About this file
This document is an Addendum to the bidding documents for the College of Coastal Georgia's (CCGA) CCGA-2420 Hargett Administration Building Terminal Unit Replacement project. The addendum provides amendments to the contract specifications, notably adding a list of three Contractors who have submitted qualifications meeting the specified requirements and are approved to bid on the project. The project involves the replacement of terminal units in the Hargett Administration Building and is located in Glynn County and the City of Brunswick, Georgia.
The addendum indicates that the contract documents are being amended as of March 18, 2024, and bidders must acknowledge receipt of this addendum on the Bid Form. The addendum does not provide any additional details on the pricing terms, set asides, incumbents, funding requirements, or other salient information beyond the specifications and approved bidders.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
College of Coastal Georgia CCGA-2420 Hargett Administration Building TU Replacement
NBP #24016
ADDENDUM NO. 1
A1 - 1
This Addendum forms part of the Contract Documents and modifies the original bidding documents dated March 1, 2024. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do may subject the bidder to disqualification.
The contract documents are herein amended under the date of March 18, 2024 as follows:
AMENDMENTS TO THE SPECIFICATIONS
1. SECTION 01 4000 – QUALITY REQUIREMENTS
A. 1.4.L.: Add the following paragraphs to the Documents:
L. The following Contractors submitted Qualifications meeting the Specified Requirements and are approved to bid:
1. Air Management
2. Certified Electric
3. Copper Construction
END OF ADDENDUM