This document outlines the estimated materials and supply needs for multiple Bureau of Land Management field offices in New Mexico for 2023. Key details include:

  • Delivery schedules and estimated quantities for 16 line items including plastic piping, valves, storage tanks, fencing materials, and concrete at the Orla Road, Junction, Tule, Crockett, Phantom Banks, and Xbar Elrod field offices. The Tule office requires the largest quantity of 1.25" plastic piping at 12,500 feet. The Xbar Elrod office requires 7,000 feet of 2" plastic piping and one 5,000 gallon storage tank.

  • The related federal contract opportunity is solicitation number 140L4023Q0030 from the Department of Interior Bureau of Land Management New Mexico Region for the 2023 Pecos District Office supply contract. Response and award dates are not provided but the schedule indicates the materials will be procured for use in 2023.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Delivery Schedule

Delivery Schedule
2023 CFO Orla Road West Fence Supply
Line ItemDescriptionQuantityUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)0Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)0Foot
31.25" threaded male fusion transition, DR-11 200 psi0Each
41.25" 90 ELL, DR-9 fusion0Each
58' rubber tire trough, 22.5" max height ~500 gallons0Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.0Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)0Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence72Rolls
10Barbless Wire Fence24Rolls
11Upright Post45Each
12Brace Post56Each
13Nut, and bolt54Each
14Twisted Wire Stays 36", 100 count bundles20Bundle
155.5' SPEC T-Posts silver top1920Each
16Sacked Ready Mix Concrete404Each
2023 CFO Junction Supply
Line ItemDescriptionQuantity estimatedUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)0Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)0Foot
31.25" threaded male fusion transition, DR-11 200 psi1Each
41.25" 90 ELL, DR-9 fusion1Each
58' rubber tire trough, 22.5" max height ~500 gallons1Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.1Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)0Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence0Rolls
10Barbless Wire Fence0Rolls
11Upright Post0Each
12Brace Post0Each
13Nut, and bolt0Each
14Twisted Wire Stays 36", 100 count bundles0Bundle
155.5' SPEC T-Posts silver top0Each
16Sacked Ready Mix Concrete42Each
2023 CFO Tule Supply
Line ItemDescriptionQuantity estimatedUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)12500Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)0Foot
31.25" threaded male fusion transition, DR-11 200 psi4Each
41.25" 90 ELL, DR-9 fusion4Each
58' rubber tire trough, 22.5" max height ~500 gallons4Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.4Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)4Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence0Rolls
10Barbless Wire Fence0Rolls
11Upright Post0Each
12Brace Post0Each
13Nut, and bolt0Each
14Twisted Wire Stays 36", 100 count bundles0Bundle
155.5' SPEC T-Posts silver top0Each
16Sacked Ready Mix Concrete168Each
2023 CFO Crockett Supply
Line ItemDescriptionQuantity estimatedUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)2000Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)0Foot
31.25" threaded male fusion transition, DR-11 200 psi0Each
41.25" 90 ELL, DR-9 fusion0Each
58' rubber tire trough, 22.5" max height ~500 gallons0Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.0Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)0Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence0Rolls
10Barbless Wire Fence0Rolls
11Upright Post0Each
12Brace Post0Each
13Nut, and bolt0Each
14Twisted Wire Stays 36", 100 count bundles0Bundle
155.5' SPEC T-Posts silver top0Each
16Sacked Ready Mix Concrete0Each
2023 CFO Phantom Banks Supply
Line ItemDescriptionQuantity estimatedUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)2000Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)0Foot
31.25" threaded male fusion transition, DR-11 200 psi0Each
41.25" 90 ELL, DR-9 fusion0Each
58' rubber tire trough, 22.5" max height ~500 gallons0Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.0Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)0Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence0Rolls
10Barbless Wire Fence0Rolls
11Upright Post0Each
12Brace Post0Each
13Nut, and bolt0Each
14Twisted Wire Stays 36", 100 count bundles0Bundle
155.5' SPEC T-Posts silver top0Each
16Sacked Ready Mix Concrete0Each
2023 RFO Xbar Elrod Supply
Line ItemDescriptionQuantity estimatedUnits
1DR-9 250 psi 1.25" PE pipe (2,000' rolls)0Foot
2DR-11 200 psi 2.00" PE pipe (2,000' rolls)7000Foot
31.25" threaded male fusion transition, DR-11 200 psi0Each
41.25" 90 ELL, DR-9 fusion0Each
58' rubber tire trough, 22.5" max height ~500 gallons0Each
61.25" Flippen float valve assembly, complete with ball, swivel, and arm.0Each
75,000 gallon PE storage (green in color) 142" wide x 88" tall (11.83' wide by 7.33' tall)1Each
8Valve Box, 24" length by 24" diameter riser and septic lid0Each
9Barbed Wire Fence0Rolls
10Barbless Wire Fence0Rolls
11Upright Post0Each
12Brace Post0Each
13Nut, and bolt0Each
14Twisted Wire Stays 36", 100 count bundles0Bundle
155.5' SPEC T-Posts silver top0Each
16Sacked Ready Mix Concrete42Each