This document is a Scope of Work for a well installation contract (2022-SW-31W) issued by the Virginia Department of Health for a location in Giles County, Virginia. The contractor is required to furnish all labor, supervision, equipment, tools, parts, supplies and materials to construct a private water well, install a pump and plumbing, and properly abandon an existing neighboring well connection. The work must comply with Virginia's Private Well Regulations and the Virginia Uniform Statewide Building Code. Bidders must provide a detailed cost breakdown for the 150-foot well installation and list any additional services at a per-foot rate. The contractor must also provide project timelines, subcontractor information, and change order requests to the VDH SWAP Grant team. Upon completion, the contractor must submit required documentation to the Giles County Health Department to obtain a Record of Inspection.
The bid should include the base cost for the 150-foot well installation, with any additional depth charged at a per-foot rate. Bidders must also list any other additional services beyond the base scope. The contractor will only be paid for the actual work performed, as verified by the well depth, casing depth, grout depth, and other measures. A pre-bid site visit is recommended to determine any necessary tree removal or site clearing. The project will be funded through the VDH SWAP Grant program.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPECIAL TERMS AND CONDITIONS.docx | DOCX document | |
| General Terms and Conditions .docx | DOCX document | |
| ARPA FUNDING-.docx | DOCX document | |
| Construction Terms and Conditions-.docx | DOCX document | |
| REDACTED 2022-SWR-31W UPDATED Permit.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Well Installation (2022-SW-31W) Address: 110 Jones Dr. Pearisburg, VA 24134
Scope of work:
The contractor shall furnish all labor, supervision, equipment, tools, parts, supplies and materials, as necessary, to perform the services as described herein:
Cost for Line Item #1 (include total cost for items A-H). These are known factors. Vendors must invoice for actual cost incurred as described herein. The initial bid should be an average cost/foot of depth for 150 feet (add other itemized costs such as mobilization/setup, etc.). Please note: 150 feet is an estimate, vendor will bill based on actual service performed, actual depth drilled (as verified on the GW-2 and VDH’s Record of Inspection). Vendor will only be paid for actual well depth drilled, casing depth, grout depth, depth of drop pipe, pump, etc. Vendor must provide a detailed bid for 150 ft., any additional footage must be listed as additional services at a per foot rate. Vendors who submit bids for over or under 150 feet; will not be accepted.
A) Construct a private water well that meets the location, construction specifications, water quantity, and water quality requirements of the Virginia Private Well Regulations (12VAC5-630-10 et seq., the Regulations).
B) Tree Removal and Site Clearing: A pre-bid site visit is recommended to determine what if any tree removal or site clearing that may need to occur. Per the above referenced Permit, remove any trees and wood debris as described in the permit and haul away wood and debris unless notified otherwise. Costs of tree removal and site clearing should be included in initial bids. Any additional site clearing or tree removal required during installation must be submitted in writing to and approved by VDH in writing including an additional cost estimate. Any personal property items that will prohibit the contractor from accessing the site or installation of the new system is the responsibility of the homeowner to remove and should not be included in the bid.
C) Construct the above class III(B) well with a minimum of 65’of casing and grout and in compliance with the Giles County Health Department Well Construction Permit 23-071-STS-8055 at 110 Jones Dr. Pearisburg, VA 24134 in the location shown on the permit. The permit may contain additional conditions, notes, and information needed to construct the well.
D) Provide, or subcontract with a licensed plumber and electrician to provide, the well pump, plumbing, and electrical required to convey the water under sanitary conditions from the well to the home plumbing system in the quantity required by the Regulations and the Virginia Uniform Statewide Building Code. This includes obtaining or assuring that the owner obtains all permits and inspections necessary by the local building authority in compliance with the Virginia Uniform Statewide Building Code.
E) Disinfect the well and plumbing as required by the Regulations and provide the required Uniform Water Well Completion Report (GW2). Obtain a final compliance inspection from the health department and a Record of Inspection and assure that the well is tested and complies with the water quality requirements of the Regulations.
F) Appropriately abandon the existing connection to the neighboring private drinking water supply/well. This may include: cutting and capping off the supply line(s) to the neighboring well, and disinfecting the well if needed or requested by the owner of the neighboring well,.
G) Follow all regulations and permitting pertaining to erosion and sediment control including stabilizing, seeding and grading the site after construction to return to the original state. Control construction runoff with proper practices so as not to become a nuisance to the owner or to neighboring properties or cause sediment to be discharged into state waters and drainage ditches. Any construction debris must also be removed from the site and disposed of properly.
H) Bidders shall comply with all requirements of the Department of Professional and Occupational Regulations (DPOR) for contracting and executing the contract with the Virginia Department of Health. Operate within the requirements of the DPOR Water Well System Provider Certification and proof of insurance. Bidders contacted by VDH to provide any missing required documents, must provide the document within 24 business hours or their bid will be considered non-responsive.
I) Provide to VDH_SWAP_GRANT@vdh.virginia the following information by the listed deadline:
· Project Start and End Dates: Estimated project start and completion dates to be provided two (2) weeks prior to the start of the installation/work or within four (4) weeks after issuance of PO (issuance of Notice to Proceed); whichever is earlier.
· Name and licensure of subcontractor(s): The contractor shall within four (4) weeks after the signing of the contract (or within two weeks of the work starting or within 1 week after changing subcontractor; whichever is earlier), notify VDH in writing of the names of subcontractors proposed for the principal parts of the work.
· Request for Change Orders: All request for changes must be provide in writing per the contract terms and conditions and are not authorized until a response in writing is sent by the SWAP team.
· Request for Extensions: If it is determined that the work will not be able to be completed by the contract expiration date listed in the Notice to Proceed and the PO, a request for an extension must be provided, in writing, a minimum of two weeks prior to contract expiration date. Justification for why work could not be performed within original contract term must be provided. Extensions requested on or after the expiration date will not be able to be accommodated.
J) Provide all required documentation (completion report, water tests GW-2, etc.) to the Giles County Health Department following completion of construction in order to obtain a Record of Inspection for the well installation.
K) Submit invoice to VDH_SWAP_Grant@vdh.virginia.gov once and the Local Health Department has inpected the w ork and has issued the Record of Inspection (ROI) along with a copy of the ROI, GW-2, lab results and completion statement.
Additional Services (If Needed) Bidder must contact VDH Project Manager listed on the Notice to Proceed for approval prior to any additional services performed. VDH will issue a change order for actual additional services rendered.
The contractor shall furnish all labor, supervision, equipment, tools, parts, supplies and materials, as necessary, to perform the services as described herein:
A. Additional depth (beyond 150 ft.): provide a per foot rate for additional depth. If bidder has an estimate of how deep the well may be at this location please provide. Examples:
a. Additional Depth (beyond 150 feet): $xx/ft, Estimated additional depth 250 feet, estimated total well depth 400 feet.
b. Additional cost for installation of a pump below 150 ft., including per foot cost for drop pipe.
B. Additional Services beyond what was quoted in A-K above (please list/enumerate and detail).
Breakdown of Total Cost When responding to solicitation Bidders must attach a document listing breakdown of total cost for line item 1. Bidders must attach a separate breakdown of cost for additional services.
Additional cost should not be included in line item 1 bid submission.
Optional site visit: If a site visit is needed please contact Angelica Cipara to arrange a day/time for a site visit.
Additional questions:
Contact Angelica Cipara via email: angelica.cipara@vdh.virginia.gov Notice to Proceed If Bidder is selected for award, the Bidder shall be required to provide a signed Notice to proceed form within 3 business days of notification. VDH will provide a form for signature.