About this file

This is Addendum 01 to the bidding and contract documents for the MVSB1 Alterations project in Clinton, Iowa, issued by the Iowa Army National Guard with architectural services provided by Shive-Hattery, Inc. The addendum modifies the original bidding documents dated June 25, 2025, and establishes key project parameters including an estimated construction cost of $209,000. Bids are due by 1:00 PM Central Time on July 18, 2025, submitted through the State of Iowa IMPACS system at https://bidopportunities.iowa.gov in accordance with specification sections 00 21 00 and 00 11 00. A virtual link for bid opening is provided in the Advertisement for Bids. The project involves alterations to an existing building that may remain partially occupied during construction, requiring contractors to maintain accessible egress capabilities and secure the building after hours. The Owner will provide power, gas, and water but will not supply toilet, phone, or internet facilities. The Owner will move all building contents except existing caging, making means and methods for installation around the caging the contractor's responsibility.

The addendum specifies that no badges are required for site access, no fencing is required around the project area, and contractors must provide a six-person meeting table for construction progress meetings without requiring a job trailer. Contractors are responsible for providing weekly waste removal and Waste Disposal Reports per specification section 01 74 19, with salvaged item reviews conducted by the Owner. Interior enclosures must be constructed using framing and reinforced polyethylene sheet materials with sealed edges, and contractors must photograph existing conditions if permitted to use Owner facilities to ensure proper restoration of finishes, flooring, walls, paint, plumbing fixtures, stairs, lifts, and elevators upon project completion. The addendum replaces section 01 50 00 entirely and revises section 09 91 13 regarding exterior painting to specify hollow metal doors and frames only.

View the file

Other files

File Type Posted
1324645-event.pdf PDF
Issued for Bid Specifications.pdf PDF
1323392-event.pdf PDF
00 11 00 Advertisement for Bids.pdf PDF
00 41 00 Form of Bid.pdf PDF
Issued for Bid Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLINTON MVSB1 ALTERATION

CLINTON, IOWA

ADDENDUM 01

00 91 11 - 1

SECTION 00 9111

ADDENDUM NUMBER 01

PARTICULARS:

DATE: July 16, 2025

PROJECT: MVSB1 Alterations

PROJECT NUMBER: 2240006160

OWNER: Iowa Army National Guard

ARCHITECT: Shive-Hattery, Inc.

TO: PROSPECTIVE BIDDERS:

THIS ADDENDUM FORMS A PART OF THE BIDDING AND CONTRACT DOCUMENTS AND

MODIFIES THE BIDDING DOCUMENTS DATED 06-25-2025 WITH AMENDMENTS AND

ADDITIONS NOTED BELOW. THIS ADDENDUM SUPERSEDES AND SUPPLEMENTS ALL

PORTIONS OF THE ORIGINAL BIDDING AND CONTRACT DOCUMENTS WITH WHICH IT

CONFLICTS.

ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED IN THE BID

FORM. FAILURE TO DO SO MAY DISQUALIFY THE BIDDER.

GENERAL CLARIFICATIONS

1. Bids are due by 1:00 PM Central Time on July 18, 2025 and must be submitted via the State of Iowa IMPACS system at https://bidopportunities.iowa.gov, in accordance with the requirements outlined in specification section 00 21 00 – Instructions to Bidders, Article 5.1, and 00 11 00 – Advertisement for Bids. There is a virtual link to join the bid opening provided in 00 11 00 – Advertisement for Bids.

2. The estimated cost of construction is $209,000.

3. No badges are required for the Contractor and their subcontractors to access the construction site.

4. The Owner will provide power, gas and water. The Owner will not provide toilet, phone, or internet.

5. The Owner will move all contents from the building for the contractors to complete the work. The Owner will not be moving any of the existing caging. Means and methods for installation in and around the existing caging is the responsibility of the Contractor.

6. Contractor shall provide a 6-person meeting table in the project area for construction progress meetings. No trailer is required. See included revised 01 50 00 – Temporary Facilities and Controls.

7. The Contractor is not required to provide fencing around the project area. See included revised 01 50 00 – Temporary Facilities and Controls.

8. The Contractor shall provide weekly waste removal and Waste Disposal Reports in accordance with specification section 01 74 19 – Construction Waste Management and Disposal. All review of salvaged items (if any) will be by Owner.

ADDENDUM 01

00 91 11 - 2

CHANGES TO THE SPECIFICATIONS

01 50 00 – TEMPORARY FACILITIES AND CONTROLS

9. REPLACE section in its entirety.

09 91 13 – EXTERIOR PAINTING

10. REVISE subparagraph 1.1.C Scope to read “Scope: Exterior hollow metal doors and frames.”

ATTACHMENTS: Specification 01 50 00

PREPARED BY: SHIVE-HATTERY, INC.

END OF ADDENDUM NUMBER 01

I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed Professional Engineer under the laws of the State of Iowa.

7/16/2025

Signature Date

Printed or Typed Name Brent Strauch

License Number 24125

My License Renewal Date is: 12-31-2026

Pages, Sheets, or Divisions covered by this Seal: Addendum 01

TEMPORARY FACILITIES AND CONTROLS

01 50 00 - 1

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Temporary utilities.

B. Temporary sanitary facilities.

C. Temporary Controls: Barriers, enclosures, and fencing.

D. Security requirements.

E. Waste removal facilities and services.

F. Field offices.

1.2 TEMPORARY UTILITIES

A. Owner will provide the following:

1. Power

2. Gas

3. Water

B. Owner will not provide the following:

1. Toilet

2. Phone

3. Internet

1.3 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

C. If contractor is permitted to use owner facilities for restrooms, staging, or other uses, existing conditions must be photographed, and damage must be repaired after construction is complete. This includes but is not limited to general finishes, flooring, walls construction, paint, plumbing fixtures, stairs, lifts and elevators.

1.4 BARRIERS

A. Provide protection for plants designated to remain. Replace damaged plants.

B. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

C. This project includes renovation of the existing main entrance to the building. The building maybe be occupied, or partially occupied by staff or students during construction. The contractor must maintain accessible egress capabilities through areas of construction to the public right of way or coordinate temporary routing with owner through alternate routes. Means and methods of providing route are the responsibility of the contractor.

1.5 FENCING

A. No fencing required.

IOWA ARMY NATIONAL GUARD

Clinton MVSB1 Alteration

TEMPORARY FACILITIES AND CONTROLS

01 50 00 - 2

1.6 INTERIOR ENCLOSURES

A. Construction: Framing and reinforced polyethylene sheet materials with closed joints and sealed edges at intersections with existing surfaces.

1.7 SECURITY

A. This project includes renovation of the existing main entrance to the building. Entry to the building must be secure after hours. The means and methods of securing temporary construction, in addition to accessible egress pathway to the right of way are the responsibility of the contractor.

1.8 WASTE REMOVAL

A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition on a daily basis.

B. Provide containers with lids. Remove trash from site weekly.

C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

D. Smoking is not allowed on site.

1.9 FIELD OFFICES

A. No field office is required.

B. Provide a table and chairs to accommodate 6 persons in the construction site for Project meetings.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION