This document is a Pre-bid Virtual Tour Guide for the 2024 Lehigh Road Phase IX Abandoned Mine Land (AML) Project in North Dakota, issued by the North Dakota Public Service Commission. The project involves drilling and grouting activities to reclaim an abandoned underground lignite coal mine site near Dickinson, North Dakota. The bid opening is scheduled for April 9, 2024, at 10:00 A.M. Central Time. The performance period is from July 15 to September 27, 2024. The project requires a pre-construction workshop, utility locates, and continuous monitoring of ground movement during pumping operations. The grout contractor is responsible for providing railroad ballast, removing excess grout and casings, and completing daily drill logs and grout injection forms.

The material testing contractor will be responsible for performing concrete tests, providing storage for grout samples, and conducting structural surveys. Bills of lading for all aggregates, fly ash, and cement must be provided to the material testing contractor. The material testing contractor representative will be required to be on-site at all times during grouting operations and record ready-mix truck arrival and departure times.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-bid Virtual Tour Guide

2024 Lehigh Road Phase IX AML Project

The Pre-bid, Virtual Tour replaces the mandatory pre-bid, onsite meeting that was required in the past for AML drilling and grouting projects. This document does not replace or take precedence over the Invitation for Bid (IFB) or any other project documents.

The 2024 Lehigh Road Phase IX AML Project IFB can be found by searching the State Procurement Office (SPO) website at:

https://apps.nd.gov/csd/spo/services/bidder/main.htm.

Bidding Information (Section 1 of IFB)

1. Bid opening: Tuesday, April 9, 2024, at 10:00 A.M., Central Time (CT). Read the IFB completely, bidder’s instructions are included. Late bids will not be accepted.

2. Include 5% bid bond or cashier’s check with bid package.

3. Deadline for questions is March 27, 2024, at 5:00 P.M., CT. Questions must be submitted in writing. Emailed questions are accepted at bjob@nd.gov

4. All attached forms must be completed with the bid.

2024 IFB Points to Highlight

1. Performance Period: July 15 to September 27, 2024.

2. All Quantities are Estimated: No allowance will be made for any increased expense, loss of expected reimbursement, or loss of anticipated profits suffered or claimed by GROUT CONTRACTOR resulting from either field conditions or unbalanced bid prices or any other cause.

3. Pre-Construction Requirements:

a. Pre-construction workshop: GROUT CONTRACTOR shall plan and conduct an informational pre-construction workshop at the site at least 3 business days prior to beginning work.

b. Aggregate source(s) with NDDOT Material Source Certificate(s) of Approval and initial gradation.

c. Schedule of Construction: start and completion dates for mobilization, drilling, grouting; list of all equipment needed to complete the job; method of grout formulation and delivery; safety plans.

d. Utility Locates: The 2024 Lehigh Road Phase IX AML Project site will require both private and public utility locates.

Once these items are completed and approved, a Notice to Proceed (NTP) will be issued. If work cannot begin as specified on the NTP, GROUT CONTRACTOR shall provide a written explanation of the delay and request an alternate firm start date. The Performance Period will remain unchanged.

4. Fugitive Dust Control

5. Payments - Invoices may be submitted no later than the 1st and 15th of each month for payment on the 10th & 25th of the month. Payments are only made on the 10 and 25th. Submit signed invoices to the Commission’s Project Manager.

6. Traffic Control

7. Clean-Up Provisions

Work Plans: Drilling and Pumping

1. The drilling and grout pumping sequences will be determined by the Commission’s Project Manager. Please see the preliminary drilling paths and existing cased holes to be pumped on the project maps (pages 4-5). Drilling must be available during grout pumping.

2. Drilling will be needed between railroad tracks. The GROUT CONTRACTOR is responsible for providing railroad ballast to mobilize equipment over and onto railroad tracks.

3. Excess grout must be cleaned up daily and hauled off-site as soon as possible.

Once a hole is filled the casing must be removed immediately.

4. All casing used as a conduit for grout must be removed immediately upon refusal or completion of pumping that hole. PVC casing must be removed as soon as possible on holes filled by adjacent pumping, but not more than 24 hours after the hole is completed.

5. The North Dakota Public Service Commission will be performing a before and after certified railroad inspection of the track adjacent to drilling and grouting construction. The Grout Contractor must use a laser level and provide skilled personnel to monitor ground movement continuously during pumping operations near all paved roads, railroads and within 250 feet of structures. Work must be halted if movement is detected.

Weather

1. Weather delays must be documented by GROUT CONTRACTOR and reviewed by Commission’s Project Manager.

2. The start date is July 15, 2024. Contractor is expected to start soon after the start date.

Documentation

1. The GROUT CONTRACTOR is expected to complete a drill log form for every hole and to submit drill log forms to the Commission’s Project Manager daily. The required form is in Section 6 Attachments of the IFB.

2. Provide grout injection forms to Commission’s Project Manager daily. The required form is in Section 6 Attachments of the IFB.

Material Testing Cooperation

1. It is the GROUT CONTRACTOR’S responsibility to ensure the Material Testing Contractor is given timely notification regarding pumping activities. The GROUT CONTRACTOR must give the Material Tester a fixed firm start date for grout pumping at least 3 workdays prior to pumping. The Material Tester will be required to be available on that date and for any pumping activities until the end of the project during the standard work week. During grouting, the GROUT CONTRACTOR must notify the material tester of any stoppages in pumping as specified in the IFB.

2. Bills of lading for all aggregate, flyash, and cement shall be given to the Material Testing Contractor.

Material Testing Contractor

1. Material Testing Contractor will be responsible for performing 50 plastic concrete tests, 50 sets of cylinder strength testing, and three fine aggregate gradations.

2. Material Testing Contractor will be responsible for providing sufficient storage for grout samples. This initial curing of concrete must comply with ASTM C31 for standard curing and transportation.

3. Materials Testing Contractor representative will be required to be on site at all times during grouting operations. They will be required to collect all concrete tickets and record ready-mix truck arrival and departure times. These tickets will be given to the Commission’s Project Manager or designated person daily.

4. Material Testing Contractor will be responsible for performing eight (8) structural surveys. These surveys will take place on four (4) separate buildings.

2024 Lehigh Road Phase IX AML Project information and photographs are included in this document for CONTRACTOR reference. Some of the 2024 project work is a continuation of the 2023 Exploratory Drilling project.

Overall Project Map

Industrial Work Area Map

Figure 1 – Lehigh Road, Stark County Right of Way

Figure 2 – Lehigh Road, Stark County Right of Way

Figure 3 – Lehigh Road and Lehigh Drive Intersection, Stark County Right of Way

Figure 4 – Lehigh Road and Lehigh Drive Intersection, Stark County Right of Way

Figure 5 – Lehigh Road, Stark County Right of Way

Figure 6 – Gascoyne Materials Handling & Recycling Storage Buildings

Figure 7 – Gascoyne Materials Handling & Recycling Storage Buildings

Figure 8 – Gascoyne Materials Handling & Recycling Rail Spur

Figure 9 – Gascoyne Materials Handling & Recycling Rail Spur

Figure 10 – Lehigh Drive, Stark County Right of Way

Figure 11 – 38th St SW, Stark County Right of Way