About this file

This document is a gymnasium floor refinishing schedule for multiple recreation centers, created by the City of St. Petersburg, Florida, covering the years 2024-2028. The schedule outlines a maintenance plan for gym floor refinishing across various facilities, including Campbell, Childs, Frank Pierce, Gladden, JW Cate, Lake Vista, Roberts, Walter Fuller, TJJ, Willis Johns, and Shore Acres recreation centers. Due to COVID-19 disruptions in the previous maintenance cycle, the city plans to complete refinishing at 6 locations in 2024, with 2 locations scheduled for 2025 and potentially 2 locations in 2026, depending on available funding.

The scheduling document indicates a standard practice of refinishing 3 courts every 3 years, which was interrupted by the pandemic. The plan now reflects a catch-up approach, with some facilities marked for multiple years of contractor involvement. The document suggests flexibility in future years' scheduling, contingent on funding availability. Each facility is marked with a "*Contractor" notation, implying that professional contractors will be engaged to perform the floor refinishing work. The schedule provides a clear visual roadmap for maintenance planning, allowing the city to track and manage gymnasium floor refinishing across its recreation center network.

View the file

Other files

File Type Posted
Recreation_Center_Gymnasium_Floors_Refinishing.pdf PDF
Gym_floors-Bid_Bond_form.docx DOCX document
Agreement-On_Going_As-Needed_Service.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Facility 2024 2025 2026 2027 2028 Campbell *Contractor *Contractor Childs *Contractor *Contractor Frank Pierce *Contractor Gladden *Contractor JW Cate *Contractor Lake Vista *Contractor Roberts *Contractor *Contractor Walter Fuller TJJ *Contractor (double) Willis Johns *Contractor *Contractor Shore Acres *Contractor

Gym Floor Refinishing Schedule / History

Normally complete 3 courts every 3 years but due to COVID schedule was disrupted. We need to complete 6 locations in 2024.

2025- 2 locations (1 location is a double court). Future years will depend on funding but will likely have 2 locations in 2026.

Sheet1

File details come from the government source that posted it. Updated .