2026-13 WATER DEPT BREAKROOM & BATHROOM IMPROVEMENT PROJECT
Solicitation number
PE-75050-NONST-2026-000000059
Issued by
Wilcox County, Georgia

About this file

This is a Request for Bids (RFB #2026-09) issued by the City of Sandersville Water Department for construction of breakroom and bathroom improvements at the water department's main shop facility. The project involves construction of a 12' x 30' breakroom and an 8' x 10' bathroom addition, including associated carpentry, masonry, plumbing, HVAC, electrical work, and finishes. The breakroom specifications include wood stud framing, plywood ceiling and walls, insulation, epoxy flooring, a commercial steel door, plexiglass window, 10 electrical receptacles, and 6 LED lights. The bathroom specifications include 8-inch cinder block construction, plumbing fixtures, handicap grab bars, exhaust fan, LED lighting, shower curtain, and washer/dryer connections. The project also requires installation of a 1-ton mini-split heat pump system. Sealed bids are due by 3:00 PM on September 15th, 2026, at City Hall, 141 West Haynes Street, Sandersville, Georgia 31082. Three copies of the bid and one digital copy on a jump drive must be submitted to Travis Fort, Water Department, P.O. Box 71. The deadline for submitting questions is 4:30 PM on Tuesday, September 8th, 2026, with responses posted on the city website.

Bids shall be submitted as lump sum amounts including all labor, materials, and delivery costs, with evaluation based on cost, availability, suitability, and quality. Contractors must include a W-9 Form, notarized E-Verify Contractor Affidavit, notarized SAVE Affidavit, Occupational Tax Certificate, General Public Liability and Property Damage Insurance Certificate with minimum limits of $1,000,000, and Worker's Compensation Proof of Insurance if employing more than three employees. Contractors must verify all quantities and measurements prior to bidding, as no change orders will be accepted due to measurement discrepancies. The contractor selected must commence work within three months of bid award and shall be solely responsible for all aspects of project execution, including compliance with all federal, state, and municipal laws and regulations. All bids received after the deadline will be deemed null and void, and the City reserves the right to accept or reject any or all bids.

View the file

Other files

File Type Posted
Break room _ Bathroom Blueprints.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Department Breakroom & Bathroom

Improvments

Request for Bids

RFB # 2026-09

Due Date: September 15th ,2026 @ 3PM

REQUEST FOR BIDS

CITY OF SANDERSVILLE

WATER DEPARTMENT

BREAKROOM & BATHROOM IMPROVMENTS

GENERAL

The City of Sandersville water department is seeking bids for the construction of a new 12’ x 30’ breakroom and a new 8’ x 10’ bathroom addition. All bids must be sealed and clearly marked.

“WATER DEPARTMENT BREAKROOM & BATHROOM IMPROVEMENTS”

The City of Sandersville will reserve the right to accept or reject any and all bids and act in the best interest of the City of Sandersville.

SPECIFICATIONS:

Submit proposal to furnish labor, materials, supervision, and equipment necessary to complete the breakroom and bathroom improvements.

Scope of Work

The work includes construction of a 12'-0" x 30'-0" breakroom and a 8'-0" x 10'-0" bathroom inside the main shop, including associated carpentry, masonry, plumbing, HVAC, electrical, finishes, and miscellaneous materials required for a complete installation as described below.

1. Breakroom Improvements

• Construct new breakroom area, approximately 12'-0" x 30'-0".

• Provide 2x4 wood studs at 16 inches on center.

• Provide 2x8x12 pine ceiling joists at 16 inches on center.

• Install 1/2-inch sanded plywood on ceiling and walls.

• Install R-13 wall insulation and R-19 ceiling insulation.

• Install all plywood with one coat primer and two coats finish paint.

• Provide epoxy paint/coating on floor.

• Provide rubber base.

• Provide one 3'-0" x 6'-8" commercial steel door.

• Provide approximately 48" x 30" plexiglass window.

• Provide 1 0 electrical receptacles 6 -4’ led lights in the breakroom area.

• Provide miscellaneous carpentry, trim, fasteners, and finish materials.

2. Bathroom Improvements

• Construct new bathroom area 8’x 10’

• Construct restroom walls with 8-inch cinder blocks.

• Provide 2x8 ceiling joists and ceiling finish materials.

• Provide one 3'-0" x 6'-8" commercial steel door.

• Provide restroom plumbing work, including rough-in and trim-out for fixtures shown in the concept layout.

• Provide shower curtain.

• Provide handicap grab bars, toilet and sink.

• Provide bath exhaust fan.

• Provide led can lights in the restroom area.

• Provide epoxy paint/coating on floor and shower walls.

• Provide miscellaneous restroom carpentry and finish materials.

• Provide painting for interior and exterior walls of bath.

• Provide washer & dryer connections to the outside back wall of bath.

3. Mechanical, Electrical, and Plumbing

• Provide plumbing improvements associated with the restroom and shower.

• Provide electrical improvements for lighting, receptacles, restroom exhaust fan, and general room power.

• Provide and install 1-ton mini-split heat pump system.

• Provide related rough-in, connections, and miscellaneous materials required for a complete installation.

CONTRACTOR’S RESPONSIBILITY

Nothing in these specifications shall be construed as placing the work under the specific direction or control of the Owner or relieving the Contractor from his liability as an independent

Contractor and, as such, he shall be solely responsible for the method, manner and means by which he shall perform his work, including, but not limited to supervision and control of his own personnel and scheduling of the work required to insure its proper and timely performance and he shall exercise due care to prevent bodily injury and damage to property in the prosecution of the work.

It shall be the responsibility of the contractor to verify all quantities and measurements prior to bidding. No change orders will be accepted due to differences in the bid packet measurements and the number of materials required to complete the scope of the project.

Until the work is accepted, it shall be in the custody and under the charge and care of the

Contractor, and he shall take every necessary precaution against injury or damage to the work by the action of all the elements, or from any other cause whatsoever. The Contractor shall restore and make good at his own expense all injuries or damages to any portion of the work before its completion and acceptance. Issuance of any estimate or partial payment to the Contractor for any part of work done will not be considered as final acceptance of any work.

The Contractor agrees to assume and shall have full and sole responsibility for compliance with all Federal, State or Municipal laws and regulations in any manner affecting the work to be performed by the Contractor or subcontractors.

BID SUBMITTAL

Bids will be lump sum and include all cost of labor and materials to include delivery to the point of destination. The bids will be evaluated and awarded based on several factors to include cost, availability, suitability and quality.

1. Bids will be received until 3:00 p.m. on September 30TH ,2026 at which time the bid opening will take place – City Hall Conference Room, 141 West Haynes Street, Sandersville, GA.

Any bids received after the deadline shall be null and void. The City of Sandersville reserves the right to accept or reject any or all bids and act in the best interest of the City of Sandersville.

2. All bids must be submitted in a sealed envelope clearly marked “Water Department

Breakroom & Bathroom Improvements” All shipping materials must be clearly marked with the project name.

3. Three (3) copies of the bid as well as a copy of your bid estimate on a jump drive with the required information must be submitted and received no later than above date to:

City of Sandersville, Attn: Travis Fort, Water Department Breakroom & Bathroom

Improvements.

P.O. Box 71, 141 W. Haynes Street, Sandersville, GA 31082

1. All bids must be submitted on the bid forms furnished and accompanied by:

• W-9 Form – Please complete attached form, check appropriate box, fill in Social

Security Number or Employer Identification Number, Sign and Date.

• Notarized E-Verify Contractor Affidavit – Please complete attached form. (To enroll in e-verify, you may visit the website www.uscis.gov/everify.)

• Notarized SAVE Affidavit – Please complete attached form.

• Occupational Tax Certificate

• General Public Liability and Property Damage Insurance Certificate with a limit of liability of not less than $1,000,000.

• Worker’s Compensation Proof of Insurance – For more than three employees.

http://www.uscis.gov/everify

2. Bid should state the start date and the work should commence within three months after the bid award.

QUESTIONS/ADDENDUMS

All communication including questions and substitutions shall be in email form. Questions will be answered and responded to until 4:30 p.m. on Tuesday September 8th, 2026

Communication may be sent to tfort@sandersvillega.org in regards to this request. Questions will be answered and posted on our website at www.sandersvillega.org under City Online, Bid

Opportunities tabs.

mailto:tfort@sandersvillega.org http://www.sandersvillega.org/

BID FORM

Water Department Breakroom & Bathroom

Improvements

Return Date: 3:00 PM, Tuesday, September 15TH, 2026.

Return to: City of Sandersville, Attn: Travis Fort

141 W. Haynes Street, Sandersville, GA 31082

LUMP SUM BID AMOUNT $ ________ ____________

EXPECTED START DATE: _____________________________

ALL BID FORMS SHOULD INCLUDE THE FOLLOWING INFORMATION:

Company Submitting Bid: ____________________________

Company Address:

Company Phone No: Company Fax No.

Authorized Representative:

Signature _ Date:___________________

Print Name and Title ____________ Phone: _______________

Email address __________________________________________________________________

Contractor Affidavit under O.C.G.A. § 13-10-91(b)(1)

By executing this affidavit, the undersigned contractor verifies its compliance with

O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services on behalf of the City of Sandersville has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned contractor will continue to use the federal work authorization program throughout the contract period and the undersigned contractor will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b). Contractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:

Federal Work Authorization User Identification Number

Date of Authorization

Name of Contractor

Name of Project

City of Sandersville

Name of Public Employer

I hereby declare under penalty of perjury that the foregoing is true and correct.

Executed on _______________, 20___ in _______________________(city), ______(state).

Signature of Authorized Officer or Agent

Printed Name and Title of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME

ON THIS THE ____ DAY OF ______________,20____.

NOTARY PUBLIC