This is a specifications book for the International Bridges Rehabilitation project submitted by Firm No. 22965 (Ricardo A. Prieto, P.E.) dated January 20, 2026, in Texas. The project encompasses comprehensive bridge maintenance and rehabilitation work at three locations: 1001 S. Stanton, 1000 S. El Paso Street, and 791 S. Zaragoza. Work activities include removal of miscellaneous concrete; application of penetrating concrete surface treatment; concrete structure repairs using epoxy mortar and vertical and overhead repair techniques; concrete crack repairs by epoxy injection and rout-and-seal methods; cleaning and sealing of existing joints; replacement of armored bridge joints; replacement of W-beam rail elements and Thrie-beam to W-beam transitions; repair of steel posts and pedestrian railings; replacement of luminaires with 250-watt equivalent LED fixtures; replacement of above-ground conduit; and implementation of construction exits, temporary sediment control fencing, biodegradable erosion control logs, barricades, signs, and traffic handling measures. The work shall be conducted in four to six phases per bridge under a single prime contract, with coordination by CONSOR Engineers, LLC (CONSOR) serving as the Owner's Representative and Civil Engineer Ricardo A. Prieto, P.E. The contract includes requirements for a full-time project superintendent, preconstruction and progress meetings, submittal procedures, quality control plans, and testing and inspection services.
Payment methodology is based on unit prices established in the bid schedule for specific line items, with measurement by square yard for sidewalk removal, square foot for concrete surface treatment and concrete structure repair, and other appropriate units for remaining work items. The Contractor shall provide all labor, materials, equipment, and tools necessary for contract completion and bears responsibility for project coordination, notification of property owners, damage to private property, temporary facilities, sanitary facilities, and safety. The specifications reference standard codes and professional association standards applicable as of the bid date. Contract documents include detailed requirements for submittals, quality assurance and quality control procedures, delegated design services where applicable, measurement and payment provisions including progress payment, material-on-hand compensation, force account methodology for extra work with established markup percentages for labor (25% overhead), insurance and taxes (55% of labor cost), materials (25% overhead), equipment (15% overhead), and subcontracting (5% administrative cost). No retainage is withheld on the Contractor, though the Contractor may withhold retainage on subcontractors in accordance with state and federal regulations, with subcontractors to be paid within 10 days of the Contractor receiving Department payment.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS BOOK
FOR
INTERNATIONAL BRIDGES
REHABILITATION
January 20th, 2026
SUBMITTED BY:
Firm No. 22965
RICARDO A. PRIETO
91123
1/21/2026
21st
GENERAL REQUIREMENTS
4 General Requirements 6 Summary 9 Project Management and Coordination
20 Submittal Procedures 28 Quality Requirements 37 Measurement and Payment
BRIDGE
52 Removing Concrete 53 Penetrating Concrete Surface 55 Concrete Structure Repair 57 Cleaning and Sealing Joints 59 Cleaning and Sealing Joints and Cracks (Concrete Pavement) 60 Guard Fence Repair 62 Metal Rail Repair 63 Concrete Crack Repair 64 Bridge Joint Repair or Replacement
ILLUMINATION
66 Roadway Illumination Assemblies 69 Maintenance of Traffic Signals and Illumination
STORMWATER POLLUTION PREVENTION
80 Temporary Erosion, Sedimentation, and Environmental Contrals
TRAFFIC CONTROL
89 Barricades, Signs, and Traffic Handling 90 Portable Changeable Message Sign
TABLE OF CONTENT
GENERAL
REQUIREMENTS
1. GENERAL DESCRIPTIONS OF THE PROJECT
The work contemplated under this contract consists of the furnishing of all labor, materials, equipment, and tools necessary for the construction of the project titled as follows:
INTERNATIONAL BRIDGES REHABILITATION.
2. CONTRACT DRAWINGS OR PLANS
The details for the above mentioned work are shown on a set of drawings dated January 21, 2026, File No. 238781. These drawings together with these specifications and contract documents form the Contract. Where figures are shown on the drawings, they shall take precedence over any scaled distances or dimensions.
3. COMMON REFERENCE STANDARDS
Reference in the Specification to known standards such as codes, specifications, etc., promulgated by professional or technical associations, institutes and societies, are intended to mean the latest edition of each such standard adopted and published as of the date of the invitation to bid on this project except where otherwise specifically indicated. Each such standard referred to shall be considered a part of the specifications to the same extent as if reproduced herein in full.
4. EQUIPMENT
Equipment of condition and design sufficient to insure a thorough and workmanlike prosecution of the project shall be used at all times and any equipment which, in the opinion of the City Engineer or his representative, has outlived its efficiency or is inadequate in design, shall be removed from the project within forty-eight (48) hours after receipt of written notice from the City Engineer or representative.
5. MATERIALS AND APPLIANCES
If at any time commencement, or during the progress of the work, the materials and appliances used appear to the City Engineer or representative as not sufficient and improper for securing the quality of the work required, he may order the Contractor to improve their character and the Contractor shall conform to such order. The failure or the City Engineer or representative to demand any improvement shall not release the contractor from his obligation to secure the quality of the work as specified.
6. DISPOSAL OF WASTE MATERIALS
All waste materials including excavation, concrete curbs, sidewalks and driveways shall be disposed of at designated points approved by the City Engineer or representative.
7. NOTIFICATION OF PROPERTY OWNERS
The Contractor shall be responsible for the notification of property owners, businesses and residents along the project route to explain the nature of construction operations. The Contractor shall be responsible for providing access to the businesses and residences for all property owners, customers and residents at all times including nights, weekends, and holidays.
8. DAMAGE TO PRIVATE PROPERTY
The Contractor shall be responsible for any damage to private property caused by the construction project. The Contractor upon receipt of a complaint of damage, shall, within 10 days, respond in writing with a proposal to repair said damage or a letter stating reason why the damage was not caused by the construction.
Except for extenuating circumstances beyond the control of the Contractor the damage shall be repaired completely within 10 days of the complaint.
The contractor shall not enter or occupy private land outside of acquired right-of-way or construction easements, except by written permission of the Owner of the private property. Copies of such written permission shall be provided to the City Engineer or his-her representative.
9. CONTRACTOR’S SUPERINTENDENT
The Contractor shall keep on the project, at all times during its progress, a qualified, competent, Resident Superintendent satisfactory to the City Engineer or his-her representative. The Resident Superintendent shall be fluent in English and capable of communicating with the public, Engineer, Inspector, and Owner.
10. SANITARY FACILITIES
The Contractor shall provide temporary toilets, wash facilities, and drinking water facilities with potable water approved by local health authorities. Comply with governing regulations including safety and health codes for the type, number, location, operation, and maintenance of fixtures and facilities; provide not less than specified requirements. Install facilities in locations that will best serve the project’s needs.
Supply and maintain toilet tissue, paper towels, paper cups, and similar disposable materials as appropriate for each facility. Provide appropriate covered waste containers for used materials.
END OF SECTION
SUMMARY
1. SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work Sequence.
4. Work restrictions.
5. Specification and Drawing conventions.
2. DEFINITIONS
A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.
3. PROJECT INFORMATION
A. Project Identification: International Bridges Rehabilitation.
B. IMPROVEMENTS
1. Project Location: 1001 S. Stanton, 1000 S. El Paso Street and 791 S.
Zaragoza
2. Owner's Representative: CONSOR Engineers, LLC (CONSOR).
C. Design Team:
1. Civil Engineer: Ricardo A. Prieto, P.E. (915) 339-5335
D. Project Coordinator for Multiple Contracts: Owner shall serve as Project coordinator.
E. Project Superintendent: A Superintendent shall be assigned to this project on a full-time basis.
4. WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
o Mobilization o Localized Traffic Control o Supervision, Coordination & General Conditions o Rehabilitation of International Bridges o Installation of Lighting o Temporary Erosion, Sediment, and Environmental Controls
B. Type of Contract
1. Project will be constructed under a single prime contract.
5. WORK SEQUENCE
A.The work shall be conducted in four to six phases per bridge.
6. WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages and other controlled substances on project site is not permitted.
C. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
D. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
7. SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations.
3. Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
END OF SECTION
PROJECT MANAGEMENT
AND COORDINATION
1. RELATED DOCUMENTS
A. Drawings, General Conditions, and other Specification Sections, apply to this Section.
2. SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:
• General coordination procedures.
• Coordination drawings.
• RFIs.
• Digital project management procedures.
• Web-based Project management software package.
• Project meetings.
3. DEFINITIONS
A. RFI: Request for Information. Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.
4. INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities, list addresses, cellular telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in Project meeting room, in temporary field office, in web-based
Project software directory, and in prominent location in each built facility. Keep list current at all times.
5. GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and direction of Project coordinator to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
6. COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop
Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe the relationship of various systems and components.
b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to conflict with submitted equipment and minimum clearance requirements.
Provide alternative sketches to Engineer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
2. Review: Engineer will review coordination drawings to confirm that, in general, the
Work is being coordinated, but not for the details of the coordination, which are
Contractor's responsibility. If the Engineer determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Engineer will so inform Contractor, who shall make suitable modifications and resubmit.
C. Coordination Drawing Process: Prepare coordination drawings in the following manner:
1. Contractor shall perform the final coordination review. As each coordination drawing is completed, Contractor will meet with Engineer to review and resolve conflicts on the coordination drawings.
D. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format:
a. Same digital data software program, version, and operating system as original
Drawings.
2. File Submittal Format: Submit or post coordination drawing files using PDF format.
7. REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return without response those RFIs submitted to Engineer by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Owner name.
3. Owner's Project number.
4. Name of Engineer.
5. Engineer's Project number.
6. Date.
7. Name of Contractor.
8. RFI number, numbered sequentially.
9. RFI subject.
10. Specification Section number and title and related paragraphs, as appropriate.
11. Drawing number and detail references, as appropriate.
12. Field dimensions and conditions, as appropriate.
13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
14. Contractor's signature.
15. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to engineer.
1. Attachments shall be electronic files in PDF format.
D. Engineer's Action: Engineer will review each RFI, determine action required, and respond.
Allow seven days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Engineer’s actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Engineer's action may include a request for additional information, in which case
Engineer's time for response will date from time of receipt by Engineer of additional information.
3. Engineer's action on RFIs that may result in a change to the Contract Time, or the
Contract Sum may be eligible for Contractor to submit Change Proposal.
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer in writing within five days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log. Use software log that is part of web-based Project management software. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Engineer.
4. RFI number, including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Engineer's response was received.
8. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
F. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.
8. DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Engineer's Data Files Not Available: Engineer will not provide Engineer's CAD drawing digital data files for Contractor's use during construction.
B. Web-Based Project Management Software Package: Use Owner's web-based Project management software package for purposes of hosting and managing Project communication and documentation until Final Completion.
1. Web-based Project management software includes, at a minimum, the following features:
a. Compilation of Project data, including Contractor, subcontractors, Engineer, Engineer's consultants, Owner, and other entities involved in Project. Include names of individuals and contact information.
b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.
c. Document workflow planning, allowing customization of workflow between project entities.
d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor Changes in the Work, Construction Change Directives, and Change Orders.
e. Track status of each Project communication in real time, and log time and date when responses are provided.
f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.
g. Processing and tracking of payment applications.
h. Processing and tracking of contract modifications.
i. Creating and distributing meeting minutes.
j. Document management for Drawings, Specifications, and coordination drawings, including revision control.
k. Management of construction progress photographs.
l. Mobile device compatibility, including smartphones and tablets.
2. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Engineer. Provide data in locked format to prevent further changes.
C. PDF Document Preparation: Where PDFs are required to be submitted to Engineer, prepare as follows:
1. Assemble complete submittal package into a single indexed file, incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
9. PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of the date and time of each meeting. Notify the Owner and Engineer of scheduled meeting dates and times a minimum of seven days prior to meeting.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. The Owner’s representative will distribute the meeting minutes to everyone concerned, including Owner and Engineer, within three days of the meeting.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 15 days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner, Engineer, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with
Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Use of web-based Project software.
h. Procedures for processing field decisions and Change Orders.
i. Procedures for RFIs.
j. Procedures for testing and inspecting.
k. Procedures for processing Applications for Payment.
l. Distribution of the Contract Documents.
m. Submittal procedures.
n. Sustainable design requirements.
o. Preparation of Record Documents.
p. Use of the premises.
q. Work restrictions.
r. Working hours.
s. Owner's occupancy requirements.
t. Responsibility for temporary facilities and controls.
u. Procedures for moisture and mold control.
v. Procedures for disruptions and shutdowns.
w. Construction waste management and recycling.
x. Parking availability.
y. Office, work, and storage areas.
z. Equipment deliveries and priorities.
aa. First aid.
bb. Security.
cc. Progress cleaning.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
4. Attendees: Authorized representatives of Owner, Engineer, and their consultants;
Contractor and its superintendent and sustainable design coordinator; major subcontractors; suppliers; and other concerned parties shall attend the conference.
Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
5. Agenda: Discuss items of significance that could affect meeting sustainable design requirements, including the following:
a. General requirements for sustainable design-related procurement and documentation.
b. Project closeout requirements and sustainable design certification procedures.
c. Role of sustainable design coordinator.
d. Construction waste management.
e. Construction operations and sustainable design requirements and restrictions.
6. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other Sections and when required for coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Engineer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Sustainable design requirements.
i. Review of mockups.
j. Possible conflicts.
k. Compatibility requirements.
l. Time schedules.
m. Weather limitations.
n. Manufacturer's written instructions.
o. Warranty requirements.
p. Compatibility of materials.
q. Acceptability of substrates.
r. Temporary facilities and controls.
s. Space and access limitations.
t. Regulations of authorities having jurisdiction.
u. Testing and inspecting requirements.
v. Installation procedures.
w. Coordination with other work.
x. Required performance results.
y. Protection of adjacent work.
z. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the
Work and reconvene the conference at earliest feasible date.
D. Project Closeout Conference: Schedule and conduct a project closeout conference; Schedule and conduct a project closeout time as established in Contract Documents.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of Owner, Engineer, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of Record Documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Procedures for completing and archiving web-based Project software site data files.
d. Submittal of written warranties.
e. Requirements for completing sustainable design documentation.
f. Requirements for preparing operations and maintenance data.
g. Requirements for delivery of material samples, attic stock, and spare parts.
h. Requirements for demonstration and training.
i. Preparation of Contractor's punch list.
j. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
k. Submittal procedures.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
E. Progress Meetings: Construction Manager will conduct progress meetings at weekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Owner and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Resolution of BIM component conflicts.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site use.
9) Temporary facilities and controls.
10) Progress cleaning.
11) Quality and work standards.
12) Status of correction of deficient items.
13) Field observations.
14) Status of RFIs.
15) Status of Proposal Requests.
16) Pending changes.
17) Status of Change Orders.
18) Pending claims and disputes.
19) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting, where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
5. Attendees: In addition to representatives of Owner and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meetings shall be familiar with Project and authorized to conclude matters relating to the Work.
6. Agenda: Review and correct or approve minutes of the previous coordination meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to combined Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
b. Schedule Updating: Revise combined Contractor's construction schedule after each coordination meeting, where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.
c. Review present and future needs of each contractor present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site use.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Status of RFIs.
14) Proposal Requests.
15) Change Orders.
16) Pending changes.
7. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
SUBMITTAL PROCEDURES
1. RELATED DOCUMENTS
A. Drawings, General Conditions, and Specification Sections, apply to this Section.
2. SUMMARY
A. Section Includes:
1. Submittal schedule.
2. Submittal formats.
3. Submittal procedures.
4. Submittal requirements.
5. Delegated-design services.
6. Contractor’s review.
7. Engineer’s review.
3. DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require
Engineer's responsive action. Action submittals are those submittals indicated in individual
Specification Sections as "action submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer 's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification
Sections as "informational submittals."
4. SUBMITTAL SCHEDULE
A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.
1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and
Contractor's construction schedule.
2. Initial Submittal Schedule: Submit concurrently with startup construction schedule.
Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.
3. Final Submittal Schedule: Submit concurrently with the first complete submittal of
Contractor's construction schedule.
a. Submit revised submittal schedule as required to reflect changes in current status and timing for submittals.
4. Format: Arrange the following information in a tabular format:
a. Scheduled date for first submittal.
b. Specification Section number and title.
c. Submittal Category: Action; informational.
d. Name of subcontractor.
e. Description of the Work covered.
f. Scheduled date for Engineer 's final release or approval.
5. SUBMITTAL FORMATS
A. Submittal Information: Include the following information in each submittal:
1. Project name.
2. Date.
3. Name of Engineer.
4. Name of Construction Manager.
5. Name of Contractor.
6. Name of firm or entity that prepared submittal.
7. Names of subcontractor, manufacturer, and supplier.
8. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier and alphanumeric suffix for resubmittals.
9. Category and type of submittal.
10. Submittal purpose and description.
11. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.
12. Drawing number and detail references, as appropriate.
13. Indication of full or partial submittal.
14. Location(s) where product is to be installed, as appropriate.
15. Other necessary identification.
16. Remarks.
17. Signature of transmitter.
B. Options: Identify options requiring selection by Engineer.
C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Engineer on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.
D. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.
E. Submittals Utilizing Web-Based Project Software: Prepare submittals as PDF files or other format indicated by Project management software.
6. SUBMITTAL PROCEDURES
A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.
1. Web-Based Project Management Software: Prepare submittals in PDF form, and upload to web-based Project management software website. Enter required data in web-based software site to fully identify submittal.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.
3. Submit action submittals and informational submittals required by the same Specification
Section as separate packages under separate transmittals.
4. Coordinate transmittal of submittals for related parts of the Work specified in different
Sections, so processing will not be delayed because of the need to review submittals concurrently for coordination.
a. Engineers reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.
Time for review shall commence on Engineer’s receipt of submittal. No extension of the
Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
4. Sequential Review: Where sequential review of submittals by Engineer's consultants, Owner, or other parties is indicated, allow 21 days for initial review of each submittal.
D. Resubmittals: Make resubmittals in the same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block, and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Engineer’s action stamp.
E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer’s action stamp.
7. SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams that show factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop
Drawings.
5. Submit Product Data before Shop Drawings, and before or concurrently with Samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base
Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
C. Samples: Submit Samples for review of type, color, pattern, and texture for a check of these characteristics with other materials.
1. Transmit Samples that contain multiple, related components, such as accessories together in one submittal package.
2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
e. Number and title of applicable Specification Section.
f. Specification paragraph number and generic name of each item.
3. Web-Based Project Management Software: Prepare submittals in PDF form, and upload to web-based Project software website. Enter required data in web-based software site to fully identify submittal.
4. Paper Transmittal: Include paper transmittal, including complete submittal information indicated.
5. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual
Specification Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit three sets of Samples. Engineer will retain two
Sample sets; remainder will be returned.
1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.
2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.
D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract
Documents or assigned by Contractor if none is indicated.
2. Manufacturer and product name, and model number if applicable.
3. Number and name of room or space.
4. Location within room or space.
E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.
F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.
G. Certificates:
1. Certificates and Certifications Submittals: Submit a statement that includes the signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. Provide a notarized signature where indicated.
2. Installer Certificates: Submit written statements on manufacturer's letterhead, certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead, certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
4. Material Certificates: Submit written statements on manufacturer's letterhead, certifying that material complies with requirements in the Contract Documents.
5. Product Certificates: Submit written statements on manufacturer's letterhead, certifying that product complies with requirements in the Contract Documents.
6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of AWS
B2.1/B2.1M on AWS forms. Include names of firms and personnel certified.
H. Test and Research Reports:
1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for substrate preparation and primers required.
2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
4. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the
Contract Documents.
5. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
6. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for
Project. Include the following information:
a. Name of evaluation organization.
b. Date of evaluation.
c. Time period when report is in effect.
d. Product and manufacturers' names.
e. Description of product.
f. Test procedures and results.
g. Limitations of use.
I. Pre-Construction Submittal: The Contractor is responsible for developing and submitting pre-construction submittals within 10 days of Notice of Award. The Pre-Construction Submittal shall include:
a. Baseline Schedule
b. Quality Control Plan
c. Safety Plan
d. Environmental Plan
e. Submittal Register
8. DELEGATED-DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Engineer.
B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and three paper copies of certificate, signed, and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the
Contract Documents. Include list of codes, loads, and other factors used in performing these services.
9. CONTRACTOR'S REVIEW
A. Action Submittals and Informational Submittals: Review each…