2024_JAC_SOW_3_Stage_Septic_Tanks_Revised.pdf

PDF 178 KB Posted

Attached to
WY-JACKSON NFH-SEPTIC SYSTEM Federal contract opportunity
Solicitation number
140FC125R0006
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This Statement of Work (SOW) details a federal contract for a 2,000-gallon, 3-stage concrete septic tank system for the Jackson National Fish Hatchery (NFH) in Wyoming. The project requires a contractor to purchase, transport, and install a complete septic system for the Volunteer Complex, including tanks, distribution box, effluent filter, alarm, low head pump station, and risers, while complying with Teton County regulations. The contractor must be appropriately licensed and certified, with excavation and upstream work to be performed by hatchery staff.

The project is set to be completed prior to June 1, 2025, with work performed at 1500 Fish Hatchery Road in Jackson, WY. The solicitation (140FC125R0006) is a 100% Small Business Set-Aside under NAICS code 238910, using a Lowest-Price Technically Acceptable (LPTA) selection process. Proposals must be submitted via email to john_ferrall@fws.gov by April 8, 2025, at 5:00 pm EDT, with construction permitted to start May 10, 2025, and completed by May 30, 2025. The primary technical contact is Sean Henderson, Fish Biologist at the Jackson NFH.

View the file

Other files for this federal contract opportunity

Other files attached to WY-JACKSON NFH-SEPTIC SYSTEM, newest first.
File Type Posted
Sol_140FC125R0006_Amd_0002.pdf PDF
Sol_140FC125R0006_Amd_0001.pdf PDF
SWF2024-0054__Issued_Permit_Package_.pdf PDF
Sol_140FC125R0006.pdf PDF
Jackson_NFH_Septic_System_Replacement_Plan_Set_Stamped_.pdf PDF
GDN_WY20250017_03-14-2025_Building__Teton_County.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (2024 11 1)

3-Stage Concrete Septic Tank

1. General:

1.1 Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001 9805.

2000 gallon, 3-Stage Concrete Septic Tank(s) System.

1.2 Purpose is to provide septic service to the Volunteer Complex at the Jackson NFH to include the RV pads and the volunteer bunkhouse.

1.3 The contractor must be appropriately licensed and certified for the construction of the concrete tank.

1.4 The contractor, or sub-contractor, whomever is transporting the concrete tank, must be appropriately licensed and certified to transport in the states that the transport will be conducted.

1.5 The contractor must follow all associated regulations and laws including: Federal, State, County, and municipal.

2. Place of Performance and Period of Performance

2.1 Work is to be performed at Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001-9805.

2.2 This project needs to be completed prior to June 1, 2025, to accommodate summer volunteers.

2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.

2.4 Non duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Martin Luther King Jr. Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day).

3. Scope

3.1 All project excavation requiring heavy equipment will be done by hatchery staff.

3.2 All work upstream of tank inlet including main line, service connections, and cleanouts will be installed by hatchery staff.

3.3 Contractor is responsible for purchase and install of septic tank(s) and all accompanying parts/ infrastructure within and downstream of tank(s) including concrete distribution box, effluent filter w/ float bracket, alarm, complete low head pump station, risers, etc. Must comply with provided design and Teton County regulations.

3.4 Tank inlet must fit 6 inch diameter main service line.

3.5 Contractor or subcontractor will transport septic tank and accessories to Jackson NFH.

3.6 Contractor or subcontractor will off-load and place septic tank at provided, excavated location.

3.7 Contractor or subcontractor will wire/ connect alarm system, pump and any other electrical components required to operate septic system.

4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line item detail on the PR is recommended)

4.1 The contractor is to provide up to 2 top seam concrete tanks with a minimum combined volume of 2000 gallon. System must be top seam, 3-stage septic tank(s) with all of the materials, penetrations, and equipment to make it legally, fully operational.

4.2 The contractor shall provide all materials and equipment required.

5. Data Management Plan (DMP)

5.1 None.

6. Government-Furnished Equipment (GFE) / Government-Furnished Information

(GFI)

6.1 Jackson NFH will provide restrooms, electricity, and water for the contractor to using while the contracted work is being completed.

6.2 Identify any limitations. N/A

7. Evaluation and Acceptance

7.1 The contractor will be evaluated as detailed herein. Government acceptance is contingent upon designated U.S. Fish and Wildlife Service representative(s) determining the work to be acceptable and in good working order.

8. Quality Control/Quality Assurance:

8.1 For commercial supplies reference clauses for inspection and acceptance. Where appropriate, QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.

8.2 Identify and detail measures for assessing quality control and acceptance; each requirement is unique and a table format is visually friendly and may be desirable.

9. Technical Coordinator:

9.1 Primary individual responsible for the final product or service.

Sean Henderson Fish Biologist 1500 Fish Hatchery Road Jackson, WY 83001-9805 Office: 307-733-2510 Cell: 307-690-8242 sean_henderson@fws.gov

9.2 Secondary individual responsible for the final product or service.

Kristopher “Kris” Johnson Facility Management Coordinator (FMC) Asset Management Coordinator (AMC) U.S. Fish and Wildlife Service Fish and Aquatic Conservation (FAC) 1380 South 2350 West Vernal, UT 84078 Cell: 435-299-5150 Office: 435-789-0351 ext. 16 kristopher_b_johnson@fws.gov mailto:sean_henderson@fws.gov mailto:kristopher_b_johnson@fws.gov

STATEMENT OF WORK (2024 11 1)
1. General:
2. Place of Performance and Period of Performance
2.1 Work is to be performed at Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001-9805.
2.2 This project needs to be completed prior to June 1, 2025, to accommodate summer volunteers.
2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Non duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Martin Luther King Jr. Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas ...
3. Scope
3.1 All project excavation requiring heavy equipment will be done by hatchery staff.
3.2 All work upstream of tank inlet including main line, service connections, and cleanouts will be installed by hatchery staff.
3.3 Contractor is responsible for purchase and install of septic tank(s) and all accompanying parts/ infrastructure within and downstream of tank(s) including concrete distribution box, effluent filter w/ float bracket, alarm, complete low head pump s...
4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line item detail on the PR is recommended)