20250128 SNC 905-010 Bid Documents - Volume II.pdf
PDF 6 MB Posted
- Solicitation number
- 36C78625B0013_1
About this file
These bid documents for Volume 2 detail the design and construction plans for correcting Facility Condition Assessment (FCA) deficiencies and performing slope rehabilitation at the Sitka National Cemetery in Sitka, Alaska. The project (VA Project No. 905CM3010) involves comprehensive site improvements, including slope stabilization using Geoweb geocell systems, drainage infrastructure installation, tree protection, erosion control, and careful management of construction activities in a sensitive cemetery environment.
Key technical specifications include installing approximately 8,700 square feet of slope rehabilitation material, implementing drainage systems with PVC storm drain pipes and dome-top inlets, establishing construction staging areas, and installing eight slope monitoring monuments. The project requires strict adherence to specific protocols, such as coordinating burial ceremonies, maintaining a clean work site, protecting existing infrastructure, and minimizing disruption to the cemetery's operations. The bid documents are dated 01/28/2025 and prepared by Vali Cooper International, LLC for the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMEND 2 .docx | DOCX document | |
| AMEND 1 .docx | DOCX document | |
| 20250128 SNC 905-010 Bid Documents - Volume I.pdf | ||
| 20250128 SNC 905-010 Combined Specifications.pdf | ||
| Wage Determination.pdf | ||
| 36C78625B0013_1 IFB Sitka Construction.docx | DOCX document | |
| Scope of Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SITE LOCATION MAP
SCALE: NTS
SITE LOCATION AND ACCESS MAP
SCALE: NTS
PROJECT TEAM
FIRM PANEL
SCALE: NTS
N
SHEET INDEX
SHEET
NO.
DRAWING
NO. SHEET TITLE
1 G-001 COVERSHEET
DEPARTMENT OF VETERANS AFFAIRS
SITKA NATIONAL CEMETERY
CORRECT FCA DEFICIENCIES
VOLUME 2
NCA PROJECT NO. 905CM3010
803 SAWMILL CREEK RD, SITKA, AK 99835
N
CODE OF CONDUCT
1. BURIAL CEREMONIES WILL BE SCHEDULED THROUGHOUT THE COURSE OF THIS PROJECT.
COORDINATE DAILY ACTIVITIES WITH THE CEMETERY DIRECTOR OR HIS APPROVED
REPRESENTATIVE TO ACCOMMODATE SCHEDULED BURIALS (COLUMBARIUM WALLS).
CONTRACTOR SHALL OBTAIN THE SCHEDULE FOR THE NEXT DAY SERVICES PRIOR TO
THE CLOSE OF BUSINESS EACH DAY. ALLOWABLE WORK TO BE DETERMINED BY THE
CEMETERY DIRECTOR.
2. BECAUSE OF THE SENSITIVE NATURE OF THE CEMETERY SITE, CONTRACTOR SHALL
MAINTAIN EACH WORK AREA IN A CLEAN AND ORDERLY APPEARANCE. TRASH AND WASTE
MATERIALS SHALL BE STORED IN APPROVED CONTAINERS AND ROUTINELY DISPOSED
OFF-SITE. CLEANUP SHALL BE REQUIRED AT THE END OF EACH DAY AND/OR MORE
FREQUENTLY AS REQUIRED.
3. THE CONTRACTOR'S STAFF AND SUBCONTRACTORS' STAFF SHALL NOT: DRESS IN
SLEEVELESS SHIRTS OR SHORT PANTS, WEAR CLOTHING WITH INAPPROPRIATE LOGOS,
PLAY MUSIC, TALK LOUD, PLACE PERSONAL ITEMS ON HEADSTONES, LEAN AGAINST OR
SIT ON HEADSTONES.
4. THE EFFECT OF WORK ON PUBLIC ACCESS SHALL BE MINIMAL AND SHALL BE
COORDINATED WITH THE CEMETERY DIRECTOR. ANY ALTERED PUBLIC TRAFFIC ROUTES
SHALL BE WELL DEFINED WITH PROFESSIONALLY MADE SIGNAGE AND/OR OTHER
APPROVED CONVENTIONAL METHODS.
5. DO NOT WORK UPON NOR STORE ANY MATERIALS ON OCCUPIED COLUMBARIUM WALLS.
ALL EFFORT WILL BE MADE TO MAINTAIN DISTANCE FROM OCCUPIED COLUMBARIUM
WALLS.
1. THE EXISTING UNDERGROUND UTILITIES SHOWN HEREON ARE
BASED UPON AVAILABLE INFORMATION. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR DETERMINING THE EXACT LOCATION OF ALL
UTILITIES PRIOR TO BEGINNING ANY WORK. IF UTILITIES OTHER THAN
THOSE SHOWN HEREIN ARE ENCOUNTERED, THE CONTRACTOR
SHALL NOTIFY THE COR IMMEDIATELY AND TAKE APPROPRIATE
MEASURES TO PROTECT THE LINE(S) AND ENSURE CONTINUED
SERVICE. DAMAGE CAUSED TO EXISTING UTILITIES BY THE
CONTRACTOR SHALL BE REPAIRED BY THE CONTRACTOR AT NO
ADDITIONAL COST TO THE OWNER. THE CONTRACTOR SHALL VERIFY
THE CONNECTION POINTS OF NEW UTILITIES TO EXISTING UTILITIES
PRIOR TO BEGINNING CONSTRUCTION.
2. THE CONTRACTOR SHALL INSTALL TREE PROTECTION BARRICADES
PRIOR TO BEGINNING EARTHWORK OPERATIONS.
3. THE CONTRACTOR SHALL NOTIFY THE COR IF UNSUITABLE MATERIAL
IS DISCOVERED PRIOR TO BEGINNING ANY REMOVAL OPERATION.
(SEE SPECIFICATION SECTION 31.20.00)
4. THE CONTRACTOR SHALL STABILIZE ALL DISTURBED AREAS WITH
SOD, NOT SHOWN FOR ASPHALT OR CONCRETE, WITHIN LIMITS OF
DEMOLITION AND PROPOSED WORK. THIS INCLUDES STAGING AREA
AND LAYDOWN AREAS.
5. CONTRACTOR SHALL GRADE ALL DISTURBED AREAS TO DRAIN FOR
POSITIVE FLOW PRIOR TO FINAL APPROVAL.
6. THE DESIGN ADEQUACY AND SAFETY OF ALL BRACING, SHORING
AND TEMPORARY SUPPORTS, ETC. IS THE SOLE RESPONSIBILITY OF
THE CONTRACTOR.
7. IN PERFORMING CONSTRUCTION OBSERVATION VISITS TO THE JOB
SITE, THE ENGINEER SHALL HAVE NEITHER CONTROL OVER NOR
RESPONSIBILITY FOR THE CONTRACTOR'S MEANS, METHODS,
SEQUENCE, TECHNIQUES OR PROCEDURES IN PERFORMING THE
WORK.
8. THE CONTRACTOR'S MEANS, METHODS, SEQUENCE, TECHNIQUES
OR PROCEDURES IN PERFORMING THE WORK IS SOLELY THE
RESPONSIBILITY OF THE CONTRACTOR, WHO IS ALSO RESPONSIBLE
FOR COMPLYING WITH ALL HEALTH AND SAFETY PRECAUTIONS AS
REQUIRED BY ANY REGULATORY AGENCY.
9. THERE SHALL BE AT ALL TIMES, WHEN WORK IS BEING DONE, A
COMPETENT PERSON WHO IS APPRISED OF THE CONDITION AND
PROGRESS OF ALL AREAS OF WORK ON SITE. THIS COMPETENT
PERSON SHALL BE ABLE TO SPEAK FOR AND ACT IN THE BEHALF OF
THE CONTRACTOR. HE SHALL BE AWARE AND KNOWLEDGEABLE OF
ALL THE SAFETY CONCERNS ON THE JOB SITE. HE SHALL BE
EMPOWERED TO IMMEDIATELY AND EFFECTIVELY MITIGATE THE
ACTIONS OF ANY WORKMAN ON SITE.
10. CONTRACTOR SHALL PREPARE AND SUBMIT A WELDING PLAN TO
THE COR PRIOR TO PERFORMING ANY FIELD WELDING SHOULD IT BE
REQUIRED. FOLLOWING APPROVAL ALL WELDS SHALL BE
PERFORMED IN ACCORDANCE WITH THE APPROVED PLAN. WELDING
PLAN SHALL LIST CERTIFIED WELDERS THE CONTRACTOR INTENDS
TO USE.
GENERAL NOTES
ARCHITECT / ENGINEER
VALI COOPER INTERNATIONAL, LLC
COVINGTON, LA 70433
CONTACT: JORDAN VANDERMEER
JORDAN.VANDERMEER@VALIINT.COM
504-684-4413
GEOTECHNICAL ENGINEER
HDL ENGINEERING CONSULTANTS, LLC
ANCHORAGE, AK 99503
CONTACT: DOUG SIMON
DSIMON@HDLALASKA.COM
907-564-2120
SITE OWNER
VA NCA
SITKA NATIONAL CEMETERY
CONTACT: DUANE MENDENHALL
DUANE.MENDENHALL@VA.GOV
907-384-7075
ELECTRICAL ENGINEER
JD ENGINEERING
CONTACT: SCOTT TURNER
SCOTT@JDENG.ORG
406-363-9022
N
SITKA NC
SAWMILL CREEK
BLVD (S-933)
C-101
INDIAN
RIVER RD
DE GROFF RD
JE
FF
D
AV
IE
S
ST
SITKA NATIONAL
CEMETERY
SITKA NC
CRESCENT
BAY
HARBOR
DR (F
99)
LINCOLN ST
LAKE ST
SAWMILL CREEKBLVD (S-933)
BIORKA ST
JE
FF
D
AV
IS
S
T
C-102
SI
ST
ER
S
LN
GEODETIC WAY
SAWMILL CREEKBLVD (S-933)
GC101 EROSION & SEDIMENTATION CONTROL PLAN & DETAILS
SLOPE REHABILITATION SITE PLAN
SLOPE REHABILITATION GRADING PLAN & PROFILES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
BID DOCUMENTS
VOLUME 2
National Cemetery Administration
Design and Construction Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
SITKA NATIONAL CEMETERY -
CORRECT FCA DEFICIENCIES
Sitka, AK
905CM3010
N/A
01/28/2025Revisions: Date: Sheet of 4
JVSF
N/A
No. 44593
PROFESSIONAL
REGISTERED
JORDAN D. VANDERMEE
RENG INE ER
01/28/2025504-684-4408; JORDAN VANDERMEER
56 LOUIS PRIMA DRIVE, SUITE B, COVINGTON, LA 70433
G-001
COVER
SAWMILL CREEK ROAD(S-933)
EX. 4" CONC. PAVING
EX.
GRAVEL
EX. STONE
PAVING
EX. 4" CONC. PAVING
EX.
TURF
EX.
TURF
EX.
TURF
SI
ST
ER
S
LA
N
E
BIO
RKA STREET
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
KEYED NOTES
SEE SURVEY SHEETS FOR EXISTING CONDITIONS LEGEND
LEGEND AND SYMBOLS
1. STRAW WATTLE, SEE DETAIL THIS SHEET.
2. TREE PROTECTION, SEE DETAIL THIS SHEET.
3. CONSTRUCTION ENTRANCE, SEE DETAIL THIS SHEET.
4. CONSTRUCTION STAGING AREA, SEE NOTES THIS SHEET.
DRIP LINE
OF TREE
METAL STAKES
@ 6' O.C. (TYP)
4' MIN
1' MIN.
HIGH VISIBILITY
ORANGE VINYL
CONSTRUCTION
FENCING
TREE PROTECTION NOTES:
1. EXCAVATION OR GRADING WITHIN THE DRIP LINE OF ANY TREE MUST UTILIZE
ALTERNATIVE METHODS SUCH AS HAND DIGGING TO LOCATE ROOTS.
2. TREE PROTECTION FENCING SHALL BE INSTALLED AROUND ALL TREES THAT HAVE A
DRIP LINE WITHIN THE LIMITS OF DISTURBANCE FOR CONSTRUCTION ACTIVITIES OTHER
THAN ASPHALT PAVING AND SHALL EXTEND A MINIMUM OF 10' FROM THE TRUNK OR THE
DRIP LINE OF THE TREE, WHICHEVER IS GREATER. (TYP)
3. THE CUTTING OF ROOTS GREATER THAN ONE (1) INCH DIAMETER MUST BE APPROVED
AND SUPERVISED BY A LICENSED ARBORIST.
4. CONTRACTOR SHALL PRESERVE AND PROTECT ALL TREES FROM DAMAGE BY
DEMOLITION OPERATIONS. ANY TREE DAMAGED BY CONSTRUCTION OPERATIONS
SHALL BE REPLACED WITH A TREE OF THE SAME SPECIES AND SIZE. IF SIZE IS NOT
AVAILABLE CONTRACTOR SHALL REPLACE WITH A 2" CAL. TREE (DECIDUOUS) OR 6'
HEIGHT TREE (EVERGREENS) AND SHALL PROVIDE A CREDIT TO THE OWNER FOR THE
MONETARY DIFFERENCE IN VALUE.
TREE PROTECTION
STRAW WATTLE
0 20 40
1 INCH = 20 FEET
GC101
EROSION & SEDIMENTATION
CONTROL PLAN & DETAILS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
BID DOCUMENTS
VOLUME 2
National Cemetery Administration
Design and Construction Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
SITKA NATIONAL CEMETERY -
CORRECT FCA DEFICIENCIES
Sitka, AK
905CM3010
N/A
01/28/2025Revisions: Date: Sheet of 4
JVSF
N/A
No. 44593
PROFESSIONAL
REGISTERED
JORDAN D. VANDERMEE
RENG INE ER
01/28/2025504-684-4408; JORDAN VANDERMEER
56 LOUIS PRIMA DRIVE, SUITE B, COVINGTON, LA 70433
EXISTING HEADSTONE
12" MIN
1 18" X 1 18" WOODEN STAKE
OR APPROVED EQUAL
9" DIA. STRAW WATTLEGENERAL NOTE:
1. WATTLE SHALL BE PLACED AT
THE TOE OF ALL EXPOSED
SLOPES. WATTLES MAY BE
REMOVED AFTER THE
ESTABLISHMENT OF TURF
GRASS.
8oz NON WOVEN
HARD SURFACE
COARSE AGGREGATE
(1.5" - 3.5")
CONSTRUCTION EXIT
GEOTEXTILE UNDERLINER
6" MIN.
20' MIN.
30' MIN.
5' RADIUS
CONSTRUCTION ENTRANCE
NOTES:
1. CONTRACTOR SHALL
CLEAN ALL DIRT &
DEBRIS FROM PUBLIC
AND PRIVATE
ROADWAYS AT THE
END OF EACH
WORKDAY.
STAGING AREA NOTES:
1. CONTRACTOR SHALL CLEAR AND GRUB THE PROPOSED STAGING
AREA AS NECESSARY. EXISTING VEGETATION CONSISTS OF SMALL
DIAMETER BRUSH.
2. CONTRACTOR SHALL INSTALL FENCING AND A LOCKABLE GATE
PER THE SPECIFICATIONS AROUND THE PERIMETER OF THE
STAGING AREA.
3. CONTRACTOR SHALL DETERMINE THE APPROPRIATE SIZE OF
STAGING AREA. SHOULD ADDITIONAL SPACE BE REQUIRED THE
CONTRACTOR IS RESPONSIBLE FOR THE ADDITIONAL CLEARING
AND FENCING NECESSARY TO OBTAIN ADDITIONAL SPACE. THE
MAXIMUM STAGING AREA SIZE SHALL NOT EXCEED 100' X 50'
AutoCAD SHX Text
MH
AutoCAD SHX Text
SCALE: NTS
AutoCAD SHX Text
STRAW WATTLE
AutoCAD SHX Text D8
AutoCAD SHX Text
SCALE: NTS
AutoCAD SHX Text
TREE PROTECTION FENCE
AutoCAD SHX Text C7
AutoCAD SHX Text
SCALE: NTS
AutoCAD SHX Text
CONSTRUCTION ENTRANCE
AutoCAD SHX Text B5
BIO
RKA STREET
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
C-101
SLOPE REHABILITATION SITE
PLAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
BID DOCUMENTS
VOLUME 2
National Cemetery Administration
Design and Construction Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
SITKA NATIONAL CEMETERY -
CORRECT FCA DEFICIENCIES
Sitka, AK
905CM3010
N/A
01/28/2025Revisions: Date: Sheet of 4
JVSF
N/A
No. 44593
PROFESSIONAL
REGISTERED
JORDAN D. VANDERMEE
RENG INE ER
01/28/2025504-684-4408; JORDAN VANDERMEER
56 LOUIS PRIMA DRIVE, SUITE B, COVINGTON, LA 70433
6.6
4'
76.18'
49.61'
50.40' 13.17'
83.82'
12.91'
26.19'
20.79'
9.4 1'
.47
28.24'
A
A
B
B
KEYED NOTESKEYED NOTES
SEE VOLUME 1 SURVEY SHEET FOR EXISTING CONDITIONS LEGEND
LEGEND AND SYMBOLS
1. SLOPE REHABILITATION MAT. GEOWEB ® GEO GEOCELL,
OR APPROVED EQUAL. (≈8,700 SF), SEE GEOWEB NOTES
THIS SHEET.
2'-0"
2'-0"
AS R
EQUIR
ED
FINISHED GRADE
EXISTING HEADSTONE
EXISTING HEADSTONE
EXISTING UNDISTURBED SUBGRADE
1'-0"
1'-0"
TOP SOIL, CONTRACTOR SHALL
RE-USE EXISTING
GEOWEB OR APPROVED EQUAL
2'-6"
AS R
EQUIR
ED
FINISHED GRADE
EXISTING HEADSTONE
1'-0"
TOP SOIL, CONTRACTOR
SHALL RE-USE EXISTING
GEOWEB OR APPROVED EQUAL
GEOWEB NOTES
1. SLOPE REHABILITATION MAT SHALL BE GEOWEB® GEO
GEOCELL OR APPROVED EQUAL.
2. MAT SHALL MEET THE FOLLOWING REQUIREMENTS:
2.1. CELL DEPTH: 6" MINIMUM
2.2. CELL SIZE 11"X12" MINIMUM
2.3. SHORT TERM PEEL STRENGTH: 480 LBS MINIMUM
2.4. SHEET THICKNESS: 50 MM MINIMUM
2.5. STRESS CRACK RESISTANCE: >5,000 HRS
SCALE: NTS
GEOWEB INSTALLATIONF2 SCALE: NTS
GEOWEB TENDON LOCATIONSF4 SCALE: NTS
GEOWEB EARTH ANCHORF7
SCALE: NTS
TYPICAL B-B HEADSTONE SETBACKSB8
SCALE: NTS
TYPICAL A-A HEADSTONE SETBACKSC9
FINISHED GRADE
GEOWEB GEO CELLS INSTALLED
PER NOTES AND DETAILS THIS
SHEET
6" COMPACTED TOPSOIL
UNDISTURBED SUBGRADE
NON-WOVEN GEOTEXTILE FABRIC
SCALE: NTS
TYPICAL A-A HEADSTONE SETBACKSB5
NOTES:
1. CONTRACTOR INSTALLER SHALL TAKE THE CERTIFIED
TRAINING COURSE PROVIDED FREE OF CHARGE BY THE
MANUFACTURER (TWO (2) HOURS IN LENGTH)
2. GEOWEB SHALL BE INSTALLED ON UNDISTURBED
SUBGRADE.
2.1. SHOULD DISTURBANCE OF THE SUBGRADE OCCUR,
CONTRACTOR SHALL COMPACT TO 85% STANDARD
PROCTOR.
3. GEOWEB CELLS SHALL BE INFILLED WITH GRAVEL FILL
MEETING THE REQUIREMENTS OF AKDOT SECTION
703-2.07 FOR SELECTED MATERIAL, TYPE B WITH A
MAXIMUM AGGREGATE SIZE OF TWO (2) INCHES IN
DIAMETER.
4. GEOWEB SHALL BE ANCHORED PER DETAILS THIS SHEET.
5. GEOWEB SHALL HAVE THREE TENSION TENDONS
INSTALLED PER DETAILS THIS SHEET.
GEOWEB
6" PVC STORM DRAIN PIPE
8" DOME TOP INLET
CLEANOUTCO
PHASING & INSTALLATION NOTES
1. CONTRACTOR SHALL DEVELOP A PHASING PLAN IN WRITING FOR APPROVAL PRIOR TO STARTING LAND
DISTURBING ACTIVITIES.
2. CONTRACTOR SHALL PROVIDE THE CEMETERY DIRECTOR 14-DAYS NOTICE PRIOR TO INSTALLATION.
3. CONTRACTOR SHALL DEVELOP AN INSTALLATION PLAN IN WRITING FOR APPROVAL PRIOR TO STARTING LAND
DISTURBING ACTIVITIES RELATED TO THE SLOPE REHABILITATION MAT.
4. INITIAL INSTALLATION SHALL BE APPROXIMATELY 1,000 S.F. OF SLOPE REHABILITATION MAT ALONG THE NORTH SLOPE TO THE EAST OF THE ROSTRUM. ADDITIONAL INSTALLATION SHALL TAKE PLACE ONLY AFTER
APPROVAL BY THE COR OF THE INITIAL 1,000 S.F.
4.1. CONTRACTOR SHALL INSTALL THREE (3) ANCHORS AND PERFORM A PULL-OUT TEST TO ESTABLISH
MINIMUM EMBEDMENT DEPTH.
4.2. PULL- OUT TEST SHALL MEET THE MINIMUM REQUIREMENTS PLUS A FACTOR OF SAFETY OF 1.40.
4.3. ANCHORS EMBEDMENT DEPTH SHALL NOT EXCEED THREE (3) VERTICAL FEET.
4.4. ANCHORS SHALL NOT BE PLACED WITHIN INTERNMENT AREAS AND WILL REQUIRE EXTENDED TENSION
CABLE TO AVOID THESE AREAS. SEE DETAIL C9 THIS SHEET.
4.5. CABLE SHALL BE STAINLESS STEEL.
4.6. CABLE SHALL NOT BE PLACED WITHIN 12" OF HEADSTONES.
5. ALL EXCESS SPOILS SHALL BE PLACED IN A STOCKPILE WITHIN THE CEMETERY PROPERTY FOR RE-USE.
TURF INSTALLATION NOTES
1. CONTRACTOR SHALL RE-USE THE EXISTING TURF GRASS OR UTILIZE A HYDROSSED MIX.
2. CONTRACTOR MAY HYRDOSEED WITH A KENTUCKY BLUE GRASS (SEE SPECIFICATIONS FOR SEED MIX) ON ALL EXPOSED SOIL SHOULD THE RE-USE OF EXISTING TURF NOT BE POSSIBLE OR SUFFICIENT FOR FULL
COVERAGE.
2.1. CONTRACTOR IS RESPONSIBLE FOR ALL EROSION CONTROL AND REPAIRS DUE TO RAINFALL EVENTS
DURING THE TURF ESTABLISHMENT PERIOD.
3. THE CEMETERY DOES NOT HAVE ACTIVE IRRIGATION, CONTRACTOR IS RESPONSIBLE FOR ALL REQUIRED
WATERING (SHOULD IT BE NECESSARY) DURING TURF ESTABLISHMENT PERIOD.
4. CONTRACTOR SHALL ENSURE HYDROSEED DOES NOT COMES IN CONTACT WITH HEADSTONES.
3 1/4" DIA. CAST ALUMINUM DOMED-TOP
MONUMENT MARKER W/ PLASTIC INSULATOR
W/ HEX SOCKET TO RECEIVE REBAR
FIELD-INCISED HAIRS ON CAP;
CROSS-HAIRS SHALL BE PARALLEL &
PERPENDICULAR TO THE GRAVESITE
GRIDLINES & PRECISE TO ±0.005'
REQUIRED TEXT
ENGRAVED ON CAP,
TYP.
DOMED TOP
PLASTIC INSERT
INTEGRAL MAGNET
COMPACTED APPROVED FILL OR
NATIVE EARTH
SMOOTH-TROWEL FINISH TOP
SURFACE, ENSURING POSITIVE
DRAINAGE
MONUMENT MARKER
(PROTECT VISIBLE SURFACES DURING
PLACEMENT INTO CONCRETE)
1'-0" LENGTH OF #6 STEEL REBAR,
FIRMLY SECURED TO MONUMENT
MARKER; SET INTO CONC.
MONUMENT BASE
GAP AROUND PVC PIPE &
SURROUNDING EARTH SHALL BE
FILLED W/CONCRETE TO WITHIN 4"
OF FINISH GRADE
8" PVC PIPE FILLED W/3,500 PSI
CONCRETE @ 28 DAYS
MONUMENT MARKER
CONCRETE BASE
EDGE OF MONUMENT MARKER SHALL
BE NO CLOSER THAN 1" TO OUTSIDE
EDGE OF CONCRETE
FINISH
GRADE
SET
FLUSH
WITH
N A
T
I O NA L C EME T ER
Y
S
LO
P E
MON I TOR I NG MONUM
E
N T
SCALE: NTS
SLOPE MONITORING MONUMENTSD6
MONUMENT NOTES
1. CONTRACTOR SHALL INSTALL
EIGHT MONITORING MONUMENTS
AT LOCATIONS DETERMINED IN THE
FIELD BY THE COR.
2. CONTRACTOR SHALL PROVIDE
SURVEY NORTHING AND EASTINGS
FOR EACH MONUMENT FOR SLOPE
MONITORING .
INITIAL INSTALLATION AREA, SEE
PHASING NOTE THREE THIS SHEET.
ANCHOR TENDON
ANCHOR
AutoCAD SHX Text
MH
AutoCAD SHX Text
GEO
AutoCAD SHX Text
%%USECTION
AutoCAD SHX Text
8" DIA.
AutoCAD SHX Text 3 1/4"
AutoCAD SHX Text 18"
AutoCAD SHX Text
%%UPLAN
AutoCAD SHX Text
1" MIN
AutoCAD SHX Text 3 1/4"
1 1/2"
SAWMILL CREEK ROAD(S-933)
BIO
RKA STREET
CO
CO
DT INLET #1
DT INLET #2
CO
DT INLET #3
DT INLET #4
CO
CO
TAPERD END SECTION #1
CLEANOUT
CLEANOUT
CLEANOUT
CLEANOUT
CO
CO
CO
CO CLEANOUT
CLEANOUT
CLEANOUT
CO
STA:0+00
STA:0+50
STA:0+88
DRAIANGE RUN - 1.0 PROFILE
VERT. SCALE: 1"=4'
HORIZ SCALE: 1"=20'
0+00 1+00 2+00
26 LF
8" PVC
@ 6.82%
36 LF
8" PVC
@ 9.00%
D T
IN
LE
T #1
ST
A=
2+
TO
P=
.5
IN
V O
U T=
.0
6"
D T
IN
LE
T #2
ST
A=
2+
TO
P=
.5
IN
V
IN
=7 3.
IN
V O
U T=
.5
6"
25 LF
6" PERFORATED PVC
@ 2.00%
36 LF
8" PVC
@ 9.00%
CLEANOUT
CLEANOUT
CLEANOUT
31 LF
8" PVC
@ 6.81%
60 LF
8" PVC
@ 6.81%
CLEANOUT
29 LF
6" PVC
@ 5.00%
13 LF
6" PVC
@ 18.15%
7 LF
6" PVC
@ 18.09%
CLEANOUT
CLEANOUT
CLEANOUT
4 LF
6" PVC
@ 18.06%
DRAIANGE RUN - 2.0 PROFILE
VERT. SCALE: 1"=4'
HORIZ SCALE: 1"=20'
0+00
D T
IN
LE
T #4
ST
A=
1+
TO
P=
.5
IN
V
IN
=7 3.
IN
V O
U T=
.5
6"
23 LF
6" PERFORATED PVC
@ 2.00%
D T
IN
LE
T #3
ST
A=
1+
TO
P=
.5
IN
V O
U T=
.0
6"
40 LF
6" PVC
@ 2.76%
CLEANOUT
13 LF
6" PVC
@ 13.50%
5 LF
6" PVC
@ 13.50%
7 LF
6" PVC
@ 13.50%
CLEANOUT
CLEANOUT
0 20 40
1 INCH = 20 FEET
C-102
SLOPE REHABILITATION
GRADING PLAN & PROFILES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
BID DOCUMENTS
VOLUME 2
National Cemetery Administration
Design and Construction Service
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
SITKA NATIONAL CEMETERY -
CORRECT FCA DEFICIENCIES
Sitka, AK
905CM3010
N/A
01/28/2025Revisions: Date: Sheet of 4
JVSF
N/A
No. 44593
PROFESSIONAL
REGISTERED
JORDAN D. VANDERMEE
RENG INE ER
01/28/2025504-684-4408; JORDAN VANDERMEER
56 LOUIS PRIMA DRIVE, SUITE B, COVINGTON, LA 70433
KEYED NOTESKEYED NOTES
SEE VOLUME 1 SURVEY SHEET FOR EXISTING CONDITIONS LEGEND
LEGEND AND SYMBOLS
1. PVC STORM DRAIN.
GENERAL NOTES:
1. CONTRACTOR SHALL MATCH THE EXISTING GRADES OF THE EXISTING BURIAL SECTION.
2. CONTRACTOR SHALL PROVIDE KEY WAY IF CONSTRUCTED IN MULTIPLE POURS.
DRAINAGE
AGGREGATE WITH
FILTER FABRIC
FINISHED GRADE
PERFORATED 6" PVC
PVC RISER
8" DOME TOP CAST-IRON GRATE,
NYLOPLAST 0899CGD OR
APPROVED EQUAL
GENERAL NOTES
1. PIPE AND
FITTINGS, EXCEPT
AS OTHERWISE
SHOWN, SHALL BE
PVC PLASTIC PIPE
2. THE ACCESS
FRAME, COVER
AND CAP SHALL
BE CAST IRON.
THE FINGER
HOLES MAY BE
DRILLED OUT OR
MAY BE BLOCKED
OUT PRIOR TO
CASTING; THEY
SHALL NOT BE
PUNCHED OUT.
RISER SHALL BE
4" SOLID PVC
DIAMETER
INSTALL CAP AND GLUE IF
TERMINAL CLEANOUTS.
INSTALL PIPE IF IN-LINE
CLEANOUTS.
INVERT ELEVATION PER PLAN
FINISH GRADE
THREAD SHIELD
REMOVABLE AFTER SLAB
IS POURED
WYE
SPECIFIED PIPE PER PLAN
SCALE: NTS
CLEAN OUT DETAILF9
CONCRETE COLLAR W/ 12"
DIAMETER AND 8" THICK WITH
2" RADIUS
8" MIN.
12" MIN.
6"
MIN.
6"
MIN.
DIAMETER
3"
MIN.
12"
PIPE
EMBEDMENT
GENERAL NOTES:
1. EXCAVATE FOR BELLS OR HUBS SO FULL LOAD IS CARRIED BY PIPE
BARRELS.
SHAPE TO FIT BELL AND HUB, AND THOROUGHLY
COMPACT UNDER PIPE. SEE NOTE I.
EXCAVATE TO UNDISTURBED
TRENCH BED. REPLACE WITH
BEDDING. PER
SPECIFICATION 31 20 00.
COMPACTED BEDDING PER SPECIFICATION 31 20 00
COMPACTED BEDDING PER SPECIFICATION 31 20 00
ENGINEERED FILL PER
SPECIFICATION 31 20 00
FINISHED GRADE OR PAVEMENT
SCALE: NTS
UTILITY TRENCHD9
12" MINIMUM
WARNING TAPE PER SPECIFICATION
33 10 00 & 33 40 00
1'-8"
2'-6" MIN.
4"8" PVC
SLOPED TO MATCH
SURROUNDING GRADE
SCALE: NTS
TAPERED END SECTIOND5
1'-0" MIN.
6" MIN.
COMPACTION ELEVATION
SCALE: NTS
DOME TOP INLETF5
EXISTING WALL
6" M
IN
6" 2.
5' M
IN
DRAINAGE RUN - 1.0
DRAINAGE RUN - 2.0
GENERAL NOTES:
1. CONTRACTOR MAY ADJUST ROUTING AS NECESSARY TO
AVOID EXISTING OBSTRUCTIONS.
2. CONTRACTOR SHALL SUBMIT FOR APPROVAL THE
PROPOSED ROUTING.
3. DRAINS SHALL MAINTAIN A MINIMUM SLOPE OF 2%.
4. CONTRACTOR SHALL RECORD ALL CHANGES IN
ALIGNEMNT AND GRADE AND PROVIDE AS-BUILT
DRAWINGS TO THE NCA.
GEOWEB
6" PVC STORM DRAIN PIPE
8" DOME TOP INLET
CLEANOUTCO
SEE ENLARGEMENT THIS SHEET
#4 REBAR EW
MH
| Sheets and Views |
| G-001 COVER |
| GC101 EROSION & SEDIMENTATION CONTROL PLAN & DETAILS |
| C-101 SLOPE REHABILITATION SITE PLAN |
| C-102 SLOPE REHABILITATION GRADING PLAN & PROFILES |
File details come from the government source that posted it. Updated .