This is an Addendum to the Request for Proposal (RFP) issued by the Town of Thunderbolt, Georgia for Thunderbolt Elevated Storage Tank Improvements (RFP No. 32667.0000). The addendum extends the bid period and updates key project deadlines. Sealed bids will now be accepted until 2:00 PM on September 30th, 2025, at the Thunderbolt Town Hall located at 2821 River Drive, Thunderbolt, GA 31404. A Pre-Bid Conference has been scheduled for Tuesday, September 16th, 2025 at 2:00 PM at the same location, with the deadline for submitting written questions set for Friday, September 19th, 2025 at 5:00 PM. All questions regarding the bid documents should be directed to Engineer Megan Cook at Thomas & Hutton, located at 50 Park of Commerce Way, Savannah, GA 31405, or via email at cook.m@tandh.com.

The addendum clarifies liquidated damages provisions in the Agreement Form. The Town and Contractor acknowledge that time is essential to the project and agree that liquidated damages will be assessed at $1,000.00 per day for each day expiring after the specified time for Substantial Completion until the work is substantially complete. An additional $1,000.00 per day in liquidated damages applies if the Contractor fails to complete remaining work within the specified time for final completion and readiness for final payment. Bidders are required to acknowledge receipt of this addendum in the Bid Form (Document 00 41 43); failure to do so will render the proposal nonresponsive. All other aspects of the project remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Z:\32667\32667.0000\Documents\Construction\Bid\Addenda\Addendum 1.doc

THUNDERBOLT ELEVATED STORAGE TANK IMPROVEMENTS

RFP NO. 32667.0000

PREPARED FOR:

TOWN OF THUNDERBOLT

THOMAS & HUTTON PROJECT NO.

J–32667.0000

ADDENDUM NO. 1 August 22, 2025

PART I – GENERAL:

This Addendum has been issued on behalf of the Town of Thunderbolt. The following information should be considered by prospective bidders in preparation of their proposals and are hereby incorporated into the Proposal Documents. Bidders shall be responsible for acknowledging receipt of this addendum in the Bid Form, Document 00 41 43. Failure to do so will result in the proposal being considered nonresponsive.

PART II – CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS:

The Proposal Documents shall be changed in the following respect:

SECTION 00 11 16 – INVITATION TO BID

Section 00 11 16 – Invitation to Bid has been revised. See revisions below:

1. The bid period shall be extended. Under section 1, sealed bids for Thunderbolt Elevated

Storage Tank Improvements will be accepted at the Thunderbolt Town Hall, located at 2821

River Drive, Thunderbolt, GA 31404, until 2:00 PM, September 30th, 2025, at which time they will be opened publicly.

2. The Pre-Bid Conference Date and deadline for questions has been updated. Under section 6:

“A Pre–Bid Conference will be held on Tuesday, September 16th, 2025 at 2:00 PM at the

Thunderbolt Town Hall, located at 2821 River Drive, Thunderbolt, GA 31404. All prospective bidders are encouraged to attend. Last day for Questions to submit in writing shall be Friday, September 19th, 2025, at 5:00 PM. All questions about the meaning and intent of the bid documents must be submitted to the Engineer, Megan Cook with

Thomas & Hutton, at 50 Park of Commerce Way, Savannah, GA 31405 or cook.m@tandh.com.”

SECTION 00 21 13 – INSTRUCTIONS TO BIDDERS

Section 00 21 13 – Instructions to Bidders has been revised. See revisions below:

1. The Pre-Bid Conference Date has been updated. Under Article 6, the Pre-Bid Conference will be held on Tuesday, September 16th, 2025, at 2:00 PM.

ADDENDUM NO. 1 August 22, 2025

Z:\32667\32667.0000\Documents\Construction\Bid\Addenda\Addendum 1.doc

SECTION 00 43 13 – BID SECURITY FORM

Section 00 43 13 – Bid Security Form has been revised. See revisions below:

1. The bid period shall be extended. The Bid Due Date shall be 2:00 PM on September 30th, 2025.

SECTION 00 52 43 – AGREEMENT FORM

Section 00 52 43 – Agreement Form has been revised. See revisions below:

1. Liquidated damages has been revised for clarification. Under Article 3 – Contract Times, section 3.2:

“Liquidated Damages. OWNER and CONTRACTOR recognize time is of the essence for this

Agreement and OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1 above, plus any extensions thereof allowed in accordance with

Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving the actual loss suffered by OWNER if the Work is not substantially complete on time. Accordingly, instead of requiring any such proof, OWNER and

CONTRACTOR agree to liquidated damages for delay (but not as a penalty) the

CONTRACTOR shall pay OWNER One Thousand, and 00/100 dollars ($ 1,000.00) for each day expiring after the time specified in paragraph 3.1 for Substantial Completion until the Work is substantially complete. After Substantial completion, if CONTRACTOR shall neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper extension thereof granted by OWNER, CONTRACTOR, shall pay OWNER One Thousand and 00/100 dollars ($ 1,000.00) for each day expiring after the time specified in paragraph 3.1 for completion and readiness for final payment.”

All other aspects of the project remain unchanged.

THOMAS & HUTTON ENGINEERING CO.

Megan Cook, PE

Project Manager

End of ADDENDUM NO. 1

THOMAS & HUTTON ENGINEERING CO.

Megan Cook, PE

Project Manager