2026-50 Addendum2.pdf

PDF 834 KB Posted

Attached to
BID 2026-50 Leland-Beavercreek Intersection Improvements Project
Solicitation number
S-C01010-00017301
Issued by
Clackamas County, Oregon

About this file

Addendum No. 2 for Clackamas County BID 2026-50 Leland-Beavercreek Intersection Improvements Project

This document is an addendum issued by the Clackamas County Department of Transportation and Development on July 14, 2026, modifying the Invitation to Bid #2026-50 for the Leland-Beavercreek Intersection Improvements Project. The addendum clarifies specifications for three pavement marking bid items (Items 37, 38, and 39) related to extruded surface markings, all referencing Specification 00865 for proper compliance. Additionally, the addendum updates Special Provision Sections 00860 and 00865 to provide clearer references to standard specifications for both paint-based and durable longitudinal pavement markings. The project involves intersection improvements at S. Leland Road and S. Beavercreek Road, including clearing and grubbing, utility coordination with multiple providers (Portland General Electric, Clackamas County Broadband Exchange, water and telecommunications), drainage improvements, asphalt concrete paving, concrete curb and gutter installation, pavement markings, signage, and permanent seeding. The bid schedule contains 45 line items encompassing general conditions, temporary features, roadwork, drainage, bases, wearing surfaces, traffic safety devices, and site restoration. Bidders must be prequalified in Earthwork and Drainage, Pavement Markings, and Signing classifications. Bids were due July 15, 2026 at 2:00 PM Pacific Time, with substantial completion required by September 30, 2026 and final completion by December 31, 2026.

The engineer's estimate for the project is $289,963.20. Single lane closures on Beavercreek Road are limited to Monday through Friday between 9:00 a.m. and 3:00 p.m., with traffic stops not exceeding 20 minutes. Liquidated damages are assessed at $800 per calendar day for failure to meet substantial completion deadlines and $500 per 15-minute increment for traffic control violations exceeding specified limits. Bidders must submit a ten percent bid bond or certified check, with performance and payment bonds each equal to 100 percent of the contract price. Workers must receive Oregon prevailing wage rates established by the Bureau of Labor and Industries. Required insurance includes Commercial General Liability coverage of $1,000,000 combined single limit per occurrence and $2,000,000 annual aggregate limit, plus Commercial Automobile Liability coverage of $1,000,000. Retainage is set at 5.0 percent of progress payments, though contractors may submit approved surety bonds in lieu of cash retainage. The contractor must maintain Engineering Stationing at 50-foot intervals, coordinate mandatory utility scheduling meetings and monthly utility coordination meetings, and deliver complete as-built drawings at project completion as a condition of final payment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026-50 addendum2 Page 1

INVITATION TO BID #2026-50

LELAND-BEAVERCREEK INTERSECTION IMPROVEMENTS

PROJECT (“BID”)

ADDENDUM NUMBER 2

July 14, 2026

On June 24, 2026, Clackamas County (“County”) published an Invitation to Bid #2026-50 (“BID”). The County has found that it is in its interest to amend the BID through the issuance of this Addendum #2. Except as expressly amended below, all other terms and conditions of the original BID and subsequent Addenda shall remain unchanged.

The following changes are made to the Project Bid Schedule:

1. Bid Item 37 for 6" White Extruded, Surface, Non-Profiled – the Specification shall be 00865. Please use the new updated Bid Schedule Form with these changes.

2. Bid Item 38 for 4" Yellow Extruded, Surface, Non-Profiled – the Specification shall be

3. Bid Item 39 for 4" White Extruded, Surface, Non-Profiled – the Specification shall be

The following changes are made to the Project Special Provisions:

1. Special Provision Section 00860 – Longitudinal Pavement Markings – Paint. The text has been updated to reference the Standard Specifications only.

2. Special Provision Section 00860 – Longitudinal Pavement Markings – Durable. The section was added to reference the Standard Specifications.

These changes will be included in the Contract for this Project. It is understood that your Bid will be submitted accordingly.

Attachments: Updated Bid schedule- dated July 2026 (2 pages); updated SPECIAL

PROVISIONS FOR LELAND-BEAVERCREEK INTERSECTION IMPROVEMENTS (53

pages)

End of Addendum #2

LELAND-BEAVERCREEK INTERSECTION IMPROVEMENTS BID SCHEDULE - UPDATED JULY 2026

BID ITEM SPECIFICATION DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL

Part 00100 - General Conditions

1 00180 Workplace Harassment Prevention Plan LS 1

2 00196 Extra Work as Authorized LS 1 $ 25,000.00 $ 25,000.00

Part 00200 - Temporary Features and Appurtenances

3 00210 Mobilization LS 1

4 00221 Temporary Work Zone Traffic Control, Complete LS 1

5 00225 Striping Removal FT 865

6 00225 Stop Bar Removal FT 45

7 00280 Erosion Control LS 1

8 00280 Sediment Barrier, Type 8 FT 210

9 00280 Aggregate Check Dam, Type 1 EACH 1

10 00280 Construction Entrance, Type 1 EACH 1

11 00280 Inlet Protection, Type 4 EACH 1

12 00290 Pollution Control Plan LS 1

Part 00300 - Roadwork

13 00305 Construction Survey Work LS 1

14 00310 Removal of Surfacings

SY

15 00310 Removal of Structures and Obstructions LS 1

16 00320 Clearing and Grubbing LS 1

17 00310 Sawcutting FT 340

18 00330 General Excavation CY 200

19 00350 Riprap Geotextile, Type 1

SY

20 00350 Subgrade Geotextile SY 200

21 00390 Loose Riprap, Class 50 CY 4

Part 00400 - Drainage and Sewers

22 00445 12 Inch Culvert Pipe, 5 FT Depth LF 33

23 00470 Concrete Inlets, Type GB-2 EACH 1

24 00470 48" Diameter Concrete Manhole EACH 1

25 00490 Connection To Existing Structures EACH 1

Part 00600 - Bases

26 00640 Aggregate Base TON 145

27 00640 Aggregate Shoulders TON 6

Part 00700 - Wearing Surfaces

28 00744 Level 3, 1/2 inch Dense ACP Mixture (PG 64-22 HMAC) TON 70

29 00759 Concrete Curbs, Low Profile Mountable Curb FT 250

30 00759 Concrete Curb & Gutter FT 85

31 00759 Concrete Surface at Mountable Truck Apron (6" Thick) SY 180

32 00759 Wheel Stops (Parking Blocks) EACH 11

Part 00800 - Permanent Traffic Safety and Guidance Devices

33 00840 Delineators, Type 2 EACH 1

34 00855 Mono-Directional White Type IAR Markers, Recessed EACH 8

35 00855 Bi-Directional Yellow Type IAR Markers, Recessed EACH 16

BID ITEM SPECIFICATION DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL

36 00857 Longitudinal Continuous Centerline Rumble Strips MILE 0.01

37 00865 6" White Extruded, Surface, Non-Profiled FT 1,090

38 00865 4" Yellow Extruded, Surface, Non-Profiled FT 234

39 00865 4" White Extruded, Surface, Non-Profiled FT 245

40 00867 Pavement Bar, Type B-HS SF 92

41 00867 Pavement Legend, Type B-HS: Disabled Parking EACH 1

Part 00900 - Permanent Traffic Control and Illumination Systems

42 00930 Perforated Steel Square Tube Anchor Sign Supports LS 1

43 00940 Signs, Standard Sheeting, Sheet Aluminum LS 1

Part 01000 - Right-of-Way Development and Control

44 01030 Permanent Seeding Mix No. 1 (10-FT Wide) AC 0.07

45 01040 Topsoil (4" Thick) CY 40

Total

PROPOSED BID SCHEDULE TOTAL COST (INCLUDE EXTRA WORK) WRITTEN NUMERICALLY ________________________________________________________________________________________

PROPOSED BID SCHEDULE TOTAL COST (INCLUDE EXTRA WORK) WRITTEN IN WORDS ____________________________________________________________________________________________

COMPANY NAME ________________________________________________________________________________________________________________

AUTHORIZED SIGNATURE ________________________________________________________________________________________________________

SPECIAL PROVISIONS

FOR

LELAND-BEAVERCREEK INTERSECTION IMPROVEMENTS

CLACKAMAS COUNTY DEPARTMENT OF TRANSPORTATION

AND DEVELOPMENT

CLACKAMAS COUNTY, OREGON

CLASS OF WORK:

EARTHWORK AND DRAINAGE, ASPHALT CONCRETE

PAVING AND OILING, PAVEMENT MARKINGS & SIGNING

UPDATED JULY 2026

Leland-Beavercreek Intersection Improvements

CLACKAMAS COUNTY DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT

FOR

ROADWORK, DRAINAGE AND SIGNING & STRIPING

Leland-Beavercreek Intersection Improvements

Clackamas County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature

I certify the Special Provision Sections listed below are applicable to the design for the subject project for Traffic Signals. Modified Special Provisions were prepared by me or under my supervision.

Sections: 00210, 00220, 00221, 00222, 00223, 00224, 00225, 00226, 00280, 00290, 00305, 00310, 00320, 00330, 00350, 00390, 00405, 00415, 00445, 00470, 00490, 00640, 00744, 00759, 00855, 00857, 00860, 00867, 00905, 00920, 00930, 00940, 01030, 01040, 02001, 02030, 02320, 02415, 02510, 02910

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

Leland-Beavercreek Intersection Improvements UPDATED JULY 2026

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

SECTION 00110 – ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND

DEFINITIONS

SECTION 00120 – BIDDING REQUIREMENTS AND PROCEDURES

SECTION 00130 – AWARD AND EXECUTION OF CONTRACT

SECTION 00140 – SCOPE OF WORK

SECTION 00150 – CONTROL OF WORK

SECTION 00160 – SOURCE OF MATERIALS

SECTION 00165 – QUALITY OF MATERIALS

SECTION 00170 – LEGAL RELATIONS AND RESPONSIBILITIES

SECTION 00180 – PROSECUTION AND PROGRESS

SECTION 00190 – MEASUREMENT OF PAY QUANTITIES

SECTION 00195 – PAYMENT

SECTION 00196 – PAYMENT FOR EXTRA WORK

SECTION 00197 – PAYMENT FOR FORCE ACCOUNT WORK

SECTION 00199 – DISAGREEMENTS, PROTESTS AND CLAIMS

SECTION 00210 - MOBILIZATION

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

SECTION 00225 - TEMPORARY PAVEMENT MARKINGS

SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT

ATTENUATORS

SECTION 00280 - EROSION AND SEDIMENT CONTROL

SECTION 00290 - ENVIRONMENTAL PROTECTION

SECTION 00305 - CONSTRUCTION SURVEY WORK

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

SECTION 00320 - CLEARING AND GRUBBING

SECTION 00330 - EARTHWORK

SECTION 00350 - GEOSYNTHETIC INSTALLATION

SECTION 00390 - RIPRAP PROTECTION

SECTION 00405 - TRENCH EXCAVATION, BEDDING, AND BACKFILL

SECTION 00415 - VIDEO PIPE INSPECTION

SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE

SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS

SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES

SECTION 00640 - AGGREGATE BASE AND SHOULDERS

SECTION 00744 - ASPHALT CONCRETE PAVEMENT

SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE

STRUCTURES

SECTION 00840 - DELINEATORS AND MILEPOST MARKER POSTS

SECTION 00855 - PAVEMENT MARKERS

SECTION 00857 - RUMBLE STRIPS

SECTION 00860 - LONGITUDINAL PAVEMENT MARKINGS - PAINT

SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE

SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND BARS

SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS

SECTION 00920 - SIGN SUPPORT FOOTINGS

SECTION 00930 - METAL SIGN SUPPORTS

SECTION 00940 - SIGNS

SECTION 01030 - SEEDING

SECTION 01040 - PLANTING

SECTION 02001 - CONCRETE

SECTION 02030 – SUPPLEMENTARY CEMENTITIOUS MATERIALS

SECTION 02320 - GEOSYNTHETICS

SECTION 02415 - PLASTIC PIPE

SECTION 02510 - REINFORCEMENT

SECTION 02910 - SIGN MATERIALS

Clackamas County Special Provisions (2024 version October 11, 2024)

SECTION 00110 – ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND DEFINITIONS

Comply with Section 00110 of the Standard Specifications supplemented and/or modified as follows:

00110.05(d) References to Laws, Acts, Regulations, Rules, Ordinances, Statutes, Orders, and Permits

Add the following to the first bullet (Statutes and Rules):

• Clackamas County’s Local Contract Review Board (LCRB) Rules are accessible online on the County’s website https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b- 9bd8-c69ee7334685

• EquipmentWatch www.equipmentwatch.com

• ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx

• ODOT Construction Surveying Manual for Contractors www.oregon.gov/ODOT/ETA/Documents_Geometronics/Construction-Survey-Manual- Contractors.pdf

00110.10 Abbreviations

Add the following:

CCDA - Clackamas County Development Agency

DTD - Clackamas County Department of Transportation and Development LCRB - Local Contract Review Board

ODFW - Oregon Department of Fish and Wildlife UNS - Utility Notification System WES - Water Environment Services of Clackamas County

00110.20 Definitions

Add or modify definitions as follows:

Agreement Form – The written agreement between the Owner and Contractor covering the work to be performed under the contract.

Amendment – A contract modification for Additional Work, Changed Work, Extra Work, Field Directives, or other changes. An Amendment changes the contract value, scope, https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685 https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685 http://www.equipmentwatch.com/ http://www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx http://www.oregon.gov/ODOT/ETA/Documents_Geometronics/Construction-Survey-Manual-Contractors.pdf http://www.oregon.gov/ODOT/ETA/Documents_Geometronics/Construction-Survey-Manual-Contractors.pdf and/or time. Amendments require formal approval by the Board of County Commissioners, pursuant to LCRB Rule Division C-049-160, prior to approval of such work.

Approved Equal - Materials or services proposed by the contractor and approved by the County as equal substitutes for those materials or services specified.

Award – Same as “Notice to Intent to Award”.

BCC – The Clackamas County Board of County Commissioners

Bid - A written offer by a bidder on forms furnished by the County to do work stated in the bid documents at the prices quoted. "Bid" is synonymous with "proposal" in these bid documents.

Bid Closing - The date and time for Bid Closing is the same as the date and time for Bid Opening.

Bid Documents- The following documents together comprise the Bid Documents:

• Invitation to Bid, Instructions to Bidders, Bid Form, Bid Proposal, Schedule of Prices, Bid

• Bond, Performance Bond

• Certificate of Insurance, Prevailing Wage Rates

• The "Oregon Standard Specifications for Construction" by ODOT and APWA, 2024 edition.

• Plans and drawings

• Other bid documents included or referenced in the bid documents

• Addenda, if any

• The Agreement Form and Special Provisions

Bonds - The bond or surety bond is a written document given by the surety and principal to the obligee to guarantee a specific obligation.

Change Order - A price agreement for Extra Work, Changed Work, field directives, or other changes. A Change Order does not change the contract value, scope, or time until it is incorporated into an Amendment. Change Orders will be agreed upon, in writing, by the County Project Manager and the Contractor’s designated representative.

Contract - The written contract agreement, including amendments, signed by the Contractor and Clackamas County, which describes the work to be done, the contract amount, and defines the relationships and obligations of the Contractor and the County.

Contract Documents - The Invitation to Bid, the Instructions to Bidders, the accepted Bid Proposal and Schedule of Prices, the Subcontractor List, the Bid Bond, the Performance and Payment Bond, the Certificate of Insurance, the Prevailing Wage Rates, the Standard Specifications and Special Provisions, Amendments, the Plans and Drawings, the

Agreement, as well as all documents incorporated by reference therein, and any and all addenda prepared by or at the direction of and adopted by the County and further identified by the signature of the parties and all modifications thereof incorporated in the documents before their execution.

County - The term "County" shall mean Clackamas County, including the Board of County Commissioners, employees and agents of the County authorized to administer the conditions of these contract documents.

Department – A subdivision of the Agency.

Engineer - The County's Project Manager either acting directly or through an authorized representative(s). When referring to approval of extra work or other Contract modifications, “Engineer” also refers to the County’s legal authority according to the LCRB rules.

Invitation to Bid - The public announcement (Notice to Contractors) inviting bids for work to be performed or materials to be furnished.

Legal Holiday - As defined in ORS 279C.540.

Lump Sum - A method of payment providing for one all-inclusive cost for the work or for a particular portion of the work.

Notice of Intent to Award - A written notice from the County notifying bidders that the County intends to award to the responsible bidder submitting lowest responsive bid.

ODOT Procurement Office – Clackamas County Purchasing Department.

Owner – Synonymous with Agency.

Plan Holder’s List – A list of contractor’s names, contact names, phone and fax numbers that the County’s Purchasing Department creates during bidding of the Project.

Project Manager – The Owner’s representative who directly supervises the engineering and administration of the contract.

Shop Drawings – Synonymous with Working Drawings.

Solicitation Document – Synonymous with Bid Documents.

Standard Drawings – The Agency-prepared detailed drawings for Work or methods of construction that normally do not change from project to project. The Standard Drawings include the ODOT Standard Drawings.

Standard Specifications - "Oregon Standard Specifications for Construction", current edition, published by the Oregon Department of Transportation and as amended by the Agency.

State - Where the term “State” or “State of Oregon” or “ODOT” appears in the contract documents it shall mean “Clackamas County”, “State of Oregon”, or “ODOT” as applicable because of context.

Work Day - Any and every calendar day from January 1 to December 31 of every year, excluding Saturdays, Sundays and Legal Holidays.

SECTION 00120 – BIDDING REQUIREMENTS AND PROCEDURES

Comply with Section 00120 of the Standard Specifications supplemented and/or modified as

00120.00 Prequalification of Bidders - Delete and replace with the following:

See Instructions to Bidders. To gain Prequalification of Bidders through ODOT:

• If delivered by electronic mail, the application shall be sent to:

ODOTProcurementOfficeConstruction@odot.oregon.gov

• If delivered by mail or parcel delivery service, the application shall be sent to:

Oregon Department of Transportation Procurement Construction Contracts, MS #33 355 Capitol Street NE Salem, OR 97301

00120.01 General Bidding Requirements – Delete and replace with the following:

See Instructions to Bidders.

00120.05 Request for Plans, Special Provisions, and Bid Booklets: – Delete and replace with the following:

See Notice of Public Improvement Contract and Instructions to Bidders.

Copies of the 2024 Oregon Standard Specifications for Construction and Supplements might be found on the Oregon Department of Transportation website at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

The Plans, which are applicable to the Work to be performed under the Contract, are included in these Special Provisions.

00120.30 Changes to Plans, Specifications, or Quantities before Opening of Bids - Delete and replace with the following:

See Instructions to Bidders.

00120.40 Preparation of Bids – Delete and replace this section with the following:

See Instructions to Bidders.

00120.45 Submittal of Bids - Delete and replace with:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

00120.50 Submitting Bids for More than One Contract – Delete this subsection.

00120.60 Revision or Withdrawal of Bids - Delete and replace with the following:

See Instructions to Bidders.

00120.70 Rejection of Nonresponsive Bids – Delete and replace with the following:

00120.95 Opportunity for Cooperative Arrangement – Delete this section.

SECTION 00130 – AWARD AND EXECUTION OF CONTRACT

Comply with Section 00130 of the Standard Specifications supplemented and/or modified as

00130.00 Consideration of Bids - Delete third paragraph.

00130.10 Award of Contract - Delete and replace with the following:

See Instructions to Bidders.

00130.15 Right to Protest Award – Delete and replace with the following:

00130.30 Contract Booklet – Add the following:

Other documents are part of the contract documents by reference. These include, but are not limited to:

• The "Oregon Standard Specifications for Construction", 2024 Edition, as published by the Oregon Department of Transportation (ODOT).

• “Oregon Standard Drawings” latest edition, as published by ODOT.

• Clackamas County Service District No. 1 "Surface Water Standard Specifications", latest edition.

00130.40 Contract Submittals - Delete and replace with the following:

00130.70 Release of Bid Guaranties – Delete and replace with the following:

SECTION 00140 – SCOPE OF WORK

Comply with Section 00140 of the Standard Specifications supplemented and/or modified as

00140.30 Agency-Required Changes in the Work – Replace the last paragraph with the following:

Upon receipt of an Engineer’s written order modifying the Work, the Contractor shall perform the Work as modified via Change Order, which may be subject to approval as an Amendment.

If an Amendment incorporating changes to the Work increases the Contract amount, the Contractor shall notify its Surety of the increase and shall provide the Agency with a copy of any resulting modification to bond documents. The Contractor’s performance of Work pursuant to Amendments shall neither invalidate the Contract nor release the Surety. Payment for changes in the Work shall be made in accordance with 00195.20. Contract Time adjustments shall be made in accordance with 00180.80.

00140.31 "As-Built" Records - Add the following section:

Maintain a current and accurate record of the work completed during the course of this contract.

This may be in the form of "as-built" drawings kept by accurately marking a designated set of the contract plans with the specified information as the Work proceeds. Accurate, complete and current "as-built" drawings are a specified requirement for full partial payment of the work completed. At project completion and as a condition of final payment, the Contractor shall deliver to the Project Manager a complete and legible set of "as-built" drawings.

The "as-built" drawings must show the information listed below. Where the term "locate" or "location" is used, it shall mean record of position with respect to both the construction vertical datum and either construction horizontal datum or a nearby permanent improvement.

1) Record location of underground services and utilities as installed.

2) Record location of existing underground utilities and services that are to remain and that are encountered during the course of the work.

3) Record changes in dimension, location, grade or detail to that shown on the plans.

4) Record changes made by change order.

5) Record details not in the original plans.

6) Provide fully completed shop drawings reflecting all revisions.

SECTION 00150 – CONTROL OF WORK

Comply with Section 00150 of the Standard Specifications modified as follows:

00150.00 Authority of the Engineer – Delete and replace the first sentence with the following:

Except as indicated elsewhere in the Contract (e.g. Amendment approval by the BCC), the Engineer has full authority over the Work and its suspension.

00150.05 Cooperative Arrangements – Delete this section.

00150.10 Coordination of Contract Documents

(a) Order of Precedence – Delete this section and replace with the following:

The Engineer will resolve any discrepancies between these documents in the following order of precedence:

• Approved Amendments;

• Approved Change Orders

• Bid Schedule with Schedule of Prices;

• Permits from governmental agencies

• Special Provisions;

• Agency-prepared drawings specifically applicable to the Project and bearing the Project title;

• Reviewed and accepted, stamped Working Drawings;

• Agreement Form;

• Standard Drawings;

• Approved Unstamped Working Drawings;

• Standard Specifications;

• All other Contract Documents not listed above.

Notes on a drawing shall take precedence over drawing details.

Dimensions shown on the drawings, or that can be computed, shall take precedence over scaled dimensions.

00150.15(c) Contractor Responsibilities - Replace this subsection, except for the subsection number and title, with the following:

The Contractor shall perform the Contactor responsibilities described in the ODOT Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305) and the following:

• Perform staking layout of Flashing Beacons and appetences.

• Perform earthwork slope staking including intersections and matchlines and set stakes defining limits for clearing which approximate right-of-way and easements.

• Inform the Engineer of any property corners monuments and/or survey markers that are not shown on the plans and are found during construction activities prior to disturbing the monuments. Allow the Agency 2 Work days for referencing all found markers before they are removed. Monuments that are noted on the plans to be protected and are disturbed by the Contractor's activities shall be replaced by the Contractor’s surveyor at the Contractor's expense.

The Contractor shall perform the Contractor responsibilities described in the ODOT Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305).

00150.50 Cooperation with Utilities: Add the following to the end of Paragraph (a):

There may be other utility servers who are not specifically listed in these Special Provisions or on the Plans that may be adjusting or inspecting their facilities within the project limits.

00150.50(c) Contractor Responsibilities – Add the following to the bulleted list:

• Hold a utility scheduling meeting and monthly utility coordination meetings (see also 00180.42);

• Maintain and re-establish utility location marks according to OAR 952-001-0090(3)(a).

Coordinate re-establishment of the location marks with the associated Utility;

• Determine the exact location before excavating within the tolerance zone according to OAR 952-001-0090(3)(c);

• Backfill any exposed utilities as recommended and approved by the Utility representative.

Obtain utility locate warning tape from the Utility and replace damaged or removed warning tape. Utility locate warning tape may not be present at all existing utilities;

• Stake, place warning tape, and maintain no work limits around critical Utility facilities as shown or directed by the Engineer and the Utility; and

• In addition to the notification required in OAR 952-001-0090(6), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues.

Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown utility issues.

The existing underground utilities shown on the Plans have been determined by as-built records and field surveys, but are not guaranteed to be complete or accurate. The Contractor shall be responsible for contacting the individual utility companies to mark locations, and arranging with them for any relocation work that should be required.

The Contractor shall make excavations and borings ahead of the work where necessary to determine the exact location of underground pipes or other features, which might interfere with construction. The Contractor shall support and protect pipes or other services where they cross the trench and shall be responsible for all damages incidental in interruptions of service that may be caused by Contractor operations. Where a new utility line crosses an existing pipeline or other conduit, the trench backfill shall be well compacted in a manner that provides for the required backfill and compaction standards while protecting the utility in question.

Add the following subsection:

00150.50(f) Utility Information (No Anticipated Relocations) - Within the Project limits, there are no anticipated relocations with the Utilities listed below. The Contractor shall contact those

Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.

Utility

Contact Person's Name, Address, Email, and Phone Number

00150.50(f) Astound Broadband Construction Travis Edge Construction PM, 36653 US-26

Sandy, OR 97055, Travis.edge@astound.com,

(503) 899-3267

Or - Jeffrey McConville Construction PM, 36653 US-26

Sandy, OR 97055, jeffreymcconville@astound.com,

(503) 318-9804

00150.50(f) Clackamas River Water Jason Branstetter Chief Engineer, PE jbranstetter@crwater.com

00150.50(f) Clackamas County Transportation Maintenance Travis Wootan, Maintenance Supervisor 19246 Wacheno Parkway Oregon City, OR 97045, twootan@clackamas.us,

(503) 853-9735

00150.50(f) Consolidated Business Services Representing Beavercreek Telephone Matt Allison, Engineering Supervisor CBS | Direct Link, 190 SE 2nd Ave., Canby, OR 97013, matt.allison@cbsoregon.com,

(503) 592-2226

The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project.

Add the following subsection:

00150.50(g) Utility Information (Anticipated Relocations):

The following organizations may be adjusting Utilities within the limits of the Project during the period of the Contract with relocation Work estimated to be completed by the following dates and times:

mailto:Travis.edge@astound.com mailto:jeffreymcconville@astound.com mailto:twootan@clackamas.us mailto:matt.allison@cbsoregon.com

Subsection Utility

Contact Person's Name, Address, Email, and Phone Number

Estimated Completion

Date

00150.50(g)(1) Portland General Electric, Inc.

Penni Bean, Construction PM; 209 Warner Milne Rd Oregon City, Oregon 97045, penni.bean@pgn.com, (503) 347-9203

June 2026

WO #M5919818

00150.50(g)(1) Portland General Electric, Inc.

Paul Prichard, Design PM;

121 SW Salmon St, Portland, OR 97204, paul.prichard@pgn.com,

(971) 359-4906

June 2026

WO #M5919818

00150.50(g)(2) Clackamas County Broadband Exchange (CBX)

Duke Dexter, TS Project Coord., 150 Beavercreek Rd #305, Oregon City, OR 97045, DDexter@clackamas.us,

(971) 219-3339

June 2026

00150.50(g)(2) Clackamas County Traffic Engineering (ITS)

Ioana Cosma, P.E., Traffic Engineer, 150 Beavercreek Rd #300, Oregon City, OR 97045, ICosma@clackamas.us,

(503) 819-9626

June 2026

The Contractor shall contact the Engineer to view the approved Utility Relocation Plans; PGE Work Order #M5919818.

The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project.

(1) (Portland General Electric, Inc.) - "Power Supplier":

The Contractor shall notify the Power Supplier(s) in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the power line(s).

The Contractor shall notify the Power Supplier in writing, with a copy to the Engineer, 30 Calendar Days before the Contractor is scheduled to begin performing road construction.

After the Power Supplier receives the notification, the Contractor shall then allow the Power Supplier 21 Calendar Days to schedule and complete the relocation and adjustment work before the Contractor begins performing road construction.

Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. The Contractor shall maintain at least 10 feet of safety clearance. Exceptions require written approval from the Power Supplier(s) and may require an On-Site safety watcher, at no cost to the Contractor. The Contractor shall provide the Engineer a copy of the written approval of exception before beginning work.

(2) Clackamas County Broadband Exchange (and Intelligent Transportation Systems

(ITS):

mailto:penni.bean@pgn.com mailto:paul.prichard@pgn.com mailto:DDexter@clackamas.us mailto:ICosma@clackamas.us

The Contractor shall notify CBX and ITS, in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the line(s).

00150.70 Detrimental Operations – Add the following:

Portions of this project might be constructed in close proximity to existing private improvements.

All private improvements disturbed by the Contractor’s operations shall be repaired or replaced to equal or better condition at the Contractor’s expense. The Engineer may withhold from future payments to the Contractor, an amount equal to the costs reasonably estimated by the Engineer to repair or replace, as the case may be, those private improvements disturbed by the Contractor’s operations. Engineer shall release the retained amount once Engineer has determined that the Contractor has completed the repair consistent with the requirements of this provision. In addition, prior to construction, the Contractor shall provide to the Engineer videotape showing private property, if any, which may be disturbed during construction.

SECTION 00160 – SOURCE OF MATERIALS

Comply with Section 00160 of the Standard Specifications supplemented and/or modified as

00160.20(a) Buy America – Delete this section and replace with the following: Federal highway funds are NOT involved on this Project.

SECTION 00165 – QUALITY OF MATERIALS

Comply with Section 00165 of the Standard Specifications modified as follows:

00165.04 Costs of Testing – Replace this section with the following sentence: All testing required to be performed by the Contractor will be at the Contractor’s expense.

00165.10(a) Field-Tested Materials – Add the following sentence: The County follows the MFTP on its projects:

00165.10(b) Nonfield-Tested Materials - Add the following sentence:

The County follows the NTMAG on its projects.

SECTION 00170 – LEGAL RELATIONS AND RESPONSIBILITIES

Comply with Section 00170 of the Standard Specifications supplemented and/or modified as

00170.02 Permits, Licenses, and Taxes – Add the following:

This project is to be constructed in Clackamas County road right of way and streets. There are no separate road opening permits required from Clackamas County to perform the work required under this contract.

If the County has acquired all necessary rights of way for the project, no modification to Section

00170.03 is required.

00170.61(a) Workers’ Compensation - Replace this subsection, except for the subsection number and title, with the following:

The Contractor shall provide workers' compensation coverage for on-the-job injuries as required by 00170.70(e).

00170.65(b)(1) Minimum Wage Rates – Replace the paragraph that begins "The Bureau of Labor and Industries (BOLI) …" with the following paragraph:

The Bureau of Labor and Industries (BOLI) determines and publishes the existing State prevailing wage rates in the publication Prevailing Wage Rates for Public Works Contracts. The Contractor shall pay workers not less than the specified minimum hourly wage rate according to ORS 279C.838 and ORS 279C.840, and shall include this requirement in all subcontracts.

Add the following subsection:

00170.67 Fees - The fee required by ORS 279C.825(1) will be paid by the Agency to the Commissioner of the Oregon Bureau of Labor and Industries under the administrative rules of the Commissioner.

00170.70(a) Insurance Coverages - Add the following to the end of this subsection:

The following insurance coverages and dollar amounts are required pursuant to this subsection:

Insurance Combined Single Limit Annual Aggregate Coverages per Occurrence Limit

Commercial General Liability $1,000,000 $2,000,000

Commercial Automobile Liability $1,000,000 (aggregate limit not required)

00170.70(d) Additional Insured - Replace the paragraph that begins "The liability insurance coverages of 00170.70(a)…" with the following paragraph:

The liability insurance coverages of 00170.70(a) shall include an Additional Insured Endorsement endorsing the “State of Oregon, the Oregon Transportation Commission and the Oregon Department of Transportation, and their respective officers, members, agents, and employees” as Additional Insureds, but only with respect to the Contractor's activities to be performed under the Contract.

Coverage shall be primary and non-contributory with any other insurance and self-insurance. The liability coverages of 00170.70(a) that are permitted by the Agency to be obtained by an appropriate Subcontractor shall include all of the foregoing as Additional Insureds and shall also include the Contractor and its officers and employees as Additional Insureds.

• Clackamas County and its officers, agents, and employees

• Clackamas County Board of Commissioners

00170.72 Indemnity/Hold Harmless – Delete and replace with the following:

Clackamas County Public Improvement Contract.

Extend indemnity and hold harmless to the Agency and the following:

• Clackamas County and its officers, agents, and employees

• Clackamas County Board of Commissioners

00170.85(b-1) Contractor Warranty for Specific Items – This subsection does not apply:

SECTION 00180 – PROSECUTION AND PROGRESS

Comply with Section 00180 of the Standard Specifications supplemented and/or modified as

00180.06 Assignment of Funds Due Under the Contract - Delete first bulleted item.

00180.21 Subcontracting - Add the following to subsection (a):

All contracts with subcontractors or suppliers shall have provisions making the contract assignable to the County, at the option of the County, if the Contractor terminates, goes out of business, declares bankruptcy, or otherwise is unable to perform provided that the County gives the subcontractor notice of assignment within fourteen (14) days of learning of the inability of the Contractor to perform.

The Engineer may revoke consent to subcontract. If the Engineer revokes consent to subcontract, the subcontractor shall be immediately removed from the Project Site.

00180.40 Limitation of Operations - Add the following to subsection (a):

The Contractor must provide, at a minimum, a 48-hour notice to the Clackamas County Project Manager in order to perform any work on Saturdays.

Add the following subsection:

00180.40(c) Specific Limitations - Limitations of operations specified in these Special Provisions include, but are not limited to, the following:

Limitations Subsection

Cooperation with Utilities ......................................... 00150.50 Contract Time ...................................................... 00180.50(h) Closed Lanes .................................................. 00220.40(e)(1) Noise Control ........................................................... 00290.32

Be aware of and subject to schedule limitations in the Standard Specifications that are not listed in this Subsection.

00180.41 Project Work Schedules – Add the following:

A Type “B” schedule as detailed in the Supplemental Specifications is required on this Contract. In addition, a three-week look ahead schedule shall be prepared by the Contractor on a weekly basis and submitted to the Engineer. It shall include all construction activities planned for the following three-week period. The three-week look ahead schedule can be hand-written and shall be in a format agreed upon by the Contractor and the Engineer.

00180.43 Commencement and Performance of Work - Add the following bullet item:

• Conduct the work at all times in a manner and sequence that will insure minimal interference with traffic. The Contractor shall not begin work that will interfere with work already started.

If it is in the County's best interest to do so, the County may require the Contractor to finish a portion or unit of the project on which work is in progress or to finish a construction operation before work is started on an additional portion or unit of the project.

Add the following subsection:

00180.50(h) Contract Time - There is one Contract Time on this Project as follows:

• The Contractor shall complete all Work to be done under the Contract not later than October 30, 2026.

00180.70 Suspension of Work - Add the following to the first bullet item:

If the Inspector has reason to believe that any safety provisions are not being adhered to, the Inspector will immediately notify the Contractor’s site foreman and/or the appropriate person and the County Project Manager. The purpose of this discussion is to determine the validity of the alleged violation. This will also allow the Contractor a reasonable amount of time to correct or improve any of the provisions for the safety on this project. If the County Project Manager finds the problem still unresolved or uncorrected, they will notify the Contractor’s Project Manager and the County’s Risk Management Safety Analyst. If the County’s Risk Management Safety Analyst finds that the job site contains any unresolved safety issues they will take appropriate action up to and including suspension of the Contractor’s operations on all or part of the Work.

00180.85(b) Liquidated Damages - Add the following paragraph:

The liquidated damages for failure to complete the Work on time required by 00180.50(h) will be $800 per Calendar Day *.

* Calendar Day amounts are applicable when the Contract time is expressed on the Calendar Day or fixed date basis.

00180.85(c) Lane Closures - Lane closures beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.

It is impractical to determine the actual damages the Agency will sustain in the event Traffic Lanes are closed beyond the limits listed in 00220.40(e). Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500.00 per 15 minutes, or for a portion of 15 minutes, per lane, for any lane closure beyond the limits listed in 00220.40(e). In addition to the liquidated damages, all added cost for traffic control measures, including flagging, required to maintain the lane closures beyond the allowed time limits, will be at no additional cost to the Agency. The required traffic control measures will be as determined by the Engineer.

The Engineer will determine when it is safe to reopen lanes to traffic. Assessment of liquidated damages will stop when all lanes have been safely reopened. Any liquidated damages assessed under these provisions will be in addition to those listed in 00180.85(b).

Add the following subsection:

00180.85(e) Traffic Delays Beyond 20 Minutes - Stopping or holding vehicles beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.

It is impractical to determine the actual damages the Agency will sustain in the event traffic is stopped or held longer than the 20-minute limit listed in 00220.02. Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500 per 20 minutes, or for a portion of 20 minutes, for stopping or holding traffic longer than 20 minutes.

Assessment of liquidated damages will stop when the Engineer determines that traffic is no longer stopped or held beyond the 20-minute limit. Any liquidated damages assessed under these provisions will be in addition to those listed in 00180.85(b).

00180.88 Workplace Harassment Prevention Plan – Submit a workplace harassment prevention plan for review 10 days before the preconstruction conference. The plan shall ensure all workers are guaranteed a safe and respectful work environment regardless of their identity or status. The plan applies to, but is not limited to, a worker’s race, gender, creed, or any protected characteristic under state or federal law. At a minimum, the plan shall include:

• A Statement that the Contractor shall provide a safe and respectful workplace on the jobsite for all workers, subcontractors, suppliers, and other persons performing work.

• A description of how the plan will be implemented and monitored during the project duration.

• A list of the in-person trainings that will be conducted for workers of all ranks working on the project to support, promote, and grow a positive jobsite culture.

• A list of meaningful policies including procedures for aggrieved workers in need of recourse.

• How incidents involving bullying or harassment will be investigated and resolved in a prompt, thorough, and impartial manner.

Contractor shall post on the jobsite and make available copies of policies about hate, intimidation, or harassment including how to report incidents and how to receive support. Materials will be provided in all languages necessary to be inclusive of the workforce.

00180.89 Measurement – No measurement of quantities will be made for workplace harassment prevention plan.

00180.95 Payment – Payment for workplace harassment prevention plan will be for developing and implementing the plan during construction of the project, in-person training, developing meaningful policies, and investigating incidents.

SECTION 00190 – MEASUREMENT OF PAY QUANTITIES

Comply with Section 00190 of the Standard Specifications supplemented and/or modified as

00190.20(g) Agency-Provided Weigh Technician: Delete and replace subsection (g) with the following:

The Contractor must provide a weigh technician. The Agency will not provide one for the Contractor.

SECTION 00195 – PAYMENT

Comply with Section 00195 of the Standard Specifications supplemented and/or modified as follows:

00195.10 Payment for Changes in Material Costs - Delete and replace with the following:

No asphalt cement cost adjustment shall be used on this project.

00195.12 Steel Material Price Escalation/De-Escalation Clause – Add the following sentence:

No steel material price escalation/de-escalations shall be used on this project. There is no option for Contractor participation.}

00195.20(b) Significant Changed Work – Add the following:

Significant is defined as:

a) An increase or decrease of more than 25 percent of the total cost of the Work calculated from the original proposal quantities and the unit contract prices; or,

b) An increase or decrease of more than 25 percent in the quantity of any one major contract item.

For condition b) above, a major item is defined as any item that amounts to 10 percent or more of the original total contract price.

00195.50(a)(1) Progress Estimates - Delete the first sentence and replace with the following:

At a regular period each month to be determined at the Preconstruction Conference, the Contractor will make an estimate of the amount and value of pay item work completed and in place. This estimate will be submitted to the Project Manager for review and approval.

(2) Value of Material on Hand - Delete the section and replace with the following:

(2) Value of Material on Hand - The Contractor will make an estimate of the amount and value of acceptable material to be incorporated in the completed work which has been delivered and stored as given in 00195.60(a) for review and approval.

(4) Limitations on Value of Work Accomplished - In the first sentence, change "Engineer's estimate" to “Contractor’s reviewed estimate”.

00195.50 (b) Retainage - Delete the first paragraph and replace with:

The amount to be retained from progress payments will be 5.0% of the value of payments made, and will be retained in one of the forms specified in Subsection (c) below. The Agency will withhold Retainage from all force account and change order work.

00195.50(c) Forms of Retainage – Delete first paragraph and replace with:

Forms of acceptable retainage are set forth below in Subsections (1) through (4). “Cash, Alternate B (Retainage Surety Bond)” or “Cash, Alternate C (No Interest Earned)” are the Agency-preferred forms of retainage. Unless the Contractor notifies the Agency otherwise in writing, the Agency will automatically hold retainage per Subsection (4) “Cash, Alternate C (No Interest Earned).” If the Agency incurs additional costs as a result of the Contractor’s election for the Agency to hold retainage per Subsections (1), (2), or (3), the Agency may recover such costs from the Contractor by a reduction of the final payment.

00195.50(c)(1) Cash, Alternate A – Replace this subsection, except for the subsection number and title, with the following:

Retainage will be deducted from progress payments and held by the Agency until final payment is made according to 00195.90, unless otherwise specified in the Contract.

The Agency will deposit the cash retainage withheld in an interest bearing account as required by ORS 279C.560(5). Interest earned on the account shall accrue to the Contractor. Amounts retained and interest earned will be included in the final payment made according to 00195.90, unless otherwise specified in the Contract.

Any retainage withheld on Work performed by a Subcontractor will be released to the Contractor according to 00195.50(d).

00195.50(c)(2) Cash, Alternate B (Retainage Surety Bond) - Replace this subsection, except for the subsection number and title, with the following:

The Contractor may submit a Surety bond in lieu of all or a portion of the retainage required under the Contract. The Agency will accept this Surety bond unless the Agency first finds in writing good cause for rejection based on unique project circumstances in accordance with ORS 279C.560(1)(c).

The Surety bond must be in substantially the form specified in ORS 701.435 (4) (Oregon House Bill 4006, 2024), and executed by a Surety bonding company that is authorized to transact Surety business in the State of Oregon and may not be a Surety obligation of an individual. The Surety bond and any proceeds of the Surety bond must be made subject to all claims and liens and in the same manner and priority specified for retainage under ORS 279C.550 to 279C.570 and ORS 279C.600 to 279C.625. Agency will reduce the cash retainage held by an amount equal to the value of the Surety bond and pay the amount of the reduction to Contractor according to ORS 279C.570. Any retainage withheld on Work performed by a Subcontractor will be released to the Contractor according to 00195.50(d).

When the Agency accepts a Surety bond in lieu of retainage from the Contractor, the Contractor shall accept Surety bonds from Subcontractors or Suppliers from which the Contractor has withheld retainage. At any time before final payment a Subcontractor may submit a Surety bond to the Contractor and request that the Contractor submit a Surety bond as described above for the portion of the Contractor’s retainage that pertains to the Subcontractor. The Surety bond the Subcontractor provides to the Contractor must meet the Agency requirements specified in the paragraph above.

When a Contractor at a Subcontractor’s request obtains and submits a Surety bond under this subsection, the Contractor may withhold from payments to the Subcontractor an amount equivalent to the portion of the Contractor’s Surety bond premium for which the Subcontractor is responsible in accordance with ORS 279C.560 (Oregon House Bill 4006, 2024).

Within 30 Days after a Subcontractor’s request the Contractor shall provide a Surety bond as described above, and the Agency will accept the Surety bond unless:

• the Agency finds in writing good cause for rejection based on unique project circumstances in accordance with ORS 279C.560;

• a Surety bond is not commercially available;

• the Subcontractor refuses to pay to the Contractor the Subcontractor’s portion of the Surety bond premium; or

• the Subcontractor refuses to provide the Contractor with a Surety bond that meets the requirements of ORS 279C.560(1)(b).

Notwithstanding 00195.50(d), within 30 Days of receiving a Surety bond from Contractor at a Subcontractor’s or Supplier’s request, Agency will release to the Contractor the amount held as retainage that is equivalent to the amount the Contractor submitted as a Surety bond. Contractor shall, within 30 Days after receiving a Surety bond from a Subcontractor or Supplier, release to the Subcontractor or Supplier the amount the Contractor holds as retainage that is equivalent to the amount of the Surety bond submitted, in accordance with ORS 279C.560(8).

00195.50(c)(3) Bonds, Securities, and Other Instruments - Replace this subsection, except for the subsection number and title, with the following:

Contractor may deposit bonds, securities or other instruments with the Agency or in a bank or other financial institution, to be held by Agency instead of cash retainage for the benefit of the Agency, which the Agency will accept unless the Agency first finds in writing good cause for rejection based on unique project circumstances, in accordance with ORS 279C.560(1)(c).

If the Contractor deposits bonds, securities or other instruments, and Agency does not reject the bonds, securities or other instruments as permitted by ORS 279C.560(1)(c), the Agency will reduce the cash retainage by an amount equal to the value of the bonds, securities and other instruments.

Interest or earnings on the bonds, securities and other instruments accrue to the Contractor.

Bonds, securities and other instruments deposited instead of cash retainage shall be of a character approved by the Director of the Oregon…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .