- Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington
About this file
This is a Request for Quotation (RFQ) issued by the Washington State Parks and Recreation Commission for mud valves and accessories. The solicitation seeks qualified firms to fabricate and provide six (6) mud valves and related accessories for the MBR plants at Fort Flagler and Dosewallips State Parks. Electronic bid responses are due by Tuesday, June 3rd, 2025, at 1:00 PM PST, to be submitted via email to BidBox@parks.wa.gov. The contract term requires delivery of products to the specified location by June 30th, 2025, upon issuance of the purchase order.
The procurement has several notable features, including a priority to award to small or veteran-owned businesses for this contract, which is estimated to be less than $150,000. Bidders can potentially receive a 5% preference for PCB-free products and packaging. The evaluation will consider factors such as pricing, experience, work plan, project schedule, and references, with a total of 100 points available. Historically, annual total sales for similar contracts were approximately $40,000, though the state does not guarantee any minimum purchase. Bidders must register in the Washington Electronic Business Solutions (WEBS) system and are encouraged to provide comprehensive documentation demonstrating their qualifications and capabilities.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMPETITIVE SOLICITATION
WITH SUPPLIER DIVERSITY STRATEGY - REQUEST FOR QUOTATION
RFQ 2025-55543 MUD VALVES & ACCESSORIES
BRIEF DESCRIPTION: The Washington State Parks and Recreation Commission (State Parks) is soliciting quotes from qualified firms to fabricate/provide six (6) mud valves and the accessories for the MBR plants at Fort Flagler and Dosewallips State Parks.
PRIORITY STATEMENT: Because the contract is estimated to be less than $150,000, State Parks will award to the lowest responsive and responsible bid from a small or veteran-owned business, unless none of these businesses meet the criteria. See Section 1.3.
Bids are due: Tuesday, June 3rd, 2025, by 1:00 PM, PST.
ELECTRONIC BID RESPONSES ONLY: Bid responses will only be accepted electronically via Email/Email Attachment to BidBox@parks.wa.gov. (PDF scan encouraged). See Section 5.1 –
Submission of Responses for expanded details.
Procurement Coordinator: Jason Smith, procurement@parks.wa.gov
Email Inquiries to: procurement@parks.wa.gov
• See also (special communication instructions) §2.1, §2.2, §2.3.
WA State’s Official Bid Notification System: Bidders are responsible for properly registering in the Washington’s Electronic Business Solutions (WEBS) system, https://fortress.wa.gov/ga/webs/ and downloading the solicitation document and all appendices and incorporated documents related to this solicitation. WEBS Registration Information:
https://des.wa.gov/services/contracting-purchasing/doing-business-state/webs-registration-search-tips.
WEBS is the official system of record for this competition. Notifications, updates, RFQ addenda, amendments, and bidders' questions and answers will only be provided through WEBS to those who have registered. Failure to register may result in receiving incomplete or inaccurate information.
Each bidder is responsible for thoroughly reading and understanding all provisions of this RFQ. If there are any questions or unclear portions, bidders should contact the Procurement Coordinator.
Bidders must carefully read, understand, and follow all instructions in this RFQ and any subsequent amendments.
mailto:BidBox@parks.wa.gov mailto:procurement@parks.wa.gov mailto:procurement@parks.wa.gov https://fortress.wa.gov/ga/webs/ https://des.wa.gov/services/contracting-purchasing/doing-business-state/webs-registration-search-tips
RFQ 2025-55543 Mud Valves and Accessories Page 2 of 41
TABLE OF CONTENTS
1 INFORMATION ABOUT THE PROCUREMENT
1.1 ACQUISITION AUTHORITY
1.2 PURPOSE OF THE PROCUREMENT – AWARD A CONTRACT
1.3 WASHINGTON STATE PROCUREMENT PRIORITIES & PREFERENCES
2 DEADLINES, QUESTIONS AND PROCUREMENT SCHEDULE
2.1 COMMUNICATION REGARDING THIS COMPETITION
2.2 QUESTION AND ANSWER PERIOD
2.3 COMPLAINT PERIOD
2.4 PROCUREMENT SCHEDULE
3 SPECIAL TERMS
3.1 ADVANCED PAYMENT PROHIBITION
3.2 GENERAL TERMS AND CONDITIONS
4 RESPONSES - REQUIRED CONTENT, FORMAT, AND SCORING:
4.1 CHECKLIST OF REQUIRED SUBMITTALS
4.2 (APPENDIX A) – BIDDER’S CERTIFICATIONS, ASSURANCES, AND WAIVER
4.3 (APPENDIX B) – BIDDER’S PROFILE
4.4 (APPENDIX C) – PRICE SHEET Table
4.5 EXPERIENCE, WORK PLAN AND PROJECT SCHEDULE
4.6 (APPENDIX D) - REFERENCES
4.7 (APPENDIX E, OPTIONAL) – PCB REDUCTION (5% PREFERENCE)
4.8 (APPENDIX F) – Diverse Business Inclusion Plan – Subcontractors
5 RESPONSES - PREPARATION AND SUBMISSION REQUIREMENTS
5.1 SUBMISSION OF RESPONSES
5.2 RESPONSE LAYOUT REQUIREMENTS
5.3 WASHINGTON STATE PROCUREMENT PRIORITIES & PREFERENCE
6 EVALUATION AND AWARD
6.1 ORAL PRESENTATION (OPTIONAL)
6.2 Oral Presentations Evaluation CRITERIA (OPTIONAL)
6.3 BID RESPONSIVENESS
6.4 BIDDER RESPONSIBILITY ANALYSIS
6.4.1 REJECTED BIDS/BIDDERS & REJECTION NOTIFICATION
6.5 GENERAL EVALUATION PROVISIONS
6.6 EVALUATION OF COMPLETION BY DATE
6.7 EVALUATION STEPS
6.7.1 Preliminary Evaluation (Procedural)
6.7.2 Substantive Evaluation: Phase 1
6.7.3 Substantive Evaluation: Phase 2 (Optional)
6.8 SELECTION OF APPARENT SUCCESSFUL BIDDER
7 ANNOUNCEMENT OF ASB, PUBLIC DISCLOSURE, DEBRIEF, AND PROTESTS
7.1 ANNOUNCEMENT OF APPARENT SUCCESSFUL BIDDER (ASB)
7.2 PROCUREMENT RECORDS DISCLOSURE
RFQ 2025-55543 Mud Valves and Accessories Page 3 of 41
7.3 DEBRIEFING OF BIDDERS
7.3.1 How To Request A Debrief Conference
7.3.2 Debrief Meeting, Discussion, And Delay
7.3.3 Debrief Is A Prerequisite For Protest
7.4 PROTEST
7.4.1 General:
7.4.2 Form And Content:
7.4.3 Content Limitations:
7.4.4 Submission Of Protests
7.4.5 Grounds Which May Be Protested
7.4.6 Manager Assignment And Review
7.4.7 Protest Determinations And Findings
7.4.8 Agency Decision is final
8 ADDITIONAL GENERAL PROVISIONS FOR ALL BIDDERS
8.1 ANNOUNCEMENT AND SPECIAL INFORMATION
8.2 CONTRACTING WITH CURRENT OR FORMER STATE EMPLOYEES
8.3 AMENDMENTS TO THE COMPETITION
8.4 RESPONSIVENESS OF BIDDER’S RESPONSE
8.5 CLARITY AND CLARIFICATIONS
8.6 COST OF RESPONSE PREPARATION
8.7 OWNERSHIP OF RESPONSES
8.8 FINAL SELECTION & NO OBLIGATION
8.9 INCORPORATION OF RESPONSE IN CONTRACT
8.10 STATEWIDE VENDOR PAYMENT REGISTRATION
8.11 WEBS REGISTRATION
8.12 POLYCHLORINATED BIPHENYLS (PCBS) NOTICE
8.13 SMALL AND DIVERSE BUSINESS
8.14 ACCESS EQUITY CONTRACT REPORTING
8.15 PUBLIC DISCLOSURE & WAIVER OF PROPRIETARY INFORMATION
8.16 CIVIL RIGHTS COMPLIANCE
9 APPENDICES AND EXHIBITS
9.1 (APPENDIX A) – BIDDER’S CERTIFICATIONS, ASSURANCES, AND WAIVER
9.2 (APPENDIX B) – BIDDER PROFILE
9.3 (APPENDIX C) - PRICE SHEET TABLE (must be legible)
9.4 (APPENDIX D) - REFERENCES (must be legible)
9.5 (APPENDIX E, optional) - PCB CERTIFICATION (must be legible)
9.6 (APPENDIX E) – DIVERSITY BUSINESS INCLUSION PLAN - SUBS
RFQ 2025-55543 Mud Valves and Accessories Page 4 of 41
1 INFORMATION ABOUT THE PROCUREMENT
This section describes the purpose of the competitive solicitation and provides information about this procurement, including the potential scope of the opportunity.
1.1 ACQUISITION AUTHORITY
In accordance with RCW 39.26 RCW, the purpose of this Request for Quotes is to procure goods and/or services as described herein. State agency purchases must follow a competitive solicitation process, ensuring that the contract is awarded to the lowest responsive and responsible bidder.
This process ensures fairness, transparency, and accountability in procurement. By following these guidelines, we seek to obtain the best value for the state while maintaining the integrity of our procurement practices. All bidders must meet specified criteria and demonstrate their ability to fulfill contract requirements. The evaluation will consider both the price and the bidder’s ability to perform the contract effectively and efficiently.
1.2 PURPOSE OF THE PROCUREMENT – AWARD A CONTRACT
The purpose of this Competitive Solicitation is to receive competitive bids to evaluate and, as appropriate, award a purchase order to procure several mud valves and accessories to upgrade the MBR plants and Fort Flagler State Park and Dosewallips State Park.
Proposals will be evaluated based upon factors that include but are not limited to: Pricing, Experience, Work Plan, Project Schedule, and References. See Section 4 Responses – Required Content, Format and Scoring.
CONTRACT TERM
Deliver products to the specified delivery location by June 30th, 2025, upon issuance of the purchase order.
ESTIMATED CONTRACT VALUE
Historically, for prior contracts, annual total sales were approximately $40,000 for the goods/services. Total potential or estimated contract sales for this Competitive Solicitation are not known. Although State Parks does not represent or guarantee any minimum purchase from the Contract for the goods/services.
1.3 WASHINGTON STATE PROCUREMENT PRIORITIES & PREFERENCES
State Parks will apply the following Washington State procurement priorities and preferences to this Competitive Solicitation which, as set forth in Section 5.3, will impact the evaluation of bids for this Competitive Solicitation:
• Statutory Preference for PCB-Free Products & Products-In-Packaging: 5%
MANDATORY AWARD TO SMALL OR VETERAN-OWNED BUSINESS: As of April 1, 2023, State Parks is required to award competitively procured services contracts with an initial value less than $150,000 to the highest-ranked responsive and responsible Small or Veteran-Owned Business, unless there was no responsive and responsible Proposal from a Small or Veteran-Owned Business, per DES Policy DES-090-06, Supplier Diversity section.
https://www.des.wa.gov/policies-legal/supplier-diversity-des-090-06
RFQ 2025-55543 Mud Valves and Accessories Page 5 of 41
Given that the contract is estimated to be less than $150,000, State Parks intends to award a contract to the lowest responsive and responsible bid from small businesses (as defined in RCW 39.26.010(22)(a)) or veteran-owned businesses under RCW 43.60A.190, unless none of these businesses are deemed responsible and responsive to this solicitation.
All bidders must meet specified criteria and demonstrate their ability to fulfill contract requirements. The evaluation process will consider both the price and the bidder’s capacity to fulfil the contract effectively and efficiently.
This approach not only supports small and veteran-owned businesses but also aligns with our commitment to supplier diversity and equitable business opportunities. By promoting competitive procurement and prioritizing these businesses, we are fostering a diverse and inclusive marketplace that benefits all involved parties.
CERTIFICATION: State Parks, in accordance with Washington law, encourage small and diverse businesses to compete for and participate in state procurements as contractors and as subcontractors.
Include proof of certification issued by the Washington State Department of Veteran Affairs or self-certify as a small business through WEBS at the time of competition. You may also include proof of certification from the Washington State Office of Minority & Women’s Business Enterprises (OMWBE). If you are a small business registered in Washington's Electronic Business Solution (WEBS), we will verify your registration to determine eligibility.
RFQ 2025-55543 Mud Valves and Accessories Page 6 of 41
2 DEADLINES, QUESTIONS AND PROCUREMENT SCHEDULE
This section identifies important deadlines for this Competitive Solicitation, where to direct questions regarding the Competitive Solicitation, and the process for potential amendments or modifications to the Competitive Solicitation.
2.1 COMMUNICATION REGARDING THIS COMPETITION
All communication should be directed to the State Parks Procurement team via the Procurement Coordinator's email listed on the face page. Contacting other State Parks staff may result in disqualification. Only responses posted on WEBS are official; all other communications are unofficial and nonbinding. State Parks reserves the right to amend this solicitation.
2.2 QUESTION AND ANSWER PERIOD
Bidders may ask questions at any time, but responses must be posted on WEBS before the bid’s due date to allow bidders to respond. The final day for questions to receive a formal response is in Section 2.4 – Procurement Schedule.
Send questions to procurement@parks.wa.gov with the bid identification number and "Question" in the subject line (e.g., "RFQ # Question"). Only responses posted on WEBS are official; all other communications are unofficial and nonbinding.
2.3 COMPLAINT PERIOD
Bidders should first address concerns during the Question-and-Answer period. If a complaint is necessary, refer to Section 2.4 – Procurement Schedule for the Complaints Period. Complaints outside this period will not be considered. Send complaints to procurement@parks.wa.gov with the bid identification number and "Complaint" in the subject line (e.g., "RFQ # Complaint"). Failure to mark correctly may result in the complaint being missed. Responses will be posted on WEBS; only these responses are official.
Bidders must follow these procedures for complaints to be considered. Complaints must be in writing, sent to the Procurement Coordinator before the deadline, to the specified email address, and with the correct subject line. The complaint must state its basis and propose a remedy Only complaints that fall into the categories below and stipulate an issue of fact shall be considered:
• The solicitation unnecessarily restricts competition.
• The solicitation evaluation or scoring is unfair or flawed; or
• The solicitation requirements are inadequate or insufficient to prepare a response.
mailto:procurement@parks.wa.gov
RFQ 2025-55543 Mud Valves and Accessories Page 7 of 41
2.4 PROCUREMENT SCHEDULE
Any stated time is Pacific Time Zone (local time).
Activity Due Dates Time
Question Period
05/19/2025 – 06/02/2025 See additional details in Section 2.2 – Question and Answer Period.
NA
Answer Period
05/19/2025 – 06/02/2025, anticipated but may take longer. All Answer Responses will be posted on WEBS. See Section 2.2 – Question and Answer Period
Complaint Period
05/23/2025 – 05/28/2025 See additional details in Section 2.3 – Complaint Period.
Complaints received before or after the Complaint period will not be considered.
NA
Bidder’s Response – Deadline
06/03/2025 See also: Section 4 - Responses – Required Content, Format, and Scoring. See also Section 4.1 Checklist of Required Submittals
1:00PM
Oral Presentations
The Oral Presentation criteria and instructions will be provided by email to the short-listed firms, if needed. (OPTIONAL)
Announcement of Apparent Successful Bidder (ASB)
After the Bid’s due date (deadline to submit bid responses) and following the evaluation, the state will Announce the Apparent Successful Bidder (ASB). See additional details in Section 7.1 – Announcement of Apparent Successful Bidder.
Debriefing of Bidders
The Bidder wanting a Debrief must request a Debrief within three business days following the day of the Announcement of Apparent Successful Bidder (ASB). See additional details in Section 7.3 – Debriefing of Bidders
Protest The DEBRIEFED Bidder wanting to submit a protest must submit a Protest within five business days following the day of the Debrief. See additional details in Section 7.4 - Protests
RFQ 2025-55543 Mud Valves and Accessories Page 8 of 41
3 SPECIAL TERMS
This section outlines special terms for this Competitive Solicitation that bidders will need to review and adhere to in order to comply with the requirements.
3.1 ADVANCED PAYMENT PROHIBITION
Payment is based on provided goods and services only, following proper documentation and invoicing. No payment will be made for non-designated goods or services. Per Washington’s Constitution Article 8, Section 5, progress payments are allowed, but no payment will be made before work is completed, delivered, and accepted. This includes deposits and security deposits.
3.2 GENERAL TERMS AND CONDITIONS
The Terms and Conditions are located at https://parks.wa.gov/about/contact-us/contracting-opportunities/contractor-and-vendor-information to help bidders understand State Parks’ typical terms and conditions. Any resulting contract or purchase order will include these terms and conditions. Bidders should review them, assess the risks and rewards, and bid accordingly. Selected bidders (Apparent Successful Bidders or ASB) often try to negotiate terms, but such negotiations will likely not be entertained. Bidders should consider all risks when forming their bid response.
Each bidder’s submission of its response confirms the bidder’s consent to these terms and conditions.
https://parks.wa.gov/about/contact-us/contracting-opportunities/contractor-and-vendor-information https://parks.wa.gov/about/contact-us/contracting-opportunities/contractor-and-vendor-information
RFQ 2025-55543 Mud Valves and Accessories Page 9 of 41
4 RESPONSES - REQUIRED CONTENT, FORMAT, AND SCORING:
This section describes the information required for the Competitive Solicitation and outlines how your bid will be scored. Additionally, bidders must review and adhere to the Competitive Solicitation requirements, including those detailed in the exhibits, which specify the information that must be provided for a bid to be considered responsive.
4.1 CHECKLIST OF REQUIRED SUBMITTALS
The following list in the table in this subsection identifies the content that must be included in each responsible submission (Bidder’s bid response). Any response that does not contain all of these items may be rejected as non-responsive. Each item is discussed in more depth in the sections following the Table.
# Submittal
Scored by Points and/or Low Price and/or
Pass/Fail
For Reference:
See Appendix Or
Section
Bidder Mark if Provided
(failure to provide as instructed may result in bid rejection)
Bidder’s Certifications (form provided, must be signed)
Pass/Fail Appendix A, Section 4.2 Section 9.1
Bidder’s Profile (form provided) Pass/Fail
Appendix B, Section 4.3 Section 9.2
Price Sheet Table (form provided) Up to 60 points Appendix C, Section 4.4 Section 9.3
Experience, Work Plan and Project Schedule (self-authored)
Up to 20 points Section 4.5
References (form provided) Up to 20 points
Appendix D, Section 4.6 Section 9.4
(OPTIONAL)
Polychlorinated Biphenyls (PCB) Preference Consideration (form provided)
Up to five percent (5%) preference
Appendix E, Section 4.7 Section 9.5
Diverse Business Inclusion Plan – Subcontractors (form provided)
Pass/Fail Required if using subcontractors
Appendix F, Section 4.8 Section 9.6
Total points available are 100, with a minimum of 60 points required for a bid to be considered responsive. If a Washington Small Business or Certified Veteran-Owned Business does not meet the minimum points, the bid will be deemed non-responsive and rejected.
The table serves multiple purposes:
RFQ 2025-55543 Mud Valves and Accessories Page 10 of 41
1. Specifies the submittals bidders must provide to State Parks in their bid response.
2. Acts as a checklist to ensure all required materials are included.
3. If State Parks does not provide a form, the bidder must "self-author" a response to fulfill the requirement.
4. The table also indicates whether submittals will be scored based on points, low price, or pass/fail and provides a courtesy reference linking the submittal to other sections of the document.
4.2 (APPENDIX A) – BIDDER’S CERTIFICATIONS, ASSURANCES, AND WAIVER
A FORM is provided for this part of your bid response. See APPENDIX A – Bidder’s Certification, Assurances, and Waiver.
The Certifications must be executed as written in Appendix A. Failure to execute the Appendix in its official form will result in the Bidder’s Proposal being disqualified.
Appendix A – Bidder’s Certifications is evaluated on a pass/fail basis.
The certification must be signed and submitted by a duly authorized representative for the bidder.
4.3 (APPENDIX B) – BIDDER’S PROFILE
A FORM is provided for this part of your bid response. See APPENDIX B – Bidder’s Profile.
The Bidder’s Profile provides general information about the bidder and/or its corporate entity. It is important to fully read the Bidder’s Profile, as there may be additional pages that the bidder must self-author and attach, depending on the bidder’s response.
Appendix B – Bidder’s Profile must be substantively completed and is evaluated on a pass/fail basis.
Note: The Bidder’s Profile must be complete. Where there are choices, the bidder must check a box.
4.4 (APPENDIX C) – PRICE SHEET TABLE
A FORM is provided for this part of your bid response. See APPENDIX C – Price Sheet.
• Appendix C – Price Sheet Table is segmented into two parts:
Appendix C - Table 1 – SPECIAL TERMS FOR BIDDER’S PRICING Appendix C - Table 2 – BIDDER’S PRICING QUOTE
Award made to the responsive and responsible bidder and who has the highest score and the lowest price.
General Evaluation Continuum
Bidder demonstrates renowned experience and/or the least or no risk, and/or ideal fit for what is being sought by State Parks (most points)
Bidder demonstrates considerable experience, and/or some minor risk, and/or a close but not ideal fit for what is being sought by State Parks.
Bidder demonstrates solid experience, and/or mild risk, and/or fair fit for what is being sought by State Parks.
Bidder demonstrates adequate experience, and/or medium risk, and/or mediocre fit for what is being sought by State Parks.
Bidder demonstrates limited experience, and/or high risk, and/or poor fit for what is being sought by State Parks.
(low points)
Bidder demonstrates no experience, and/or grave risk, and/or a bad fit for what is being sought by State Parks (no points)
RFQ 2025-55543 Mud Valves and Accessories Page 11 of 41
All costs rolled in, except tax: Bidder your unit price must factor in all cost drivers, such as but not limited to: travel, shipping, packaging, material cost, etc. The only thing you should not include in the unit price is the sales tax. Washington State government agencies DO PAY sales tax but that should appear separately on the invoice and not as part of the unit price on the Price Sheet provided by the Bidder.
A bidder’s failure to identify all costs in a manner consistent with the instructions in this Competitive Solicitation is sufficient grounds for disqualification.
This part of the bid response is scored up to 60 points with a pro rata share for higher-cost bids. For example, if three bids are received (A @ $25, B @ $26.50, C @ $50):
• Bid A get 60 points (25/25 = 1.0 x 60 points = 60),
• Bid B gets 56.60 points (25/26.50 = .943 X 60 points = 56.60),
• Bid C gets 30 points (25/50 = .5 X 60 points = 30).
COST CONTROL: A bid may be deemed non-responsive if it exceeds the average of all other bids by 20%.
Inclusive Pricing: Bidders must identify and include all cost elements in their pricing. In the event that bidder is awarded a Contract, the total price for the goods and/or services shall be bidder’s price as submitted. Except as provided in the Contract, there shall be no additional costs of any kind.
Credit Cards (P-Cards): In the event that bidder is awarded a Contract, the total price for the goods and/or services shall be the same regardless of whether Purchasers make payment by cash, credit card, or electronic payment. Bidder shall bear, in full, any processing or surcharge fees associated with the use of credit cards or electronic payment.
4.5 EXPERIENCE, WORK PLAN AND PROJECT SCHEDULE
Bidder this part of your bid response is SELF-AUTHORED by you, no form is provided.
• Title this “4.5 Experience, Work Plan and Project Schedule”.
Experience, Work Plan, and Project Schedule: Include all project requirements and the proposed tasks, services, activities, etc., necessary to accomplish the scope of the project defined in this RFQ. This section must contain sufficient detail to convey to the evaluation team the bidder’s experience, knowledge of the subjects, and skills necessary to successfully complete the project. The bidder may also present any creative approaches that might be appropriate and provide any pertinent supporting documentation.
Project Schedule: Include a project schedule indicating when the elements of the work will be completed. The project schedule must ensure that any requested deliverables are met.
This part of the bid response is scored up to 20 points.
4.6 (APPENDIX D) - REFERENCES
A FORM is provided for this part of your bid response. See (APPENDIX D – REFERENCES.
Bidder this part of your bid response requires you to submit reference from other parties (do not use WA State Parks and Recreation Commission as a reference).
Bidder must provide at least FIVE (5) Reference WITH FRESH ACTIVITY.
Provide a minimum of five references for similar services, with name and phone number.
This part of the bid response is scored up to 20 points.
RFQ 2025-55543 Mud Valves and Accessories Page 12 of 41
4.7 (APPENDIX E, OPTIONAL) – PCB REDUCTION (5% PREFERENCE)
A FORM is provided for this part of your bid response. See (APPENDIX E – PCB
REDUCTION.)
Statutory Preference for PCB-Free Products and the product’s packaging. Pursuant to RCW 39.26.280, State Parks is providing a bid preference (incentive) of up to five percent (5%) to any bidder that provides products AND the product’s packaging that do not contain Polychlorinated Biphenyls (PCBs).
Bidders seeking the preference must make the certification on the certification form embedded below and/or separately posted on WEBS for this competition. Bidders who seek to obtain bid preference for PCB-Free Products AND the product’s packaging must, in regard to the products AND product’s packaging pertaining to this procurement, certify either that (a) all of their products AND product’s packaging; or (b) specific products And product’s packaging are PCB-free.
To be deemed to be ‘PCB-free,’ the applicable product(s) AND packaging must be tested, within the previous 365 days, by an independent, third party laboratory using Environmental Protection Agency Analytical Method 1668c, and have been found NOT to contain PCBs above the practical quantification limit. Such test for the applicable products must be attached to the certification. The cost for conducting any such testing is at the bidder’s expense.
FURTHER: For the documents to be considered for the preference, the Bidder SHALL, organize the material in an EASY-TO-UNDERSTAND format and clearly describe which Price Sheet line item it applies to (crosswalk if need). State Parks will not expend large amounts of time to determine the documents’ veracity and if the document(s) cannot be quickly and easily understood, at the State Parks’ discretion, the document(s) will not be considered, and no preference will be applied.
4.8 (APPENDIX F) – DIVERSE BUSINESS INCLUSION PLAN – SUBCONTRACTORS
A FORM is provided for this part of your bid response. See APPENDIX E – Diverse Business Inclusion Plan – Subcontractors.
Appendix E – Diverse Business Inclusion Plan - Subcontractor is evaluated on a pass/fail basis.
REQUIRED ONLY if Bidder will be using subcontractors to perform the Contract: This exhibit outlines the inclusion plan for diverse business subcontractors pertaining to the Contract.
RFQ 2025-55543 Mud Valves and Accessories Page 13 of 41
5 RESPONSES - PREPARATION AND SUBMISSION REQUIREMENTS
This section identifies how to prepare and submit your bid for this Competitive Solicitation. By responding to this Competitive Solicitation and submitting a bid, bidders acknowledge having read and understood the entire Competitive Solicitation and accept all information contained within this Competitive Solicitation.
5.1 SUBMISSION OF RESPONSES
Bids must be complete, legible, signed, and follow all instructions stated in the Competitive Solicitation (including the appendices, and exhibits). Unless otherwise specified in writing by documents included with an electronic bid must be prepared in MS Word, MS Excel, or Adobe PDF. Where required to do so, bidders may sign using either a physical or electronic signature.
Bidder’s electronic bid must be emailed to the Procurement Coordinator at the following email address: BidBox@parks.wa.gov. The email subject line should include the bid identification number, "Bid," and your company name (e.g., "RFQ # Bid ACME"). Ensure the email, including attachments, is less than 30MB. It's recommended to keep it under 25MB. Zipped files are not accepted. All responses and any accompanying documentation become the property of State Parks and will not be returned.
State Parks will send an automatic acknowledgment of bid receipt. This acknowledgment does not determine the bid’s responsiveness. If the bidder does not receive an acknowledgment within a reasonable time, it is the bidder's responsibility to contact State Parks for confirmation.
VERIFICATION: Bidders are welcome to contact the State Parks Contracts and Grants Program team (CGP) to see if your bid response was received, however, this process works best if there’s enough time between the date and time submitted and the bid’s due date deadline. Send verification requests to:
procurement@parks.wa.gov The email subject line should include the bid identification number, "Verification," and your company name (e.g., "RFQ # Verification ACME") CAUTION: Submit your bid response early as a safeguard against any technological slow-down or delays. Bids received after the deadline for any reason, no matter the cause, regardless of responsibility, will be rejected.
--- Late submissions will be considered non-responsive and may be rejected. ---
5.2 RESPONSE LAYOUT REQUIREMENTS
The Bidder’s bid response should be logically assembled so that the evaluators can easily understand what they are reading and relate what they are reading back to the competition document’s requirement. Evaluators appreciate landmarks or references using the competition document’s section numbers and section titles. One mistake that Bidders make is that they have a previously prepared statement or materials that don’t precisely relate to the competition document’s individual requirement (it wasn’t tailored or designed for the requirement), or that the previously prepared statement (or material) is supposed to relate to two or more requirements of the competition document. That can be confusing and may result in a negative impact to the evaluation of the Bidder’s bid response.
mailto:BidBox@parks.wa.gov mailto:contracts@parks.wa.gov
RFQ 2025-55543 Mud Valves and Accessories Page 14 of 41
NOTE: If evaluators cannot easily identify the statement/material or cannot easily link it to the competition’s section reference, requirement, or question the statement/material may be misunderstood, disregarded, or may negatively impact the evaluation of the response.
5.3 WASHINGTON STATE PROCUREMENT PRIORITIES & PREFERENCE
The following Washington State procurement priorities and preferences apply to this Competitive Solicitation:
• WASHINGTON SMALL BUSINESSES AND/OR CERTIFIED VETERAN-OWNED
BUSINESSES. In furtherance of Washington’s business inclusion goals State Parks will evaluate bids for best value and will provide a bid preference to any bidder who certifies.
• WASHINGTON SMALL BUSINESS. Bidder is a Washington Small Business as defined in RCW 39.26.010. To qualify as a Washington Small Business, Bidder must meet three (3) requirements:
o Location. Bidder’s principal office/place of business must be located in and identified as being in the State of Washington. A principal office or principal place of business is a firm’s headquarters where business decisions are made and the location for the firm’s books and records as well as the firm’s senior management personnel.
o Size. Bidder must be owned and operated independently from all other businesses and qualify as one of the following:
• Bidder Qualifies as a Small Business – i.e.,
• Bidder has fifty (50) or fewer employees; or
• Bidder has an annual gross revenue of less than $7,000,000 as reported on Bidder’s federal income tax return or its return filed with the Washington State Department of Revenue over the previous three (3) consecutive years.
• Bidder Qualifies as a Mini business – i.e., Bidder has an annual gross revenue of less than $3,000,000, but $1,000,000 or more, as reported on Bidder’s federal income tax return or its return filed with the Washington State Department of Revenue.
• Bidder Qualifies as a Microbusiness – i.e., Bidder has an annual gross revenue of less than $1,000,000 as reported on Bidder’s federal income tax return or its return filed with the Washington State Department of Revenue.
o WEBS Certification. Bidder must have certified its Washington Small Business status in Washington’s Electronic Business Solution (WEBS).
• CERTIFIED VETERAN-OWNED BUSINESS. Bidder is a Certified Veteran-Owned Business under RCW 43.60A.190. To qualify as a Certified Veteran-Owned Business, Bidder must meet four (4) requirements:
o 51% Ownership. Bidder must be at least fifty-one percent (51%) owned and controlled by:
RFQ 2025-55543 Mud Valves and Accessories Page 15 of 41
(a) A veteran as defined as every person who at the time he or she seeks certification has received a discharge with an honorable characterization or received a discharge for medical reasons with an honorable record, where applicable, and who has served in at least one of the capacities listed in
RCW 41.04.007;
(b) A person who is in receipt of disability compensation or pension from the department of veterans affairs; or
(c) An active or reserve member in any branch of the armed forces of the United States, including the national guard, coast guard, and armed forces reserves.
o Washington Incorporation/Location. Bidder must be either an entity that is incorporated in the state of Washington as a Washington domestic corporation or, if not incorporated, an entity whose principal place of business is located within the State of Washington.
o WEBS Certification. Bidder must have certified its Veteran-Owned Business status in Washington’s Electronic Business Solution (WEBS).
o WDVA Certification. Bidder must have provided certification documentation to the Washington Department of Veterans’ Affairs WDVA) and be certified by WDVA and listed as such on WDVA’s website (WDVA – Veteran-Owned Businesses)
• STATUTORY PREFERENCE FOR PCB-FREE PRODUCTS & PRODUCTS-IN-
PACKAGING. Pursuant to RCW 39.26.280, State Parks is providing a bid preference in the amount of five percent (5%) per product line item tested to any bidder who certifies that Bidder’s products or products-in-packaging do not contain Polychlorinated Biphenyls (PCBs).
All bidders must certify whether they are seeking the Statutory Preference for PCB-Free Products & Products-In-Packaging. Bidders who seek to obtain the five percent (5%) bid preference for PCB-Free Products & Products-In-Packaging must, in regard to the products and products-in-packaging pertaining to this Competitive Solicitation, certify either (a) that all of their products & products-in packaging; or (b) specific products & products-in-packaging are PCB-free. To be deemed to be ‘PCB-free,’ the applicable products must be tested, within the previous 365 days, by an independent, third party laboratory using Environmental Protection Agency Analytical Method 1668c, and have been found NOT to contain PCBs. Such test for the applicable products must be attached to this certification
RFQ 2025-55543 Mud Valves and Accessories Page 16 of 41
6 EVALUATION AND AWARD
This section identifies how bids for this Competitive Solicitation will be evaluated.
6.1 ORAL PRESENTATION (OPTIONAL)
Oral presentations, if deemed necessary by State Parks, may be used to select the winning response. State Parks reserves the right, at its sole discretion, to invite the top-scoring firms from the written evaluation to participate in an oral presentation. The top-scoring firms will be contacted to schedule a date, time, and location for the presentation. All key personnel must participate in the oral presentation. The Procurement Coordinator will reach out to the bidder(s) to arrange a date and time and will provide further instructions. Any commitments made by the Contractor during the oral presentation will be considered binding.
There will be a maximum of 100 points awarded based on bidder’s demonstration. All points will be cumulative. The oral presentation will determine the apparently successful bidder.
6.2 ORAL PRESENTATIONS EVALUATION CRITERIA (OPTIONAL)
Oral Presentation Evaluation Criteria Maximum Possible Point Total
Organization:
- Management Plan
25 points
Project Management:
- Project Scheduling
25 points
Expertise
- Understanding of this project
25 Points
Experience
- Relevant Past Projects
25 Points
TOTAL: 100 Points
Points for Oral Presentation will be determined according to the following guidelines, and weighted appropriately:
Bidder demonstrates renowned experience (5 points)
Bidder demonstrates considerable experience (4 points)
Bidder demonstrates solid experience (3 points)
Bidder demonstrates adequate experience (2 points)
Bidder demonstrates limited experience (1 points)
Bidder demonstrates no experience (0 points)
6.3 BID RESPONSIVENESS
All Responses received by the stated deadline will first be reviewed by the Procurement Coordinator to ensure that the Responses appear to contain the information required in this competition document. Only Bid Responses that meet the requirements will be forwarded for further substantive review. Any Response that does not appear to contain all of the required information or any Bidder who does not meet the mandatory qualifications will be rejected as non-responsive and will be removed from further evaluation. However, the
RFQ 2025-55543 Mud Valves and Accessories Page 17 of 41
Procurement Coordinator has the right to waive minor informalities, and/or seek clarification if confused provided that neither alters the content of the Response. A bidder’s failure to provide requested clarification within five (5) business days may result in disqualification.
State Parks reserves the right to: (1) Waive any informality (State Parks reserves the right to determine the actual level of Bidders’ compliance with the requirements specified in this competition and to waive informalities in a bid). An informality is an immaterial variation from the exact requirements of the competition, having no effect or merely a minor or negligible effect on quality, quantity, or delivery of the supplies or performance of the services being procured.; (2) Reject any or all bids, or portions thereof; (3) Cancel the Competitive Solicitation and may re-solicit bids; and/or (4) Negotiate with the lowest responsive and responsible Bidder(s) (or Bidder with the most points) to determine if such bid can be improved. If, after a reasonable period of time, State Parks, in its sole judgement, cannot reach agreement on acceptable Contract terms with such bidder, State Parks may suspend negotiations and undertake negotiations with the next highest scored responsive, responsible bidder as determined by the evaluations.
6.4 BIDDER RESPONSIBILITY ANALYSIS
For responsive bids, State Parks must determine whether the bidder is a ‘responsible bidder.’ In determining bidder responsibility, State Parks must consider the following statutory elements:
a) The bidder’s ability, capacity, and skill to perform the contract or provide the service required;
b) The bidder’s character, integrity, reputation, judgment, experience, and efficiency;
c) Whether the bidder can perform the contract within the time specified;
d) The bidder’s performance quality pertaining to previous contracts or services;
e) The bidder’s compliance with laws relating to the contract or services;
f) Whether, within the three-year period immediately preceding the date of the
Competitive Solicitation, the bidder has been determined by a final and binding citation and notice of assessment issued by the Washington State Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW; and
g) Such other information as may be secured having a bearing on the decision to award the Contract.
See RCW 39.26.160(2)(a)-(g). In addition, State Parks may consider the following:
• Best Value Criteria:
a) Whether the bid satisfies the needs of the state as specified in the solicitation documents;
b) Whether the bid encourages diverse contractor participation;
c) Whether the bid provides competitive pricing, economies, and efficiencies;
d) Whether the bid considers human health and environmental impacts;
e) Whether the bid appropriately weighs cost and non-cost considerations; and
f) Life-cycle cost.
See RCW 39.26.160(3)(a)-(f).
• Financial Information: State Parks may request financial statements, credit ratings, references, record of past performance, clarification of bidder’s offer, on-site
RFQ 2025-55543 Mud Valves and Accessories Page 18 of 41 inspection of bidder's or subcontractor's facilities, or other information as necessary to determine bidder’s capacity to perform and the enforceability of bidder’s contractual commitments. Failure to respond to these requests may result in a bid being rejected as non-responsive.
• References: State Parks reserves the right to use references to confirm satisfactory customer service, performance, satisfaction with service/product, knowledge of products/service/industry and timeliness. Any negative or unsatisfactory reference can be reason for rejecting a bidder as non-responsible.
6.4.1 REJECTED BIDS/BIDDERS & REJECTION NOTIFICATION & REJECTION
RESPONSE
This Rejection Response process is not governed by Washington’s Administrative Procedures Act (APA), RCW 34.05, nor does it confer any additional rights above and beyond what the Bidder already enjoys as a taxpayer. The purpose of this process is to allow State Parks to correct evaluation process errors and problems before a contract is executed.
State Parks will perform a preliminary evaluation which is largely procedural. See Section
6.7.1 - Preliminary Evaluation (Procedural) and all of this section’s subparts.
If State Parks determines that a bid or Bidder must be rejected under 6.7.1 and/or subparts, State Parks will send a rejection notification to the email address provided by the Bidder in the Bidder’s Profile form (Appendix B). State Parks bears no responsibility for any issue or technological issue preventing actual receipt of the notification to the rejected Bidder.
Two Business-day Response Period: The Bidder may refute the rejection. The rejected Bidder must respond to the rejection within two (2) business-days following the day of rejection notification.
• The Bidder’s Rejection Response must be sent to procurement@parks.wa.gov.
• Subject line must include the bid’s identification number and “Rejection”. See the first page or footer for the bid’s identification number. (e.g., "RFQ # Rejection")
• The Bidder must explain how and why State Parks erred in rejecting the Bidder’s bid under Section 6.7.1 - Preliminary Evaluation (Procedural).
State Parks will consider the rejected Bidder’s response, and if in State Parks’ opinion, it determines error on our part, the bid will be moved forward to further evaluation. If State Parks determines it did not err, the bid will not be moved forward for evaluation.
The process detailed in this section does not supersede or displace the DEBRIEF process or PROTEST process. A Bidder may after the Announcement of Apparent Successful Bidder is announced, request a Debrief, and a Debrief is a prerequisite for a Protest. See Section 7.3 – Debriefing of Bidders and Section 7.4 – Protests for expanded details about the process and what State Parks will recognize as legitimate.
6.5 GENERAL EVALUATION PROVISIONS
The evaluation process is designed to award a contract to the Bidder with the best value based on the selected evaluation criteria.
Evaluations of subjective material will likely be conducted by the customer program requiring the goods/services or an evaluation team. State Parks has sole discretion over the selection of evaluators and will make such selections based on each potential evaluator’s availability, knowledge, skills, and experience with the subject matter. Evaluator(s) will independently grade and score or consensus score the Bidder’s material based on their own independent
RFQ 2025-55543 Mud Valves and Accessories Page 19 of 41 judgment, and in accordance with the format noted herein for each respective requirement.
Evaluator(s) will only evaluate the material contained in the Responses and will not incorporate outside material into their determinations. The evaluator(s) has sole discretion over his or her final scores.
Bidders should take every precaution to assure that all answers are clear, complete, and directly responsive to each specific requirement.
6.6 EVALUATION OF COMPLETION BY DATE
State Parks reserves the right to require that the Apparent Successful Bidder (ASB) provide within three (3) business days after request, satisfactory evidence of ability to have the services performed and completed by: not used. Failure to provide satisfactory evidence may be grounds for submittal rejection.
6.7 EVALUATION STEPS
6.7.1 Preliminary Evaluation (Procedural)
a) Did the bid response arrive by the due date (deadline) to the proper location? Pass/Fail.
b) Did the Bidder, on behalf of the Bidder’s Firm, appear to bind the company to the commitment of the competition (manifestation of assent)? Pass/Fail. Acceptable manifestations of assent may include:
• Is the bid signed by an individual (a person and NOT a group or team) electronic, with a wet-ink signature albeit provided as a PDF scan, photo, or other similar visual copy representation?
c) Did the Bidder appear to provide and complete the information requested? Pass/Fail.
d) Does the Bidder appear to accept the State Parks terms and conditions without reservation? Pass/Fail.
e) Does the Bidder, under penalty of perjury, certify it is not a Wage violator (see Certification
- Wage Theft Prevention)? Pass/Fail.
f) Does the Bidder, under penalty of perjury, certify it supports worker’s rights (see
Certification - Supporting Workers’ Rights)? Pass/Fail.
g) If submittals were required, were the submittals provided and do they appear to be complete so that the bid could be compared to other conforming bids? Pass/Fail.
h) If any bid is rejected at this stage, send a Rejection Letter to the Bidder’s email address provided by the Bidder in Appendix B – Bidder’s Profile. See also Section 6.4.1 – Rejected Bids/Bidders & Rejection Notification & Rejection Response. Allow the Rejection process to run its course and then for all remaining responsive bids, advance the bid(s) to Section
6.7.2 – Substantive Evaluation: Phase 1.
6.7.2 Substantive Evaluation: Phase 1
a) Preferences and penalties: Preferences and penalties that are required by law, rule, or competition document will be applied to bid pricing. Preference reduces the Bidder’s stated price by the amount of the preference and is an advantage to the Bidder. A penalty increases the Bidder’s stated price by the amount of the penalty and is a disadvantage to the Bidder. Preferences and penalties are applied to the pricing for evaluation purposes only but are not applied for purchasing purposes if awarded the contract.
• Determine Reciprocity under RCW 39.26.271, WAC 200-300-075, DES Reciprocity Map (list). Determine the business address from which the bid was submitted. Check https://app.leg.wa.gov/RCW/default.aspx?cite=39.26&full=true#39.26.271 https://apps.leg.wa.gov/wac/default.aspx?cite=200-300-075 https://www.naspo.org/reciprocity1 https://www.naspo.org/reciprocity1
RFQ 2025-55543 Mud Valves and Accessories Page 20 of 41 the DES Reciprocity Map (list) to determine, for evaluation purposes only, if the bid’s pricing must be increased or rejected.
• Determine Polychlorinated Biphenyls (PCB)
b) If submittals were required, were the submittals provided and were they materially complete so that the material aspects of the bid response can be compared to other conforming bids? Pass/Fail. If a points methodology is being used instead of a pass/fail methodology, then determine the points.
c) Determine the low bid; use subtotal value. If a points methodology is being used instead of low bid methodology, then determine the points.
d) References: If not waived by State Parks, do the references reflect good customer service and good product quality, and no meaningful apprehension from using this Firm in the future? Pass /Fail. If a points methodology is being used instead of a pass/fail methodology, waiver is not allowed, State Parks must determine the points.
e) Responsibility of the Bidder: In determining the responsibility of the Bidder, State Parks may also consider: RCW 39.26.160 Bid awards—Considerations—Requirements and criteria to be set forth—Negotiations—Use of enterprise vendor registration and bid notification system. If considered then Pass/Fail.
f) Upon determining the lowest priced responsive and responsible Bidder (or responsive and responsible Bidder with the most points), perform the Announcement of ASB UNLESS the Substantive Evaluation: PHASE 2 (optional) is used.
6.7.3 Substantive Evaluation: Phase 2 (Optional)
a) Following PHASE 1 if State Parks so chooses the lowest priced responsive and responsible Bidder (or responsive and responsible Bidder with the most points) may be required to appear in some form and/or present additional materials to validate to the State Parks that the services or items offered meets the State Parks’ needs and meets all other competition terms & conditions. If State Parks requests materials it deems necessary to validate the services or item offered, the materials must be provided within five (5) business days or face possible elimination. The Bidder WILL NOT be allowed to materially change its bid response and the examination will be limited to the validation of the item and/or services offered. If State Parks in its sole discretion determines that the Bidder’s bid does not meet the State Parks needs and/or other competition terms & conditions, the Bidder’s bid response will be rejected and the next lowest responsive and responsible (or responsive and responsible Bidder with the most points) bid response may be considered.
This process may repeat itself until an Apparent Successful Bidder (ASB) is determined or the competition is cancelled.
b) Upon determining the lowest priced responsive and responsible Bidder (or responsive and responsible Bidder with the most points), perform the Announcement of ASB.
6.8 SELECTION OF APPARENT SUCCESSFUL BIDDER
Note: The Bidder meeting all responsive criteria and having the lowest costs (or, highest final cumulative score) will be selected as the Apparent Successful Bidder (ASB).
State Parks will notify the Apparent Successful Bidder, and the non-successful Bidders, via email to the address provided in the Bidder’s Profile – Appendix B - Primary Contact Person for Questions/Contract Negotiations.
https://app.leg.wa.gov/RCW/default.aspx?cite=39.26.160
RFQ 2025-55543 Mud Valves and Accessories Page 21 of 41
7 ANNOUNCEMENT OF ASB, PUBLIC DISCLOSURE, DEBRIEF, AND PROTESTS
This section provides information about the announcement of the apparent successful bidder, public disclosure, and details the applicable requirements for complaints, debriefs, and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .