This is a comprehensive plan set for the Rehabilitation of Barrington Bridge (Bridge No. 012301) in Barrington, Rhode Island, prepared by the Rhode Island Department of Transportation under Contract No. 2025-CB-033. The project scope encompasses replacement of deck expansion joints, concrete patching repairs to substructure and concrete arch panels, restoration of bearing contact areas, underwater repairs to tremie seals at bridge piers, and installation of scour countermeasures. Deliverables include approximately 9,000 cubic feet of Portland cement concrete for underwater repairs, 1,700 cubic yards of grout bags for scour remediation, 5,100 cubic yards of placed stone riprap, and 5,600 cubic feet of cementitious grout. The work is organized into four construction phases with phased traffic control plans to maintain at least one sidewalk open across the bridge during construction. Work authorization is restricted to October 15 through January 31 annually, with a substantial completion date of January 6, 2028. The solicitation opened March 13, 2026 at 11:00 AM EDT and closed April 10, 2026 at 1:00 PM EDT, with contractor questions accepted through April 1, 2026. Shop drawings must be submitted within 45 days of notice to proceed. Liquidated damages are assessed at $2,350 per calendar day for project delays.
The contract is federally funded under the Federal-Aid Highway program with 80 percent federal funding and 20 percent state participation. Contractors must comply with the Rhode Island Department of Transportation Standard Specifications for Road & Bridge Construction (August 2025 edition), prevailing wage requirements under the Davis-Bacon Act ranging from $24.79 to $64.52 per hour by classification, and all Buy America provisions requiring domestic sourcing of manufactured products and construction materials. Performance and payment bonds of 100 percent are required, along with workers' compensation insurance of $100,000 per accident, general liability insurance of $1,000,000 per occurrence, and automobile liability insurance of $1,000,000 per occurrence. Contractors must maintain a 30 percent self-performance requirement and submit certified weekly payrolls documenting compliance with prevailing wage rates and labor standards. Quality control personnel must be independent third parties with minimum five years of experience. A 0.33 percent contract administrative fee is withheld from all invoices effective January 1, 2026. The project requires coordination with the United States Coast Guard, the Town of Barrington Harbormaster, and other environmental agencies, and contractors must comply with all federal, state, and local environmental permits and regulations governing work in the sensitive Barrington River environment.
Text of this file
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
W:\ACTIVE PROJECT YEARS\2024\3833OC-2 BRIDGE GROUP 15F – BARRINGTON BRIDGE ROUTE 114 OVER BARRINGTON RIVER\DRAWINGS\CIVIL\SHEET\FINAL PLANS\100% SUBMISSION PLANS\SHEET SET\02 STANDARD PLAN SYMBOLS AND STANDARD LEGEND.DWG PER DPM 450.06
STANDARD PLAN SYMBOLS AND STANDARD LEGENDS
01/28/26
MG
SS
30220262025-CB-033
BARRINGTON
SCALE: NOT TO SCALE
CURB SETTING DETAIL
REMOVE AND DISPOSE TELEPHONE DUCT BANKS
TREE PROTECTION DEVICE
SHRUB PROTECTION DEVICE
LOG AND HAY CHECK DAM
GRANITE CURB (STRAIGHT)
GRANITE CURB (CIRCULAR)
LIMIT OF DISTURBANCE LIMIT OF DISTURBANCE
PRECAST TYPE "A" HANDHOLE
TIE EXISTING PIPE INTO NEW STRUCTURE
4" WOOD CHIP MULCH
DETECTABLE WARNING SYSTEM
IMPACT ATTENUATOR
COLD PLANE
PAVED WATERWAY
PRECAST 4'-0" OR 6'-0" SQUARE MANHOLE OR CATCH BASIN
CONSTRUCTION ACCESS
PRECAST CONCRETE SLOPED FACE CURB (STRAIGHT)
PRECAST CONCRETE SLOPED FACE CURB (CIRCULAR)
PRECAST CONCRETE SLOPED FACE TRANSITION CURB
6'-0" GRANITE TRANSITION CURB
GRANITE 2'-0" RADIUS CORNER
ASPHALT BERM
RIP-RAP DITCH
BITUMINOUS CONCRETE LIP CURB
BALED HAY DITCH AND SWALE EROSION CHECK
PAVED DITCH
GRANITE APRON STONE (FOR ROUND CATCH BASIN)
BALED HAY DITCH EROSION CHECK AND SILT FENCE COMBINED
DEWATERING BASIN
STONE MASONRY STEPS
CONCRETE RETAINING WALL
WET STONE MASONRY RETAINING WALL
BALED HAY CATCH BASIN INLET PROTECTION
RUBBLE MASONRY WALL
GRANITE APRON STONE (FOR SQUARE CATCH BASIN)
PRECAST CONCRETE DROP INLET
PRECAST 4'-0", 5'-0", OR 6'-0" ROUND CATCH BASIN
LIGHT-DUTY SQUARE FRAME AND ROUND COVER
HIGH CAPACITY FRAME AND GRATE
SQUARE FRAME AND GRATE (BICYCLE SAFE)
LIGHT-DUTY ROUND FRAME AND COVER
HEAVY-DUTY ROUND FRAME AND COVER
PRECAST CONCRETE DROP INLET LATERAL OUTLET
PRECAST CONCRETE DROP INLET LONGITUDINAL OUTLET
HIGH CAPACITY FRAME AND GRATE (BICYCLE SAFE)
CATCH BASIN AND MANHOLE STEP
ROUND FRAME AND GRATE
PRECAST CONCRETE CURB (STRAIGHT)
PRECAST CONCRETE CURB (CIRCULAR)
PRECAST CONCRETE INLET STONE (FOR SQUARE CATCH BASIN)
PRECAST CONCRETE INLET STONE (FOR ROUND CATCH BASIN)
PRECAST CONCRETE APRON STONE (FOR SQUARE CATCH BASIN)
PRECAST CONCRETE APRON STONE (FOR ROUND CATCH BASIN)
6'-0" PRECAST CONCRETE TRANSITION CURB
3'-0' PRECAST CONCRETE TRANSITION CURB
DRIVEWAY DEVELOPMENT FOR 6'-0" TRANSITION CURB
FLARED GUARDRAIL END TREATMENT
NEW FIRE HYDRANT WITH GATE VALVE
TIE NEW PIPE INTO EXISTING STRUCTURE
LIMIT OF DISTURBANCE
CEMENT CONCRETE DRIVEWAYS
STEEL BEAM GUARDRAIL REFLECTORIZED TRIANGULAR DELINEATOR
STEEL BEAM GUARDRAIL TERMINAL END SECTION
STEEL BEAM GUARDRAIL ANCHORAGE TRAILING END SECTION
STEEL BEAM GUARDRAIL CONNECTION TO NEW END POST
STEEL BEAM GUARDRAIL THRIE BEAM TRANSITION PANEL
ASPHALT SIDEWALK
CEMENT CONCRETE SIDEWALK
BARRIER MOUNTED DELINEATOR
WHEELCHAIR RAMP
WHEELCHAIR RAMP FOR LIMITED RIGHT-OF-WAY AREAS
DRIVEWAY DEVELOPMENT FOR 3'-0" TRANSITION CURB
PVC PLASTIC PIPE TYPE III BARRICADE
POLYETHYLENE DRUM WITH MARKINGS
CHAIN LINK FENCE 3'-0" TO 4'-0"
CHAIN LINK FENCE 5'-0" TO 6'-0"
STEEL BEAM GUARDRAIL, TL-2
STEEL BEAM GUARDRAIL, TL-3
CHAIN LINK FENCE 5'-0" TO 6'-0" INTERMEDIATE POST
WOVEN WIRE RIGHT-OF-WAY FENCE (STEEL POST)
STEEL BEAM GUARDRAIL DOUBLE FACE ASSEMBLY
ALUMINUM LIGHTING STANDARDS
PRECAST TYPE "B" HEAVY DUTY HANDHOLE
STREET SIGN MOUNTING DETAIL
POST AND MOUNTINGS FOR RURAL MAILBOX
CONCRETE HIGHWAY BOUND
POST AND MULTIPLE MOUNTINGS FOR RURAL MAILBOXES
CONCRETE HEADWALLS FOR PIPE CULVERTS
PRECAST CONCRETE FLARED END SECTION
BRICK/SOLID BLOCK 4'-0" ROUND MANHOLE
BRICK/SOLID BLOCK 5'-0" OR 6'-0" ROUND MANHOLE
BRICK/SOLID BLOCK TYPE "D" ROUND CATCH BASIN
BRICK/SOLID BLOCK TYPE "F" SQUARE CATCH BASIN
BRICK/SOLID BLOCK ROUND CATCH BASIN WITH GUTTER INLET
BRICK/SOLID BLOCK TYPE "R" CATCH BASIN
PRECAST 6'-0" ROUND MANHOLE
RELOCATE UTILITY POLE (BY OTHERS)
R.I.D.O.T. COMMUNICATIONS MANHOLE
RIP-RAP PAD (SEE DETAIL)
NOT IN THIS CONSTRUCTION CONTRACT
IMPERVIOUS DITCH LINER
REMOVE AND RELOCATE SIGN
FILTER FABRIC RIPRAP FLARED END UNDERLAYMENT
4" PLANTABLE SOIL AND SEED
REMOVE AND STOCKPILE TRAFFIC SIGNAL SYSTEM
REMOVE AND STOCKPILE GUARDRAIL
CLEARING AND GRUBBING
WITH GUTTER INLET
EDGING, STRAIGHT, CIRCULAR (ALL TYPES)
CLEAN CATCH BASIN
CLEAN AND FLUSH PIPE
REMOVE, HANDLE, HAUL, TRIM, RESET CURB
RECONSTRUCT TYPE "D" CATCH BASIN, TO CATCH BASIN
CLEAN MANHOLE
12" EPOXY RESIN PAVEMENT MARKINGS - WHITE
4" EPOXY RESIN PAVEMENT MARKINGS - YELLOW
4" EPOXY RESIN PAVEMENT MARKINGS - DOUBLE YELLOW
PERMANENT CHECK DAM
LIMIT OF REGRADING
STONE BAFFLE
REMOVE PAVEMENT MARKINGS
PRECAST MEDIAN BARRIER TRANSITION UNIT
SINGLE-FACED PRECAST MEDIAN BARRIER
BI-DIRECTIONAL CONTROL DEVICE
CONCRETE THRUST BLOCK
4.2.1
4.2.0
3.4.3
3.4.1
3.7.0
3.4.0
3.4.5
1.1.0
1.3.0
2.1.0
2.3.0
3.2.0
3.3.2
3.3.0
DRIP LINE TREE PROTECTION DEVICE
GRANITE TRANSITION CURB (VERTICAL FACE TO SLOPE FACE)
GRANITE SLOPED FACE TRANSITION CURB
GRANITE SLOPED FACE CURB
GRANITE INLET STONE (FOR ROUND CATCH BASIN)
GRANITE INLET STONE (FOR SQUARE CATCH BASIN)
PRECAST 2'-0" RADIUS CORNER
SQUARE FRAME AND GRATE
TREE WELL
HEAVY DUTY SQUARE FRAME AND ROUND COVER
SOLID BLOCK SHALLOW 5'-0" OR 6'-0" SQUARE CATCH BASIN
BRICK/SOLID BLOCK TYPE "F" ROUND CATCH BASIN
BRICK/SOLID BLOCK TYPE "D" SQUARE CATCH BASIN
SQUARE FRAME AND GRATE
SOLID BLOCK SHALLOW TYPE "F" SQUARE CATCH BASIN
SOLID BLOCK FLUSH SQUARE CATCH BASIN
SOLID BLOCK FLUSH ROUND CATCH BASIN
BRICK/SOLID BLOCK DROP INLET
STRUCTURAL DISPOSITION - SEE CS PAGES OF SPECIFICATION
REMOVE AND STOCKPILE HYDRANT
REMOVE AND STOCKPILE FENCE
REMOVE AND STOCKPILE SIGN
REMOVE AND STOCKPILE GRANITE CURB
TREE TRIMMING
RELOCATE MAILBOX (BY OTHERS)
RELOCATE LAMP POST
FURNISH AND INSTALL NEW WATER CURB STOP BOX
FURNISH AND INSTALL NEW WATER GATE VALVE BOX
4" LOAM AND SEED
REMOVE AND DISPOSE TRAFFIC SIGNAL SYSTEM
REMOVE AND DISPOSE FRAME AND GRATE
ADJUST FRAME AND GRATE TO GRADE
ADJUST FRAME AND COVER TO GRADE
ADJUST HANDHOLE TO GRADE
NO.
TYPE
MATERIAL
TYPE
(NAME)
AREA SUBJECT TO STORM FLOW
100-YEAR FLOOD PLAIN
ASSF
RAILROAD TRACKS
CUT AND MATCH
RIP-RAP
CUT SLOPE
FILL SLOPE
AREA GRADED TO DRAIN
ROCK CUT
WETLAND PERIMETER
EDGE OF WETLAND125
TOP OF SLOPE
ROADWAY
TOE OF SLOPE
ELEV.
ROCK SHELF
ROCK CUT
ROADWAY
BORINGS
FENCE
WOOD OR BRUSH LINE
TREES
RIVER OR STREAM
WETLAND AREA
BUILDING
FOUNDATION
BUILDING TO BE REMOVED
EXISTING
EXIST. S.H.L. PLAT NO. XX
EXIST. S.F.L. PLAT NO. XX
PWW
CITY NAME
TOWN NAME
R.I.H.B.
ELEV.
S.B.
(SIZE)T
(SIZE)E
WG OR GG
HYD
1+00
(SIZE)D
(SIZE)SD
(SIZE)S
STATE HIGHWAY LINE
STATE FREEWAY LINE
PROPERTY LINE
CITY OR TOWN LINE
PAVED WATERWAY
CONTOUR LINE
OPEN DITCH
R.I. HIGHWAY BOUND
STONE BOUND
RETAINING WALL
FIELD STONE WALL
NEW S.H.L. PLAT NO. XX
WATER MAIN
GAS MAIN
TELEPHONE DUCT
ELECTRIC DUCT
FLARED END SECTION
HEADWALL
WATER OR GAS GATE
CATCH BASIN
MANHOLE
HYDRANT
BASELINE OR CENTERLINE
ABANDONED UTILITY
PLUG AND CAP PIPE
N(SIZE)W
N(SIZE)G
N-#(SIZE)T
N-#(SIZE)E
(Length Size)
BERM
CURB
SIGN
EDGE OF PAVEMENT
GUARDRAIL
MAILBOX
UTILITY POLE
POLE GUY
LUMINARE
SUBDRAIN
STORMDRAIN
SANITARY SEWER
NEW
NO.
GUY
N(SIZE)SD
UNDERDRAIN
BRICK/SOLID BLOCK ROUND MANHOLE OR(DIA.)
CATCH BASIN GREATER THAN 12'-0"
BRICK/SOLID BLOCK 5'-0" OR 6'-0" ROUND CATCH BASIN
PRECAST 4'-0" ROUND MANHOLE
PRECAST 5'-0" ROUND MANHOLE
REMOVE AND DISPOSE FLARED END SECTIONDFE
REMOVE AND DISPOSE PAVED WATERWAY
REMOVE AND DISPOSE SIGN
REMOVE AND DISPOSE SIDEWALK
REMOVE AND DISPOSE UTILITY POLE
REMOVE AND DISPOSE RIGID BASE
DWW
DUP
DRB
DS
DSW
REMOVE AND DISPOSE PIPE
REMOVE AND DISPOSE HIGHWAY BOUND
REMOVE AND DISPOSE MEDIAN BARRIER
REMOVE AND DISPOSE GUARDRAIL
REMOVE AND DISPOSE FLEXIBLE PAVEMENT
REMOVE AND DISPOSE HEADWALL
REMOVE AND DISPOSE MANHOLE
REMOVE AND DISPOSE LIGHT AND FOUNDATION
REMOVE AND DISPOSE HANDHOLE
REMOVE AND DISPOSE OBSERVATION WELL
REMOVE AND DISPOSE MEDIAN MARKER
REMOVE AND DISPOSE FIRE HYDRANT
DMM
DFP
DMB
DL
DHH
DMH
DG
DH
DHB
DPB
DOW
DFH
REMOVE AND DISPOSE FENCE
REMOVE AND DISPOSE CONCRETE CURB
REMOVE AND DISPOSE DROP INLET
REMOVE AND DISPOSE CATCH BASIN
REMOVE AND DISPOSE BITUMINOUS CURBDB
DCB
DDI
DC
DF
AE ADJUST ELECTRIC MANHOLE TO GRADE
ADJUST TELEPHONE MANHOLE TO GRADE
ADJUST SANITARY SEWER MANHOLE TO GRADE
ADJUST GAS GATE BOX TO GRADE
ADJUST WATER GATE BOX TO GRADE
AG
AW
AT
AS
ADJUST DRAINAGE MANHOLE TO GRADE
ADJUST CATCH BASIN TO GRADE
ADJUST CURB STOP TO GRADE
ADJUST CATCH BASIN TO MANHOLEABM
AB
AD
AC
CONCRETE CONNECTING COLLAR
(DIA.)
(DIA.)
(DIA.)
4.2.2
GRANITE WHEELCHAIR RAMP TRANSITION CURB
3" CLASS 9.5 HMA
8" GRAVEL BORROW SUBBASE COURSE
BITUMINOUS CONCRETE DRIVEWAY
DFG
DSS
DTD
BPS
CCB
BCD
CFP
CP
CG
CMH
CCP
CPP
FF
IDL
IA
LOD
GET
LS
LOR
12W
P.G.L.
4Y
6WT
6Y
4DY
TT
WCM
6W
TEP
TBBC
TNP
TBT
STS
TB
31.2.1
34.2.1
34.2.5
34.2.2
34.1.0
31.3.0
34.2.0
34.3.2
34.3.1
34.3.4
34.3.3
9.8.0
26.2.0
20.2.0
24.6.1
31.2.0
31.1.0
26.3.0
10.2.0
10.1.0
10.3.0
9.9.0
15.2.0
18.3.0
18.2.0
18.2.2
14.1.0
10.4.0
15.1.0
9.5.0
9.7.0
8.4.0
8.2.0
8.3.0
9.3.0
9.4.0
7.5.0
7.6.0
7.5.1
7.4.1
7.4.0
7.4.2
51.1.1
51.2.0
51.1.0
40.2.1
40.3.0
48.1.0
43.3.0
43.1.0
43.2.0
43.4.1
43.4.0
43.5.0
43.3.1
40.5.0
51.3.0
7.3.4
7.3.8
7.3.5
7.3.7
7.3.6
7.2.0C
7.3.0C
7.3.3
7.3.2
7.2.2
7.2.1
7.3.0S
7.1.6
7.1.4
7.1.5
7.2.0S
7.1.8
7.1.7
7.1.1
7.1.2
7.1.0C
4.3.0
4.4.0
4.5.0
5.4.0
6.1.0
6.1.1
4.5.2
4.5.1
5.3.0
7.1.0S
6.3.1
6.2.1
6.3.0
6.3.4
6.3.3
6.4.0
6.3.2
6.2.0
THRIE BEAM TRANSITION
THRIE BEAM BRIDGE CONNECTION
STEEL BEAM BRIDGE CONNECTION TRAILING END (W/NESTED RAIL)
STEEL BEAM BRIDGE CONNECTION APPROACH END (W/0 NESTED RAIL)
CUT AND PLUG PIPE (ALL TYPES, ALL SIZES)
CUT AND CAP PIPE WITH RESTRAINT (ALL SIZES)
SPECIAL GRADED AGGREGATE
REMOVE AND DISPOSE FRAME AND COVERDFC
AHH
AFC
AFG
6" EPOXY RESIN PAVEMENT MARKINGS - YELLOW
6" EPOXY RESIN PAVEMENT MARKINGS - WHITE
6" PREFORMED PATTERNED MARKING (HIGH PERFORMANCE TAPE)
BUILD NEW STRUCTURE OVER EXISTING PIPE
SH
SGR
RRP
RUP
SB
RRS
SF
SGA
SGC
SBTE
SBAE
SD-
SS
RLP
RHH
RCM
PS
RCB
PCD
NIC
NWB
NWCB
NFH
RMB
RPM
PROFILE GRADE LINE
2.2.0 STANDARD HEADWALLS FOR MULTIPLE
3'-6" TO 7'-0' PIPE CULVERTS
3.2.1
3.3.3
3.4.2
3.4.4
3.5.0
3.5.1
3.6.0
CONCRETE COLLARS
PRECAST CONCRETE TRANSITION CURB
(VERTICAL FACE TO SPLOPED FACE)
TREE WALL51.4.0
(SIZE)G
(SIZE)W
(Length Size)
1+00
NEW S.F.L. PLAT NO. XX
LIMIT OF CLEARINGLIMIT OF CLEARING
BALED HAY & SILT FENCE
BALED HAY RI STD 9.1.0
SPOT GRADE00 00
(SIZE)
(DIA.)
(SIZE)
PERMANENT EASEMENT LINE NEW P.E.B.
TEMPORARY EASEMENT LINE NEW T.E.B.
DP
REMOVE AND DISPOSE PAVEMENT AND RIGID BASE
FURNISH AND INSTALL NEW WATER GATE VALVE AND BOXNWVB
FURNISH AND INSTALL NEW WATER CURB STOP AND BOXNWSB
(DEPTH)
(NO.)
MB
NO.
SIGN
CB
MH
EXIST. P.E.B.
EXIST. T.E.B.
LP
ELEV
NO. NO.
100 YR. FLOOD BOUNDARY
00.00
RI STD. 9.3.0
TYPICAL GUARDRAIL INSTALLATION AT STRUCTURES 34.1.1
STEEL BEAM GUARDRAIL ENCASED POST FOR 34.1.2
ROADSIDE GUARDRAIL (GENERAL NOTES, INSTALLATION,
POST & OFFSET BLOCK DETAILS)
SHALLOW INSTALLATION
STEEL BEAM GUARDRAIL DEEP POST INSTALLATION 34.1.3
STEEL BEAM GUARDRAIL INSTALLED IN CONCRETE OR HMA SURFACE 34.1.4
STEEL BEAM GUARDRAIL APPROACH END TREATMENT34.3.0
GUARDRAIL CONNECTION TO EXISTING END POST APPROACH 34.3.5 END SECTION
GUARDRAIL CONNECTION TO EXISTING END POST TRAILING 34.3.6 END SECTION
34.3.7 STEEL BEAM GUARDRAIL TRANSITION TO RIGID BARRIER
34.3.8 MASH GUARDRAIL TRANSITION TO EXISTING GUARDRAIL
34.3.9 STEEL BEAM GUARDRAIL LONG SPAN, TL-3
34.5.3 STEEL THRIE BEAM GUARDRAIL SINGLE FACE
34.5.4 STEEL THRIE BEAM GUARDRAIL DOUBLE FACE
34.5.5 STEEL THRIE BEAM GUARDRAIL LONG SPAN
40.1.0 F SHAPE CONCRETE BARRIER DOUBLE FACE
40.2.0 F SHAPE CONCRETE BARRIER SINGLE FACE
40.2.1 F SHAPE CONCRETE BARRIER WITH CONCRETE SEPARATOR
PRECAST MEDIAN BARRIER TRANSITION UNIT40.3.0
PRECAST MEDIAN BARRIER FOR LIGHT STANDARD 40.4.0
BARRIER MOUNTED DELINEATOR 40.5.0
FOR EXISTING TREES
PRECAST TYPE "H" HEAVY-DUTY HANDHOLE18.2.1
PAVEMENT TRANSVERSE DROP-OFFS CUT AND MATCH47.1.1
RHODE ISLAND
DEPARTMENT OF TRANSPORTATION
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
W:\ACTIVE PROJECT YEARS\2024\3833OC-2 BRIDGE GROUP 15F – BARRINGTON BRIDGE ROUTE 114 OVER BARRINGTON RIVER\DRAWINGS\CIVIL\SHEET\FINAL PLANS\100% SUBMISSION PLANS\SHEET SET\03 STANDARD NOTES- 1.DWG PER DPM 450.06
STANDARD NOTES - 1
01/28/26
MG
SS
30320262025-CB-033
NOT TO SCALENOT
NNNN
ITEM CODE
SCALE: NOT TO SCALE
UTILITY NOTES:
DRAINAGE AND EROSION CONTROL NOTES:
16. DETENTION AND RETENTION BASINS MAY BE ROUGH GRADED AND STABILIZED WITH
VEGETATION AND/OR OTHER EROSION CONTROL MEASURES AS REQUIRED BY THE
ENGINEER PRIOR TO USE AS TEMPORARY SEDIMENTATION BASINS DURING PROJECT
CONSTRUCTION. FINAL BASIN CONSTRUCTION SHALL NOT COMMENCE UNTIL ALL
SOURCES OF SEDIMENT HAVE BEEN REMOVED AND INFILTRATION IS REESTABLISHED,
FINAL ROADSIDE VEGETATION IS ESTABLISHED AND USE OF TEMPORARY BASINS IS NO
LONGER REQUIRED TO COMPLY WITH THE PLANS, SPECIFICATIONS, AND PERMITS. ANY
ISSUES RELATING TO EROSION AND/OR SEDIMENT TRANSPORT INTO WETLAND AREAS
RESULTING FROM SUCH USE OF SEDIMENTATION BASINS DURING CONSTRUCTION SHALL
BE THE RESPONSIBILITY OF THE CONTRACTOR. ANY CORRECTIVE ACTION AND COSTS
REQUIRED TO RESOLVE SUCH ISSUES IS THE RESPONSIBILITY OF THE CONTRACTOR.
17. THE TOE OF ANY FILL SLOPE IS TO REMAIN AT LEAST 1' INSIDE OF ALL EROSION
CONTROLS. UNDER NO CIRCUMSTANCES SHALL THE CONTRACTOR COVER ANY PORTION
OF THE EROSION CONTROL MEASURES WITH MATERIAL. ANY MATERIAL THAT IS PLACED
ON ANY EROSION CONTROLS BY THE CONTRACTOR, OR ANY AGENT OF THE
CONTRACTOR, SHALL BE IMMEDIATELY REMOVED BY THE CONTRACTOR, AND ANY
NECESSARY REPAIRS TO THE EROSION CONTROLS ACCOMPLISHED.
18. PRIOR TO COMMENCING CONSTRUCTION ACTIVITIES, EROSION AND SEDIMENTATION
CONTROLS SHALL BE INSTALLED AT THOSE AREAS INDICATED ON THE PLANS. CLEARING
MAY OCCUR PRIOR TO INSTALLATION OF SUCH CONTROLS, HOWEVER NO GRUBBING,
GRADING, FILLING, OR OTHER SOIL DISTURBANCE SHALL OCCUR PRIOR TO
INSTALLATION. THE LIMITS OF CLEARING AND SURFACE DISTURBANCE MUST BE
STRICTLY ADHERED TO IN ALL AREAS.
19. ALL COMPOST FILTER SOCK, STRAW BALES, SILT FENCE OR TEMPORARY PROTECTION
SHALL REMAIN IN PLACE UNTIL AN ACCEPTABLE STAND OF GRASS IS ESTABLISHED. IF
NEEDED, TEMPORARY SEEDING CAN HELP TO MINIMIZE EROSION. TEMPORARY SEED
WILL CONFORM TO R.I.D.O.T. STANDARD TEMPORARY SEED MIX.
20. THE CONTRACTOR MUST REPAIR AND/OR RESEED ANY AREAS THAT DO NOT DEVELOP
WITHIN THE PERIOD OF ONE YEAR AND SHALL DO SO AT NO ADDITIONAL EXPENSE TO
THE STATE.
21. THE NORMAL ACCEPTABLE SEASONAL SEEDING DATES ARE SPECIFIED IN SUBSECTION
L.02.03 OF THE R.I.D.O.T. STANDARD SPECIFICATIONS, LATEST EDITION.
22. ALL COSTS ASSOCIATED WITH ADHERENCE TO THE SWPPP SHALL BE CONSIDERED
INCIDENTAL TO THE CONSTRUCTION AND INCLUDED WITH THE COST FOR THE
ASSOCIATED BID ITEMS. ADDITIONAL SEDIMENT AND EROSION CONTROLS, SHALL BE
INSTALLED IN ACCORDANCE WITH THE SWPPP REPORT. THESE ADDITIONAL ITEMS WILL
BE PAID AT THE UNIT PRICE FOR THAT BID ITEM.
23. ANY OBSERVATIONS OF ILLICIT CONNECTIONS OR DISCHARGES TO RIDOT'S DRAINAGE
NETWORK OR OUTFALLS SHALL BE REPORTED TO THE RIDOT STORMWATER UNIT
IMMEDIATELY.
DRAINAGE AND EROSION CONTROL NOTES (CONTINUED):GENERAL NOTES:
b.
1. ANY DAMAGE TO EXISTING PAVEMENT, BRIDGES, DRAINAGE STRUCTURES,
DRAINAGE PIPES, INFILTRATION AREAS, ROADSIDE, CONDUIT, SIDEWALK, FENCES,
ETC., CAUSED BY THE CONTRACTOR SHALL BE REPAIRED BY THE CONTRACTOR
AT NO ADDITIONAL COST TO THE STATE.
2. THE CONTRACTOR SHALL PLACE ALL EQUIPMENT AND MATERIAL AS FAR AWAY AS
POSSIBLE FROM THE EDGE OF THE TRAVEL LANE SO AS NOT TO CAUSE A
SAFETY HAZARD, IN ACCORDANCE WITH SECTION 106.05 OF THE R.I.D.O.T.
STANDARD SPECIFICATION, LATEST EDITION. EQUIPMENT AND MATERIAL SHALL
NOT BE STORED IN AREAS DESIGNATED FOR STORMWATER INFILTRATION OR
OUTSIDE THE L.O.D. WITHOUT WRITTEN PERMISSION FROM THE ENGINEER.
3. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE THAT THE EXISTING
CONDITIONS ARE NOT DISTURBED OR OBLITERATED BEFORE SURVEY GROUND
CONTROL POINTS ARE LOCATED, VERIFIED, AND DEEMED ADEQUATE FOR
CONSTRUCTION LAYOUT. THE CONSTRUCTION LAYOUT SHALL BE PROVIDED IN
SUFFICIENT DETAIL, THEREBY ENABLING THE CONTRACTOR TO CONSTRUCT THE
PROJECT IN CONFORMITY WITH THE PLANS AND SPECIFICATIONS. SURVEY WILL
BE PROVIDED BY THE CONTRACTOR. THE CONTRACTOR SHALL NOT BEGIN
CONSTRUCTION ACTIVITIES UNTIL ADEQUATE SURVEY GROUND CONTROL POINTS
HAVE BEEN ESTABLISHED, TIED DOWN, AND VERIFIED IN WRITING BY THE
CONTRACTOR'S PROFESSIONAL LAND SURVEYOR.
4. ALL R.I. STD. 9.9.0 CONSTRUCTION ACCESS ROADS SHALL BE CONSTRUCTED
PRIOR TO ANY ROADWAY ACCEPTING CONSTRUCTION TRAFFIC.
5. THE FREQUENCY AND APPLICATION RATES FOR THE DUST CONTROL ITEMS WILL
BE DETERMINED BY THE CONTRACTOR TO MEET THE REQUIREMENTS OF SECTION
907.
6. ALL SIDEWALK AND DRIVEWAYS DESIGNATED FOR REPLACEMENT SHALL BE CUT
AND MATCHED AT LOCATIONS SHOWN ON THE PLANS OR AS DIRECTED BY THE
ENGINEER.
7. ASPHALT EMULSION TACK COAT SHALL BE PLACED PRIOR TO PAVEMENT
PLACEMENT ON THE CONCRETE BASE OR COLD PLANED PAVEMENT, AND ON ANY
NEW COURSE WHICH HAS BEEN OPEN TO TRAFFIC, OR ANY NEW COURSE WHICH
HAS BEEN EXPOSED FOR MORE THAN 7 DAYS, AND/OR AS DIRECTED BY THE
ENGINEER. IT SHALL ALSO BE APPLIED TO VERTICAL PAVEMENT FACES BETWEEN
ADJOINING PAVEMENT SECTIONS. ALL APPLICATIONS ON BOTH HORIZONTAL AND
VERTICAL SURFACES SHALL BE INCIDENTAL TO THE APPLICABLE PAVEMENT ITEMS.
8. THE LIMITS OF CLEARING AND SURFACE DISTURBANCE SHALL BE STRICTLY
ADHERED TO IN ALL AREAS. IN ADDITION TO THOSE AREAS SPECIFICALLY
DESIGNATED ON THE PLANS, THE CONTRACTOR WILL BE RESPONSIBLE FOR
PROVIDING AND PLACING, AT ITS OWN EXPENSE, PLANTABLE SOIL AND SEED IN
AREAS WHICH ARE OUTSIDE OF THE PROJECT'S AREAS OF DISTURBANCE AND
WHICH ARE IMPACTED BY CONSTRUCTION OPERATIONS INCLUDING THOSE AREAS
WHERE VEHICLES, EQUIPMENT AND MATERIALS ARE STORED.
9. THE CONTRACTOR WILL NOT BE ALLOWED TO STOCKPILE REMOVED PAVEMENT
MATERIALS WITHIN THE PROJECT LIMITS.
10. CLEANING AND SWEEPING OF PAVEMENT WILL INCLUDE REMOVAL OF ALL
PAVEMENT DEBRIS PRIOR TO THE PLACEMENT OF EACH BITUMINOUS PAVEMENT
LIFT. ALL CLEANING AND SWEEPING SHALL BE DONE TO THE SATISFACTION OF
THE ENGINEER. CLEANING WITH COMPRESSED AIR SHALL ONLY BE ALLOWED
WITH THE APPROVAL OF THE ENGINEER.
11. PRIOR TO INSTALLATION, ALL SIGNS, MOUNTINGS AND LOCATIONS SHALL BE AS
SHOWN ON THE PLANS AND SHOP DRAWINGS OR AS MODIFIED BY THE
ENGINEER.
12. THE COORDINATE SYSTEM, IF SHOWN, IS THE RHODE ISLAND STATE PLANE
COORDINATE SYSTEM.
13. PAVEMENT OPERATIONS FOR CURBED SECTIONS: IN AREAS WHERE CURBING IS
SET TO FINISH LINE AND GRADE, THE CONTRACTOR WILL NOT BE REQUIRED TO
UTILIZE THE SENSOR AND SKY-TYPE DEVICE FOR AUTOMATIC GRADE CONTROL,
BUT WILL BE ALLOWED TO MANUALLY ADJUST THE BITUMINOUS PAVER FOR
CONTROLLING GRADE.
14. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING ALL ROADWAYS
FREE OF DEBRIS RESULTING FROM THEIR CONSTRUCTION OPERATIONS. ALL
DEBRIS SHALL BE REMOVED TO MAINTAIN THE SAFE TRAVEL OF THE PUBLIC AT
NO ADDITIONAL COST TO THE STATE.
15. NO FUEL STORAGE, VEHICLE REFUELING, OR EQUIPMENT STORAGE SHALL TAKE
PLACE IN DESIGNATED WETLANDS, NOR WITHIN 100' OF ANY WATER BODY. THIS
REQUIREMENT SHALL NOT SUPERSEDE ANY FEDERAL, STATE OR LOCAL LAW,
ORDINANCE, RULE OR REGULATION THAT APPLIES TO THE SAME, UNLESS THIS
REQUIREMENT IS MORE STRINGENT THAN SAID LAW, ORDINANCE, RULE OR
REGULATION.
16. THE CONTRACTOR SHALL BE RESPONSIBLE TO ENSURE THAT AT THE END OF
FINAL PAVING OPERATIONS, FLOW TO NEW AND EXISTING DRAINAGE STRUCTURES
HAS BEEN PROPERLY ESTABLISHED AND THAT NO ISOLATED DEPRESSIONS
REMAIN. THERE SHALL BE NO SEPARATE PAYMENT FOR THIS PROVISION; ANY
CORRECTIVE ACTION SHALL BE CONSIDERED INCIDENTAL TO PAVING AND COLD
PLANING OPERATIONS.
17. ALL EMBANKMENTS SHALL BE PLACED IN HORIZONTAL LAYERS NOT EXCEEDING
12" (AFTER COMPACTION) AND SHALL BE COMPACTED AS SPECIFIED BEFORE
THE NEXT LAYER IS PLACED. ALSO, EMBANKMENT CONSTRUCTION SHALL
CONFORM TO SECTION 202.03.2 OF THE R.I.D.O.T. STANDARD SPECIFICATIONS,
LATEST EDITION.
18. IF THIS PROJECT IS ON A HURRICANE EVACUATION AND DIVERSIONARY ROUTE,
AS DESIGNATED ON THE COVERSHEET, THE CONTRACTOR IS ADVISED THAT UPON
12 (TWELVE) HOURS NOTICE THE ROADWAY SHALL BE OPEN TO EVACUEES AND
EMERGENCY PERSONNEL. ANY EXTRA WORK NECESSARY TO COMPLY WITH THIS
REQUIREMENT WILL BE REIMBURSED UNDER FORCE ACCOUNT PROCEDURES.
19. THE CONTRACTOR SHALL READ, BECOME FAMILIAR WITH, AND ADHERE TO ALL OF
THE PROVISIONS, CONDITIONS, AND STIPULATIONS STATED IN THE
ENVIRONMENTAL APPROVALS ISSUED FOR THE PROJECT FROM THE DEPARTMENT
OF ENVIRONMENTAL MANAGEMENT (RIDEM). AND/OR THE ARMY CORPS OF
ENGINEERS (ACOE). AND/OR THE COASTAL RESOURCES MANAGEMENT COUNCIL
(CRMC). COPIES OF EACH OF THESE PERMITS ARE INCLUDED IN THE CS PAGES
OF THE CONTRACT DOCUMENTS. ALL COSTS ASSOCIATED WITH THESE CONDITIONS
SHALL BE CONSIDERED INCIDENTAL TO THE CONSTRUCTION AND INCLUDED WITH
THE COST FOR THE ASSOCIATED BID ITEM(S).
20. FOR ALL PROJECTS INVOLVING KNOWN SITE REMEDIATION ISSUES, THE
CONTRACTOR SHALL READ, BECOME FAMILIAR WITH, AND ADHERE TO ALL OF THE
CONSTRUCTION RELATED PROVISIONS, CONDITIONS, AND STIPULATIONS OF ANY
REMEDIAL ACTION WORK AND/OR SOIL MANAGEMENT PLANS DEVELOPED FOR THE
PROJECT. COPIES OF THESE DOCUMENTS ARE INCLUDED IN THE CS PAGES OF
THE CONTRACT DOCUMENTS. ALL COSTS ASSOCIATED WITH COMPLIANCE WITH
THESE DOCUMENTS SHALL BE CONSIDERED INCIDENTAL TO THE CONSTRUCTION
AND INCLUDED WITH THE COST FOR THE ASSOCIATED BID ITEM(S).
21. NO UNPROTECTED CONSTRUCTED FEATURE MAY PROJECT MORE THAN 4 INCHES
ABOVE THE FINISHED GRADE OF A TRAVERSABLE SLOPE IN A CLEAR ZONE, e.g.
HEADWALL, DRAINAGE INLET, ETC.
22. THE REMAINING SECTION OR STUB OF A BREAKAWAY BASE MAY NOT PROJECT
MORE THAN 4 INCHES ABOVE THE FINISHED GRADE OF A TRAVERSABLE SLOPE
IN A CLEAR ZONE, e.g. SIGN POSTS, LIGHT POLES, FIRE HYDRANTS, ETC.
GENERAL NOTES (CONTINUED):
1. THE CONTRACTOR IS REQUIRED TO ADHERE WITH THE A SITE SPECIFIC STORM WATER
POLLUTION PREVENTION PLAN (SWPPP) IN ORDER TO REMAIN IN COMPLIANCE WITH
THE RIPDES GENERAL PERMIT FOR STORMWATER DISCHARGES ASSOCIATED WITH
CONSTRUCTION ACTIVITIES. THE CONTRACTOR SHALL READ, BECOME FAMILIAR WITH,
AND ADHERE TO ALL OF THE PROVISIONS, CONDITIONS, AND STIPULATIONS OF THE
GENERAL PERMIT AND THE SITE-SPECIFIC SWPPP FOR THIS PROJECT. THE
CONTRACTOR IS RESPONSIBLE FOR MODIFYING THE SWPPP AS SITE CONDITIONS
WARRANT. A COPY OF THE SWPPP MUST BE ON-SITE AT ALL TIMES. COPIES OF
THESE DOCUMENTS ARE INCLUDED IN THE CS PAGES OF THE CONTRACT DOCUMENTS.
2. NO UNDISTURBED AREAS SHALL BE GRUBBED OF EXISTING VEGETATION AFTER
OCTOBER 15 OF ANY CALENDAR YEAR OR DURING ANY PERIOD OF FULL OR LIMITED
WINTER SHUTDOWN. ALL DISTURBED SOILS EXPOSED PRIOR TO OCTOBER 15 OF ANY
CALENDAR YEAR SHALL BE SEEDED OR PROTECTED BY THAT DATE. ANY SUCH AREAS
THAT DO NOT HAVE ADEQUATE VEGETATIVE STABILIZATION, AS DETERMINED BY THE
RESIDENT ENGINEER OR ENVIRONMENTAL INSPECTOR, BY NOVEMBER 15 OF ANY
CALENDAR YEAR, MUST BE STABILIZED THROUGH THE USE OF EROSION CONTROL
MATTING OR HAY MULCH, IN ACCORDANCE WITH SPECIFICATIONS CONTAINED WITHIN
THE R.I. SOIL EROSION AND SEDIMENT CONTROL HANDBOOK. IF WORK CONTINUES
WITHIN ANY OF THESE AREAS DURING THE PERIOD FROM OCTOBER 15 THROUGH
APRIL 15, CARE MUST BE TAKEN TO ENSURE THAT ONLY THE AREA REQUIRED FOR
THAT DAY'S WORK IS EXPOSED, AND ALL ERODIBLE SOIL MUST BE RESTABILIZED
WITHIN 5 WORKING DAYS. ANY WORK TO CORRECT PROBLEMS RESULTING FROM
FAILURE TO COMPLY WITH THIS PROVISION SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR. THERE WILL BE NO SEPARATE PAYMENT FOR THIS PROVISION, IT SHALL
BE CONSIDERED INCIDENTAL TO CONSTRUCTION OPERATIONS. STABILIZATION OF ONE
FORM OR ANOTHER AS DESCRIBED ABOVE SHALL BE ACHIEVED WITHIN 2 WEEKS OF
FINAL GRADING.
3. STOCKPILES OF MATERIAL SHALL NOT BE LOCATED WITHIN REGULATED WETLANDS OR
BUFFER ZONE AREAS. THEY SHALL HAVE SIDE SLOPES NO GREATER THAN 30% AND
STOCKPILES OF ERODIBLE MATERIAL SHALL ALSO BE SEEDED AND RINGED WITH
APPROPRIATE SEDIMENT AND EROSION CONTROL MEASURES TO STABILIZE. STOCKPILES
OF CONTAMINATED MATERIALS MUST BE PLACED ON TOP OF A POLY-ETHYLENE SHEET
AND COVERED AT ALL TIMES UNLESS IT IS AN ACTIVE WORKING PILE.
4. IF THE PLANS INCLUDE SPECIFIC AREAS FOR PLACEMENT OF CONSTRUCTION
DEWATERING BASINS AND/OR EQUIPMENT AND MATERIALS STORAGE AND STOCKPILING,
AND IF THE CONTRACTOR ELECTS TO UTILIZE ANY OTHER AREAS FOR THESE
PURPOSES, THIS SHALL BE APPROVED BY THE ENGINEER ONLY AFTER OBTAINING ANY
NECESSARY PERMITS AND/OR PERMIT MODIFICATIONS FROM THE APPROPRIATE
REGULATORY AUTHORITY(IES). ANY PERMITTING REQUIREMENTS SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE ACCOMPLISHED AT NO COST TO
THE STATE. THE ENGINEER WILL COORDINATE SUBMISSION OF ANY REQUIRED PERMIT
APPLICATION MATERIALS WITH THE R.I.D.O.T. ENVIRONMENTAL DIVISION.
5. SURFACE EROSION CONTROL MATTING SHALL BE USED TO STABILIZE PLANTABLE SOIL
AND/OR LOAM IN ALL DITCHES, ON ALL SLOPES ADJACENT TO WETLANDS AND
WETLAND PERIMETERS, AND ON ALL SLOPES WITHIN WATER QUALITY BASINS. JUTE
MESH IN DITCHES SHALL EXTEND TO AN ELEVATION 2 FEET ABOVE THE BOTTOM OF
THE DITCH.
6. SEEDING ON ALL SLOPES 3 TO 1 OR STEEPER SHALL CONSIST OF THE FOLLOWING
APPLICATIONS UNLESS CHANGED IN THE CONTRACT.
a. SEEDING TYPE I.
b. ADHESIVE MULCH STABILIZER
7. UNVEGETATED SLOPES SHALL NOT BE UNATTENDED OR EXPOSED FOR PERIODS IN
EXCESS OF 2 WEEKS OR THROUGH THE INACTIVE WINTER SEASON.
8. PRIOR TO CONSTRUCTION OPERATIONS, THE CONTRACTOR IS RESPONSIBLE FOR
CLEANING ALL CATCH BASINS AND FLUSHING THE PIPES, AND THEN VERIFYING THE
LOCATION (HORIZONTAL AND VERTICAL) OF ALL EXISTING PIPES AND/OR STRUCTURES
WHICH ARE TO BE CONNECTED. ANY VARIATION FOUND FROM THE PLANS MUST BE
BROUGHT TO THE ENGINEER'S ATTENTION.
9. ALL DRAINAGE AND UTILITY STRUCTURES WITHIN THE PAVED ROADWAY SHALL BE
ADJUSTED TO GRADE WITH THE SURROUNDING PAVEMENT PRIOR TO THE WINTER
SHUTDOWN.
10. DURING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING
THE EFFICACY OF THE DRAINAGE SYSTEM. ONCE CONSTRUCTION IS COMPLETED THE
CONTRACTOR IS RESPONSIBLE FOR CLEANING ALL CATCH BASINS AND FLUSHING ALL
PIPES OF ANY CONSTRUCTION RELATED DEBRIS AT NO ADDITIONAL COST.
11. CATCH BASIN RIM GRADES FOR STRUCTURES NOT IN A TRAVEL LANE NOTED ON
PLANS ARE DEPRESSED 0.1' LOWER THAN THE GUTTER GRADE. RIM ELEVATIONS
SHOWN ARE FINAL GRADES. THE CONTRACTOR SHALL PLACE FRAMES AND GRATES 0.1'
BELOW THE GRADE CONSTRUCTED IN THIS CONTRACT OR AS DIRECTED BY THE
ENGINEER.
12. PROVISIONS FOR CLEARING TO ACCESS OUTFALLS DURING THE CLEANING AND
FLUSHING OF THE CLOSED DRAINAGE SYSTEM SHALL STRICTLY ADHERE TO THE PLANS
AND SPECIFICATIONS.
13. THE CONTRACTOR SHALL INSTALL ALL SEDIMENT AND EROSION CONTROL DEVICES FOR
OUTLET PROTECTION PRIOR TO CLEANING AND FLUSHING STORM WATER DRAINAGE.
SEDIMENT AND EROSION CONTROL DEVICES SHALL REMAIN IN PLACE UNTIL ALL
FLUSHED SEDIMENTS ARE REMOVED. AT ALL OUTFALL LOCATIONS WHERE PIPES ARE
TO BE CLEANED AND FLUSHED, OUTLET PROTECTION (R.I. STD. 9.1.0 0R 9.3.0) SHALL
BE INSTALLED TO TRAP SEDIMENTS. THESE SEDIMENTS SHALL THEN BE REMOVED AND
DISPOSED OF LEGALLY BEFORE THE OUTLET PROTECTION DEVICES ARE REMOVED. IF
OUTLET PROTECTION AT THE OUTFALL IS NOT FEASIBLE, THEN THE OUTLET PIPE OF
THE LAST DRAINAGE STRUCTURE TO BE CLEANED SHALL BE PLUGGED TO CAPTURE
ALL MATERIALS FLUSHED FROM PIPES. AFTER THE MATERIALS ARE REMOVED FROM
THE DRAINAGE STRUCTURE, THE OUTLET SHALL BE UNPLUGGED TO RESUME NORMAL
FUNCTIONING.
14. R.I. STD. 9.8.0 BALED STRAW INLET PROTECTION SHALL BE INSTALLED AT ALL CATCH
BASINS AND INLETS WHENEVER SUBBASE IS EXPOSED, AND SHALL REMAIN IN PLACE
UNTIL THE ABUTTING GROUND SURFACES ARE STABILIZED.
15. WHERE BALED STRAW INLET PROTECTION AND SILT FENCES ARE USED AT CATCH
BASINS, THEY SHALL BE REMOVED AT THE END OF THE PROJECT OR AS DIRECTED BY
THE ENGINEER IN ORDER TO PREVENT CLOGGING OF THE INLET.
1. EXISTING UTILITIES HAVE BEEN SHOWN ON THE PLANS USING THE BEST AVAILABLE
INFORMATION AND ARE APPROXIMATE. BUILDING SERVICE CONNECTIONS (ELECTRIC,
GAS, TELEPHONE, WATER AND SANITARY) ARE NOT SHOWN. CONTRACTOR IS TO
ASSUME SERVICES ARE PRESENT TO ALL BUILDINGS.
2. THE CONTRACTOR SHALL VERIFY THE LOCATIONS OF ALL EXISTING DRAINAGE AND
UTILITIES BOTH UNDERGROUND AND OVERHEAD BEFORE EXCAVATION BEGINS IN
ACCORDANCE WITH CHAPTER 39-1.2 OF THE R.I. GENERAL LAWS ENTITLED
"EXCAVATION NEAR UNDERGROUND UTILITY FACILITIES", WITH AMENDMENTS EFFECTIVE
AS OF NOVEMBER 1, 2009 AND, WHEN NECESSARY, BY CONTACTING THE INDIVIDUAL
UTILITY COMPANIES. EXCAVATION SHALL BE IN ACCORDANCE WITH ALL STATUTES,
ORDINANCES, RULES AND REGULATIONS OF ANY APPLICABLE CITY, TOWN, STATE OR
FEDERAL AGENCY. THE CONTRACTOR SHOULD UNDERSTAND THAT NOT ALL UTILITIES
SUBSCRIBE TO THE DIG SAFE PROGRAM. IT IS THE CONTRACTOR'S RESPONSIBILITY
TO NOTIFY ALL UTILITY COMPANIES AND AND AND ENSURE THAT ALL UTILITIES HAVE
BEEN MARKED PRIOR TO COMMENCING THEIR WORK. ANY DAMAGE TO EXISTING
UTILITIES MARKED IN THE FIELD, OR AS A RESULT OF FAILING TO CONTACT THE
APPROPRIATE UTILITY COMPANY, SHALL BE REPAIRED OR REPLACED AT NO
ADDITIONAL COST TO THE STATE.
3. ALL EXISTING UTILITIES TO BE ABANDONED SHALL BE CAPPED.
4. EXISTING WATER SERVICES SHALL BE RECONNECTED TO THE NEW WATER MAINS.
5. UTILITY SERVICE CONNECTIONS SHALL BE MAINTAINED TO ALL EXISTING FACILITIES
TO REMAIN.
6. FIRE HYDRANTS SHALL NOT BE REMOVED FROM SERVICE WITHOUT WRITTEN
AUTHORIZATION FROM THE FIRE DEPARTMENT OR THE WATER AUTHORITY.
7. ALL NEW WATER LINES SHALL BE DISINFECTED TO THE SATISFACTION OF THE WATER
AUTHORITY IN ACCORDANCE WITH THE SPECIFICATIONS.
8. ALL UTILITY POLE RELATED WORK SHALL BE BY OTHERS.
9. THE CONTRACTOR SHALL PROVIDE 72-HOUR ADVANCE NOTICE TO THE RIDOT TMC
(401-222-2378) FOR WORK AROUND RIDOT OWNED INFRASTRUCTURE (DRAINAGE,
LIGHTING, ITS EQUIPMENT, TOLL GANTRIES, COUNTING STATIONS, ETC.). ANY
DAMAGE TO THIS INFRASTRUCTURE MARKED IN THE FIELD, OR AS A RESULT OF
FAILING TO CONTACT RIDOT IN ADVANCE, SHALL BE REPAIRED OR REPLACED AT NO
ADDITIONAL COST TO THE STATE.
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
W:\ACTIVE PROJECT YEARS\2024\3833OC-2 BRIDGE GROUP 15F – BARRINGTON BRIDGE ROUTE 114 OVER BARRINGTON RIVER\DRAWINGS\CIVIL\SHEET\FINAL PLANS\100% SUBMISSION PLANS\SHEET SET\04 STANDARD NOTES- 2.DWG PER DPM 450.06
STANDARD NOTES - 2
01/28/26
MG
30420262025-CB-033
ITEM CODE
SCALE: NOT TO SCALE
STRUCTURAL NOTES FOR HIGHWAY SIGNS,
ALL SALVAGED TRAFFIC SIGNAL EQUIPMENT SHALL BE DELIVERED TO THE R.I.D.O.T.
MAINTENANCE HEADQUARTERS, 360 LINCOLN AVENUE, WARWICK, RHODE ISLAND, 02888.
THE COST FOR DELIVERY IS CONSIDERED INCIDENTAL TO THE WORK.
BACK PLATES SHALL BE INSTALLED ON ALL TRAFFIC SIGNAL HEADS.
THE CONTRACTOR SHALL SUPPLY AND INSTALL ON THE UPPER LEFT HAND CORNER
OF THE BACK OF THE CONTROLLER CABINET DOOR A LAMINATED INTERSECTION
GRAPHIC AND TABLE DEPICTING THE TRAFFIC DETECTOR RELAY CHANNEL ASSIGNMENTS.
THE DIAGRAM SHALL BE A GRAPHIC OF THE INDIVIDUAL INTERSECTION ORIENTED
SIMILAR TO THE PLANS SHOWING THE LOCATIONS OF EACH OF THE LOOP DETECTORS.
THE DIAGRAM SHALL, AT A MINIMUM, INCLUDE DETECTOR NUMBERS, STREET NAME
LABELS, NORTH ARROW, AND CONTROLLER CABINET LOCATION. THE ASSIGNMENT
INFORMATION SHALL BE INCLUDED IN A TABLE WHICH SHALL INCLUDE, AT A MINIMUM,
THE APPROACH NAME, DETECTOR NUMBER, TERMINAL NUMBER, DETECTOR RACK SLOT
NUMBER, RELAY NUMBER, RELAY CHANNEL NUMBER, AND PHASE ASSOCIATED WITH
EACH DETECTOR.
TRAFFIC CONTROLLER CABINETS, UNLESS OTHERWISE NOTED, SHALL BE NEMA TS2
TYPE 1 CABINET SIZE 6 ("P" TYPE) WITH NOMINAL DIMENSIONS OF 52"Hx44"Wx24"D.
ALL DELAY AND EXTENSION TIMES, AS CALLED FOR ON THE PLANS, FOR PROPOSED
LOOP DETECTORS SHALL BE PROGRAMMED IN THE TRAFFIC SIGNAL CONTROLLER AND
NOT THE DETECTOR RELAY.
INSULATED GROUND WIRE SHALL BE PLACED IN ALL PVC CONDUITS AND SHALL BE
BONDED TO GROUND RODS IN ACCORDANCE WITH SECTION T.03 OF THE RHODE
ISLAND DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS FOR ROAD AND
BRIDGE CONSTRUCTION.
THE FINAL POSITION OF SIGNAL HEADS, PEDESTRIAN PUSHBUTTONS, DETECTORS, AND
STOP LINE AND CROSSWALK PAVEMENT MARKINGS SHALL BE AS DIRECTED BY THE
ENGINEER IN THE FIELD ACCORDING TO ACTUAL INTERSECTION CHARACTERISTICS.
A 2' MINIMUM BUFFER SHALL BE PROVIDED BETWEEN THE CURB AND ALL LATERAL
OBSTRUCTIONS (INCLUDING ALL SIGNAL POLES AND TRAFFIC/PEDESTRIAN SIGNAL
HEADS) TO PROVIDE ADEQUATE CLEARANCE FOR TURNING VEHICLES.
ALL FOUNDATIONS MUST HAVE CONES OR BARRELS BOLTED TO FOUNDATION BASES
UNTIL ACTUAL POLE IS INSTALLED.
WHEN PLACING TRAFFIC SIGNAL HANDHOLES OR CONDUIT IN EXISTING PORTLAND
CEMENT CONCRETE SIDEWALKS, THE ENTIRE SIDEWALK SQUARE OF CONCRETE SHALL
BE REPLACED IN ACCORDANCE WITH R.I. STD. 43.1.0. NO PATCHES WILL BE
ALLOWED.
ALL PEDESTRIAN PUSHBUTTONS SHALL BE COMPLIANT WITH "THE AMERICANS WITH
DISABILITIES ACT ACCESSIBILITY GUIDELINES FOR BUILDINGS AND FACILITIES" (ADAAG)
AND SHALL INCLUDE A PRESSURE-ACTIVATED (NON-MOVING) BUTTON. SIGNS
APPLICABLE TO PUSHBUTTON ACTUATION SHALL BE INSTALLED SUCH THAT THE
CROSSING ASSIGNED TO EACH BUTTON IS CLEARLY INDICATED. IF SITE CONDITIONS DO
NOT ALLOW PEDESTRIAN PUSHBUTTONS TO BE INSTALLED WHERE CALLED FOR ON THE
PLANS, THE R.I.D.O.T. TRAFFIC ENGINEERING UNIT SHALL BE CONSULTED WITH
THROUGH AN R.F.I. PRIOR TO INSTALLING THE PUSHBUTTONS. THE FINAL PLACEMENT
OF ALL PEDESTRIAN PUSHBUTTONS SHALL BE IN ACCORDANCE WITH ADAAG AND THE
MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, LATEST EDITION.
ALL LOOP DETECTORS SHALL BE CENTERED WITHIN EACH LANE AS DELINEATED,
UNLESS OTHERWISE DIMENSIONED ON PLANS.
ALL LOOP DETECTORS SHALL BE CUT INTO THE FINAL PAVEMENT SURFACE COURSE.
TRAFFIC SIGNAL CONTROLLERS AND CABINETS SHALL BE PROGRAMMED AND WIRED SO
THAT ANY FIRE PRE-EMPTION SHALL OVERRIDE MANUAL (PUSH BUTTON) OPERATION.
THE CONTRACTOR SHALL WORK CONTINUOUSLY TO RESTORE TRAFFIC SIGNAL
OPERATION TO ITS INTENDED PURPOSE WHEN REPLACING THE TRAFFIC SIGNAL
EQUIPMENT. A POLICE DETAIL IS REQUIRED TO DIRECT TRAFFIC AT THE INTERSECTION
AT ALL TIMES WHEN THE TRAFFIC SIGNAL IS INOPERATIVE. AT NO TIME SHALL THE
CONTRACTOR LEAVE THE SITE BEFORE RESTORING FULL TRAFFIC OPERATIONS.
1.
TRAFFIC SIGNAL NOTES:
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
MAINTENANCE AND PROTECTION OF TRAFFIC NOTES:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
ALL MAINTENANCE AND PROTECTION OF TRAFFIC CONTROL SETUPS, SIGNS,
CHANNELIZING DEVICES, ETC., SHALL BE IN ACCORDANCE WITH THE MANUAL
ON UNIFORM TRAFFIC CONTROL DEVICES, LATEST EDITION.
ALL SIGN MOUNTINGS FOR TEMPORARY AND CONSTRUCTION SIGNS SHALL BE
IN ACCORDANCE WITH THE R.I.D.O.T. STANDARD SPECIFICATIONS, LATEST
EDITION.
THE CONTRACTOR SHALL COVER ALL EXISTING AND/OR TEMPORARY SIGNS
THAT ARE NOT RELEVANT TO THE TRAFFIC CONTROL REQUIRED DURING ANY
PARTICULAR STAGE OF THE CONTRACT.
ADVANCE FLAGPERSON SIGNS (W20-7A) SHALL BE USED IN ADVANCE OF
ANY POINT AT WHICH A FLAGPERSON OR A POLICE OFFICER HAS BEEN
STATIONED TO CONTROL TRAFFIC. WHEN NEEDED, AN APPROPRIATE DISTANCE
MESSAGE MAY BE DISPLAYED ON A SUPPLEMENTAL PLATE (24"x18") BELOW
THE FLAGPERSON SYMBOL SIGN. THE SIGN SHALL BE PROMPTLY REMOVED
OR COVERED WHENEVER THE FLAGPERSON IS NOT AT THE STATION.
POLICE OFFICERS AND FLAGPERSONS SHALL BE UTILIZED AS OUTLINED IN
SECTIONS 913 & 914 OF THE RI STANDARD SPECIFICATIONS FOR ROAD AND
BRIDGE CONSTRUCTION.
POLYETHYLENE DRUMS SHALL BE UTILIZED AS A CHANNELIZING DEVICE WHEN
A TRAFFIC CONTROL SET-UP IS TO REMAIN BEYOND WORKING HOURS WHEN
NO WORKERS ARE PRESENT. CONES SHALL BE UTILIZED WHEN A TRAFFIC
CONTROL SET-UP IS TO REMAIN ONLY DURING WORKING HOURS AND IS
SUBSEQUENTLY BROKEN DOWN AT THE END OF THE WORKDAY.
ARROW PANELS SHALL BE SET IN THE FLASHING FOUR CORNERS CAUTION
MODE UNLESS UTILIZED FOR A MERGING TAPER. ARROW PANELS SET IN THE
FLASHING ARROW MODE SHALL NOT BE UTILIZED FOR LANE SHIFTS.
TEMPORARY CONSTRUCTION SIGNS AND OTHER WORKZONE TRAFFIC CONTROL
DEVICES THAT ARE DAMAGED OR REQUIRE RELOCATION SHALL BE REPLACED
AND / OR RELOCATED UNDER THE PAY ITEM FOR "MAINTENANCE AND
MOVEMENT TRAFFIC PROTECTION."
THE PRIVATE VEHICLES OF CONSTRUCTION WORKERS SHALL NOT BE PARKED
ON THE TRAVEL LANES OR SHOULDERS. THEY MAY BE PARKED WITHIN THE
STATE RIGHT-OF-WAY ONLY IN AREAS BEYOND THE OUTSIDE EDGE OF THE
TRAVEL LANES AND/OR IN AREAS APPROVED BY THE ENGINEER.
TEMPORARY CONSTRUCTION SIGNS AND OTHER TEMPORARY TRAFFIC CONTROL
DEVICES SHALL BE INSTALLED PRIOR TO THE START OF WORK IN ANY AREA
OPEN TO TRAFFIC, AND SHALL BE REMOVED AS SOON AS PRACTICAL WHEN
THEY ARE NO LONGER APPROPRIATE.
THE INTENDED VEHICLE PATHS THROUGH EACH WORK ZONE SHALL BE
CLEARLY MARKED AT ALL TIMES. APPROVED PAVEMENT MARKINGS SHALL BE
INSTALLED BEFORE THE END OF THE WORK SHIFT ON ALL COLD-PLANED
AND NEW ROADWAY SURFACES THAT WILL BE OPENED TO TRAFFIC AT THE
END OF THE SHIFT. FAILURE TO COMPLY WILL RESULT IN AN ASSESSMENT
OF A CHARGE AS OUTLINED IN SECTION 937 OF THE RI STANDARD
SPECIFICATIONS FOR ROAD AND BRIDGE CONSTRUCTION.
ALL SUPPORT DESIGNS AND ASSOCIATED SHOP DRAWING REVIEWS SHALL BE
IN CONFORMANCE WITH THE LATEST EDITION AND REVISIONS, OF THE AASHTO
LRFD SPECIFICATIONS FOR STRUCTURAL SUPPORTS FOR HIGHWAY SIGNS,
LUMINARIES, AND TRAFFIC SIGNALS, INCLUDING THE LATEST INTERIM
SPECIFICATIONS, EXCEPT AS MODIFIED HEREIN.
LANDSCAPE NOTES:
ALL PLANT MATERIAL MUST BE TAGGED AT THE NURSERY (A RECOGNIZED GROWER
OF PLANT MATERIAL) IN ACCORDANCE WITH THE R.I.D.O.T. STANDARD
SPECIFICATIONS, LATEST EDITION. ALL PLANT MATERIAL MUST BE NURSERY GROWN;
NO PLANTATION GROWN PLANT MATERIAL WILL BE ACCEPTED.
ALL PLANT SUBSTITUTIONS AND/OR CHANGES IN PLANT LOCATION MUST BE
APPROVED IN ACCORDANCE WITH THE R.I.D.O.T. STANDARD SPECIFICATIONS, LATEST
EDITION.
ALL PLANT MATERIAL IS TO BE FIELD LOCATED BY A REPRESENTATIVE FROM THE
R.I.D.O.T. LANDSCAPE ARCHITECTURE UNIT.
COORDINATE WITH THE R.I.D.O.T. CONSTRUCTION MANAGER PRIOR TO ALL
TRIMMING AND CLEARING NECESSARY TO COMPLETE THE WORK AS SHOWN ON
THE PLANS.
ANY TOPSOIL USED AS PLANTABLE SOIL SHALL HAVE A SANDY LOAM TEXTURE
RELATIVELY FREE OF SUBSOIL MATERIAL, STONES, ROOTS, LUMPS OF SOIL, TREE
LIMBS, TRASH OR CONSTRUCTION DEBRIS, AND SHALL CONFORM TO SECTION
M.18 OF THE R.I.D.O.T. STANDARD SPECIFICATIONS, LATEST EDITION.
ALL TREES AND SHRUBS SHALL BE MULCHED WITH PINE BARK MULCH IN
ACCORDANCE WITH THE R.I.D.O.T. STANDARD SPECIFICATIONS, LATEST EDITION.
ALL TREES AND/OR SHRUBS THAT ARE PLANTED AS A BED SHALL BE MULCHED
AS A BED.
PROVIDE A MINIMUM 6'-8" BRANCHING STANDARD ON ALL TREES INSTALLED
ADJACENT TO SIDEWALKS AND/OR PEDESTRIAN ACCESS AREAS.
THE CONTRACTOR SHALL PROVIDE CERTIFICATION THAT THERE ARE NO
CONTAMINANTS THAT EXCEED THE R.I.D.E.M. PERMISSIBLE LEVELS IN THE SOILS
USED AS LOAM OR PLANTABLE SOIL.
LUMINAIRES AND TRAFFIC SIGNALS:
1.
GENERAL
THE FOLLOWING NOTES SHALL BE INCLUDED ON ALL PLANS AND/OR SHOP
DRAWINGS IN REFERENCE TO ANCHOR BOLTS:
CONSTRUCTION DRAWINGS AND DETAILS
"PRETENSIONING OF ALL ANCHOR NUTS IS REQUIRED, AND SHALL BE
ACCOMPLISHED BY TIGHTENING TO 1/6TH TURN BEYOND THE
SNUG-TIGHT POSITION."
"THE MAXIMUM CLEARANCE BETWEEN THE BOTTOM OF THE LEVELING
NUTS AND THE TOP OF THE CONCRETE IS CRITICAL AND SHALL NOT
EXCEED THE AMOUNT SPECIFIED ON THIS DRAWING."
1.
THE USE OF GROUT UNDER BASE PLATES SHALL GENERALLY NOT BE
PERMITTED. IF SPECIFIC CONDITIONS WARRANT ITS USE, THE GROUT SHALL
NOT BE CONSIDERED LOAD CARRYING; LOADS SHALL BE DIRECTLY
SUPPORTED BY THE ANCHOR BOLTS. ADEQUATE DRAINAGE SHALL BE
PROVIDED.
THE DAMPENING EFFECTS OF VIBRATION MITIGATION DEVICES SHALL NOT BE
CONSIDERED IN THE DESIGN OF STRUCTURAL SUPPORTS FOR SIGNS AND
TRAFFIC SIGNALS. IF THE CONTRACTOR CHOOSES TO USE THESE DEVICES
FOR WARRANTY PURPOSES, THE TYPE OF DEVICES PROPOSED SHALL BE
APPROVED BY THE DEPARTMENT PRIOR TO FABRICATION OF SUPPORTS.
2.
11.
3.
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
W:\ACTIVE PROJECT YEARS\2024\3833OC-2 BRIDGE GROUP 15F – BARRINGTON BRIDGE ROUTE 114 OVER BARRINGTON RIVER\DRAWINGS\CIVIL\SHEET\FINAL PLANS\100% SUBMISSION PLANS\SHEET SET\05 JOB SPECIFIC PLAN SYMBOLS, LEGENDS AND NOTES.DWG PER DPM 450.06
JOB SPECIFIC SYMBOLS, LEGEND AND NOTES
01/28/26
MG
30520262025-CB-033
ITEM CODE
EXISTING CONDITIONS:
1. EXISTING CONDITIONS PROVIDED IN THESE DRAWINGS IS BASED ON THE ORIGINAL RECORD
PLANS, THE 2019, REPAIR PLANS, THE 2021 UNDERWATER INSPECTION REPORT, AND A
LIMITED UNDERWATER VISUAL INSPECTION PERFORMED IN 2024.
2. THE CONTRACTOR IS NOTIFIED OF THE STRONG CURRENTS, TIDAL VARIATION AND LIMITED
VISIBILITY UNDERWATER.
3. SOME EXPOSED PORTIONS OF TREMIE A MAY HAVE BROKEN OFF AND THE REMAINING
SHAPE IS IRREGULAR AND MAY BE SUSCEPTIBLE TO BEING DAMAGED DURING THE WORK.
4. TREMIE A AT PIER 5 AND 6 IS COVERED BY GROUT BAGS FROM THE TOP SURFACE TO
THE CHANNEL BOTTOM.
5. SPAN 4 (BETWEEN PIERS 3 AND 4) IS MARKED WITH USCG NAVIGATIONAL AIDS. THE
CONTRACTOR IS RESPONSIBLE FOR COORDINATING WITH THE BARRINGTON HARBORMASTER
FOR TEMPORARY DELINEATION OF THE NAVIGABLE WATERWAY.
6. POLICE COVE PARK SHALL NOT BE USED FOR STAGING OPERATIONS.
7. THE CONTRACTOR IS NOTIFIED THAT THE BARRINGTON RIVER SOUTH OF THE BRIDGE IS
HEAVILY OCCUPIED BY MOORED VESSELS DURING THE PEAK SEASON. THE CONTRACTOR IS
RESPONSIBLE FOR COORDINATING WITH THE THE BARRINGTON HARBORMASTER TO ENSURE
BARGES, EQUIPMENT, ETC. CAN BE TRANSPORTED TO THE SITE WITHOUT NEED TO
RELOCATE MOORINGS.
JOB SPECIFIC GENERAL NOTES:
1. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH ENVIRONMENTAL APPROVALS
(WHEN ISSUED) FROM THE RI DEPARTMENT OF ENVIRONMENTAL MANAGEMENT (RIDEM),
THE US ARMY CORPS OF ENGINEERS (ACOE), AND THE COASTAL RESOURCES
MANAGEMENT COUNCIL (CRMC). THESE PERMITS SHALL BE INCLUDED AS PART OF THE
CONTRACTOR DOCUMENTS.
2. THE CONTRACTOR IS NOTIFIED OF THE ENVIRONMENTAL SENSITIVITY OF THE BARRINGTON
RIVER.
3. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND MAINTAINING ENVIRONMENTAL
CONTROLS AS REQUIRED BY FEDERAL, STATE AND LOCAL REGULATIONS AND PERMITS.
ANY MATERIAL THAT FALLS INTO THE WATER AS A RESULT OF THE CONTRACTOR'S
OPERATIONS SHALL BE REMOVED IMMEDIATELY.
4. THE CONTRACTOR IS RESPONSIBLE FOR PROTECTING THE WATERWAY AGAINST SPILLS AND
EVAPORATION WHILE REFUELING, LUBRICATING, RESTORING EQUIPMENT. ALL FUEL, OIL,
AND LUBRICANTS SHALL BE HANDLED IN ACCORDANCE WITH ALL FEDERAL, STATE, AND
LOCAL REGULATIONS.
5. THE CONTRACTOR SHALL COORDINATE ALL MOVEMENT AND STAGING OF BARGES WITH
THE UNITED STATES COAST GUARD (USCG), RIDOT, AND THE TOWN OF BARRINGTON
HARBORMASTER.
SCALE: NOT TO SCALE
SURVEY NOTES:
1. THESE PLANS WERE DEVELOPED ON AERIAL ORTHOIMAGERY FROM ARCGIS MAPS. ACCURACY
OF INFORMATION IS WITHIN ONE-HALF FOOT.
JOB SPECIFIC PLAN SYMBOLS
EXISTING CATCH BASIN
CB
JOB SPECIFIC LEGEND
REMOVE AND DISPOSER & D
TOTAL LIMIT OF DISTURBANCE
EXISTING OVERHEAD WIRESEOW
RHODE ISLAND
DEPARTMENT OF TRANSPORTATION
VOIDS IN TREMIE A
VOIDS IN TREMIE B
STEEL PIPE/TIMBER DEBRIS
CONCRETE
COLLAPSED AREA OF TREMIE
HURRICANE EVACUATION ROUTE
1. ON BARRINGTON BRIDGE, VEHICLES TRAVELING EAST CAN TURN LEFT ONTO NEW MEADOW
ROAD AND CONTINUE ALONG IT TOWARD MASSACHUSETTS. ALTERNATIVELY, VEHICLES CAN
TURN LEFT ONTO SOWAMS ROAD AND CONNECT TO EITHER BARNEYVILLE ROAD OR NEW
MEADOW ROAD TO MASSACHUSETTS.
2. VEHICLES TRAVELING WEST ON THE BRIDGE CAN TURN RIGHT TO CONTINUE ON COUNTY
ROAD, THEN TURN LEFT ONTO MAPLE AVENUE, FOLLOWED BY A RIGHT TURN TO CONNECT
TO MIDDLE HIGHWAY AND PROCEED TOWARDS PROVIDENCE COUNTY. VEHICLES CAN ALSO
STAY ON COUNTY ROAD AND EITHER TURN RIGHT ONTO LINCOLN AVENUE TO CONNECT TO
MIDDLE HIGHWAY OR TAKE A RIGHT ONTO FEDERAL ROAD TO CONNECT TO MIDDLE
HIGHWAY.
3. SOURCE: https://riema.ri.gov/planning-mitigation/evacuation - BARRINGTON
4. TITLE: RHODE ISLAND HURRICANE EVACUATION STUDY HURRICANE EVACUATION MAPPING
JUNE 2013 BARRINGTON
1. WORK MUST BE PERFORMED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS
INCLUDING THE SPECIFICATIONS, SPECIAL PROVISIONS, DRAWINGS AND THE
ASSOCIATED REFERENCES. KEEP AT LEAST ONE COPY OF THE CONTRACT DOCUMENTS
ON SITE FOR THE DURATION OF WORK.
2. ADHERE TO ALL OF THE CONDITIONS, AND STIPULATIONS STATED IN THE ENVIRONMENTAL
APPROVALS ISSUED FOR THE PROJECT FROM THE DEPARTMENT OF ENVIRONMENTAL
MANAGEMENT (RIDEM) AND/OR THE ARMY CORPS OF ENGINEERS (ACOE). AND/OR THE
COASTAL RESOURCES MANAGEMENT COUNCIL (CRMC). COPIES OF EACH OF THESE
PERMITS ARE INCLUDED IN THE CS PAGES OF THE CONTRACT DOCUMENTS. ALL COSTS
ASSOCIATED WITH THESE CONDITIONS SHALL BE CONSIDERED INCIDENTAL TO THE
CONSTRUCTION AND INCLUDED WITH THE COST FOR THE ASSOCIATED BID ITEM(S).
IN-WATER WORK SHALL COMPLY WITH THE PERMITS.
3. EXISTING DIMENSIONS, ELEVATIONS, AND CONDITIONS RELATING TO THE WORK ARE BASED
ON ARCHIVE PLANS AND INFORMATION OBTAINED DURING AN UNDERWATER INSPECTION
CONDUCTED ON SEPTEMBER 24, 2024 AND ARE APPROXIMATE VERIFY AS NEEDED TO
COMPLETE THE WORK.
4. SELECTED DRAWINGS FROM THE ARCHIVE PLANS ARE PROVIDED AS REFERENCE,
HOWEVER, THE CONTRACTOR IS ENCOURAGED TO REVIEW THE ARCHIVE PLAN SET.
5. DETERMINE CONSTRUCTION PROCEDURES AND SEQUENCE TO ENSURE SAFE
CONSTRUCTION. PROVIDE TEMPORARY SHORING, BRACING, GUYS OR TIEDOWNS. SUCH
MATERIAL SHALL REMAIN THE PROPERTY OF THE CONTRACTOR, SHALL BE COMPLETELY
REMOVED AFTER THE COMPLETION OF THE PROJECT, AND SHALL BE CONSIDERED
INCIDENTAL TO THE WORK. SEE THE MATERIALS REQUIREMENTS FOR THE PERMANENT
FORMWORK AND APPURTENANCES INCORPORATED INTO THE WORK.
6. THE CONTRACTOR IS RESPONSIBLE FOR DAMAGE DONE TO ADJACENT STRUCTURES AND
VESSELS OR INJURIES TO THE PUBLIC AND RIDOT'S REPRESENTATIVES AS A RESULT
OF PERFORMING THE WORK. DAMAGE MUST BE REPAIRED WITH NO ADDITIONAL COST TO
THE STATE.
7. PROVIDE AND MAINTAIN ENVIRONMENTAL CONTROLS AS REQUIRED BY FEDERAL, STATE
AND MUNICIPAL REGULATIONS AND PERMITS. THE CONTRACTORS'S ATTENTION IS
DRAWN MUST BE REPAIRED WITH NO ADDITIONAL COST TO THE STATE.
8. FOLLOW APPLICABLE FEDERAL, STATE AND MUNICIPAL REGULATIONS, INCLUDING THE
FEDERAL DEPARTMENT OF LABOR, SAFETY, HEALTH ACT, U.S. ARMY CORPS OF
ENGINEERS, STATE/LOCAL WETLAND CONTROL, AND PERMITS.
9. STORAGE, FUELING AND LUBRICATION OF EQUIPMENT AND MOTOR VEHICLES MUST BE
CONDUCTED IN A MANNER THAT AFFORDS THE MAXIMUM PROTECTION AGAINST SPILL AND
EVAPORATION. FUEL, LUBRICANTS AND OIL MUST BE MANAGED AND STORED IN
ACCORDANCE WITH ALL FEDERAL, STATE, REGIONAL, AND LOCAL LAWS AND REGULATIONS.
EQUIPMENT OPERATION, ACTIVITIES, OR PROCESSES PERFORMED BY THE CONTRACTOR
MUST BE IN ACCORDANCE WITH ALL FEDERAL AND STATE AIR EMISSION AND
PERFORMANCE LAWS AND STANDARDS.
10. CONTRACTOR IS ADVISED THERE MAY BE UNDETECTED CONSTRUCTION DEBRIS OR OTHER
DEBRIS WITHIN AND AROUND THE WORK AREA.
11. THE PUBLIC BOAT RAMP TO THE NORTHWEST OF THE PROJECT IS OWNED AND
OPERATED BY THE TOWN OF BARRINGTON. OBTAIN WRITTEN APPROVAL FOR
CONTRACTOR USE FROM THE TOWN AND SUBMIT TO THE ENGINEER A MINIMUM OF ONE
WEEK BEFORE STARTING THE WORK.
12. COORDINATE VESSEL OPERATIONS AND MATERIAL STAGING WITH RIDOT, THE TOWN OF
BARRINGTON'S HARBORMASTER, AND THE UNITED STATES COAST GUARD
CONTACT: BRIAN HUNT, CHAIRMAN, BARRINGTON HARBOR COMMISSION AND
HARBORMASTER
PHONE: (401)437-2531
EMAIL: bhunt@barrington.ri.gov
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
RHODE ISLANDREVISIONS REVISIONS
NO. DATE BY NO. DATE BY
DESIGNED BY:
CHECKED BY:
DATE:
SHEET:
OF:
RHODE ISLAND
CONTRACT NO.
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETS
REHABILITATION OF
BARRINGTON BRIDGE (NO. 012301)
W:\ACTIVE PROJECT YEARS\2024\3833OC-2 BRIDGE GROUP 15F – BARRINGTON BRIDGE ROUTE 114 OVER BARRINGTON RIVER\DRAWINGS\CIVIL\SHEET\FINAL PLANS\100% SUBMISSION PLANS\SHEET SET\06 BRIDGE GENERAL NOTES.DWG PER DPM 450.06
BRIDGE GENERAL NOTES
01/28/26
MG
30620262025-CB-033
BRIDGE NOTES
1. ALL CONSTRUCTION INDICATED ON THESE PLANS SHALL BE IN ACCORDANCE WITH:
· THE AUGUST 2025 EDITION OF AND SUPPLEMENTS TO THE RHODE ISLAND
DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS FOR ROAD AND BRIDGE
CONSTRUCTION (RI STANDARD SPECIFICATIONS).
· THE AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO) LRFD BRIDGE CONSTRUCTION SPECIFICATIONS, FOURTH EDITION, INCLUDING
THE LATEST INTERIM REVISIONS.
2. DIMENSIONS, STATIONS ELEVATIONS AND ANGLES OF THE EXISTING STRUCTURE HAVE
BEEN OBTAINED FROM PLANS OF THE ORIGINAL CONSTRUCTION AND LIMITED FIELD
MEASUREMENTS. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS REQUIRED FOR
PROPER PERFORMANCE OF THE WORK. FIELD CONDITIONS MAY EXIST WHICH DEVIATE
FROM THE DIMENSIONS SHOWN ON THESE PLANS. THE CONTRACTOR SHALL BE SOLELY
RESPONSIBLE FOR FABRICATION AND FIT OF HIS HIS WORK.
3. THE BASE OF LEVELS, TO WHICH THE PLAN ELEVATIONS ARE REFERENCED, ARE BASED
ON THE ORIGINAL (2003) RECORD DRAWINGS. NORTH ARROWS ARE NAD83 GRID NORTH.
4. ANY DAMAGE TO EXISTING STATE OR PRIVATE PROPERTY CAUSED BY THE CONTRACTOR'S
OPERATIONS SHALL BE REPAIRED BY THE CONTRACTOR AT NO ADDITIONAL COST TO THE
STATE.
5. THE CONTRACTOR SHALL PLACE ALL EQUIPMENT AND MATERIALS AS FAR AWAY AS
POSSIBLE FROM THE EDGE OF THE TRAVEL LANE SO AS NOT CAUSE A SAFETY HAZARD,
IN ACCORDANCE WITH SECTION 106.05 OF THE R.I.D.O.T. STANDARD SPECIFICATIONS,
LATEST EDITION.
6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING ALL ROADWAY FREE OF
DEBRIS RESULTING FROM THEIR CONSTRUCTION OPERATIONS. ALL DEBRIS SHALL BE
REMOVED TO THE SATISFACTION OF THE ENGINEER AT NO ADDITIONAL COST TO THE
STATE.
7. THE CONTRACTOR SHALL TAKE THE PROPER PRECAUTION TO ENSURE THE STABILITY OF
ALL STRUCTURAL ELEMENTS DURING CONSTRUCTION UNTIL ALL REPAIRS ARE COMPLETE.
NOT TO SCALENOT
NNNN
ITEM CODE
DESIGN DATA
1. DESIGN SPECIFICATIONS
· THE AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS, TENTH EDITION, 2024, INCLUDING
ALL INTERIM REVISIONS TO DATE.
· THE RHODE ISLAND LRFD BRIDGE MANUAL, 2007 EDITION INCLUDING ALL REVISIONS
TO DATE.
· ALL OTHER APPLICABLE DESIGN SPECIFICATIONS ARE REFERENCED IN SECTION 1 OF
THE RHODE ISLAND LRFD BRIDGE DESIGN MANUAL DATED 2007.
· IN CASE OF CONFLICT, THE RHODE ISLAND LRFD BRIDGE MANUAL SHALL GOVERN.
GROUT:
AS SPECIFIED IN JOB SPECIFIC SPECIFICATION 817.9901
TYPE II PORTLAND CEMENT, FINE AGGREGATES, ADMIXTURES, FLY ASH, HIGH REACTIVITY
POZZOLAN; F'C=3000 PSI
DOWEL BARS:
#5 LONGITUDINAL BARS TO BE USED
SCALE: NOT TO SCALE
RHODE ISLAND
DEPARTMENT OF TRANSPORTATION
EXISTING CONDITIONS
1. WORK MUST BE PERFORMED IN ACCORDANCE WITH THE CONTRACT DOCUMENTS INCLUDING
THE SPECIFICATIONS, SPECIAL PROVISIONS, DRAWINGS AND THE ASSOCIATED REFERENCES.
KEEP AT LEAST ONE COPY OF THE CONTRACT DOCUMENTS ON SITE FOR THE DURATION
OF WORK.
CLASS F
MINIMUM CEMENTITIOUS CONTENT, lb/yd³ 400
MAXIMUM CEMENTITIOUS CONTENT, lb/yd³ 700
MAXIMUM W/CM 0.45
ACCEPTANCE CRITERIA
CONSISTENCY RANGE³, ASTM C1611 SPREAD, IN.
This is the start of the file's text. The full file is on GovTribe.
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .