2024.02.12 Tech Rebid Specifications.pdf

PDF 6 MB Posted

Attached to
KRESA CTE Technology Bid Package Project #214175
Solicitation number
RFP - KRES - 240000001240
Issued by
Kalamazoo County, Pontiac City, Michigan

About this file

This document contains the contract specifications for the Career Connect Campus Technology Bid Package Project No. 214175 for the Kalamazoo Regional Educational Service Agency (KRESA). The project involves all low voltage systems for the new Career and Technical Education Center, including audio/video, cabling, clocks, electronic access control, electronic surveillance, infrastructure equipment, wireless access points, switches, UPS, patch cables, distributed antenna system, and paging. Bids are due on February 27, 2024 at 4:00 PM EST to the KRESA office in Portage, MI. A pre-bid meeting will be held virtually on February 14, 2024 at 3:30 PM EST. The contract form will be the AIA A101 Owner/Contractor Agreement, with a stipulated sum payment. Contractors must provide a 5% bid bond, and the awarded contractor will need to provide a 100% performance and payment bond. The contract completion date is to be determined but the Contractor agrees that time is of the essence. Pricing terms include allowances, unit prices, and liquidated damages, and the Owner reserves the right to accept or reject any alternate proposals.

View the file

Other files

File Type Posted
2024.02.22 Addendum 2.pdf PDF
2024.02.20 Addendum 1.pdf PDF
2024.02.12 Tech Rebid Specifications (1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS

AND

SPECIFICATIONS

FOR THE

KALAMAZOO REGIONAL

EDUCATIONAL SERVICE

AGENCY

Career Connect Campus Technology Bid Package

February 12, 2024

Kalamazoo Regional Educational Service Agency Wightman

Career Connect Campus - Technology Bid Package 2/12/2024

Project No. 214175

TABLE OF CONTENTS 00 00 01 - 1

00 00 00 PROCUREMENT AND CONTRACT REQUIREMENTS

00 01 01 PROJECT TITLE PAGE

00 11 13 ADVERTISEMENT FOR BIDS

00 21 13 INSTRUCTIONS TO BIDDERS

00 22 13 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

00 25 13 PRE-BID MEETINGS

00 26 00 PROCUREMENT SUBSTITUTION PROCEDURES

CSI SUBSTITUTION REQUEST DURING BIDDING

00 31 13 PRELIMINARY SCHEDULES

00 41 13 BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)

00 43 13 BID SECURITY FORMS

00 43 23 ALTERNATES FORM

00 43 24 FAMILIAL DISCLOSURE STATEMENT

00 43 25 IRAN AFFIDAVIT OF COMPLIANCE

00 43 93 BID SUBMITTAL CHECKLIST

00 60 00 PROJECT FORMS

A101-2017 OWNER/ CONTRACTOR AGREEMENT

A101-2017 EXHIBIT A

A201-2017 GENERAL CONDITIONS

A701-1997 INSTRUCTIONS TO BIDDERS

G702 APPLICATION AND CERTIFICATE FOR PAYMENT

G703 SCHEDULE OF VALUES

LIST OF SUBCONTRACTORS AND SUPPLIERS

01 00 00 GENERAL REQUIREMENTS

01 21 00 ALLOWANCES

01 22 00 UNIT PRICES

01 25 00 SUBSTITUTION PROCEDURES

CSI SUBSTITUTION REQUEST AFTER BIDDING

27 00 00 COMMUNICATIONS

27 05 00 BASIC COMMUNICATIONS SYSTEMS REQUIREMENTS

27 05 03 THROUGH PENETRATION FIRE STOPPING

27 05 26 COMMUNICATIONS BONDING

27 05 28 INTERIOR COMMUNICATION PATHWAYS

27 05 43 EXTERIOR COMMUNICATION PATHWAYS

27 05 53 IDENTIFICATION AND ADMINISTRATION

27 11 00 COMMUNICATION EQUIPMENT ROOMS (CER)

27 13 00 BACKBONE CABLING REQUIREMENTS

27 15 00 HORIZONTAL CABLING REQUIREMENTS

27 17 10 TESTING

27 17 20 STRUCTURED CABLING SYSTEM WARRANTY

27 41 00 PROFESSIONAL AUDIO_VIDEO SYSTEM

27 51 13 PAGING SYSTEMS

28 00 00 ELECTRONIC SAFETY AND SECURITY

TABLE OF CONTENTS 00 00 01 - 2

28 05 00 BASIC ELECTRONIC SAFETY AND SECURITY SYSTEM

REQUIREMENTS

28 05 03 THROUGH PENETRATION FIRE STOPPING

28 05 37 DISTRIBUTED ANTENNA SYSTEM (DAS) FOR PUBLIC SAFETY

NETWORKS

28 13 00 ELECTRONIC ACCESS CONTROLS

28 23 00 VIDEO SURVEILLANCE

28 26 05 RESCUE ASSISTANCE COMMUNICATION

END OF TABLE OF CONTENTS

PROJECT TITLE PAGE 00 01 01 - 1

DOCUMENT 00 01 01 - PROJECT TITLE PAGE

1.1 PROJECT MANUAL

A. Career & Technical Education Center – Technology Bid Package. (Project No. 214175)

Career Connect Campus 3500 Vanrick Drive Kalamazoo, MI 49001

B. Owner:

Kalamazoo RESA 1819 East Milham Road Portage, MI 49002

C. Architect:

Wightman Associates, Inc.

433 East Ransom Street Kalamazoo, MI 49007 Tel: 269-927-0100 www.gowightman.com

D. Issued: February 12, 2024

E. Copyright (2023, Wightman & Associates). All rights reserved.

END OF DOCUMENT 00 01 01

http://www.gowightman.com/

ADVERTISEMENT FOR BIDS 00 11 13 - 1

DOCUMENT 00 11 13 - ADVERTISEMENT FOR BIDS

1.1 PROJECT INFORMATION

A. Notice to Bidders: Qualified bidders may submit bids for the project as described in this Document. Submit bids according to the Instructions to Bidders.

B. Project Identification: Career Connect Campus – Technology Bid Package

Project Location: Career Connect Campus 3500 Vanrick Drive

Kalamazoo, Michigan 49001

C. Owner: Kalamazoo Regional Educational Service Agency 1819 East Milham Road Portage, Michigan 49002

D. Architect: Wightman Associates, Inc.

433 East Ransom Street Kalamazoo, Michigan 49007 Web Site: www.gowightman.com

E. Project Description: All low voltage systems shown in the project documents including audio/video, cabling, clocks, electronic access control, electronic surveillance, infrastructure equipment, wireless access points, switches, UPSs, patch cables, DAS, and paging for the entire building of the new Career and Technical Education Center Project. Note: Fire alarm, in-wall pathways and floor penetrations are by others and not included in this bid package.

F. Construction Contract: Bids will be received for the following Work:

1. Bids shall be received from one prime contractor for all work as outlined in the Specifications and Construction Drawings, see project description above.

2. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over the construction of the project shall apply to the project throughout.

3. Contractors shall note that the project is subject to the Common Construction Wage Act (effective July 1, 2015) for record-keeping, and all terms of this Act shall be followed in their entirety.

4. The contract form for the project will be AIA Document A101.

5. Contract will be made to the responsive, responsible bidder awarded by the

Owner.

6. Kalamazoo Regional Educational Service Agency is tax-exempt. Contractors are responsible for appropriate sales/use tax in accordance with the State of Michigan Department of Treasury for construction projects, i.e. flat panels are exempt, in-wall cabling is not.

http://www.gowightman.com/

ADVERTISEMENT FOR BIDS 00 11 13 - 2

1.2 BID SUBMITTAL AND OPENING

A. Owner will receive sealed lump sum bids until the bid time and date at the location given below. Owner will consider bids prepared in compliance with the Instructions to Bidders issued by Owner, and delivered as follows:

1. Bid Date: February 27, 2024

2. Bid Time: 4:00 p.m. Eastern Standard Time.

3. Location: Kalamazoo RESA

1819 East Milham Road Portage, MI 49001

B. Bids will thereafter be publicly opened and read aloud.

C. Bids shall be submitted on the forms provided with all blanks populated. Bid form and other documents required to be submitted with the bid shall be enclosed in a sealed envelope with the Bidder’s name, addressed to:

Kalamazoo Regional Educational Service Agency, Attention: Career Connect Center - Technology Bid Package.

D. Bids received after the designated time for closing will be returned unopened.

1.3 BID SECURITY

A. Bid security shall be submitted with each bid in the amount of five (5) percent of the bid amount.

B. No bids may be withdrawn for a period of 60 days after the opening of bids. The owner reserves the right to reject any and all bids and to waive informalities and irregularities.

1.4 PRE-BID MEETING

A. Pre-bid Meeting: See Document 00 25 13 "Pre-bid Meetings."

B. Pre-bid Meeting: A pre-bid meeting for all bidders will be held virtually 3:30 p.m.

Eastern Standard Time, Wednesday, February 14, 2024. Prospective prime bidders are requested to attend. Meeting attendance by Teams, Meeting ID: 242 291 356 128 Passcode: 3zmfGv

1.5 DOCUMENTS

A. Online Procurement and Contracting Documents:

1. State of Michigan Sigma:

https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

2. Wightman Bidding Website: https://bids.gowightman.com/ https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService https://bids.gowightman.com/

ADVERTISEMENT FOR BIDS 00 11 13 - 3

1.6 TIME OF COMPLETION

A. Successful bidder shall begin the Work on receipt of the Notice to Proceed and shall complete the Work within the Contract Time.

1.7 BIDDER'S QUALIFICATIONS

A. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the Work.

B. A 100% Performance Bond and a separate Labor and Material Payment Bond, and Insurance in a form acceptable to the Owner will be required of the awarded bidder.

C. Each bid proposal shall include all labor, material, and services necessary to complete the project in strict accordance with the contract documents as prepared and on file in the office of Wightman Associates, Inc. The Owner reserves the right to reject any or all bids.

D. Each bidder is responsible for reading and being thoroughly familiar with the Contract Documents and Specifications. Failure by omission of any Bidder to do any of the foregoing shall not relieve the Bidder from any obligation with respect to their bid.

1.8 NOTIFICATION

A. This Advertisement for Bids document is issued by order of the Kalamazoo Regional Educational Service Agency.

END OF DOCUMENT 00 11 13

INSTRUCTIONS TO BIDDERS 00 21 13 - 1

DOCUMENT 00 21 13 - INSTRUCTIONS TO BIDDERS

1.1 INSTRUCTIONS TO BIDDERS

A. AIA Document A701, "Instructions to Bidders," is hereby incorporated into the Procurement and Contracting Requirements by reference.

1. A copy of AIA Document A701, "Instructions to Bidders," is bound in this Project Manual.

END OF DOCUMENT 00 21 13

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 00 22 13 - 1

DOCUMENT 00 22 13 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

1.1 INSTRUCTIONS TO BIDDERS

A. Instructions to Bidders for Project consist of the following:

1. AIA Document A701, "Instructions to Bidders," a copy of which is bound in this Project Manual.

2. The following Supplementary Instructions to Bidders that modify and add to the requirements of the Instructions to Bidders.

1.2 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS, GENERAL

A. The following supplements modify AIA Document A701, "Instructions to Bidders."

Where a portion of the Instructions to Bidders is modified or deleted by these Supplementary Instructions to Bidders, unaltered portions of the Instructions to Bidders shall remain in effect.

B. REPRESENTATIONS

C. Revise Section 2.1.3 to strike, “The Bidder has visited the site, become familiar . . .”

D. Add Section 2.1.3.1:

1. 2.1.3.1 - The Bidder has investigated all required fees, permits, and regulatory requirements of authorities having jurisdiction and has properly included in the submitted bid the cost of such fees, permits, and requirements not otherwise indicated as provided by Owner.

2. State of Michigan.

E. Add Section 2.1.5:

1. 2.1.6 - The Bidder has incorporated into the Bid adequate sums for work performed by subcontractors whose qualifications meet those indicated in the Procurement and Contracting Documents.

1.3 ARTICLE 3 - BIDDING DOCUMENTS

A. Revise Section 3.1 Copies to strike, “. . .in the number and for the deposit sum, if any, stated therein. The deposit will be refunded to Bidders who submit a bona fide Bid and return the Bidding Documents in good condition within ten days after receipt of Bids.

The cost of replacement of missing or damaged documents will be deducted from the deposit. A Bidder receiving a Contract award may retain the Bidding Documents and the Bidder’s deposit will be refunded.

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS 00 22 13 - 2

B. 3.2 - Interpretation or Correction of Procurement and Contracting Documents:

1. Revise Section 3.2.2 to read “. . .shall reach the Architect at least four business days prior to the date for receipt of Bids.”

2. Revise Section 3.3.2 to read “. . .has been received by the Architect at least five business days prior to the receipt of Bids.”

3. Revise Section 3.4.3 “will be issued no later than four calendar days prior to the date for receipt of Bids. . . “

1.4 ARTICLE 4 - BIDDING PROCEDURES

A. 4.1 - Preparation of Bids:

1. Add Section 4.1.1.1:

2. Add Section 4.1.8:

a. 4.1.8 - Bids shall include applicable sales and use taxes.

1.5 ARTICLE 7 - PERFORMANCE BOND AND PAYMENT BOND

A. 7.1 - Bond Requirements:

1. Revise Section 7.1.1 to strike, “If stipulated in the Bidding Documents, the . . .” “

1.6 ARTICLE 9 - EXECUTION OF THE CONTRACT

A. Add Article 9:

1. 9.1.1 - Subsequent to the Notice of Intent to Award, and within 10 days after the prescribed Form of Agreement is presented to the Awardee for signature, the Awardee shall execute and deliver the Agreement to Owner through Architect, in such number of counterparts as Owner may require.

2. 9.1.2 - Owner may deem as a default the failure of the Awardee to execute the Contract and to supply the required bonds when the Agreement is presented for signature within the 15 days.

3. 9.1.4 - In the event of a default, Owner may declare the amount of the Bid security forfeited and elect to either award the Contract to the next responsible bidder or re-advertise for bids.

END OF DOCUMENT 00 22 13

PREBID MEETINGS 00 25 13 - 1

DOCUMENT 00 25 13 – PRE-BID MEETINGS

1.1 PRE-BID MEETING

A. Owner and Architect will conduct a Pre-bid meeting as indicated below:

1. Meeting Date: February 14, 2024

2. Meeting Time: 3:30 p.m. EST.

3. Location: Virtually via Microsoft Teams at https://teams.microsoft.com/l/meetup-join/19%3ameeting_YmM5MzI3YmEtNzEzZC00MzQ1LTlmYmYtNDYyYjJiYjQzY 2Iz%40thread.v2/0?context=%7b%22Tid%22%3a%22ef1960ce-394f-420e-92c0- 55d423f8150a%22%2c%22Oid%22%3a%2282bca742-fc70-4d95-8d83- 42a09e82001f%22%7d

a. Meeting ID: 242 291 356 128

b. Passcode: 3zmfGv

B. Attendance:

1. Prime Bidders: Attendance at Pre-Bid meeting is recommended.

C. Bidder Questions:

1. Submit written questions to be addressed at the Pre-Bid to Stefany Holland at sholland@gowightman.com or Courtney James at cjames@gowightman.com

2. Questions following the meeting shall be submitted to Stefany Holland at sholland@gowightman.com or Courtney James at cjames@gowightman.com

D. Agenda: Pre-Bid meeting agenda will include a review of topics that may affect the proper preparation and submittal of bids, including the following:

1. Procurement and Contracting Requirements:

a. Advertisement for Bids.

b. Instructions to Bidders.

c. Bidder Qualifications.

d. Bonding.

e. Insurance.

f. Bid Security.

g. Bid Form and Attachments.

h. Bid Submittal Requirements.

i. Bid Submittal Checklist.

j. Notice of Award.

2. Communication during Bidding Period:

a. Obtaining documents.

b. Bidder's Requests for Information.

c. Bidder's Substitution Request/Prior Approval Request.

d. Addenda.

mailto:sholland@gowightman.com mailto:cjames@gowightman.com mailto:sholland@gowightman.com mailto:cjames@gowightman.com

PREBID MEETINGS 00 25 13 - 2

3. Contracting Requirements:

a. Agreement.

b. The General Conditions.

c. The Supplementary Conditions.

d. Other Owner requirements.

4. Construction Documents:

a. Scopes of Work.

b. Variations from originally issued bid package.

c. Temporary Facilities.

d. Use of Site.

e. Work Restrictions.

f. Alternates, Allowances, and Unit Prices.

g. Substitutions following award.

5. Separate Contracts:

a. Work by Owner.

b. Work of Other Contracts.

6. Schedule:

a. Project Schedule.

b. Contract Time.

c. Bidder Questions.

7. Post-Meeting Addendum.

END OF DOCUMENT 00 25 13

PROCUREMENT SUBSTITUTION PROCEDURES 00 26 00 - 1

DOCUMENT 00 26 00 - PROCUREMENT SUBSTITUTION PROCEDURES

1.1 DEFINITIONS

A. Procurement Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Procurement and Contracting Documents, submitted prior to receipt of bids.

B. Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Contract Documents, submitted following Contract award. See Section 012500 "Substitution Procedures" for conditions under which Substitution requests will be considered following Contract award.

1.2 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.3 PROCUREMENT SUBSTITUTIONS

A. Procurement Substitutions, General: By submitting a bid, the Bidder represents that its bid is based on materials and equipment described in the Procurement and Contracting Documents, including Addenda. Bidders are encouraged to request approval of qualifying substitute materials and equipment when the Specifications Sections list materials and equipment by product or manufacturer name.

B. Procurement Substitution Requests will be received and considered by Owner when the following conditions are satisfied, as determined by Architect; otherwise requests will be returned without action:

1. Extensive revisions to the Contract Documents are not required.

2. Proposed changes are in keeping with the general intent of the Contract

Documents, including the level of quality of the Work represented by the requirements therein.

3. The request is fully documented and properly submitted.

1.4 SUBMITTALS

A. Procurement Substitution Request: Submit to Stefany Holland, sholland@gowightman.com or Courtney James cjames@gowightman.com .

Procurement Substitution Request must be made in writing in compliance with the following requirements:

mailto:sholland@gowightman.com mailto:cjames@gowightman.com

PROCUREMENT SUBSTITUTION PROCEDURES 00 26 00 - 2

1. Requests for substitution of materials and equipment will be considered if received no later than February 19, 2024.

2. Submittal Format: Submit written Procurement Substitution Request, using CSI Substitution Request Form.

a. Identify the product or the fabrication or execution to be replaced in each request. Include related Specifications Sections and drawing numbers.

b. Provide complete documentation on both the product specified and the proposed substitute, including the following information as appropriate:

1) Point-by-point comparison of specified and proposed substitute product data, fabrication drawings, and installation procedures.

2) Copies of current, independent third-party test data of salient product or system characteristics.

3) Samples where applicable or when requested by Architect.

4) Detailed comparison of significant qualities of the proposed substitute with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

5) Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

6) Research reports, where applicable, evidencing compliance with building code in effect for Project.

7) Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, which will become necessary to accommodate the proposed substitute.

8) Schedule impacts

9) Cost implications

c. Provide certification by manufacturer that the substitute proposed is equal to or superior to that required by the Procurement and Contracting Documents, and that its in-place performance will be equal to or superior to the product or equipment specified in the application indicated.

d. Bidder, in submitting the Procurement Substitution Request, waives the right to additional payment or an extension of Contract Time because of the failure of the substitute to perform as represented in the Procurement Substitution Request.

B. Architect's Action:

1. Architect may request additional information or documentation necessary for evaluation of the Procurement Substitution Request. Architect will notify all bidders of acceptance of the proposed substitute by means of an Addendum to the Procurement and Contracting Documents.

PROCUREMENT SUBSTITUTION PROCEDURES 00 26 00 - 3

C. Architect's approval of a substitute during bidding does not relieve Contractor of the responsibility to submit required shop drawings and to comply with all other requirements of the Contract Documents.

END OF DOCUMENT 00 26 00

PRELIMINARY SCHEDULES 00 31 13 - 1

DOCUMENT 00 31 13 - PRELIMINARY SCHEDULES

1.1 PROJECT SCHEDULE

A. This Document, with its referenced attachments, is part of the Procurement and Contracting Requirements for the Project. They provide the Owner's information for the Bidders' convenience and are intended to supplement rather than serve in lieu of the Bidders' investigations. They are available for Bidders' convenience and information but do not affect Contract Time requirements. This Document and its attachments are not part of the Contract Documents.

B. Available Project information includes the following:

1. Bid Schedule

a. 02/14/2024 – Pre-Bid Meeting @ 3:30 p.m. EST, Virtual

b. 02/21/2024 – Final Addendum Issued (if necessary)

c. 02/27/2024 – Bids due @ 4:00 p.m., KRESA Building

d. 02/29/2024 – Post-Bid Interviews, Virtual

e. Week of March 4, 2024 – KRESA Board Meeting for Approval and Contract

Award

C. The project schedule, including design and construction milestones, is available for viewing following this Section. CSM Group’s schedule is provided for reference.

1. Technology contractor key dates are:

a. 03/2024 – Access Control Pre-Installation Meeting

b. 06/2024 – Network Operational

c. 09/2024 through 01/2025 – Equipment Installation

d. 10/2024 – Site Surveillance Camera Installation

e. 01/2025 – Flat Panel Installation

f. 02/2025 through 03/2025 – Owner Training

g. 02/18/2025 - Substantial Completion

h. 03/2025 – Warranty Commencement

D. Related Requirements:

1. CSM Group construction schedule is attached for reference as to the other trades on site.

END OF DOCUMENT 00 31 13

ID %

Complete

Task Name Duration Start Finish

0 40% KRESA 840 days Mon 1/3/22 Tue 4/8/25 25 96% Bid Phase 449 days Mon 1/3/22 Tue 9/26/23 81 70% Submittals & Procurement 471 days Fri 9/16/22 Wed 7/17/24

128 21% Construction Phase 820 days Mon 1/3/22 Tue 3/11/25 129 71% Sitework 541 days Thu 9/1/22 Wed 10/9/24

159 12% Building Construction 815 days Mon 1/3/22 Tue 3/4/25

161 0% DELAY ACTIVITES (weather, material, resources) 1 day Mon 1/3/22 Mon 1/3/22

162 0% List delay here 1 day Mon 1/3/22 Mon 1/3/22 163 58% Excavation & Structural 340 days Mon 3/27/23 Wed 7/24/24

164 86% Excavation & Structural - Area B 249 days Mon 3/27/23 Fri 3/15/24

186 0% Install trench drains 10 days Wed 2/7/24 Tue 2/20/24 187 0% Fine grade for SOG 2 days Wed 2/21/24 Thu 2/22/24 188 0% Area B - Prep 1st Floor 3 days Mon 2/26/24 Wed 2/28/24 189 0% Area B - Pour 1st Floor (includes 7 day cure time) 1 day Thu 2/29/24 Thu 2/29/24 190 0% Area B - Pour 1st Floor Cure Time 3 days Fri 3/1/24 Tue 3/5/24 191 0% Install Interior Thicken Slab Mason Walls 8 days Tue 3/5/24 Thu 3/14/24 192 0% Pour Locker Bases 1 day Fri 3/15/24 Fri 3/15/24 193 80% Excavation & Structural - Area D 276 days Fri 4/7/23 Mon 5/6/24

202 85% Remaining Waterproofing/Insulation 1 day Tue 10/24/23 Tue 10/24/23 203 80% Remaining Backfill 1 day Wed 10/25/23 Wed 10/25/23 210 0% Pour stairs & landing 3 days Tue 1/9/24 Thu 1/11/24 212 0% Final Grade/Install stone 2 days Thu 3/28/24 Fri 3/29/24 213 0% Area D - 1st Floors Pour (includes 7 day cure time) 10 days Mon 4/1/24 Fri 4/12/24 214 0% Interior Masonry Walls 15 days Mon 4/15/24 Fri 5/3/24 215 0% Pour Locker Bases 1 day Mon 5/6/24 Mon 5/6/24 216 41% Excavation & Structural - Area C 300 days Fri 4/14/23 Mon 6/17/24

222 100% Area C - Structural Steel & Level 2 Decking Installation

20 days Tue 10/17/23 Mon 11/13/23

223 75% Remaining Backfill 5 days Tue 11/14/23 Mon 11/20/23 224 50% Underground Utilities - Electrical 10 days Tue 11/21/23 Tue 12/5/23 225 50% Underground Utilities - Plumbing 10 days Tue 11/21/23 Tue 12/5/23 226 90% Area C - Pour 2nd Floor SOMD 2 days Tue 1/2/24 Wed 1/3/24 227 0% Learning Terrace & Planters 37 days Mon 1/8/24 Tue 2/27/24 228 0% MEP utilities 5 days Mon 1/8/24 Fri 1/12/24 229 0% Footing Excavation 1 day Mon 1/15/24 Mon 1/15/24 230 0% F/R/P - Pour #1 Footing 2 days Mon 1/15/24 Tue 1/16/24 231 0% Control Conduit 0.5 days Wed 1/17/24 Wed 1/17/24 232 0% Backfill 1 day Wed 1/17/24 Wed 1/17/24 233 0% Strip Footings, Form Walls 5 days Wed 1/17/24 Tue 1/23/24 234 0% Strip Footings, Pour Walls - pour 2 5 days Wed 1/24/24 Tue 1/30/24 235 0% Pour 3 - Higher Planter Bottom 2 days Wed 1/31/24 Thu 2/1/24 236 0% Pour 4 - Walls 2 days Fri 2/2/24 Mon 2/5/24 237 0% Pour 5 - Lower Planter Bottom 2 days Tue 2/6/24 Wed 2/7/24 238 0% Set Remaining Steel & Decking Area C 5 days Mon 2/19/24 Fri 2/23/24 239 0% Pour Remaining SOMD 2 days Mon 2/26/24 Tue 2/27/24 240 0% Final Grade/Install stone 3 days Tue 5/7/24 Thu 5/9/24 241 0% Area C - Pour 1st Floor Slab 10 days Fri 5/10/24 Thu 5/23/24 242 0% Seal concrete 4 days Fri 5/24/24 Thu 5/30/24 243 0% Install Metal Pan Stairs & Landing 10 days Fri 5/24/24 Fri 6/7/24 244 0% Interior Masonry Walls 15 days Fri 5/24/24 Fri 6/14/24 245 0% Pour stairs & landing 3 days Mon 6/10/24 Wed 6/12/24

Cannon Concrete

Cannon Concrete

Leidal & Hart

Cannon Concrete

CJs Coating

Hoffman Bros

OIK

Hoffman Bros

Cannon Concrete

Leidal & Hart

Cannon Concrete

Area C - Structural Steel & Level 2 Decking Installation

Hoffman Bros

Buist

RW LaPine

Cannon Concrete

Buist,RW LaPine

Hoffman Bros

Cannon Concrete

Buist,RW LaPine

Hoffman Bros

Cannon Concrete

Cannon Concrete

Cannon Concrete

Cannon Concrete

Cannon Concrete

VanDellen Steel

Cannon Concrete

Hoffman Bros

Cannon Concrete

Applied Flooring

OIK

Leidal & Hart

OIK

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter

KRESA CTE Center Mon 2/12/24

Task Name Duration Start Finish

246 0% Pour Locker Bases 1 day Mon 6/17/24 Mon 6/17/24 247 67% Excavation & Structural - Area A/E/F 192 days Tue 5/9/23 Thu 2/8/24

255 99% Waterproofing/Insulation 1 day Mon 10/16/23 Mon 10/16/23 256 0% Remaining Backfill 1 day Tue 10/17/23 Tue 10/17/23 257 15% Underground Utilities - Electrical 6 wks Thu 12/28/23 Thu 2/8/24 258 15% Underground Utilities - Plumbing 6 wks Thu 12/28/23 Thu 2/8/24 259 24% Excavation & Structural - Area A 137 days Mon 11/27/23 Fri 6/7/24

260 71% Area A - Structural Steel & Level 2 Decking Installation 24 days Mon 11/27/23 Fri 12/29/23

261 0% Area A - Prep for 2nd Floor Pour 4 days Fri 2/23/24 Thu 2/29/24 262 0% Area A - Pour 2nd Floor 2 days Thu 2/29/24 Fri 3/1/24 263 0% Area A - Cure Time 2nd Floor 5 days Mon 3/4/24 Fri 3/8/24 264 0% Final Grade/Install stone 5 days Tue 4/23/24 Mon 4/29/24 265 0% Area A - Prep 1st Floor 5 days Tue 4/30/24 Mon 5/6/24 266 0% Area A - Pour 1st Floor 3 days Tue 5/7/24 Thu 5/9/24 267 0% Area A - Cure 1st Floor 7 days Fri 5/10/24 Mon 5/20/24 268 0% Install Metal Pan Stairs & Landing 10 days Tue 5/21/24 Tue 6/4/24 269 0% Pour stairs & landing 3 days Wed 6/5/24 Fri 6/7/24 270 0% Pour Locker Bases 2 days Tue 5/21/24 Wed 5/22/24 271 21% Excavation & Structural - Area E 139 days Thu 12/21/23 Mon 7/8/24

272 75% Area E - Structural Steel & Level 2 Decking Installation 20 days Thu 12/21/23 Fri 1/19/24

273 0% Area E -Prep for Pour 2nd Floor 4 days Thu 3/14/24 Wed 3/20/24 274 0% Area E - Pour 2nd Floor 3 days Wed 3/20/24 Fri 3/22/24 275 0% Area E - Cure 2nd Floor 5 days Mon 3/25/24 Fri 3/29/24 276 0% Seal concrete 4 days Tue 3/26/24 Fri 3/29/24 277 0% Final Grade/Install stone 5 days Mon 5/20/24 Fri 5/24/24 278 0% Area E - Prep 1st Floor 5 days Tue 5/28/24 Mon 6/3/24 279 0% Area E - Pour 1st Floor 4 days Tue 6/4/24 Fri 6/7/24 280 0% Area E - Cure 1st Floor 7 days Mon 6/10/24 Tue 6/18/24 281 0% Install Metal Pan Stairs & Landing 10 days Wed 6/19/24 Tue 7/2/24 282 0% Pour stairs & landing 3 days Wed 7/3/24 Mon 7/8/24 283 0% Pour Locker Bases 2 days Wed 6/19/24 Thu 6/20/24 284 5% Excavation & Structural - Area F 131 days Mon 1/22/24 Wed 7/24/24

285 20% Area F - Structural Steel & Level 2 Decking Installation 15 days Mon 1/22/24 Fri 2/9/24

286 0% Area F - Prep for Pour 2nd Floor 4 days Fri 4/5/24 Thu 4/11/24 287 0% Area F - Pour 2nd Floor 1 day Thu 4/11/24 Thu 4/11/24 288 0% Area F - Cure Time 2nd Floor 5 days Fri 4/12/24 Thu 4/18/24 289 0% Seal concrete 4 days Mon 4/15/24 Thu 4/18/24 290 0% Final Grade/Install stone 5 days Tue 6/11/24 Mon 6/17/24 291 0% Area F - Prep 1st Floor 3 days Tue 6/18/24 Thu 6/20/24 292 0% Area F - Pour 1st Floor 3 days Fri 6/21/24 Tue 6/25/24 293 0% Area F - Pour 1st Floor 7 days Wed 6/26/24 Fri 7/5/24 294 0% Install Metal Pan Stairs & Landing 10 days Mon 7/8/24 Fri 7/19/24 295 0% Pour stairs & landing 3 days Mon 7/22/24 Wed 7/24/24 296 0% Pour Locker Bases 2 days Mon 7/8/24 Tue 7/9/24 297 18% Core & Shell 282 days Thu 6/8/23 Tue 7/16/24

298 47% Structural Steel/Fire Proofing 231 days Thu 6/8/23 Thu 5/2/24

301 0% Area B - Fireproofing 8 days Tue 10/17/23 Thu 10/26/23 302 0% Area D - Fireproofing 8 days Mon 11/27/23 Wed 12/6/23 303 0% Area C - Fireproofing 10 days Thu 1/4/24 Wed 1/17/24 304 0% Area A - Fireproofing 10 days Mon 3/11/24 Fri 3/22/24

Cannon Concrete

CJs Coating

Hoffman Bros

Buist

RW LaPine

Area A - Structural Steel & Level 2 Decking Installation

Cannon Concrete

Cannon Concrete

Cannon Concrete

Hoffman Bros

Cannon Concrete

Cannon Concrete

Cannon Concrete

OIK

OIK

Cannon Concrete

Area E - Structural Steel & Level 2 Decking Installation

Cannon Concrete

Cannon Concrete

Cannon Concrete

Applied Flooring

Hoffman Bros

Cannon Concrete

Cannon Concrete

Cannon Concrete

OIK

OIK

Cannon Concrete

Area F - Structural Steel & Level 2 Decking Installation

Cannon Concrete

Cannon Concrete

Cannon Concrete

Applied Flooring

Hoffman Bros

Cannon Concrete

Cannon Concrete

Cannon Concrete

OIK

OIK

Cannon Concrete

H & H Painting

H & H Painting

H & H Painting

H & H Painting

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

Task Name Duration Start Finish

305 0% Area E - Fireproofing 10 days Mon 4/1/24 Fri 4/12/24 306 0% Area F - Fireproofing 10 days Fri 4/19/24 Thu 5/2/24 307 24% Mass Timber and CLT Deck 147 days Mon 10/30/23 Fri 5/24/24

309 85% Area D - CLT Deck 16 days Wed 12/20/23 Fri 1/12/24 310 0% Area C - Glulam/CLT 20 days Fri 1/26/24 Thu 2/22/24 311 0% Area A - Glulam/CLT 10 days Tue 3/12/24 Mon 3/25/24 312 0% Area E - Glulam//CLT 10 days Mon 4/1/24 Fri 4/12/24 313 0% Area F - Glulam/CLT 10 days Mon 4/22/24 Fri 5/3/24 314 0% Area C/A/E/F - Nano Panel 15 days Mon 5/6/24 Fri 5/24/24 315 11% Façade & Windows 174 days Thu 11/9/23 Tue 7/16/24

316 47% Exterior - Area B 74 days Thu 11/9/23 Fri 2/23/24 317 98% Exterior Façade (CFMF) 38 days Thu 11/9/23 Thu 1/4/24 318 50% Vapor Barrier 15 days Mon 12/11/23 Tue 1/2/24 319 15% Exterior Façade (IMP) 20 days Fri 12/29/23 Fri 1/26/24 320 10% Curtain Wall/Glazing 35 days Mon 1/8/24 Fri 2/23/24 321 3% Exterior - Area D 55 days Mon 1/15/24 Fri 3/29/24 322 10% Exterior Façade (CFMF) 25 days Mon 1/15/24 Fri 2/16/24 323 0% Vapor Barrier 15 days Mon 2/5/24 Fri 2/23/24 324 0% Exterior Façade (IMP) 20 days Mon 2/5/24 Fri 3/1/24 325 0% Curtain Wall/Glazing 35 days Mon 2/12/24 Fri 3/29/24 326 0% Exterior - Area C 55 days Fri 2/23/24 Thu 5/9/24 327 0% Exterior Façade (CFMF) 25 days Fri 2/23/24 Thu 3/28/24 328 0% Vapor Barrier 15 days Fri 3/15/24 Thu 4/4/24 329 0% Exterior Façade (IMP) 20 days Fri 3/8/24 Thu 4/4/24 330 0% Curtain Wall/Glazing 35 days Fri 3/22/24 Thu 5/9/24 331 0% Exterior - Area A 35 days Tue 3/26/24 Mon 5/13/24 332 0% Area A Exterior Façade (CFMF) 10 days Tue 3/26/24 Mon 4/8/24 333 0% Vapor Barrier 10 days Tue 4/2/24 Mon 4/15/24 334 0% Area A Exterior Façade (IMP) 10 days Tue 4/9/24 Mon 4/22/24 335 0% Area A Curtain Wall/Glazing 15 days Tue 4/23/24 Mon 5/13/24 336 0% Exterior - Area E 40 days Mon 4/15/24 Mon 6/10/24 337 0% Area E Exterior Façade (CFMF) 15 days Mon 4/15/24 Fri 5/3/24 338 0% Vapor Barrier 10 days Mon 4/29/24 Fri 5/10/24 339 0% Area E Exterior Façade (IMP) 15 days Mon 5/6/24 Fri 5/24/24 340 0% Area E Curtain Wall/Glazing 15 days Mon 5/20/24 Mon 6/10/24 341 0% Exterior - Area F 40 days Mon 5/6/24 Mon 7/1/24 342 0% Area F Exterior Façade (CFMF) 15 days Mon 5/6/24 Fri 5/24/24 343 0% Vapor Barrier 10 days Mon 5/20/24 Mon 6/3/24 344 0% Area F Exterior Façade (IMP) 15 days Tue 5/28/24 Mon 6/17/24 345 0% Area F Curtain Wall/Glazing 15 days Tue 6/11/24 Mon 7/1/24 346 0% Exterior Façade (ACM) - All Areas 20 days Tue 6/18/24 Tue 7/16/24 347 0% Exterior Façade (Screen Wall) - A, E, F 20 days Tue 6/18/24 Tue 7/16/24 348 16% Roofing 154 days Thu 11/9/23 Mon 6/17/24

350 90% Area B - Roofing Installation 15 days Mon 12/4/23 Fri 12/22/23 351 0% Area D - Roof Vapor Barrier Installation 3 days Mon 1/15/24 Wed 1/17/24 352 0% Area D - Roof Installation 15 days Mon 2/5/24 Fri 2/23/24 353 0% Area C - Skylight Framing 3 days Tue 2/20/24 Thu 2/22/24 354 0% Area C - Roof Installation 15 days Fri 2/23/24 Thu 3/14/24 355 0% Area C - Skylight Installation 3 days Tue 3/12/24 Thu 3/14/24 356 0% Area A - Roof Installation 15 days Tue 4/9/24 Mon 4/29/24 357 0% Area E - Roof Installation 15 days Mon 5/6/24 Fri 5/24/24 358 0% Area F - Roof Installation 15 days Tue 5/28/24 Mon 6/17/24 359 0% Building Shell Complete - Area B 0 days Fri 2/23/24 Fri 2/23/24

H & H Painting

H & H Painting

Christman

Christman

Christman

Christman

Christman

Christman

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Bouma Corp

CJs Coating

Universal Wall

Forman Glass

Universal Wall

Universal Wall

McDonald Roofing

McDonald Roofing

McDonald Roofing

Forman Glass

McDonald Roofing

Forman Glass

McDonald Roofing

McDonald Roofing

McDonald Roofing

Building Shell Complete - Area B

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

Task Name Duration Start Finish

360 0% Building Shell Complete - Area D 0 days Fri 3/29/24 Fri 3/29/24

361 0% Building Shell Complete - Area C 0 days Thu 5/9/24 Thu 5/9/24

362 0% Building Shell Complete - Area A/E/F 0 days Mon 7/1/24 Mon 7/1/24

363 0% Interior Build Out 319 days Mon 12/4/23 Tue 3/4/25

364 0% Primary Switch Gear & Panels 35 days Thu 7/18/24 Thu 9/5/24

365 0% Area B 227 days Mon 12/4/23 Tue 10/22/24

366 0% Area B - Level 2 193 days Mon 12/4/23 Wed 9/4/24

367 0% Mechanical Mains 25 days Mon 12/4/23 Tue 1/9/24 368 0% Electrical Mains 25 days Mon 12/4/23 Tue 1/9/24 369 0% Piping/Plumbing Mains 25 days Mon 12/4/23 Tue 1/9/24 370 0% Fire Protection Mains 25 days Mon 12/4/23 Tue 1/9/24 371 0% Wall Framing 27 days Tue 12/26/23 Thu 2/1/24 372 0% MEP In Wall Installation 30 days Wed 1/10/24 Tue 2/20/24 373 0% Set AHU & DOAS equipment 5 days Fri 2/2/24 Thu 2/8/24 374 0% Ceiling Framing 15 days Fri 1/26/24 Thu 2/15/24 375 0% Hang Drywall 15 days Mon 2/26/24 Fri 3/15/24 376 0% Finish Drywall 10 days Mon 3/18/24 Fri 3/29/24 377 0% Interior Glass & Glazing 10 days Mon 4/1/24 Fri 4/12/24 378 0% Millwork 5 days Mon 4/1/24 Fri 4/5/24 379 0% Painting/Tile/Wall Coverings 30 days Mon 4/1/24 Fri 5/10/24 380 0% Ceilings 22 days Mon 4/29/24 Wed 5/29/24 381 0% Flooring 25 days Mon 5/13/24 Mon 6/17/24 382 0% Install Lockers 2 days Thu 5/30/24 Fri 5/31/24 383 0% Lighting/Electronics 17 days Tue 6/4/24 Wed 6/26/24 384 0% HVAC/Plumbing Trim Out 17 days Tue 6/4/24 Wed 6/26/24 385 0% FP Trim Out 12 days Fri 6/7/24 Mon 6/24/24 386 0% Connect/Install Owner Equipment 35 days Fri 6/7/24 Fri 7/26/24 387 0% Install Doors & Hardware 15 days Tue 6/11/24 Mon 7/1/24 388 0% Final Cleaning 10 days Mon 7/29/24 Fri 8/9/24 389 0% T&B 5 days Mon 8/12/24 Fri 8/16/24 390 0% Install Overhead/Coiling Doors/Fire Curtains 10 days Wed 8/21/24 Wed 9/4/24 391 0% Area B - Level 1 207 days Wed 1/3/24 Tue 10/22/24

392 0% Mechanical Mains 25 days Wed 1/3/24 Tue 2/6/24 393 0% Electrical Mains 25 days Wed 1/3/24 Tue 2/6/24 394 0% Piping/Plumbing Mains 25 days Wed 1/3/24 Tue 2/6/24 395 0% Fire Protection Mains 25 days Wed 1/3/24 Tue 2/6/24 396 0% Wall Framing 28 days Fri 3/15/24 Tue 4/23/24 397 0% MEP In Wall Installation 30 days Fri 3/29/24 Thu 5/9/24 398 0% Ceiling Framing 15 days Wed 4/17/24 Tue 5/7/24 399 0% Hang Drywall 15 days Fri 5/10/24 Fri 5/31/24 400 0% Finish Drywall 10 days Mon 6/3/24 Fri 6/14/24 401 0% Interior Glass & Glazing 10 days Mon 6/17/24 Fri 6/28/24 402 0% Millwork 5 days Mon 6/17/24 Fri 6/21/24 403 0% Painting/Tile/Wall Coverings 30 days Mon 6/17/24 Mon 7/29/24 404 0% Flooring 25 days Tue 7/16/24 Mon 8/19/24 405 0% Ceilings 23 days Fri 7/26/24 Tue 8/27/24 406 0% Lighting/Electronics 18 days Fri 7/26/24 Tue 8/20/24 407 0% HVAC/Plumbing Trim Out 18 days Fri 7/26/24 Tue 8/20/24 408 0% FP Trim Out 13 days Thu 8/1/24 Mon 8/19/24 409 0% Install Doors & Hardware 15 days Tue 8/13/24 Tue 9/3/24 410 0% Connect/Install Owner Equipment 35 days Tue 8/20/24 Tue 10/8/24 411 0% Final Cleaning 10 days Wed 10/9/24 Tue 10/22/24

Building Shell Complete - Area D

Building Shell Complete - Area C

Building Shell Complete - Area A/E/F

Buist

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Bouma Corp,RW LaPine

RW LaPine

Bouma Corp

Bouma Corp

Bouma Corp

Forman Glass

Hazelhoff

H & H Painting

Bouma Corp

Yoxheimer Tile

Rayhaven

Buist

RW LaPine

Blaze FP

Clark

RW LaPine

Overhead Doors BC

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Bouma Corp

Forman Glass

Hazelhoff

H & H Painting

Yoxheimer Tile

Bouma Corp

Buist

RW LaPine

Blaze FP

Clark

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

Task Name Duration Start Finish

412 0% Area D 232 days Mon 2/5/24 Tue 12/31/24

413 0% Area D - Level 2 180 days Mon 2/5/24 Wed 10/16/24

414 0% Mechanical Mains 25 days Mon 2/5/24 Fri 3/8/24 415 0% Electrical Mains 25 days Mon 2/5/24 Fri 3/8/24 416 0% Piping/Plumbing Mains 25 days Mon 2/5/24 Fri 3/8/24 417 0% Fire Protection Mains 25 days Mon 2/5/24 Fri 3/8/24 418 0% Wall Framing 27 days Mon 2/26/24 Tue 4/2/24 419 0% MEP In Wall Installation 30 days Mon 3/11/24 Fri 4/19/24 420 0% Ceiling Framing 15 days Wed 3/27/24 Tue 4/16/24 421 0% Hang Drywall 15 days Mon 4/22/24 Fri 5/10/24 422 0% Finish Drywall 15 days Mon 5/13/24 Mon 6/3/24 423 0% Interior Glass & Glazing 10 days Tue 6/4/24 Mon 6/17/24 424 0% Millwork 25 days Tue 6/4/24 Tue 7/9/24 425 0% Painting/Wall Covering 30 days Tue 6/25/24 Tue 8/6/24 426 0% Ceilings 23 days Mon 7/8/24 Wed 8/7/24 427 0% Flooring 25 days Wed 7/24/24 Tue 8/27/24 428 0% Lighting/Electronics 18 days Wed 8/14/24 Mon 9/9/24 429 0% HVAC/Plumbing Trim Out 18 days Wed 8/14/24 Mon 9/9/24 430 0% Kitchen Equipment Installation 18 days Wed 8/14/24 Mon 9/9/24 431 0% Connect/Install Owner Equipment 35 days Wed 8/14/24 Wed 10/2/24 432 0% Install Lockers 2 days Thu 8/15/24 Fri 8/16/24 433 0% FP Trim Out 13 days Fri 8/16/24 Wed 9/4/24 434 0% Install Doors & Hardware 15 days Wed 8/21/24 Wed 9/11/24 435 0% Install Coiling Doors/Fire Curtains 10 days Tue 9/10/24 Mon 9/23/24 436 0% Final Cleaning 10 days Thu 10/3/24 Wed 10/16/24 437 0% T&B 5 days Thu 10/10/24 Wed 10/16/24 438 0% Area D - Level 1 212 days Mon 3/4/24 Tue 12/31/24

439 0% Mechanical Mains 25 days Mon 3/4/24 Fri 4/5/24 440 0% Electrical Mains 25 days Mon 3/4/24 Fri 4/5/24 441 0% Piping/Plumbing Mains 25 days Mon 3/4/24 Fri 4/5/24 442 0% Fire Protection Mains 25 days Mon 3/4/24 Fri 4/5/24 443 0% Wall Framing 28 days Mon 5/6/24 Thu 6/13/24 444 0% MEP In Wall Installation 30 days Mon 5/20/24 Mon 7/1/24 445 0% Ceiling Framing 15 days Fri 6/7/24 Thu 6/27/24 446 0% Hang Drywall 15 days Tue 7/2/24 Tue 7/23/24 447 0% Finish Drywall 15 days Wed 7/24/24 Tue 8/13/24 448 0% Interior Glass & Glazing 10 days Wed 8/14/24 Tue 8/27/24 449 0% Millwork 25 days Wed 8/14/24 Wed 9/18/24 450 0% Painting/Wall Covering 30 days Thu 9/5/24 Wed 10/16/24 451 0% Ceilings 23 days Tue 9/17/24 Thu 10/17/24 452 0% Flooring 25 days Thu 10/3/24 Wed 11/6/24 453 0% Lighting/Electronics 18 days Thu 10/24/24 Mon 11/18/24 454 0% HVAC/Plumbing Trim Out 18 days Thu 10/24/24 Mon 11/18/24 455 0% FP Trim Out 13 days Mon 10/28/24 Wed 11/13/24 456 0% Connect/Install Owner Equipment 35 days Mon 10/28/24 Mon 12/16/24 457 0% Install Doors & Hardware 15 days Thu 10/31/24 Wed 11/20/24 458 0% Final Cleaning 10 days Tue 12/17/24 Tue 12/31/24 459 0% Area C 242 days Fri 2/23/24 Tue 2/4/25 460 0% Area C - Level 1 242 days Fri 2/23/24 Tue 2/4/25

461 0% Mechanical Mains 25 days Fri 2/23/24 Thu 3/28/24 462 0% Electrical Mains 25 days Fri 2/23/24 Thu 3/28/24 463 0% Piping/Plumbing Mains 25 days Fri 2/23/24 Thu 3/28/24 464 0% Fire Protection Mains 25 days Fri 2/23/24 Thu 3/28/24 465 0% Wall Framing 28 days Fri 5/24/24 Wed 7/3/24

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Bouma Corp

Forman Glass

Hazelhoff

H & H Painting

Bouma Corp

Yoxheimer Tile

Buist

RW LaPine

Stafford Smith

Rayhaven

Clark

Overhead Doors BC

RW LaPine

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Bouma Corp

Forman Glass

Hazelhoff

H & H Painting

Bouma Corp

Yoxheimer Tile

Buist

RW LaPine

Blaze FP

Clark

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

Task Name Duration Start Finish

466 0% Ceiling Framing 15 days Thu 6/27/24 Thu 7/18/24 467 0% MEP In Wall Installation 30 days Mon 6/10/24 Mon 7/22/24 468 0% Hang Drywall 30 days Tue 7/23/24 Tue 9/3/24 469 0% Finish Drywall 30 days Tue 8/20/24 Tue 10/1/24 470 0% Interior Glass & Glazing 10 days Wed 10/2/24 Tue 10/15/24 471 0% Ceilings 23 days Wed 10/2/24 Fri 11/1/24 472 0% Millwork 25 days Wed 10/2/24 Tue 11/5/24 473 0% Painting/Wall Covering 30 days Wed 10/2/24 Tue 11/12/24 474 0% Flooring 25 days Wed 10/30/24 Wed 12/4/24 475 0% Lighting/Electronics 18 days Wed 11/6/24 Mon 12/2/24 476 0% HVAC/Plumbing Trim Out 18 days Wed 11/6/24 Mon 12/2/24 477 0% Install Lockers 2 days Wed 11/13/24 Thu 11/14/24 478 0% FP Trim Out 13 days Fri 11/22/24 Wed 12/11/24 479 0% Connect/Install Owner Equipment 35 days Fri 11/22/24 Tue 1/14/25 480 0% Install Doors & Hardware 15 days Wed 11/27/24 Wed 12/18/24 481 0% Install Coiling Doors/Fire Curtains 10 days Tue 12/3/24 Mon 12/16/24 482 0% Final Cleaning 10 days Wed 1/15/25 Tue 1/28/25 483 0% T&B 5 days Wed 1/29/25 Tue 2/4/25 484 0% Area C - Level 2 187 days Fri 3/15/24 Fri 12/6/24

485 0% Mechanical Mains 25 days Fri 3/15/24 Thu 4/18/24 486 0% Electrical Mains 25 days Fri 3/15/24 Thu 4/18/24 487 0% Piping/Plumbing Mains 25 days Fri 3/15/24 Thu 4/18/24 488 0% Fire Protection Mains 25 days Fri 3/15/24 Thu 4/18/24 489 0% Wall Framing 28 days Fri 4/5/24 Tue 5/14/24 490 0% Ceiling Framing 15 days Wed 5/8/24 Wed 5/29/24 491 0% MEP In Wall Installation 30 days Fri 4/19/24 Fri 5/31/24 492 0% Hang Drywall 30 days Mon 6/3/24 Mon 7/15/24 493 0% Finish Drywall 30 days Mon 7/1/24 Mon 8/12/24 494 0% Interior Glass & Glazing 10 days Tue 8/13/24 Mon 8/26/24 495 0% Ceilings 23 days Tue 8/13/24 Fri 9/13/24 496 0% Millwork 25 days Tue 8/13/24 Tue 9/17/24 497 0% Painting/Wall Covering 30 days Tue 8/13/24 Tue 9/24/24 498 0% Flooring 25 days Wed 9/11/24 Tue 10/15/24 499 0% Lighting/Electronics 18 days Wed 9/18/24 Fri 10/11/24 500 0% HVAC/Plumbing Trim Out 18 days Wed 9/18/24 Fri 10/11/24 501 0% FP Trim Out 13 days Fri 10/4/24 Tue 10/22/24 502 0% Connect/Install Owner Equipment 35 days Fri 10/4/24 Thu 11/21/24 503 0% Install Doors & Hardware 15 days Wed 10/9/24 Tue 10/29/24 504 0% Final Cleaning 10 days Fri 11/22/24 Fri 12/6/24 505 0% Area A/E/F 196 days Tue 5/28/24 Tue 3/4/25

506 0% Area A/E/F - Level 2 175 days Tue 5/28/24 Mon 2/3/25

507 0% Mechanical Mains 30 days Tue 5/28/24 Tue 7/9/24 508 0% Electrical Mains 30 days Tue 5/28/24 Tue 7/9/24 509 0% Piping/Plumbing Mains 30 days Tue 5/28/24 Tue 7/9/24 510 0% Fire Protection Mains 30 days Tue 5/28/24 Tue 7/9/24 511 0% Wall Framing 26 days Fri 6/7/24 Mon 7/15/24 512 0% Ceiling Framing 15 days Mon 7/1/24 Mon 7/22/24 513 0% MEP In Wall Installation 30 days Fri 6/28/24 Fri 8/9/24 514 0% Hang Drywall 25 days Mon 8/12/24 Mon 9/16/24 515 0% Finish Drywall 25 days Tue 9/17/24 Mon 10/21/24 516 0% Millwork 25 days Tue 10/8/24 Mon 11/11/24 517 0% Painting 30 days Tue 10/8/24 Mon 11/18/24 518 0% Interior Glass & Glazing 10 days Tue 10/15/24 Mon 10/28/24 519 0% Ceilings 22 days Tue 10/22/24 Wed 11/20/24

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Forman Glass

Bouma Corp

Hazelhoff

H & H Painting

Yoxheimer Tile

Buist

RW LaPine

Rayhaven

Blaze FP

Clark

Overhead Doors BC

RW LaPine

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Forman Glass

Clark

Hazelhoff

H & H Painting

Yoxheimer Tile

Buist

RW LaPine

Blaze FP

Clark

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Hazelhoff

H & H Painting

Forman Glass

Bouma Corp

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

Task Name Duration Start Finish

520 0% Flooring 25 days Tue 10/29/24 Tue 12/3/24 521 0% Install Lockers 2 days Tue 11/19/24 Wed 11/20/24 522 0% Lighting/Electronics 18 days Tue 11/19/24 Fri 12/13/24 523 0% HVAC/Plumbing Trim Out 18 days Tue 11/19/24 Fri 12/13/24 524 0% FP Trim Out 13 days Thu 11/21/24 Tue 12/10/24 525 0% Connect/Install Owner Equipment 30 days Thu 11/21/24 Mon 1/6/25 526 0% Install Doors & Hardware 15 days Tue 11/26/24 Tue 12/17/24 527 0% Install Coiling Doors/Fire Curtains 10 days Mon 12/16/24 Mon 12/30/24 528 0% Final Cleaning 15 days Tue 1/7/25 Mon 1/27/25 529 0% T&B 5 days Tue 1/28/25 Mon 2/3/25 530 0% Area A/E/F - Level 1 176 days Tue 6/25/24 Tue 3/4/25

531 0% Mechanical Mains 30 days Tue 6/25/24 Tue 8/6/24 532 0% Electrical Mains 30 days Tue 6/25/24 Tue 8/6/24 533 0% Piping/Plumbing Mains 30 days Tue 6/25/24 Tue 8/6/24 534 0% Fire Protection Mains 30 days Tue 6/25/24 Tue 8/6/24 535 0% Wall Framing 26 days Wed 7/10/24 Wed 8/14/24 536 0% Ceiling Framing 15 days Thu 8/1/24 Wed 8/21/24 537 0% MEP In Wall Installation 30 days Wed 7/31/24 Wed 9/11/24 538 0% Hang Drywall 25 days Thu 9/12/24 Wed 10/16/24 539 0% Finish Drywall 25 days Thu 10/17/24 Wed 11/20/24 540 0% Millwork 25 days Thu 11/7/24 Thu 12/12/24 541 0% Painting 30 days Thu 11/7/24 Thu 12/19/24 542 0% Interior Glass & Glazing 10 days Thu 11/14/24 Wed 11/27/24 543 0% Ceilings 22 days Thu 11/21/24 Mon 12/23/24 544 0% Flooring 25 days Fri 11/29/24 Mon 1/6/25 545 0% HVAC/Plumbing Trim Out 18 days Fri 12/6/24 Thu 1/2/25 546 0% Lighting/Electronics 18 days Fri 12/20/24 Thu 1/16/25 547 0% Install Lockers 2 days Fri 12/20/24 Mon 12/23/24 548 0% FP Trim Out 13 days Tue 12/24/24 Mon 1/13/25 549 0% Install Doors & Hardware 15 days Mon 12/30/24 Mon 1/20/25 550 0% Connect/Install Owner Equipment 30 days Tue 12/31/24 Tue 2/11/25 551 0% T&B 5 days Tue 1/21/25 Mon 1/27/25 552 0% Final Cleaning 15 days Wed 2/12/25 Tue 3/4/25 553 0% Elevators 87 days Tue 6/11/24 Fri 10/11/24 554 0% Elevator (Area A) 15 days Tue 6/11/24 Mon 7/1/24 555 0% Elevator (Area F) 15 days Tue 7/2/24 Tue 7/23/24 556 0% Elevator Interior Finishes 4 days Tue 10/8/24 Fri 10/11/24 557 0% Project Acceptance 136 days Wed 8/28/24 Tue 3/11/25

558 0% MEP Rough-in Inspection - Mains 5 days Wed 8/28/24 Wed 9/4/24 559 0% MEP In Wall Inspection 5 days Thu 9/5/24 Wed 9/11/24 560 0% CSM Final QC Inspection Walkthrough 5 days Fri 1/10/25 Thu 1/16/25 561 0% Agency Final Inspections 3 days Fri 1/17/25 Tue 1/21/25 562 0% Punch list Walkthrough w/ Owner & A/E 5 days Wed 2/12/25 Tue 2/18/25 563 0% Punchlist Completion 15 days Wed 2/19/25 Tue 3/11/25 564 0% Attic Stock Turn-Over to Owner 2 days Wed 1/22/25 Thu 1/23/25

565 0% Owner Training 5 days Wed 1/22/25 Tue 1/28/25

566 0% Project Turnover To KRESA 0 days Tue 3/11/25 Tue 3/11/25

567 0% Project Closeout 19 days Wed 3/12/25 Tue 4/8/25

Yoxheimer Tile

Rayhaven

Buist

RW LaPine

Blaze FP

Clark

Overhead Doors BC

RW LaPine

RW LaPine

Buist

RW LaPine

Blaze FP

Bouma Corp

Bouma Corp

Buist,RW LaPine

Bouma Corp

Bouma Corp

Hazelhoff

H & H Painting

Forman Glass

Bouma Corp

Yoxheimer Tile

RW LaPine

Buist

Rayhaven

Blaze FP

Clark

RW LaPine

Project Turnover To KRESA

9/17 11/5 12/24 2/11 3/31 5/19 7/7 8/25 10/13 12/1 1/19 3/9

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 1

DOCUMENT 00 41 13 - BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT)

1.1 BID INFORMATION

A. Bidder: ___________________________________________________________.

B. Project Name: Career Connect Campus – Technology Bid Package

C. Project Location: 3500 Vanrick Drive, Kalamazoo, MI 49001

D. Owner: Kalamazoo Regional Educational Service Agency

E. Architect: Wightman & Associates, Inc.

F. Architect Project Number: 214175

1.2 CERTIFICATIONS AND BASE BID

A. Base Bid, Single-Prime (All Trades) Contract: The undersigned Bidder, having carefully examined the Procurement and Contracting Requirements, Conditions of the Contract, Drawings, Specifications, and all subsequent Addenda, as prepared by Wightman and Associates and Architect's consultants, and being familiar with all conditions and requirements of the Work, hereby agrees to furnish all material, labor, equipment and services, including all scheduled allowances, necessary to complete the construction of the above-named project, according to the requirements of the Procurement and Contracting Documents, for the stipulated sum of:

1. __________________________________________________________ Dollars

2. The above amount may be modified by amounts indicated by the Bidder on the attached Document 00 43 23 "Alternates Form."

1.3 GUARANTEES

A. The undersigned Bidder agrees to furnish Performance and Payments Bond constituting 100% of the total awarded contract sum. The cost of such bond INCLUDED in the base bid is:

1. ____________________________________________ Dollars ($_________)

B. In the event Owner does not offer Notice of Award within the time limits stated above, Owner will return to the undersigned the cash, cashier's check, certified check, U.S.

money order, or bid bond.

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 2

1.4 UNIT PRICES

A. The following unit prices apply to specific portions of the work should the Owner elect to add or reduce the quantity.

1. Unit Price #1: Provide unit price to add a 1-port data drop. Assume a cable distance of 180’-0”.

____________________________________________ Dollars ($_________)

2. Unit Price #2: Provide cost to add a 2nd AV camera at the wall opposite camera (AV-CAM1-W) of an instructional studio of the same kind. Cost shall include cabling and programming.

____________________________________________ Dollars ($_________)

1.5 ALLOWANCES

A. Base bid includes $285,000 allowance for undetermind DAS system scope. _______ (enter X above to indicate it has been included)

1.6 SUBCONTRACTORS AND SUPPLIERS

A. Attach a list of all subcontractors/suppliers and manufacturers to be used (found in section 00 60 00 Project Forms) and the expected work performed. Also, areas of work that will be self-performed.

1.7 TIME OF COMPLETION

A. The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract Documents on a date specified in a written Notice to Proceed to be issued by Architect and shall fully complete the Work within that Contract Time.

1.8 ACKNOWLEDGMENT OF ADDENDA

A. The undersigned Bidder acknowledges receipt of and use of the following Addenda in the preparation of this Bid:

1. Addendum No. 1, dated ____________________.

2. Addendum No. 2, dated ____________________.

3. Addendum No. 3, dated ____________________.

1.9 BID SUPPLEMENTS

A. The following supplements are a part of this Bid Form and are attached hereto.

BID FORM - STIPULATED SUM (SINGLE-PRIME CONTRACT) 00 41 13 - 3

1. Section 00 43 23 Alternates Form.

2. Section 00 43 24 Familial Disclosure Statement.

3. Section 00 43 24 Iran Affidavit of Compliance.

4. Section 00 60 00 Project Forms - AIA G703 Schedule of Values

5. Section 28 23 00 Video Surveillance NVMS…

This is the start of the file's text. The full file is on GovTribe.