20220824_CoP_Addendum1_412_Blvd_Build-out.pdf

PDF 222 KB Posted

Attached to
412 Blvd of the Allies City Offices Build-out & Construction
Solicitation number
2022-IFB-175
Issued by
Allegheny County, Philadelphia City, Pennsylvania

About this file

This document is Addendum #1 for the City of Pittsburgh's interior fit-out project located at 412 Boulevard of the Allies, issued by AE7 Pittsburgh, LLC on August 24, 2022. The addendum provides comprehensive modifications to the original 100% Bid Documents, including changes to the Responsibility Matrix, room layouts, finish specifications, accessory schedules, and technical requirements across multiple disciplines such as architectural, plumbing, fire protection, mechanical, electrical, and AV/telecom/security systems. Key changes include removing demountable partitions from project scope, renaming specific rooms, updating material and finish specifications, adjusting room dimensions, and adding or relocating electrical outlets, data ports, and technical equipment.

The addendum does not specify precise budget or funding details but indicates a detailed interior renovation project involving multiple building systems and room reconfigurations. Significant modifications include owner-furnished appliances, contractor-installed accessories, adjustments to room configurations on various floors, updates to material specifications for walls, floors, and panels, and technical infrastructure changes like adding daylight sensors, data outlets, and dedicated circuits for specific areas such as the Traffic Management Center. The document suggests a comprehensive build-out of office spaces with specific attention to technical infrastructure, material quality, and functional room layout optimization.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AE7 Pittsburgh, LLC – 2840 Liberty Ave. – Suite 403 – Pittsburgh, PA 15222 Tel: 412-932-2044 / Fax: 412-932-2045

August 24, 2022

RE: City of Pittsburgh, 412 Blvd of the Allies: Addendum #1

To All Bidders and Plan Holders, Please be advised that the following change has been hereby made a part of the 100% BID DOCUMENTS for the City of Pittsburgh interior fit-out project, fully and completely as if the same were fully contained therein. Revised drawings and specifications will be issued at a later date. All other terms, conditions, and specifications of the original 100% BID DOCUMENTS remain unchanged.

This amendment must be acknowledged.

Changes to 100% BID DOCUMENTS are as follows:

General

1. The furnishing and installation of demountable partitions is not part of this project’s scope.

Demountable partitions and doors shown on A151, A152, A153, A154, and A601 are for coordination purposes. Refer to the Responsibility Matrix on sheet G002 for coordination requirements.

2. Revised Responsibility Matrix (G002)

a. Appliances shall be owner furnished; contractor installed.

b. All toilet room accessories shall be contractor furnished and installed.

c. Flat screen monitors shall be AV contractor furnished and installed.

Architectural

3. Adjusted Room Layout:

a. Room 211 “Huddle” shall be renamed “Office”.

b. Room 213 “Drawing Storage” shall be renamed “Office”. Door 02-07 shall be relocated to within a modular wall and removed from the door schedule on sheet A600.

c. The north wall of Room 401 Office shall be shifted north, increasing the room area and reducing the area of Rom 402 Storage.

4. Finish Schedule:

a. Updated Finish Notes

b. Updated WF-02 specification to be Solyx SXJ-0500, White Dusted Matte Dot Gradient.

c. Updated RT-02 to Norament Arago 5171 Fortitude model, and RT-03 specification to

Norament Arago 5179 Tranquil model.

d. Updated MB-01 specification color to Dark Anodized Aluminum.

e. Updated AP-01 specification to Designtex Acoustical Panels, surfacing imaging – “Enhanced

Wannabe Hanging Panel” in “201 Dandelion – Squares 3”, felt material, 4’8’ sizing, ceiling hung.

f. Updated PT-12 specification to Scuff Master Solid Metals in SM10054.

g. Updated WC-02 specification to be vinyl wallcovering, “Cusp” in Petrel by Maharam.

5. Accessory Schedule:

a. Updated AC-08 specification to be Rex Glass, custom model, 24”x36” clear tempered mirrored glass, ¼” thick with matte black metal framing, and AC-09 specifications to be Rex Glass, custom model, 60”x22” clear tempered mirrored glass, ¼” thick with matte black metal framing.

6. Door 01-10 on LVL 01 removed from project scope

7. 6 wall to wall adjustable shelves in Storage 217, 310 and 403, material PL-02. 2’-0” shelf depth with required wall-mounted supports.

8. Edited detail 12/A573 to show PT-04 instead of PL-04.

9. PL-02 material added to detail 7/A574 for coat closets.

Plumbing

10. Add floor drains in individual toilet rooms 006, 007, 008 and remove the floor drain located in the adjacent corridor.

Fire Protection

11. Uninstall and reinstall existing FP at restroom vestibules as required for new ACT ceilings according to architectural Reflected Ceiling Plans (Levels 2-4).

Mechanical

12. Uninstall and reinstall existing mechanical equipment at restroom vestibules as required for new

ACT ceilings according to architectural Reflected Ceiling Plans (Levels 2-4).

Electrical

13. Provide additional daylight sensors on the 2nd through 4th floors.

14. Data to match T1.01 at transaction counters.

15. Data to match T1.04 for Medium Conference 432

16. Data to match T1.02 for Huddle 204 and Drawing Storage 205

17. Power/Data locations to match T1.01 at Huddle 108.

18. Orientation for B1 Meeting Rooms to follow architectural and IT/AV drawing layout. Keep existing floor boxes in current locations with addition of a power and data boxes at F02 table locations.

19. 1 power added at enclosed end of island as noted in architectural millwork drawings for (3) Break

Room islands.

20. Plan for disconnect of existing lighting at LVL 02 and LVL 03 Restroom Vestibules. EC to reinstall after new ceiling are installed.

21. Quad receptacle required for each workstation at Traffic Management Center 433.

22. The (3) electrical poke-throughs (PT1) in Large Conference room 212, shall be the wiremold Legrand

8AT version. Conduits shall be the same as indicated on E001A.

23. Provide (2) outlets, one in each column on LVL 02 at Copy/Print A 210 at F30 tables and (2) outlets in the existing gypsum walls at F24 tables on LVL 02 at Copy/Print A 210 and Break Room 213.

AV / Telecom / Security

24. 2 additional furniture mounted data outlets shall be included in Room 212 Open Office area.

25. Updated AV equipment list for basement Meeting Room 1 and 2. Forthcoming as part of next drawing addendum.

26. Existing projection screen and speakers in Meeting Room 1 (Room 001) shall be disconnected, removed, and returned to owner for future use.

27. Dedicated circuit required for Video Wall in Traffic Management Center 433.

Regards, Patrick Rakszawski Project Manager

AE7