This is a Justification and Approval (J&A) document for other than full and open competition for the Library of Congress to award a sole-source contract to CGS Publishing Technologies International LLC for maintenance and support of a Metis DRS 2000 large format digital scanner. The contract period of performance is January 11, 2025 through January 10, 2030, consisting of a base year plus four option years.

The J&A justifies limiting competition because CGS is the only authorized distributor qualified to service Metis scanners in the United States through an exclusivity agreement. The required services include preventative maintenance, repair services, parts, skilled labor, travel costs, software updates, security monitoring, and unlimited telephone consultations with Metis factory representatives. The scanner is installed in the Prints and Photographs Division and is described as essential to the Library's digitization mission. The document notes that using any other service provider would void warranties and quality assurances, and result in substantial duplicate costs. The Library will publish an advance notice on SAM.gov for 15 days before contract award, though no other sources expressed interest. The contracting officer will conduct a price evaluation prior to award to ensure fair and reasonable pricing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Justification and Approval For Other than Full and Open Competition

Plan ID Number: 2025-LGD-0057

Form Updated 4/14/2023

Justification & Approval

As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.

This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.

This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.

Part 1 – Identification

1. Contracting Agency and Activity: Library of Congress, LCSG, DSD, CDD, DOS

2. Nature of Action Being Approved

Contract (or modification) LoC or Leg Branch Order (or modification) GSA Schedule or GWAC: Identify Schedule/Contract Other: Identify

Plan ID Number: 2025-LGD-0057 Contractor (or Brand Name): CGS Publishing Technologies International LLC Estimated Value (Base and all options):

Period of Performance: 01/11/2025 - 01/10/2030

3. Description of Supplies or Services Required to Meet Library Needs

Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.

The Library requires the following supplies or services:

The Library of Congress (Library) requires contractor support to provide ongoing annual preventative maintenance service and support for one (1) Metis DRS 2000 large format digital scanner to ensure the scanner operates efficiently, stays in good condition, and minimizes downtime. The Metis DRS 2000 is a high-end digital scanner specially designed for digitizing large -format items, including artwork, historical documents, maps, books and various cultural artifacts. The scanner offers extremely high-resolution imaging, advanced color accuracy, and precise detail capture making it suitable for preservation and archiving projects where quality is paramount.

This scanner is installed in the Prints and Photographs Division (P&P) of the Library. The Metis DRS 2000 digital scanner is imperative to the Library’s mission for it is the primary digitization scanner system used, and it provides essential capabilities to P&P. This scanner is in the final year of its current service contract and a renewal of this contract is required.

The contractor shall provide ongoing annual preventative maintenance service and support visits to include preventative maintenance and support, repair services, parts equipment, skilled labor, travel costs, manuals, software updates and unlimited telephone consultations with Metis factory representatives. The contractor shall also provide continuous security monitoring systems by routine security scanning to identify and remediate software vulnerabilities. Further, the contractor shall provide end-of-support services on all hardware and software failures that cannot be fixed by the contractor.

Part 2 – Program Office Justification & Approval

4. Authority for Contracting Without Competition Over $250,000 For this requirement over $250,000, under FAR part 6, the basis for contracting without providing for full and open competition is:

There is only one responsible source and no other supplies or services will satisfy Library requirements.

41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.

Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).

Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302-

1(b)(2).

Other exception identified in FAR 6.302-1: Identify the exception

There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.

41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.

Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5: Identify the authority

Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302: Identify the exception

Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable

IT Standard Data Sheet)

Up to and including $250,000 For this requirement up to $250,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:

Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.

Product or service is reasonably available from only one source.

Source controls copyrights, patents or other exclusive licensing arrangements.

Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.

Source is expressly authorized or required by statute: Identify the authority

Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable

IT Standard Data Sheet)

GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:

An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.

FAR 8.405-6(a)(1)(i)(A).

Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).

In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).

Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable

Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:

The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).

The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR

16.505(b)(2)(i)(B).

A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).

To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).

Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).

The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41

U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable

5. Rationale for Contracting Without Competition

In supporting an action not providing for full and open competition, it is not sufficient to demonstrate that the contractor is exceptionally well qualified or even the best qualified, or that the required brand name product is well suited to the Library’s needs. The rationale must demonstrate that no one else, or no other competing product, can satisfactorily fulfill the Library’s requirement. Do not focus on the importance of the requirement; the issue is the rationale for not competing.

In supporting urgency, address the following: What are the unexpected facts or the unpredictable events that led to this situation? When is the required delivery or performance start date? Why this date? What specific harm to the Government will occur if the delivery is not made or performance not begun as scheduled? (Note that expiration of funds is not sufficient harm to justify not competing.) Demonstrate that the contract is only for items and quantities urgently needed until a competitive procurement action can be developed, or that a separate competitive follow-on is not practical.

In supporting a brand name justification, the brand name or feature must be essential to the Library’s requirements, and market research indicates that other company’s similar products or products with similar features cannot meet or be modified to meet the Library’s needs.

We are authorized to limit competition on the basis of the citation in section 4 because:

Only one responsible source, CGS Publishing Technologies International, LLC, provides supplies and services for Metis brand scanners. No other supplies or services will satisfy the Library’s requirements. Metis currently provides limited distribution and servicing to only CGS Publishing Technologies Internation LLC. Metis ensures that CGS receives consistent, specialized training, directly from Metis, to provide authorized, high-quality service and support. By restricting distribution to one trusted partner, Metis upholds strict quality control standards.

Only CGS possesses the unique capability to provide the required ongoing annual preventative maintenance service and support services. CGS is the only authorized distributor who is qualified to service Metis scanners. CGS has an exclusivity agreement with Metis making it the only vendor to sell, maintain and service Metis scanners in the United States. An award to any other source would result in substantial duplication of costs to the Government that cannot be expected to be recovered through competition. Award to another other source would also violate the Metris service agreement, and all guarantees, warranties, and quality assurances would be voided because no other service distributor is authorized to work on Metis scanner except for CGS.

Therefore, a full and open competition to make an award to any contractor other than CGS, is not applicable.

Without a valid Metris service agreement, the Library would have to pay the full costs of repairs and Metis parts. Only Metis trained technicians can support the scanner without voiding the service agreement. Repairs must be performed only by an authorized Metis technician. For all of the reasons stated above, a sole source award to CGS Publishing Technologies International, LLC is the only reasonable and appropriate course of action.

6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required

State what actions, if any, the program office can take to overcome barriers to competition before a contracting for this requirement again, such as:

using action to provide time to develop specifications for a competitive procurement by a certain date; licensing copyrights or patents so other contractors may use the works; or breaking the requirement into parts that may be purchased competitively. If this is a one-time requirement, explain that action to increase future competition is not needed. If the source is expressly required by statute, state “Source is statutory.”

To increase competition, we will:

Continuously survey the market to identify additional Metis authorized service providers and distributors.

7. Program Office Certification

I certify that the description of the Government’s minimum needs, schedule requirements, and technical information that provide the basis for this justification are accurate and complete.

Digital Imaging Specialist 11/20/2024

Name

Title

Signature

Date

0BPART 3 – CONTRACTING OFFICER DETERMINATIONS & CERTIFICATION

8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.

Advance notice will be published in sam.gov for 15 days before a contract is awarded. FAR 5.203(a).

Advance or concurrent notice will be published in sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).

Advance notice will not be published because the action meets the following FAR exception:

Notice would compromise national security. FAR 5.202(a)(1).

Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).

Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).

Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).

Order will be placed against GSA schedule or other competitively-awarded contract. FAR 5.202(a)(11).

Other:

Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.

We made the following efforts to interest potential sources in this award: None

9. Listing of Sources That Expressed Interest in Writing

The following sources expressed interest in this award: None

10. Additional Information

The following additional information is relevant to this justification and approval: N/A

11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):

Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other: Comparison of quote to historical prices Prices obtained through competitive proposals

The following analysis (based on attached pricing information) supports my determination: Contracting Officer will conduct a price evaluation prior to award.

12. Contracting Officer Determination of Responsibility Checked System for Award Management (or will check in the case of competitive proposals for a brand name product)

13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because: CGS is the only Metis authorized source who can provide the required parts and services without voiding the scanner’s warranty. After comparing the prices to historical pricing and the contractor’s quote, and due to the fact that only CGS can provide the required services, the CO has determined that this award represents the best value to the Library.

14. Contracting Officer Certification I certify that, to the best of my knowledge and belief, this justification is accurate and complete. For those actions up to $750,000, I approve contracting without competition for this requirement.

11/21/2024

Name

Signature

Date