This is an addendum to an Invitation for Quote/Bid issued by the Palm Beach County Board of County Commissioners, Facilities Development and Operations Department, Capital Improvements Division, for the Midwestern Government Center—Clerk of Court Renovation project (Project Number 2024-031316). The addendum modifies the original bid documents and extends the bid due date from November 19, 2026, by 2:00 PM to December 10, 2026, by 2:00 PM. The project scope includes renovation work at the government center involving sprinkler systems, access control systems, security cameras, door hardware, lighting fixtures, electrical systems, fire alarm systems, and flooring materials. The addendum addresses 34 questions from prospective bidders regarding clarifications on scope responsibilities, equipment specifications, existing conditions, and project requirements. Key clarifications indicate that the winning contractor is responsible for providing turnkey solutions for sprinkler systems, access control systems (including card readers, power supplies, and cabling), security cameras, and related installations. Work hours and phasing requirements are specified in the original scope of work attachment, and bidders are required to acknowledge receipt of this addendum by signing and attaching it to their bid proposal to avoid disqualification.
The addendum establishes that the contractor holds primary responsibility for most installation and integration work, with certain systems controlled by Palm Beach County's Enterprise Support Services (ESS) upon project completion and approval. Specific equipment and material requirements are detailed, including Milliken—The Magic Hour LVT Horizon flooring for certain areas, iPro IP cameras to connect to existing server infrastructure, and Lithonia lighting fixtures as specified in the fixture schedule. The contractor must verify existing electrical circuit capacity in the field and coordinate with ESS regarding access control panel location in Mechanical Room 419 and confirmation of spare network ports and power availability at the existing camera head-end in Room 416. The addendum requires contractors to perform a pre-bid walkthrough and confirms that an asbestos test is in progress with results to be provided in a subsequent addendum. No structural drawings exist for the project, and the contractor is responsible for all testing and final connections unless explicitly assigned to ESS or the owner in the specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOARD OF COUNTY COMMISSIONERS
PALM BEACH COUNTY, FLORIDA
FACILITIES DEVELOPMENT AND OPERATIONS DEPARTMENT
CAPITAL IMPROVEMENTS DIVISION
PROJECT NAME: Midwestern Gov Center – Clerk of Court Renovation
PROJECT NUMBER: 2024-031316
ADDENDUM NUMBER: ONE
DATE OF ISSUANCE: 11/17/2026
TO: Prospective Bidders
This addendum forms a part of the contract documents, modifies the original bid documents and shall be as binding as if contained therein. Acknowledge receipt of this addendum in the space provided on the "Bid Proposal Form". Failure to do so may subject the Bidder to disqualification.
This Addendum consists of five (5) pages and two (2) attachments.
Attachments:
• Attachment #1 – REVISED Midwestern Hardware
• Attachment #2 – Sec 28-1300 Access Control System Specs
CHANGE TO INVITATION FOR QUOTE/BID:
1. Change bid due date from “November 19, 2026, by 2:00 PM” to read “December 10, 2026, by
2:00 PM”
RESPONSES TO REQUEST FOR INFORMATION:
Perez-Borroto Construction LLC dba TrueBuild Group
Question 1: Can you please clarify who the sprinkler contractor is for this project, and who will be controlling the sprinkler system?
Response: The winning bidder shall be supplying the contractor. ESS will be controlling the fire system once project has been completed and approved.
Ralph Della-Pietra Inc.
Question 2. Card readers and power supplies are “by security systems integrator per drawings. Who furnishes, wires, programs and ties in the readers, power supplies, door contacts and REX:
PBC ESS, or the contractor?
Response: Contractor – This is turnkey
Question 3: Can you confirm whether the 4 cameras and the monitor are furnished and installed by the contractor or by ESS.
Response: Contractor – This is turnkey
Question 4: Confirm the door 101 scope and which existing readers are reused versus returned. The schedule and E-2 show no reader at 101. Demo note 11 returns an existing reader to the Owner while Groups 02 and 03 reuse existing readers.
Response: No reader needed at door 101
Question 5: LVT is scheduled in 405 and 418A, but there is no LVT spec section (only a color reference, “LVT Juniper”, in 08211). Could you provide a spec. Or manufacture?
Response: For LVT provide Milliken – The Magic Hour LVT Horizon. Color to be determined.
Question 6: The new wood ceiling feature in Lobby 401 has no spec (species, veneer, finish, support system) and no detail beyond A-3. Could we request details and spec.
Response: There is no NEW wood ceiling feature in the project. Existing wood ceiling feature is to remain.
Question 7: Can we confirm if the doors are a red oak veneer, and whether the doors are factory finished.
Response: Doors to match existing, contractor to VIF.
Question 8: Wall Type A and the slab detail say, “refer to structural drawings”; there are none. Can we confirm there are no structural drawings?
Response: Correct, there are no structural drawings on this project.
Question 9: Can we request the asbestos survey report.
Response: The asbestos test is in progress. Once completed, a copy will be made available.
Question 10: Can you confirm the allowed work hours and phasing if required.
Response: Work hours are specific in the scope of work under “IFQ/B Attachment C/
1. General/c.
Question 11: Can you confirm if the permit has been applied for and who will be responsible for the fees.
Response: Specifically stated in IFQ/B Attachment C/1.General/a.
Protect Video, Inc.
Question 12: E-2 keynote 2 calls for camera rough-in only (j-box, 3/4" conduit, pull string to the head-end in Room 416), but spec 282300 requires a turnkey system: cameras, software, licenses, cabling and warranty. Which governs? If turnkey, is it the electrical contractor’s scope or PBC ESS / Owner-furnished?
Response: This is a turnkey project. Contractor.
Question 13: What camera brand and video management software run at this facility now? Spec 282300 requires new cameras to extend the existing system.
Response: Contractor to provide iPro IP cameras to connect to existing server.
Question 14: Are the two existing cameras removed on DE-2 (Lobby 401, Tax Collector 402) to be reused at the new locations, or replaced with new?
Response: Provide new cameras as shown on plan.
Question 15: Does the existing head-end in Room 416 have spare network ports and power (PoE) for 4 cameras and enough recording storage? Is any head-end hardware in this contract?
Response: Sufficient recording storage has been confirmed. However, confirmation of spare network ports and power (POE) will be provided in the next Addendum.
Question 16: Door 106 shows a card reader on A-2 and E-2, but the hardware schedule (08710) only covers Doors 101–104. Please provide a hardware group for Door 106, or confirm it has no reader.
Response: Hardware group for door 106 to be 01, it does require a card reader, See attachment
#1 revised Finish Hardware section 08710.
Question 17: Hardware Group 03 relocates Door 101 and reuses its existing card reader, but E-2 shows no rough-in at 101. Is electrical rough-in required at the relocated opening?
Response: Electrical plan matches architectural Plan. No card reader is required at this location.
Door 101 is a new door, refer to door schedule. See attachment #1 revised Finish Hardware section 08710 for revised Finish Hardware group.
Question 18: Hardware groups list card readers and power supplies “by Security Systems Integrator.”
Please identify the integrator. Is it PBC ESS or a contractor under this contract? Confirm that access control cabling, terminations and programming are not in the electrical scope.
Response: Access control devices and cabling to be provided by contractor via turnkey solution as per attachment #2 Sec 28-1300 Access Control System specification.
Question 19: Where are the access control panel and lock power supply located? Is a dedicated 120V circuit required? None is shown in the drawings.
Response: Existing card access panel resides in Mechanical Room 419.
Question 20: Detail 1/E-2 shows 1-1/4" conduit from the 4x4 j-box, while E-2 note 1 says all conduit is 3/4" unless noted. Please confirm the conduit size and where the 1-1/4" run terminates.
Response: 3.4” to devices (i.e., card reader, door contacts, lockset, etc.). 1-1/4” to access control headend. ESS to confirm head-end location.
Question 21: The emergency battery unit is listed as “recessed” on the E-3 schedule, but E-4 photometrics use a Lithonia EU2L wall-mounted unit. Which is required, and how many?
Response: Wall mounted unit as per fixture schedule on sheet E-4.
Question 22: The Type A fixture is listed as “2x4 recessed parabolic LED, 38W” on E-3, but E-4 lists
Lithonia 2ESL4 48L EZ1 LP840. Please confirm the catalog number.
Response: Catalog number as per fixture schedule on sheet E-4.
Question 23: RCP keynote 3 (A-3) requires removing and relocating existing ceiling fixtures where the grid is replaced. Please confirm the quantity and locations, since the E-sheets don’t identify them.
Response Refer to electrical Demo plan sheet DE-2 for fixtures to be removed. Refer to Lighting plans sheet E-3 for new fixture locations.
Question 24: RCP keynote 1 removes the wood veneer ceiling feature and its recessed Lights. Please confirm how many existing downlights are removed and whether any are reused in the new wood feature.
Response: Refer to electrical Demo plan sheet DE-2 for fixtures to be removed. Refer to Lighting plans sheet E-3 for new fixture locations.
Question 25: Please confirm how many existing exit signs are removed (RCP keynote 4).
Response: Refer to electrical Demo plan sheet DE-2 for fixtures to be removed. Refer to Lighting plans sheet E-3 for new fixture locations. Zero exit signs indicated to be removed;
provide new exit signs as shown.
Question 26: How are the receptacles at the new ADA service desks fed: from the adjacent partition, floor box or poke-through? If through the floor, is core drilling or X-ray by the GC per E- 2 general note 5?
Response: Fed from adjacent partition.
Question 27: E-2 says new devices “tie to existing circuits left from the demolition stage.” Please confirm the existing circuits have capacity, and that no new breakers or panel work is required.
Response: Trace and verify in field. Existing circuit load is adequate per as-builts.
Question 28: Spec 201215 requires 1" minimum station conduit for voice/data, while E-2 note 1 says
3/4". Please confirm 1" for data outlets.
Response: Confirmed 1” for data outlets as per specification.
Question 29. What is the existing fire alarm control panel manufacturer and model?
Response: EST iO1000
Question 30: Spec 283100 references FA devices “to be installed by ESS”. Please clarify which fire alarm work PBC ESS performs versus the contractor (programming, final connections, testing)
Response: Contractor is responsible for all requirements per the specification. Separation of work as per attachment #2 Sec 28-1300 Access Control System specification.
Question 31: Are any existing smoke detectors or speakers affected by the ceiling replacement and needing relocation? None are shown on the E-sheets.
Response: Perform work as indicated on plan. Perform pre-bid walk-thru as per note G on sheet
E-0.
Question 32: A-2 and E-2 show existing panic devices removed and reinstalled, who programs and tests them with the central station: contractor, PBC or ESS?
Response: Contractor responsible for removing and installing the existing panic buttons. Any modification and testing will be performed by the contractor.
Question 33: Spec 260519 section 3.5 says both the Owner and the Contractor will engage an independent testing agency. Please clarify which party is responsible.
Response: Contractor is responsible – turnkey.
Question 34: Will work be allowed during normal business hours in the occupied facility, or are after-hours or phased shutdowns required?
Response: Specifically stated in IFQ/B Attachment C/1.General/c.
PLEASE ACKNOWLEDGE RECEIPT OF THIS ADDENDUM NO. ONE BY SIGNING
BELOW AND ATTACHING THIS ADDENDUM TO YOUR BID FORM. THIS ADDENDUM
MUST BE SIGNED BY AN AUTHORIZED AGENT AND ATTACHED TO YOUR BID FORM,
AND RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED ON THE “BID
PROPOSAL FORM”. FAILURE TO DO THIS MAY RESULT IN BIDDER’S
DISQUALIFICATION.
ACKNOWLEDGMENT OF RECEIPT:
END OF ADDENDUM 1
| BOARD OF COUNTY COMMISSIONERS |
| PALM BEACH COUNTY, FLORIDA |
| ADDENDUM NUMBER: ONE |
| TO: Prospective Bidders |
| PLEASE ACKNOWLEDGE RECEIPT OF THIS ADDENDUM NO. ONE BY SIGNING BELOW AND ATTACHING THIS ADDENDUM TO YOUR BID FORM. THIS ADDENDUM MUST BE SIGNED BY AN AUTHORIZED AGENT AND ATTACHED TO YOUR BID FORM, AND RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED ON... |