2026 08 03 - Spanish Moss and Jeb Court Reconstruction_100 Specifications.pdf

PDF 3 MB Posted

Attached to
Spanish Moss Court & Drive and Jeb Court Reconstruction
Solicitation number
Bid #Q-0826-01
Issued by
Dallas County, Texas

About this file

Summary

This is a construction specification and bidding document issued by the City of Coppell, Texas for the Spanish Moss Drive & Court and Jeb Court Reconstruction Project (ST18-01A), Bid No. Q-0826-01. The project involves removal and replacement of 7,600 square yards of 6-inch reinforced concrete street pavement, 7,600 square yards of lime stabilized subgrade, 2,100 square yards of concrete sidewalk, storm drain infrastructure (1,500 linear feet of pipe with inlets and manholes), water line installation (2,000 linear feet), wastewater line installation (1,900 linear feet), and restoration of sod, landscaping, irrigation, mailboxes, and signs. The bidding documents are available digitally at www.bidnetdirect.com and for examination at the City Engineer's office. A non-mandatory pre-bid conference is scheduled for August 20, 2026, at 10:00 a.m. at Coppell City Hall. Sealed bids are due August 27, 2026, at 10:00 a.m., with bid opening conducted remotely via Zoom. Bidders must submit one hard copy and one digital copy (PDF) on flash drive. The contract time is a bidding consideration with a maximum of 400 calendar days allowed; bids exceeding this will be rejected. The award will be made to the lowest evaluated bidder based on Base Bid plus Time Bid (Calendar Days × $1,500.00).

The contract includes liquidated damages of $1,500 per calendar day for delays and corresponding incentives of $1,500 per day for early completion, with maximum incentive not to exceed $67,500. Bidders must provide a bid security (5 percent of maximum total bid), performance bond, payment bond, and maintenance bond (50 percent of contract value for two years post-completion). Prevailing wage rates apply with classifications ranging from $10.06 to $21.07 hourly. The contractor is responsible for all traffic control, site coordination with residents regarding access, and must document existing conditions via video prior to construction. Sales tax exemption applies to tangible personal property incorporated into the project. Insurance requirements include workers' compensation, commercial general liability ($1,000,000), automobiles ($500,000), and umbrella coverage ($1,000,000). The contractor must comply with federal, state, and local laws, provide subcontractor lists if requested, and maintain a permanent place of business.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SPECIFICATIONS

AND

CONTRACT DOCUMENTS

FOR

THE CITY OF COPPELL

Spanish Moss Drive & Court And

Jeb Court

(ST18-01A)

Bid No. Q-0826-01

Prepared by

5430 LBJ Freeway, Suite 1500, Dallas, TX 75240

August 3, 2026

TABLE OF CONTENTS

Page # Section 1 - Bidding Documents

Notice to Bidders 1-1 Instructions to Bidders 1-3 Bid Form 1-15 Proposal/Bid Schedule 1-18 Bid Summary 1-26 Proposal Guaranty 1-27 Prevailing Wage Rates 1-28 Bid Affidavit 1-29 Conflict of Interest 1-31

Section 2 - Contract Documents Standard Form of Agreement (Contract) 2-1 Certificate of Insurance 2-7 Instructions for Bonds 2-8 Performance Bond 2-9 Payment Bond 2-11 Maintenance Bond 2-13

For this project, the Standard Specifications for Public Works Construction – North Central Texas Council of Governments Fourth Edition, the City of Coppell Standard Construction Details (Ord.#2006-1129), and Appendix ‘C’ Design Criteria and Standards in the City of Coppell Subdivision Ordinance (Ord.#94-643) shall govern all work to be done, together with any additional Supplementary Conditions, Specific Project Requirements, General Notes, Description of Pay Items and/or Technical Specifications included herein.

Section 3 - City of Coppell's Supplementary Conditions 3-1 to the NCTCOG General Provisions

Section 4 - Specific Project Requirements 4-1

Section 5 - Description of Pay Items 5-1

Section 6 - Technical Specifications City of Coppell Project Sign

6-1

Turf and Grasses 6-2

Appendix A - Geotechnical Report

SECTION 1

BIDDING

DOCUMENTS

1-1 Bidding Documents

NOTICE TO BIDDERS

The City of Coppell is accepting bids for the reconstruction of Spanish Moss Drive & Court and Jeb Court Reconstruction Project (ST18-01A).

The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows: The work shall consist of the removal and replacement of 7,600 square yards of 6” reinforced concrete street pavement, 7,600 square yards of lime stabilized subgrade, 2,100 square yards of concrete sidewalk, removal and construction of storm drain inlets and manholes, 1,500 linear feet of storm drain pipe, 2,000 linear feet of water line and 1,900 feet of wastewater line, and associated valves, manholes, water/wastewater services, and other appurtenant structures. This project includes restoration of sod, landscaping, irrigation, mailboxes, signs, and any other items disturbed during the project. The overall scope of work shall include all components necessary for the “turnkey” construction of the project as shown in the plans for the Spanish Moss Drive & Court and Jeb Court Reconstruction Project (ST18-01A).

The Contractor for this project shall be responsible for coordinating with the residents regarding driveway access, mail/trash pickup (as applicable) and available street parking within the project.

Digital copies of the bidding documents can be downloaded at www.bidnetdirect.com.

Bidding documents also may be examined free of charge at the offices of the City Engineer, City of Coppell, 255 Parkway Boulevard, Coppell, Texas. To ensure proper notification of Addendums, make sure that you are a registered plan holder on the plan holder’s list.

Sealed bids addressed to Procurement Services, City of Coppell, Texas, for the construction of Spanish Moss Drive & Court and Jeb Court Reconstruction Project (ST18-01A) will be received in the Purchasing Office at the City of Coppell Town Center, 255 E. Parkway Boulevard, Coppell, Texas, Each Bidder shall submit one hard copy of this bid and one digital copy (PDF format) saved on a flash drive with the City of Coppell Bid No. Q- 0826-01 designated clearly on the exterior of the bid envelope.

A Non-Mandatory Pre-Bid Conference has been scheduled for this project at the Coppell City Hall (255 E. Parkway Boulevard, Coppell TX 75019) at 10:00 a.m. on Thursday, August 20, 2026. Attendance at the Pre-Bid Conference is not mandatory but strongly encouraged.

Pre-Bid meeting – Thursday, August 20th, 2026, 10:00 a.m.

Refer to Bidnetdirect for Zoom link

Bid Open – Thursday, August 27th, 2026, 10:00 a.m.

Refer to Bidnetdirect for Zoom link

1-2 Bidding Documents

The Owner reserves the right to reject any or all bids and to waive formalities. Unreasonable or unbalanced unit prices will be considered sufficient cause for rejection of any bid or bids.

NO BID TRANSMITTED BY FAX WILL BE ACCEPTED.

Bidders are expected to inspect the site of the work and to inform themselves regarding local conditions and conditions under which the work is to be done.

Complete sets of bidding documents must be used in preparing Bids; the City of Coppell assumes no responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

NO SALES TAX ON TANGIBLE PERSONAL PROPERTY INCORPORATED INTO OR MADE A

PART OF THE PROJECT. The bidder shall not include or provide for sales tax on tangible personal property to be incorporated into the project. (Note: This procedure may not be used, however, for materials which do not become a part of the finished product, such as, equipment rental or purchase, form materials, etc.). In order to be exempt from the sales tax on such tangible personal property, the contract shall separate and provide separate charges for materials to be incorporated into the project from charges for labor. The City will provide the Contractor with an exemption certificate for the materials. The contractor is expected to issue a resale certificate in lieu of paying a sales tax at the time of purchase. The bidder shall show the cost of materials (tangible personal property) in the space provided on the bid form. The successful bidder's bid form will be used to develop a separated contract and determine the extent of the tax exemption.

1-3 Bidding Documents

INSTRUCTIONS TO BIDDERS

1. Defined Terms.

Terms used in these Instructions to Bidders which are defined in the Standard Specifications for Public Works Construction - North Central Texas Council of Governments Fourth Edition, and the Supplementary Conditions of Agreement have the meanings assigned to them in these General Conditions. The term "Bidder" means one that submits a Bid directly to Owner, as distinct from a sub- bidder, who submits a bid to a Bidder. The term "Successful Bidder" means the lowest, qualified, responsible Bidder, as determined after review of calendar days, overall price, and qualifications, to whom the Owner (on the basis of the Owner's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Notice to Bidders, Instructions to Bidders, the Bid Form, the Construction Plans and Specifications, and the proposed Contract Documents (including all Addenda issued prior to receipt of bids). Specific defined terms are:

Owner: Wherever the word “Owner” or "OWNER" is used in the specifications and Contract Documents, it shall be understood as referring to the City of Coppell, Texas.

Engineer: Wherever the word “Engineer” or "ENGINEER" is used in the Specifications and Contract Documents, it shall be understood as referring to the City Engineer or his authorized representative, City of Coppell, P.O. Box 9478, Coppell, Texas 75019.

Consulting Engineer: Wherever the word “Consulting Engineer” or "Design Engineer" is used in the Specifications and Contract Documents, it shall be understood as referring to the Design Engineer or his authorized representative, Huitt-Zollars Professional Services Inc., 5430 Lyndon B Johnson Fwy Ste 1500, Dallas, TX, 75240.

Inspector: The authorized representative of the City of Coppell assigned to observe and inspect any or all parts of the work and the materials to be used therein.

2. Scope of Work.

The work shall consist of the removal and replacement of 6,800 square yards of 6” reinforced concrete street pavement, 7,573 square yards of lime stabilized subgrade, 2,118 square yards of concrete sidewalk, removal and construction of storm drain inlets and manholes, 1,600 linear feet of storm drain pipe, 2,000 linear feet of water line and 1,900 feet of wastewater line, and associated valves, manholes, water/wastewater services, and other appurtenant structures.

This project includes restoration of sod, landscaping, irrigation, mailboxes, signs, and any other items disturbed during the project.

Work shall include all components necessary for the “turn key” construction of the project as shown in the plans for the Spanish Moss Drive & Court and Jeb Court Reconstruction Project ST18-01A. It will be necessary to maintain access to the adjacent properties at all times throughout the project. The project contractor shall be responsible for all traffic control and any additional work necessary to maintain the safe operation of traffic through the project site.

3. Copies of Bidding Documents.

3.1 Digital copies of the bidding documents can be downloaded at www.bidnetdirect.com. Bidding documents also may be examined free of charge at the offices of the City Engineer, City of Coppell, 255 Parkway Boulevard, Coppell, Texas.

After award of the Contract, the successful Bidder will be furnished two (2) full-size sets and three (3) half-size sets of Contract Documents at no charge. Additional sets will be furnished for an additional fee per set.

3.2 Complete sets of Bidding Documents must be used in preparing Bids; the City of

Coppell assumes no responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. No partial sets of plans, specifications or proposal forms will be issued.

3.3 The Owner, in making copies of Bidding Documents available on the above terms, does so only for the purpose of obtaining Bids on the Work and does not confer a license or grant for any other use.

4. Qualifications of Bidders.

The Bidder shall submit within five (5) days of the Owner's request such evidence as the Owner may require establishing his financial responsibility, experience and possession of such equipment as may be needed to prosecute the work in an expeditious, safe and satisfactory manner. Submissions will be made to City Engineer, City of Coppell, 255 Parkway Boulevard, Coppell, Texas. The required information to be submitted shall consist of, but shall not necessarily be limited to, the following:

A. Current Project Experience: A list of all projects presently under construction by the bidder including approximate cost and completion date shall be submitted upon request.

B. Past Project Experience: A list of comparable street reconstruction and water/sewer replacement projects completed within the previous five years including approximate cost(s), quantities, and completion date(s).

C. Equipment: A list of equipment, which will be used on this project. The

Bidder shall demonstrate that he has adequate equipment to complete this project, properly and expeditiously and shall state what additional equipment, if any, that he must rent/lease as may be required to complete this project.

1-4 Bidding Documents

1-5 Bidding Documents

D. Financial: Each Bidder shall be prepared to submit upon request of the Owner a balanced financial statement with no evidence of threatening losses as evidenced by an audited certified financial statement (current within the last six (6) months of bid date). This information will be used to confirm that the Bidder has suitable financial status to meet obligations incidental to performing the work.

E. Technical Experience: The Bidder shall demonstrate to the satisfaction of the Owner that he has the technical experience to properly complete this project.

F. Proof that the bidder maintains a permanent place of business.

5. Conflict of Interest.

City Charter states that no officer or employee of the City shall have a financial interest (direct or indirect) in any contract with the City, nor shall be financially interested (directly or indirectly) in the sale to the City of any land, or rights or interest in any land, materials, supplies or services. This prohibition does not apply when the interest is represented by ownership of stock in a corporation involved, provided such stock ownership amounts to less than one percent (1%) of the corporation stock. Any violation of this prohibition will constitute malfeasance in office. Any officer or employee of the City found guilty thereof should thereby forfeit his office or position. Any violation of this prohibition with the knowledge, expressed or implied, of the persons or corporations contracting with the City shall render the contract voidable by the City Manager or the City Council. By submitting a bid, the Contractor represents that no employee or officer of the City has an interest in the Contractor.

6. Examination of Contract Documents and Site.

6.1 Access to the site will be available on the day of the pre-bid meeting. It shall be the

Contractor’s responsibility before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to become familiar with local conditions that may affect cost, progress, performance or furnishing of the Work, (c) consider federal, state and local Laws and Regulations that may affect cost, progress, performance or furnishing of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. Failure to make these examinations shall in no way relieve any Bidder from the responsibility of fulfilling all of the terms of the contract, without additional cost to the OWNER.

6.2 Information and data reflected in the Contract Documents with respect to

Underground Facilities at or contiguous to the site is based upon information and data furnished to the Owner by Owners of such underground Facilities or others, and the Owner does not assume responsibility for the accuracy or completeness thereof.

All existing structures, improvements, and utilities shall be adequately protected, at the expense of the Contractor, from damage that might otherwise

1-6 Bidding Documents occur due to construction operations. Where construction comes in close proximity to existing structures or utilities, or if it becomes necessary to move services, poles, guy wires, pipe lines, or other obstructions, it shall be the Contractor's responsibility to notify and cooperate with the utility or structure owner. The utility lines and other existing structures shown on the plans are for information only and are not guaranteed by the City to be complete or accurate as to location and/or depth. It shall be the Contractor's responsibility to verify locations and depths sufficiently in advance of construction such that necessary adjustments may be made to allow for the proper installation of proposed improvements as indicated in the plans. The Contractor shall be liable for damage to any utilities resulting from the construction of this project.

6.3 Before submitting a Bid, each Bidder will, at Bidder's own expense, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and underground facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing of the Work and which Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price and other terms and conditions of the Contract Documents.

6.4 On request in advance, the Owner will provide each Bidder access to the site to conduct explorations and tests as each Bidder deems necessary for submission of a Bid. Bidder shall fill all holes, clean up and restore the site to its former conditions, according to the City standards, upon completion of such explorations.

6.5 The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by Contractor in performing the Work, are identified in the Contract documents.

6.6 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 6, that without exception the Bid is premised upon performing and furnishing the work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

7. Interpretations and Addenda.

7.1 All questions about the meaning or intent of the Contract Documents are to be directed to the City of Coppell Purchasing Agent. Interpretations or clarifications considered necessary by the City of Coppell Purchasing Agent in response to such questions will be issued by Addenda mailed or delivered to all bidders recorded as having received the Bidding Documents. Questions received less than two days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations

1-7 Bidding Documents or clarifications will be without legal effect. Each Bidder shall acknowledge on the bid proposal that all Addenda issued have been received.

7.2 Addenda may also be issued to modify the Bidding Documents as deemed advisable by the Owner.

8. Contract Time.

8.1 The time of completion of the project will be set through the bidding technique used in the Proposal Form. A more detailed explanation of the bidding technique and completion time is given in Item 1.7 of the Specific Project Requirements (Section 4).

Completion time will be a strong factor in the awarding of a contract for this project.

8.2 Prior to the issuance of the Notice to Proceed by the Owner, the Contractor shall submit a detailed Progress and Schedule chart to the Owner for approval.

8.3 Extension of the contract time shall be based on a Change Order or written amendment as specified in Item 108.8 of the General Provisions.

9. Liquidated Damages.

Provisions for liquidated damages are set forth in the Contract and Item 1.7 of the Specific Project Requirements.

10. Substitute or "Or-Equal" Items.

The Contract, if awarded, will be on the basis of materials and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute or "or-equal" items. Whenever it is indicated in the Drawings or specified in the Specifications that a substitute or "or-equal" item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. No substitutions should be considered during the bidding process.

11. Subcontractors, Suppliers, and Others.

11.1 If the Owner requests the identity of any Subcontractors, Suppliers, or other persons or organizations to be submitted to the Owner in advance of the specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within seven (7) days after the request submit to the Owner a list of all such Subcontractors, Suppliers and other persons and organizations proposed for those portions of the Work for which such identification is requested. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, supplier, person or organization if requested by the Owner.

If the Owner, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, other person or organization, Owner may, before the Notice of Award is given, request the apparent Successful

1-8 Bidding Documents

Bidder to submit an acceptable substitute in which case the apparent Successful Bidder shall submit an acceptable substitute. Bidder's Bid price may be increased (or decreased) by the difference in cost occasioned by such substitution, and the Owner may consider such price adjustment in evaluating Bids and making the contract award.

If the apparent Successful Bidder declines to make any such substitution, the Owner may award the contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, other persons and organizations. The declining to make requested substitutions will not constitute grounds for sacrificing the Bid security of any Bidder.

11.2 No Contractor shall be required to employ any Subcontractor, Supplier, other person or organization against whom Contractor has reasonable objection.

12. Bid Proposal.

12.1 One (1) completed Bid Proposals must be submitted in a sealed envelope as described in Item 15 of these Instructions to Bidders. The blank spaces in the Bid Form shall be filled in for each item for which a quantity is given and the Bidder shall state the price for which he proposes to do each item of work. All blanks on the bid form must be completed in ink or typed. No substitutions, revisions, or omissions from the plans and/or specifications will be accepted unless authorized in writing by the Owner.

12.2 The legal status of the Bidder, that is, as a corporation, partnership, or individual, must be stated on the Bid Form.

A corporation Bidder must name the state in which the organization is chartered. Bids which are signed for a corporation shall have the correct corporate name thereof, its post office address, and the signature of the president or other authorized officer of the corporation, manually written below the corporate name in the following manner:

"By ."

If the bid is made by a firm or partnership, the name and post office address of the managing member of the firm or partnership shall be given or the bid may be signed by an attorney-in-fact. If signed by an attorney-in-fact, there shall be attached to the bid a power of attorney evidencing authority to sign the bid, executed by the members of the firm or partners.

If the bid is made by an individual, his post office address shall be given. Bids which are not signed by the individuals making them shall have attached thereto a power of attorney evidencing authority to sign the bid in the name of the person for whom it is signed.

13. Provision Concerning Escalator Clauses.

Bids containing any condition which provides for changes in the stated bid prices due to increase or decrease in the costs of materials, labor, or other items required

1-9 Bidding Documents for this project, may be rejected and returned to the Bidder without being considered.

14. Estimates of Quantities.

The quantities listed in the Bid Form will be considered as approximate and will be used for the comparison of bids, unless stated otherwise in the description of pay items. Payments will be made to the Contractor only for the actual quantities of work performed or materials furnished in accordance with the contract. The quantity of work to be done and the materials may be increased or decreased as provided for in the Contract Documents. If an item is noted as a “Plans Quantity” then only the quantity shown in the unit bid price schedule will be paid.

15. Submission of Bids.

Bids will be received by the Purchasing Agent, and shall be submitted to the Purchasing Agent, City of Coppell, at the Town Center, 255 East Parkway Boulevard, Coppell, Texas 75019 until, until 10:00 a.m., Thursday, August 27th, 2026, and then publicly opened and read aloud remotely via a Zoom meeting. One copy of the bid enclosed in an opaque sealed envelope and marked with the Project title, City of Coppell Spanish Moss Drive & Court and Jeb Court Reconstruction Project (ST18- 01A), and the name and address of the Bidder shall be submitted. If the Bid is sent through the mail or other delivery system the sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED Reconstruction of: Spanish Moss Drive & Court and Jeb Court Reconstruction Project ST18-01A on the face of it and addressed to the Purchasing Agent, City of Coppell, Texas. Bid submission shall include Bid Form, Bid Affidavit, Bid Bond and Conflict of Interest Form.

16. Modification and Withdrawal of Bids.

16.1 Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids.

16.2 If, within twenty-four hours after the Bids are opened, any Bidder files a duly signed written notice with the Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of the Bid, that Bidder may withdraw his bid. Thereafter, that Bidder will be disqualified from further bidding on the work.

1-10 Bidding Documents

17. Rejection of Bids.

Bids may be rejected if they show alterations of form, additions not called for, conditional bids, incomplete bids, erasures or irregularities of any kind. The Owner reserves the right to waive any irregularities in the bids as received and to reject any and all bids without qualification(s). More than one bid from an individual, firm or partnership, corporation or association, under the same or different names, will not be considered. Reasonable grounds for believing that a Bidder is interested in more than one such bid may cause the rejection of all bids in which said Bidder is interested. Bids in which prices are obviously unbalanced may be rejected. Bids submitted without a Proposal Guaranty, per NCTCOG’s Item 102.5 of the Standard Specifications for Public Works will be rejected. Bids with more than 400 Calendar Days for the time of completion will be rejected.

18. Bids to Remain Subject to Acceptance.

All Bids will remain subject to acceptance for ninety (90) calendar days after the day of the Bid opening, but the Owner may, in its sole discretion, release any Bid prior to that date.

19. Award of Contract.

19.1 For the purpose of award, each bid submitted shall consist of:

Base Bid (A) = Bid Proposal Total for Items 101-162 and project allowances for Spanish Moss Drive & Court and Jeb Court = The correct summation of the products of the estimated quantities shown in the proposal, multiplied by their bid unit prices for the construction of Spanish Moss Drive & Court and Jeb Court.

Alternate Bid (C) = Bid Proposal Total for Base Bid (A) + Bid Alternate Items

(B) for Spanish Moss Drive & Court and Jeb Court = The correct summation of the products of the estimated quantities shown in the proposal, multiplied by their bid unit prices for the construction of Spanish Moss Drive & Court and Jeb Court.

Time Bid (D) = Total Calendar Days x Daily Value = The time for completion in calendar days written on the Bid Form in the space provided multiplied by $1,500.00 for each calendar day.

The lowest evaluated bid (total Bid) will be determined by the Owner as the lowest sum of the Base Bid (A) or Alternate Bid (C) plus Total Calendar Days x $1,500.00 (D)

1-11 Bidding Documents

19.2 The Owner reserves the right to reject any and all Bids, to waive any and all informalities except for the time of submission of the Bid and to negotiate contract terms with the Successful Bidder. The Owner also reserves the right to reject all nonconforming, non-responsive, unbalanced or conditional Bids. Also, the Owner reserves the right to reject the Bid of any Bidder if the Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or has doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner. Discrepancies in the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

19.3 In evaluating Bids, the owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid form or prior to the Notice of Award. Time of completion will be a consideration in the award of the bid.

19.4 The Owner may consider the qualifications and experience of any Subcontractors, Suppliers, or other persons or organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as requested by the Owner. The Owner also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award.

19.5 The Owner may conduct such investigations as the Owner deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial stability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to the Owner's satisfaction within the prescribed time.

19.6 If contract is to be awarded, it will be awarded to the lowest and best qualified Bidder whose evaluation by the Owner indicates to the Owner that the award will be in the best interests of the Project.

19.7 If the contract is to be awarded, the Owner will give the Successful Bidder a Notice of Award within ninety (90) calendar days after the date of the Bid opening.

20 Incentive/Liquidated damages.

The Owner desires to expedite construction on this contract to minimize the inconvenience to the traveling public and to reduce the time of construction. In order to achieve this, an incentive/liquidated damages provision is established for this contract.

20.1 Time of Completion. The maximum time of completion that will be allowed for the

Spanish Moss Drive & Court and Jeb Court Reconstruction Project is 400 calendar days. A contract time bid of more than 400 days will be considered nonresponsive and, therefore, rejected.

1-12 Bidding Documents

20.2 Liquidated Damages. Failure to complete the Project within the established number of calendar days, plus any additional calendar days granted, will result in liquidated damages being assessed for every calendar day in excess of the stated number.

20.3 Credit for Completion of Work Ahead of Time. Should the Contractor complete the Project under the number of calendar days specified in the proposal, a credit in the amount of the incentive per calendar day (equal to the liquidated damage rate) for the number of calendar days under the number stipulated in the proposal, plus any additional calendar days that may be granted. This credit will be added to the money due or to become due the Contractor under the contract. The total incentive payment shall not exceed $67,500.00 ($1,500 x 45 days).

21. Execution of Agreement.

Within fifteen (15) days after written notification of award of the contract, the Successful Bidder shall execute and furnish to the Owner three (3) original signed contracts and a Certificate of Insurance.

22. Affidavit of Bills Paid.

Prior to final acceptance of this project by the Owner, the Contractor shall execute an affidavit that all bills for labor, materials, and incidentals incurred in the project construction have been paid in full, and that there are no claims pending.

23. Bid Compliance.

Bid must comply with all Federal, State, county and local laws. Contractor shall not hire nor work any illegal alien.

24. Notice to Proceed.

Upon execution of the Contract, the Owner will issue a written Notice to Proceed to the Contractor requesting that he proceed with the construction. The Calendar day count for the project shall commence within ten (10) calendar days after the date of the Notice to Proceed or when the contractor begins work, whichever occurs first.

25. Sales Tax.

The bidder shall not include or provide for sales tax on tangible personal property to be incorporated into the project. In order to be exempt from the sales tax on such tangible personal property, the contract shall separate and provide separate charges for materials to be incorporated into the project from charges for labor. The City will provide the Contractor with an exemption certificate for the materials. The contractor is expected to issue a resale certificate in lieu of paying a sales tax at the time of purchase. The bidder shall show the cost of materials to be incorporated into the contract (tangible personal property) in the space provided on the bid form. The successful bidders bid form will be used to develop a separated contract and

1-13 Bidding Documents will determine the extent of the tax exemption. Upon execution of the construction contract, the successful bidder shall provide a per item breakdown of:

a) materials incorporated into the project; and

b) labor, equipment, supervision and materials not incorporated into the project.

26. Silence of Specification.

The apparent silence of these specifications as to any detail or to the apparent omission from it of a detailed description concerning any point, shall be regarded as meaning that only the best commercial practices are to prevail. All interpretations of these specifications shall be made on the basis of this statement by Owner or their authorized representative.

27. Change Orders.

No oral statement of any person shall modify or otherwise change, or affect the terms, conditions or specifications stated in the resulting Contract. All change orders to the Contract will be made in writing by the Owner.

28. Assignment.

The Successful Bidder shall not sell, assign, transfer or convey this Contract, in whole or in part, without the prior written consent of Owner.

29. Venue.

This agreement will be governed and construed according to the laws of the State of Texas. This agreement is performable in Dallas County, Texas.

30. Maintenance Bond.

The Contractor shall provide a two-year Maintenance Bond in the amount of 50% of the value of the work at the completion of the project. The bond must be provided prior to final payment by the City.

31. Testing Requirements.

The Owner shall make arrangements with an independent laboratory acceptable for testing as required by the construction plans and standard specifications. The Contractor shall bear all related costs of retests or re-inspections. The Contractor shall notify the ENGINEER in a timely manner of when and where tests or inspections are to be made so that they may be present. One copy shall be provided to the Contractor of all reports and laboratory test results. Testing by the City does not alleviate the contractor’s responsibility for his own quality assurance/quality control testing. Contractor shall replace any deficient construction items at his own expense.

32. Overtime.

1-14 Bidding Documents

Hours worked before 8:00 a.m. or after 5:00 p.m., all weekends and holidays are subject to overtime. Overtime request or scheduled testing must be made in writing and approved by the City of Coppell with Seventy-two (72) hours advance-notice is required. All overtime incurred by the City for inspection services and any overtime incurred by the testing laboratory shall be paid by the Contractor. If not paid, such cost may be deducted from partial payments. The pay rate for Inspector overtime charges will be $54.00/HR.

33. Payment.

Contractor shall submit Applications for Payment in accordance with Item 109.5 of the General Provisions. Applications for Payment will be processed by Engineer as provided in the General Provisions.

34. Documentation of Existing Conditions.

Contractor must prepare a video and provide a copy to City of existing conditions within entire work area prior to the start of construction. This is subsidiary to Bid Item No.3, the pay item for Right-of-way Preparation. Contractor must mark each resident’s sprinkler heads, obtain permission to run their irrigation system, and video the sprinkler system condition prior to the start of construction.

35. Bid Security.

Contractor must submit a bid security in the amount of five (5%) percent of the amount of the maximum total bid as a guarantee that the Bidder will promptly enter into a Contract and execute a Performance, Payment and Maintenance Bonds on the forms included in the Contract Documents if awarded the contract.

Acceptable Bid Security are:

a) Certified or cashier’s check made payable to the Owner.

b) An approved Bidder’s Bond underwritten by a surety named in the current list of “Surety Companies Acceptable on Federal Bonds” as published in the Federal Register by the Audit Staff Bureau of Accounts, U.S. Treasury Department.

36. Bonds.

Performance, Payment and Maintenance Bonds are required for this project and shall be provided in accordance with the General Conditions.

1-15 Bidding Documents

BID FORM

PROJECT IDENTIFICATION: Spanish Moss Drive & Court and Jeb Court

Reconstruction Project ST18-01A

Coppell, Texas

BID OF DATE

(NAME OF FIRM)

THIS BID IS SUBMITTED TO: City of Coppell (hereinafter called OWNER) c/o Purchasing Manager 255 East Parkway Boulevard Coppell, Texas 75019

CITY OF COPPELL BID NO: Q-0826-01

1. The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.

2. BIDDER accepts all of the terms and conditions of the Advertisement or Notice to

Bidders and Instructions to Bidders. This Bid will remain subject to acceptance for ninety (90) days after the day of Bid opening. BIDDER will sign and submit the Agreement with other documents required by the Bidding Requirements within fifteen

(15) days after the date of OWNER's Notice of Award.

3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that:

(a) BIDDER has examined copies of all the Bidding Documents and of the following Addenda (receipt of all which is hereby acknowledged):

No:

Date:

Rec'd:

1-16 Bidding Documents

(b) BIDDER has familiarized itself with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work.

(c) BIDDER has studied carefully all reports of exploration and tests of subsurface conditions contained in the contract documents and which have been used in preparation of the contract documents. CONTRACTOR may rely upon the accuracy of the technical data contained in such reports, but not upon nontechnical data, interpretations or opinions contained therein or for the completeness thereof for CONTRACTOR's purposes. Except as indicated in the immediately preceding sentence, CONTRACTOR shall have full responsibility with respect to subsurface conditions at site.

BIDDER has studied carefully all drawings of the physical conditions in or relating to existing surface or subsurface structures on the site, which are contained in the contract documents and which have been utilized in preparation of the contract documents. CONTRACTOR may rely upon the accuracy of the technical data contained in such drawings, but not for the completeness thereof for CONTRACTOR's purposes. Except as indicated in the immediately preceding sentence, CONTRACTOR shall have full responsibility with respect to physical conditions in or relating to such structures.

(d) BIDDER has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests and studies (in addition to or to supplement those referred to in (c) above) which pertain to the subsurface or physical conditions at the site or otherwise may affect the cost, progress, performance or furnishing of the Work as BIDDER considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents; and no additional examinations, investigations, explorations, tests reports or similar information or data are or will be required by BIDDER for such purposes.

(e) BIDDER has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports or similar information or data in respect of said Underground Facilities are or will be required by BIDDER in order to perform and furnish the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the

(f) BIDDER has correlated the results of all such observations, examinations, investigations, explorations, tests, reports and studies with the terms and conditions of the Contract Documents.

1-17 Bidding Documents

(g) BIDDER has given ENGINEER written notice of all conflicts, errors or discrepancies that it has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to BIDDER.

(h) This bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;

BIDDER has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER has not sought by collusion to obtain for itself any advantage over any other Bidder or over

OWNER.

(i) It is understood and agreed that the following quantities of work to be done at unit prices are approximate only and are intended principally to serve as a guide in evaluating bids.

(j) It is understood and agreed that the quantities of work to be done at unit prices and materials to be furnished may be increased or diminished as may be considered necessary in the opinion of the OWNER to complete the work fully as planned and contemplated, and that all quantities of work, whether increased or decreased, are to be performed at the unit prices set forth, except as provided for otherwise in the Contract Documents.

4. BIDDER understands that the work for each street will be completed in multiple phases. Plans for phasing or move-ins by utility and paving contractors will require approval by the Engineer. It is understood and agreed that all work under this contract will be completed within the bid calendar days. Completion date will be established in the Notice to Proceed. It is understood that time of completion will be a consideration in the award of the bid.

5. It is understood and agreed that the contractor’s experience in this type of work will be a strong consideration in the award of the bid.

6. It is strongly recommended that each BIDDER visit the site prior to submitting a bid. Construction constraints exist, including heavy traffic volume along the roadway and accessibility requirements to & from adjacent streets, neighborhoods and properties, which could affect productivity.

7. BIDDER will complete the Work for the following price(s):

1-18 Bidding Documents

Spanish Moss Drive & Court and Jeb Court Reconstruction Project ST18-01A

UNIT PRICE BID SCHEDULE

BASE BID

Item No.

Bid Quantity

Unit

Description and Unit Price in Words

Unit Price

Total Price

LS

Mobilization, Complete In Place, Dollars and Cents per LUMP SUM

EA

Furnish, install, and maintain Project Sign, Complete In Place, Dollars and per EACH

Project Communication, Complete In Place, Dollars and

Pre-Project and Post-Project Video Survey, Dollars and

Furnish, Install and Maintain Temporary Traffic Control Devices and Detours, Complete In Place, Dollars and

Furnish, Install, Maintain and Remove Erosion Control Devices, Complete In Place, Dollars and

Right of Way Preparation, Complete In Place, Dollars and

CY

Unclassified Excavation, Complete In Place, Dollars and per CUBIC YARD

1,441

Embankment, Complete In Place

Dollars and

9,541

SY

Sawcut, Remove & Dispose of Concrete Pavement and Sidewalk (All Thicknesses), Complete In Place

Dollars and per SQUARE YARDS

2,118

Construct 4" Reinforced Concrete Sidewalk, Complete In Place, Dollars and per SQUARE YARD

Construct TxDOT Pedestrian Ramp, Complete In Place, Dollars and

7,632

Construct 6" Reinforced Concrete Street Pavement, No. 8 Bars 18” OCEW, Complete In Place, Dollars and

1,269

Construct 6" Reinforced Concrete Driveway Pavement, Complete In Place, Dollars and

7,573

Furnish and Install Lime Stabilized Subgrade, Complete In Place, Dollars and

TON

Furnish and Install Lime Slurry, Complete In Place, Dollars and per TONNAGE

Construct Concrete Steps, Complete In Place, Dollars and per CUBIC YARDS

Tree Removal, Complete In Place, Dollars and

Restore Parkways and Disturbed Area, Complete In Place, Dollars and

Remove and Reset Existing Mailbox, Dollars and

Remove and Reset Street Signs, Complete In Place, Dollars and

Coordination to Remove and Relocate Light Pole, Complete In Place, Dollars and

Adjust Existing Utility Box, Complete In Place, Dollars and

Concrete Panel Replacements On Steamboat Dr. (As Directed By City), Complete In Place, Dollars and

LF

Furnish and Install 21” Class III RCP, Complete In Place, Dollars and per LINEAR FOOT

Furnish and Install 30” Class III RCP, Complete In Place, Dollars and

Furnish and Install 36” Class III RCP, Complete In Place, Dollars and

Furnish and Install 3’x3’ Class III RCB, Complete In Place, Dollars and

Furnish and Install 4’x3’ Class III RCB, Complete In Place, Dollars and

Furnish and Install 6’x3’ Class III RCB, Complete In Place, Dollars and

Furnish and Install 10’ Standard Curb Inlet, Complete In Place, Dollars and

Furnish and Install 15’ Standard Curb Inlet, Complete In Place, Dollars and

Furnish and Install 4’ Square Storm Drain Manhole, Complete In Place, Dollars and

Furnish and Install 6’ Square Storm Drain Manhole, Complete In Place, Dollars and

Furnish and Install Flowable Backfill, Complete In Place, Dollars and

Remove & Dispose of Existing Storm Drain Inlet, Complete in Place, Dollars and

Remove & Dispose of Existing Storm Drain Pipe, Complete in Place, Dollars and

1,500

Trench Safety, Complete in Place, Dollars and

3,000

Television Inspection for Drainage Improvements, Complete in Place, Dollars and

2,015

Abandon Existing 8” Water Main, Complete in Place, Dollars and

Furnish and Install 6” PVC Class 200 DR-14 Water Pipe, Complete in Place, Dollars and

1,984

Furnish and Install 8” PVC Class 200 DR-14 Water Pipe, Complete in Place, Dollars and

Furnish and Install Ductile Iron Fittings for Water Line, Complete in Place, Dollars and per TON

Furnish and Install 6” Gate Valve, Complete in Place, Dollars and

Furnish and Install 8” Gate Valve, Complete in Place, Dollars and

Furnish and Install Blow Off Valve, Complete in Place, Dollars and

Furnish and Install 3/4” Residential Water Service, Complete in Place, Dollars and

Furnish and Install Fire Hydrant, Complete in Place, Dollars and

Remove and Dispose or Deliver Existing Fire Hydrant, Complete in Place, Dollars and

Connect to Existing Water Line, Complete in Place, Dollars and

Repair, Replace, Modify and Restore Existing Irrigation System, Complete In Place, Dollars and

Furnish and Install 8” PVC SDR-35 Sanitary Sewer Pipe, Complete In Place, Dollars and

1,700

Furnish and Install 10” PVC SDR-35 Sanitary Sewer Pipe, Complete In Place, Dollars and

Furnish and Install 10" PVC, 150 Pressure Class Pipe, ASTM D2241, (DR-26), Complete In Place, Dollars and

Furnish and Install 16" Steel Casing, 3/16" Thick, Complete In Place, Dollars and

1,875

Abandon Existing Sanitary Sewer Pipe, Complete In Place, Dollars and

Furnish and Install 4” Residential Sanitary Sewer Lateral, Complete In Place, Dollars and

Furnish and Install 4’ Sanitary Sewer Manhole, Complete In Place, Dollars and

Trench Safety, Complete in Place, Dollars and

TV Inspection for Drainage Improvements, Complete in Place, Dollars and

Remove and Dispose of Existing Sanitary Sewer Manhole, Complete In Place, Dollars and

Remove and Dispose of Existing Sanitary Sewer Access Device, Complete In Place, Dollars and

X-1

Project allowance for Paving Improvements, Dollars and

$80,000

$80,000

X-2

Project allowance for Storm Improvements, Dollars and

$ 30,000

X-3

Project allowance for Water and Wastewater Improvements, Dollars and

X-4

Project allowance for Landscape Improvements, Dollars and

X-5

Project allowance for Project Contingency, Dollars and

$ 140,000

$ 140,000

TOTAL BASE BID (A) =

BID ALTERNATE:

7,573

Furnish and Install 8” Flexbase Subgrade, Complete In Place, Dollars and

-7,573

Furnish and Install Lime Stabilized Subgrade, Complete In Place, Dollars and

-171

Furnish and Install Lime Slurry, Complete In Place, Dollars and per TONNAGE

TOTAL BID ALTERNATE (B) =

BID SUMMARY

Spanish Moss Drive & Court and Jeb Court Reconstruction Project

ST18-01A BID NO. Q-0826-01

Coppell, TX

TOTAL BID ITEMS BASE BID (A) $

TOTAL ALTERNATE BID ITEMS (B) $

TOTAL ALTERNATE BID (C) = A+B $

TOTAL TIME BID TO COMPLETE PROJECT CALENDAR DAYS

TOTAL OF CALENDAR DAYS X $1,500 (D) $

BASIS FOR COMPARISON OF BIDS (A) + (D)* $

BASIS FOR COMPARISON OF BIDS (C) + (D)* $

*The lowest evaluated bid (total bid) will be determined by the owner as the lowest sum of the base bid (A) or Alternate Bid (C) plus total Calendar Days X $1,500.00 (D)

NOTE: A TIME BID OF MORE THAN 400 CALENDAR DAYS SHALL BE

CONSIDERED NONRESPONSIVE AND WILL BE REJECTED.

1. Communications concerning this Bid shall be addressed to the address of BIDDER…