the Proposal. The price so stated shall constitute full compensation for all labor, tools, equipment, materials, testing, and all incidentals necessary to complete the work, all in accordance with the plans and this specification, complete, and accepted by the

Engineer.

JS-16

CODE T17.9901

OVERHEAD SIGN STRUCTURE 35 FOOT SPAN - STEEL

DESCRIPTION. The work under this Section shall consist of furnishing, fabricating, transporting, and erecting the sign structure, electrical components, and wiring as detailed on the plans and in accordance with Section T17 of the RI Standard Specifications and these special provisions. The existing sign support posts are stored at the RIDOT Maintenance Yard at 750

Taunton Avenue in East Providence and shall be re-used by the Contractor. If the top face of the existing bridge foundations are found to be unusable, this Section will also include repairs to top face of existing bridge foundations so that proposed sign foundation can be properly connected with dowels as detailed on the plans.

The approximate quantities shown on the plans for this item are intended for estimating purposes only, and RIDOT assumes no responsibility for their accuracy. Any increase or decrease in the quantities listed shall in no way relieve the Contractor of his responsibility under the Contract.

Before fabricating the overhead sign supports, verify the locations of the foundations in the field, and establish and verify all elevations, dimensions, and longitudinal grades.

CONSTRUCTION METHODS. All work performed under this item shall be done in a cautious and professional manner. At the south sign support, construction activities shall not damage the

AMTRAK fence adjacent to the proposed foundation. If any damage occurs, the Contractor is responsible for repairing the fence at their own expense. At the north sign support, any damage to the sidewalk and curb beyond 18 feet during construction shall be restored by the Contractor at their own expense. The Contractor is responsible for the proper disposal of the existing overhead sign panel support that is not utilized for this project. The poles shall be maintained to be re-used.

The Contractor shall coordinate the new electrical service on existing utility pole #70 with RI

Energy representative Fernando Depina (401) 784-4367, email: FJDepina@RIEnergy.com. The

Contractor is responsible for testing that the lighting on the sign is functioning as designed.

The following sign specifications shall be followed as shown on the plans:

1. Aluminum facing and border strips shall conform to RIDOT Standard Specification 832

(Bridge Signs).

2. Aluminum facing shall be painted black. Border strips shall be painted white.

3. Sign backing shall be 1/4” thick 2447 white translucent acrylic sheet.

4. Sealing material shall be expanded closed cell polyethylene foam with bonding material suitable for attachment to steel plate.

JS-17

mailto:FJDepina@RIEnergy.com

5. Coatings: All steel shall be coated after fabrication in accordance with RIDOT Standard

Specifications (Metalized and Painted).

6. Top-Coat Colors:

a. Exterior color shall be federal standard color number 24260 (green semi gloss)

b. Interior color (behind sign face) shall be federal standard color number 17925

(white gloss)

7. Existing steel posts to be blast cleaned to SSPC SP-10 near white finish prior to providing the three-coat paint system per RIDOT Standard Specifications.

The following sign panel specifications shall be followed as shown on the plans:

1. Face of rivets on facing within letter to be black. Rivets and bolts on border strips to be white.

2. Maximum spacing of rivets to be 12”.

3. Install two lock bolts per panel. See elevation for approximate locations.

4. Install three hinges per panel. See elevation for approximate locations.

The following lighting specifications shall be followed as shown on the plans:

1. LED Strip Light: Exterior grade.

2. Acceptable Product: Flexfire LEDs Outdoor (IP65) Ultrabright Architectural Series LED

Strip Light or equal.

3. Light output: Approximately 500 lumens per foot.

4. Light color: 5000K – Bright White.

5. Dimmable.

6. Includes all hardware and wiring to make the lighting functional (dimmer control, power driver, etc.).

JS-18

The following RIDOT Standard Specifications shall be followed for general electrical materials and installations:

1. Section M15 –Traffic Control and Highway Lighting Systems

2. Section T01 – Electrical Work

3. Section T03 – Ground Rods and Bare Ground Wire

4. Section T04 – Wire and Cable

5. Section T06 – Conduit

The following is the electrical one line diagram for the work to be performed.

JS-19

METHOD OF MEASUREMENT. This item does not require a measurement for payment.

BASIS OF PAYMENT. “Overhead Sign Structure 35 Foot Span - Steel” will be paid for at the contract lump sum price as listing in the Proposal. The price so stated shall constitute full compensation for all labor, tools, equipment, materials, disposal, and all incidentals necessary to complete the work, all in accordance with the plans and this specification, complete and accepted by the Engineer.

JS-20