This is a Questions and Answers document from the Port of Portland related to Solicitation 2026-14260 for wayfinding signage replacement at Portland International Airport's Terminal and Concourse areas. The project involves replacing existing signs with new wayfinding signage, including internally illuminated signs, digital displays (FM4 type with LED modules), and structural support systems throughout multiple concourses and sectors. The scope includes sign fabrication, installation, electrical connections, Division 26 and 27 work (power and controls), CAT6A cabling infrastructure, and remedial work for wall and ceiling patching where existing signs are removed. A virtual tour reference file was provided on August 6, 2026, for 360-degree images of sign locations. The non-mandatory bidders' conference was held on August 11, 2026. No specific bid closing date extension was granted due to schedule requirements. The contract will be awarded to the responsible bidder with the lowest responsive Base Bid, with liquidated damages assessed at $500 per day for delays beyond the substantial completion date.
The project requires contractors to maintain Oregon Construction Contractors Board registration prior to bid submission and perform at least 25 percent of the total contract cost with their own organization. The Port will provide artwork, message schedules, evacuation maps, and content for digital displays; however, RR10 sign artwork will be delivered by December 31, 2026. The contractor is responsible for all structural design integration, electrical infrastructure, and FM4 digital display hardware installation and commissioning, while the Port assumes responsibility for developing final digital content and media player programming. Installation work hours are flexible in public and exterior areas but must assume 50 percent of hold room work occurs between 10 p.m. and 4 a.m. and 50 percent of sterile area work occurs between 8 p.m. and 4 a.m. All changes to scope will be issued as change orders by the Port. The Engineer's Estimate will be released at bid opening. Fabrication should commence only after shop drawing approval, and 100 percent completed and approved product samples may be installed as finished contract work.
View the file
Other files
Show 40 more
Latest 50 of 248 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026-14260 Wayfinding Signage
Questions and Answers
# Question Answer
1 Is the fence you are requesting temporary fencing or permanent? If temporary, how long will the rental be needed for?
The project will be replacing signs within Terminal and Concourse areas. The Port does not anticipate the need for temporary or permanent fencing.
2 Do liquidated damages apply to this scope? Please refer to project manual page 004100-2 "The bidder agrees to pay, as liquidated damages to the Port for any delay, the sum of $500 per day for each day of delay beyond the substantial completion date so promised.
3 What is the award criteria for this project? Please Reference project manual page 004100-2, The Contract will be awarded to the responsible bidder with the lowest responsive Base Bid
4 If remedial works is in signage contractors scope: Existing-finish restoration standard Reference: G0.001–G0.004 general notes; demolition plans; Section
024119 Where existing signs are removed, please define the required restoration standard. Is localized patching and finish matching acceptable, or is refinishing of the entire wall, ceiling panel, or architectural surface required? If an existing finish is unavailable or cannot reasonably be matched, please confirm that full-area refinishing will be treated as additional work.
Where existing signs are removed, localized patching and finish matching is acceptable. If finish is unavailable or cannot be matched, full-area refinishing will be treated as additional work at the Port’s discretion.
5 Full-size samples—quantity and disposition Reference: Section 101400, 1.4.F–G and 1.5.C–D Please confirm whether each required full-size sign sample is included within the scheduled contract quantity or is an additional unit. Identify which approved samples may be installed as finished contract work and which samples will be retained permanently by the Port or Designer and must therefore be priced in addition to the scheduled quantities.
Please Reference project manual page 101400-2, 1.4, F "100% Completed and approved product samples may be installed."
6 Can you clarify, is the final power connection to be in the signage installers scope?
The final power connection will be in the contractors scope.
7 Missing drawing G2.321 Reference: GI1.000; message schedules G0.002–G0.004
Drawing G2.321, “Terminal – Mezzanine – Sector 21 – Floor Plan Signage,” is listed in the drawing index and referenced for signs K10-027, K10-028, RR10-066, and RR10-067, but it is not included in the issued drawing archive. Please issue the missing drawing and confirm the locations and mounting conditions for these signs.
G2.321 was included in the ZIP file “1026-14260 Drawings.zip” as sheet “PDX
2026-512 (188) G.231.pdf”.
8 For remedial work for ceiling connections, etc or resulting from careful removal that causes wall damages - we presume PDX operations has a small works crew to do the repairs?
The contractor will be responsible for any damage as a result of demolition and installation of any work associated with the project.
9 Can you provide a schedule of sign removals, with quantities of type, pictures and other details needed to price removal scope accurately?
Please refer to file titled "2016-14260 Virtual Tour.pdf". This was uploaded on
8/6/26 for 360 degree images at locations throughout the Concourses and
Terminal
10 Is it mandatory to have Oregon CCB registration prior to award, or we can have it later if the project is awarded?
No bid will be considered unless the bidder is registered with the State of Oregon
Construction Contractors Board to the extent required by ORS Chapter 701, prior to submitting a bid.
11 We missed the virtual meeting on 8/11/26. Can we still bid on this project? This was not a mandatory meeting so yes.
12 what is the estimated budget for this project ? The Engineers Estimate will be released at the time of bid opening.
13 Are alternate manufacturers allowed ? Reference project manual page 002100-1, A, “PRE-BID APPROVED EQUAL”
14 Is it mandatory to have Oregon county registration prior to award, or we can have it later if the project is awarded?
No bid will be considered unless the bidder is registered with the State of Oregon
Construction Contractors Board to the extent required by ORS Chapter 701, prior to submitting a bid.
15 Can you provide the record as-built drawings from the signage project at PDX T-
CORE?
The record as-builts drawings are not complete for TCORE. If there is specific information that is needed from the current drawings, some sheets can be distributed (if available).
16 25% self-performance calculation Reference: FAA General Provision 80-01
Please confirm whether direct labor performed by the prime contractor at its own off-site facility—including fabrication, graphic production, electrical assembly, final assembly, project management, and logistics—counts toward the required
25% self-performance, or whether only direct on-site work is eligible.
Anything managed in-house by the general contractor counts.
17 Division 26/27 and lighting-control boundary Reference: E2.700-series; E5.001;
T6.001; Sections 260933 and 271000 Please confirm whether the prime signage contractor is to carry all Division 26 and 27 work shown, including branch power, disconnects, DMX wiring, 0–10V controls, CAT6A connections, lighting-control devices, programming, and commissioning. Identify any work to be completed by the Port, an existing controls contractor, or another separate contractor.
All work is to be completed by contractor unless noted in specifications, Port support is minimal. See specifications 260933 for further information on requirements for lighting control dimming.
18 FM4 digital display basis of design and responsibility matrix Reference: G9.117;
T6.001; T7.001; Sections 271000 and 101400 Please provide the approved manufacturer/model or complete performance specification for the FM4 fine-pitch LED displays and video processors. Also confirm responsibility for: Six LED display faces associated with the three FM4 assemblies LG WP601 or equivalent media players Video processors and HDMI cabling CAT6A cabling and jacks
Network ports, IP addresses, and cross-connects GIDS content, software licensing, configuration, programming, testing, and commissioning
See 101400 section 2.10 for performance specifications. No specific LED manufacturer is specified. Responsibility is for the bidder to supply all hardware, software, installation, configuration, programming, testing, and commissioning to provide completed functioning signs. Signage player LG WP601 is required in order to integrate with the Port’s existing content management system. The Port will be responsible for developing the content for each signage player. 271000 includes bidder responsibility for providing Cat6A cabling and termination hardware to each sign location. Refer to drawing T6.01, keynote 1 for additional information.
19 Structural steel and support scope marked “by others” Reference: G9.102;
G9.117; S6.100–S6.130; Section 101400 G9.102 identifies the steel post and pipe attachment as “BY OTHERS,” while other details require additional structure to support new signs. Please confirm which structural posts, frames, backing, attachment steel, delegated engineering, and existing-building modifications are included in the signage contractor’s scope and which, if any, will be furnished under a separate Port contract.
Any and all structural posts, frames, backing, attachment steel, delegated engineering, and existing-building modifications shown in the drawings are in this contract and are the responsibility of the bidder. Exact delegation of specific scopes of work to subcontractors is the responsibility of the bidder. References to ‘BY OTHERS’ shall be removed by an upcoming addendum.
20 Reference: Section 101400, including 1.1 and 1.4; G0.001–G0.004 Please confirm when the final production-ready Adobe Illustrator artwork, approved message schedule, evacuation maps, symbols, arrows, and all presently TBD content will be issued. Please also confirm that print ready artwork is supplied by
PDX?
Artwork - Artwork is provided in the signage detail sheets, with the exception of
RR10 signs, which are currently in development, and will be provided on or before
12/31/26.
Message Schedule – See sheets G0.001-G0.004.
Evacuation Maps – VM sign evacuation map inserts will be provided by the Port.
Symbols - See sheet G9.001.
Arrows – Provided in message schedule on sheets G0.001-G0.004, or included in layout on signage detail sheets.
Other TBD Content – This will be provided on or before 12/31/26.
Production Ready Adobe Illustrator Artwork – This will be is provided by the project
- see spec section 101400-1.4 for sign fabricator responsibilities.
21 Locations for K10-025 and K10-026 Reference: G0.002 message schedule Signs
K10-025 and K10-026 are identified as “EXTRA – NOT SHOWN ON SLP,” with the plan-sheet reference listed as N/A. Please provide the exact location, orientation, elevation, mounting condition, power/control connection, and required installation phase for each sign.
These two signs shall be fabricated by the bidder and delivered to the Port for future installation by Port staff.
22 Work Hours: What are the permitted installation work hours, including any required night or off-hour work?
General - All work areas, work hours, and work sequencing shall be coordinated through the Port.
Public, Ticketing, and Baggage Claim Areas – There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Secure – There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Exterior Areas - There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Hold room Areas – Bidders to assume that 50% of the signage work will be performed between 10 pm and 4 am for operational hold room areas. Contractor will need to coordinate with Port for arrival and departure schedules for gate hold rooms.
Sterile Areas - Bidders to assume that 50% of the signage work will be performed between 8 pm and 4 am.
23 Project Manual noted sector 51 will have signs in Sign Group 2, but sheet G2.251 doesn't seem to have any signs noted that belong to the Sign Group 2, please clarify if there was a typo somewhere.
There are no sign group 2 signs in sector 51.
24 Are the FM4 digital displays in this scope? FM4 digital displays are in the scope. See Sheet G0.001, G9.117, and specifications 101400.
25 Are permits required for any of the signage or work? The Port will obtain all permits for the project with the exception of trade permits.
26 Can we get an extension to closing date - 2 weeks? Due to schedule requirements, the Port will not be able to extend the bid submission date.
27 There appear to be missing details / drawings for WM4 sign type? The detail for WM4 sign type appears on Sheet G9.118.
28 Temporary passenger wayfinding Reference: Removal plans; Section 015000
Please confirm whether temporary passenger-directional signage is required during removal and replacement of permanent signs. If required, please provide the temporary message plan, design standard, estimated quantities, installation durations, and responsibility for updates, or establish an allowance.
Bidder to propose installation schedule and procedures to mitigate need for temporary signage. All temporary signage required is the responsibility of the bidder, with design assistance provided by the design team.
29 Installation hours, shutdowns, and phasing Reference: Sections 011100, 013513, and 015000; Bid Form completion period Please provide the anticipated phasing/area-release schedule and the permitted installation hours for public, sterile, secure, holdroom, ticketing, baggage-claim, and exterior areas. Confirm which work must be performed at night and whether the bid should include multiple mobilizations, escorts, shutdowns, and restricted work windows beyond those expressly shown.
General - All work areas, work hours, and work sequencing shall be coordinated through the Port.
Public, Ticketing, and Baggage Claim Areas – There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Secure – There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Exterior Areas - There is no limitation on work hours, provided work does not interfere with normal passenger flow and airport activities.
Hold room Areas – Bidders to assume that 50% of the signage work will be performed between 10 pm and 4 am for operational hold room areas. Contractor will need to coordinate with Port for arrival and departure schedules for gate hold rooms.
Sterile Areas - Bidders to assume that 50% of the signage work will be performed between 8 pm and 4 am.
30 Content Responsibility Question: For Sign Type FM4, please confirm that the Port will furnish all final digital content and identify whether the Contractor is responsible only for hardware configuration and integration or also for content creation, formatting, testing, scheduling and future content revisions?
See 101400 section 2.10 for performance specifications. No specific LED manufacturer is specified. Responsibility is for the bidder to supply all hardware, software, installation, configuration, programming, testing, and commissioning to provide completed functioning signs. Signage player LG WP601 is required in order to integrate with the Port’s existing content management system. The Port will be responsible for developing the content for each signage player. 271000 includes bidder responsibility for providing Cat6A cabling and termination hardware to each sign location. Refer to drawing T6.01, keynote 1 for additional information.
31 Existing Sign Salvage vs. Disposal Question: Please provide a definitive schedule identifying which existing signs, electrical components and associated equipment are to be salvaged and delivered to the Port, relocated/reinstalled, or demolished and disposed of by the Contractor?
Any signage or equipment to be salvaged or relocated will be indicated on the plans and specifications.
32 Port Artwork / Message Release Question: When will the Port provide final production-ready digital artwork, sign messages, typography and graphic files for all sign types, Artwork - Artwork is provided in the signage detail sheets, with the exception of
RR10 signs, which are currently in development, and will be provided on or before
12/31/26.
Message Schedule – See sheets G0.001-G0.004.
Evacuation Maps – VM sign evacuation map inserts will be provided by the Port.
Symbols - See sheet G9.001.
Arrows – Provided in message schedule on sheets G0.001-G0.004, or included in layout on signage detail sheets.
Other TBD Content – This will be provided on or before 12/31/26.
Production Ready Adobe Illustrator Artwork – This will be is provided by the project
- see spec section 101400-1.4 for sign fabricator responsibilities.
33 Structural Engineering Please identify which sign structures, connections, attachments and supplementary supports require Contractor-provided delegated structural engineering and Oregon PE-stamped calculations, and which structural design and attachment engineering is complete and provided by the Engineer of
Record?
All signs indicated in the structural drawings have attachments to existing structure that have been designed by the EOR. This scope does not require any delegated design. The signs are considered a product, and KPFF will review these for general structural integrity as part of our typical EOR submittal review.
34 Full-Size Samples / Prototype Cost and Ownership Reference: Section 101400, 1.4.F The specification requires full-size completed samples for numerous sign types and states that some samples will be retained by the Port Which samples the port like to retain?
Reference project manual page 101400-2, 1.4, F "100% Completed and approved product samples may be installed."
35 Airport Escort / Restricted-Area Installation Costs Reference: Section 013513, Airport Security, Safety and Operating Regulations Please confirm which sign installation locations require SIDA/AOA/Sterile Area access, whether Port-provided escorts will be available for deliveries and occasional unbadged specialty personnel, and whether escort costs and delays resulting from Port access restrictions are to be carried in the Base Bid?
Reference Specification Section 013513 “Airport Security, Safety, and Operating
Regulations”.
36 Division 27 Specialty Cabling Contractor Reference: Section 271000, 1.5 and 1.6
Please confirm whether the Signage Contractor is required to retain an Oregon
Limited Energy Journeyman and a manufacturer-certified Berk-Tek/Leviton installer for all CAT6A work associated with the FM4 signs, including the specified extended manufacturer warranty, or whether any portion of this work will be performed by the Port's technology contractor?
Confirmed, installers must meet requirements outlined in 271000.
37 Section 101400 notes that up to ten fabrication shop visits may be required.
Could you kindly confirm that fabrication carried out in accordance with approved shop drawings and approved samples will not necessitate removal, replacement, or refabrication at the Contractor’s cost, if comments or design changes are introduced during subsequent Port/Designer shop reviews?
Any changes of scope will be issued as a change order from the Port.
38 Where field verification identifies that an existing wall, ceiling, truss or other substrate cannot support the specified sign attachment as detailed, will supplemental building reinforcement and associated engineering be provided by the Port as a Change Order, or is such reinforcement required to be included in the Base Bid?
Any changes of scope will be issued as a change order from the Port.
39 Section 101400 requires a “complete system with headend equipment, controllers, components, transmitters and receivers for fully functioning system”;
please identify the exact headend equipment, controllers, transmitters, receivers, licenses and other system components that are required to be furnished by the
Signage Contractor for Sign Type FM4 versus those furnished by the Port or other
Contractor is responsible for purchasing and installing the LG WP601-B media player. The Port will program and configure the media player with content, including licensing. Cat6A cabling and infrastructure is to be provided by Div 27.
LED modules, video controllers, and associated cabling must be fully configured and commissioned before engaging the Port for IP assignments and media player content configuration. Also see detail sheets per sign type, e.g. G9.103, for information on internal sign components
40 Will the Airport provide staging approximate 40×40 area and one room with lock and key?
A staging area will be provided for the general contractor.
41 Temporary Barricade Graphics Reference: Section 015000, Article 1.25, Sign
Policy Does the Contractor identification sign limitation in Section 015000, Article 1.25 also apply to graphics installed on temporary construction barricades, or may larger project-information and wayfinding graphics be installed on the barricades with prior Port approval?
Specification Section 015000, 1.25 is not intended for temporary wayfinding signage
42 Existing Structural Framing Reference: Section 051200, Structural Steel Framing;
S-Series Structural Drawings If previously unknown damage or deficiencies are discovered in the existing building framing or trusses at a proposed sign-support location, will the Port provide the engineered remedial design, or is the Contractor required to engineer and perform the repair as part of the Base Bid?
Any changes of scope will be issued as a change order from the Port.
43 Patching and Finish Repair Reference: Section 017329, Cutting and Patching;
Section 101400, Identifying Devices Where existing signs are removed and the mounting surfaces require patching and finish repair, is localized patching acceptable if the repair is not visible from a normal viewing distance, or is the
Contractor required to refinish the entire affected surface to the nearest intersection or natural break?
Where existing signs are removed, localized patching and finish matching is acceptable.? If finish is unavailable or cannot be matched, full-area refinishing will be treated as additional work at the Port’s discretion.
44 Sign Type ID1 Quantity Reference: Drawing G9.125, Note 1; Document 004100, Bid Form Drawing G9.125 states that Sign Type ID1 consists of two signs, Side A and Side B, at each door frame; should each ID1 location therefore be priced as one complete two-sign set?
Yes.
45 Dimming Control Grouping Reference: Section 260933, Central Dimming
Controls; Sequence of Operation for Internally Illuminated Signage Please provide the required control-grouping logic for the internally illuminated signs, including whether ON/OFF and dimming groups are to be organized by concourse, sector, sign type/function, or another Port-defined grouping?
Group signs for control as follows:
Concourse D
Sector 52: Hold room sign type FM3 signs to be grouped together for dimming control.
Sector 52: Concourse signs type WM2 and CMB2 to be dimming controlled individually.
Sector 53: Hold room sign type FM3 signs to be grouped together for dimming control.
Sector 53: Concourse signs type WM2 to be dimming controlled individually.
Sector 00: Hold room sign type FM3&4 signs to be grouped together with sector 01 FM3 sign for dimming control.
Sector 00: Concourse signs type WM2 & CM2 to be dimming controlled individually.
Sector 01: Hold room sign type FM3 sign to be grouped together with sector 01 FM3&4 signs for dimming control.
Concourse C
Sector 70: Hold room sign type FM3 signs to be grouped together with sector 71 west side FM3 for dimming control.
Sector 70: Concourse signs type CM2 to be dimming controlled individually.
Sector 71: Hold room sign type FM2 & 3 west side signs to be grouped with together sector 70 FM3 signs for dimming control.
Sector 71: Hold room sign type FM2 & 3 east side signs to be grouped together with (3) sector 72 west side FM3 signs for dimming control.
Sector 71: Concourse signs type CM2 to be dimming controlled individually.
Sector 72: Hold room sign type FM3 west side signs to be grouped together with sector 71 east side FM3 signs for dimming control.
Sector 72: Hold room sign type FM3 & CBL east side signs to be grouped together with (3) sector 73 FM2&3 signs for dimming control.
Sector 72: Concourse signs type CM2 to be dimming controlled individually.
Sector 73: Hold room sign type FM2&3 signs to be grouped together with sector 72 east side FM3 & CBL signs for dimming control.
Sector 73: Concourse signs type CM2 to be dimming controlled individually.
Sector 40: Hold room sign type FM3 signs to be grouped together with sector 41 FM3 sign for dimming control.
Sector 40: Concourse signs type CM2 to be dimming controlled individually.
Sector 41: Hold room sign type FM3 signs to be grouped together with sector 40 FM3 signs for dimming control.
46 FM4 Media Player / Network Commissioning Reference: Section 101400, Media
Controller for Sign Type FM4; Section 260933, Central Dimming Controls For Sign
Type FM4, please confirm whether the Contractor’s responsibility for the LG
WP601-B media player and CAT6A infrastructure ends with furnishing, installation, and connection, with Port IT responsible for IP assignment and final
LG SuperSign platform integration, or whether the Contractor is also required to provide final SuperSign configuration and commissioning?
Contractor is responsible for purchasing and installing the LG WP601-B media player. The Port will program and configure the media player with content, including licensing. Cat6A cabling and infrastructure is to be provided by Div 27.
LED modules, video controllers, and associated cabling must be fully configured and commissioned before engaging the Port for IP assignments and media player content configuration.
47 FM4 Media Player / Network Commissioning Reference: Section 101400, Media
Controller for Sign Type FM4; Section 260933, Central Dimming Controls
Does not appear to be a question.
48 Existing Electrical Circuits Reference: Equipment Connection Schedule, Keynote
1 Will the Port provide available electrical as-builts for the affected areas to assist with field verification of the existing circuits, and if an existing circuit is found to be non-functional, unsuitable, or the serving panel has insufficient capacity, will the required new circuit or home run be treated as a Change Order?
Any changes of scope in contract documents will be issued as a change order.
49 Approved prototypes can be used on the project — do you anticipate the prototyping phase running in parallel, or only after approvals?
Reference project manual page 101400-2, 1.4, F "100% Completed and approved product samples may be installed." Fabrication should only start after approval of shop drawings.
50 Do we need to prioritize production of shop drawings for prototypes before total submittals?
Shop drawings will be a submittal to the Port. Reference Specification Section
013300 Submittal Procedures.
51 Please confirm the required paint extent at patch locations. Should painting be limited to the repaired area, or extend to the nearest boundary (e.g., corner-to-corner) for a uniform finish?
Where existing signs are removed, localized patching and finish matching is acceptable.? If finish is unavailable or cannot be matched, full-area refinishing will be treated as additional work at the Port’s discretion.
52 Per Note 4 "WHERE NEW OR EXTENDED CIRCUITS ARE REQUIRED, CONCEAL
CONDUIT AND PROVIDE PATCHING AND PAINTING AS REQUIRED" , please provide desired routing and areas of impact that will require patching and painting.
Where existing signs are removed, localized patching and finish matching is acceptable.? If finish is unavailable or cannot be matched, full-area refinishing will be treated as additional work at the Port’s discretion.
53 Please confirm the existing structure can support the new signage, including additional loads.
The structural drawings have been prepared by a Registered Engineer in the State of Oregon.
54 Traffic Control: What specific traffic-control requirements apply to signage installation, including any engineered plans, professional traffic-control services, or required barricades?Are standard industry traffic-control devices, coordinated with the Airport Authority, adequate for signage installation?
Standard industry devices coordinated with the Port of Portland should be adequate for signage installation.
55 Paging System Relocation / Outages Reference: Section 260500, Existing Signal and Communication Systems; applicable Technology Drawings For relocation of existing paging speakers, what work hours and allowable outage durations apply, and is this work required to be performed during night shifts or other Port-designated outage windows?
See Technology Key Note: Paging circuitry shall be demolished back to the nearest existing paging speaker. contractor shall maintain paging zone operation by reestablishing temporary paging zone circuitry until new permanent paging zone circuitry is installed for final conditions.
56 Are fabricators prohibited from beginning fabrication until prototypes are fully approved?
Any fabrication initiated prior to such approval shall be performed at the fabricator’s sole risk and may be subject to rejection, removal, or replacement at no cost to the Owner.
57 Progress Payment Clarification We assume progress payments will be based on an approved Schedule of Values, invoiced monthly according to percentage of completion. Typical milestones include Bonds (if applicable), Engineering, Shop
Drawings, Material Procurement, Fabrication, Delivery, and Installation.Since the majority of signage project costs are incurred before materials arrive on site, we request confirmation that payments will be processed on the basis of % completion with supporting evidence, rather than solely upon installation.
Otherwise, bidders would be required to invest a substantial sum before receiving payment.Can you confirm if our understanding is accurate and meets your approval?
Reference Specification Section 007202 “Port General Conditions (FAA Projects)” and Specification Section 013200 “Construction Progress Documentation”
58 Could you please provide the pictures of sign types along with quantities that require removal?
Please refer to file titled "2016-14260 Virtual Tour.pdf". This was uploaded on
8/6/26 for 360 degree images at locations throughout the Concourses and
Terminal. Typical doors with signs will be shown.
59 Self-Performance: The Contract Documents appear to state both 25% and 8% self-performance requirements. Which percentage governs this Contract?
007200-27, paragraph 2 is correct "The Contractor shall perform, with his organization, an amount of work equal to at least 25 percent of the total contract cost." This has been corrected in Addendum 1.
60 For purposes of FAA Buy American/BABA compliance, please confirm whether the domestic-content requirements apply to the complete fabricated sign assembly, including aluminum, LED modules/displays, LED drivers, controllers, media players, power supplies and other electronic components, and identify any specified signage components for which the Port has already obtained or intends to obtain an FAA waiver?
The bidder should determine whether the sign assembly satisfies the BABA manufactured-product test based on the cost of its components. If the manufacturer can substantiate that the cost of U.S.-manufactured components exceeds 60% of the total cost of all components, the bidder may certify compliance even if some minor components are foreign or their origin is not specifically certified. The Port does not certify that all products and manufacturers are individually BABA compliant.
61 Are sales, use, or other taxes applicable to this project, and if so, which portions of the Work are taxable?
The bidder shall pay or ensure payment of sales, consumer, use, and other similar taxes required of the bidder and its subcontractors under any Law with respect to performance under this Contract. See Document 007200, Item 70-02, and
Document 007202, Item 6.29.
62 Apprentice Participation: If qualified apprentices are unavailable for specialized signage installation/rigging, will documented good-faith efforts under Section
16.6(D) satisfy the requirement, and grant us a waiver/reduction required?
Yes, in the event that the Contractor is unable to accomplish the Port’s target for registered apprentice participation, the Contractor shall demonstrate that a good faith effort has been made as detailed under Section 16.6(D) of Document
007202, and may provide supplemental information as listed in Section 16.6(E).
63 Is this project taxable? The bidder shall pay or ensure payment of sales, consumer, use, and other similar taxes required of the bidder and its subcontractors under any Law with respect to performance under this Contract. See Document 007200, Item 70-02, and
Document 007202, Item 6.29.
64 PlanetBids Attachments (RFI Clarification) We will reference bid document drawing/specification numbers wherever feasible. Can supporting vendor documents, drawings, or images (e.g., LED/sign components) be attached directly to an RFI when needed, or should they instead be emailed as required?
Our intent is simply to ensure there is a reliable means of including such supporting materials when clarification is necessary.
The question should be clearly stated in Planet Bids and not in an attachment.
Planet Bids does allow for attachments for reference.
65 Builder’s Risk / Installation Floater: Our insurance broker advises that sign installation is an installation exposure, not a Builder’s Risk exposure. Can an
Installation Floater be provided in lieu of Builder’s Risk?
Coverage will be reviewed for compliance prior to contract execution.
66 Umbrella / Excess Liability: Can the required $5 million liability limit be met through combined CGL and Umbrella/Excess coverage?
Coverage will be reviewed for compliance prior to contract execution.