2022 Fire Truck Tank PWS.pdf

PDF 134 KB Posted

Attached to
Fire Truck Tank Replacement
Solicitation number
F9E6SQ2146A001
Issued by

View the file

Other files

File Type Posted
Truck 3.jpg JPG image
fire truck Data plate.jpg JPG image
Truck 2.jpg JPG image
Truck 4.jpg JPG image
Data plate 2.jpg JPG image
Sources Sought Info Req Form.docx DOCX document
Truck 1.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

P-26 TANK REMOVAL &

REPLACEMENT

106th Rescue WING

150 Old Riverhead Road

Westhampton Beach, NY 11978

LOCATED ON

Gabreski Airport ANGB

JUNE 7, 2022

1. SCOPE OF WORK

The contractor shall provide all equipment, tools, materials, supervision, and services necessary to complete the work as described in this Performance Work Statement (PWS).

Work location is on site. If work location needs to be at vendor, vendor must provide transportation of vehicle, tank & all parts. All tank equipment will be removed & re-installed onto new tank. This includes but not limited too. piping, dumps, air lines, ladders, switches, electrical & lights.

2. AREA OF WORK

Contractor shall work only on areas of the equipment as described in this statement of work.

3. DESCRIPTION OF WORK

Contractor will remove & re-install entire tank back to factory setting.

4. PERIOD OF PERFORMANCE

Contractor shall complete all work within a three month period of time from tank being built.

5. MATERIALS

P-26 Tank will be supplied as part of a separate contract. The tank will be pre-assembled & painted. Means of lifting tank will not be supplied.

6. GOVERNMENT WORKING HOURS

Work / Pick-up and delivery hours will be Monday through Friday 0730 -1530 based on Available personnel, with the exception of scheduled off federal holidays.

7. DISPOSAL OF MATERIALS AND CLEANUP

Contractor is responsible to properly dispose of any hazardous waste generated performing contract duties (If any). Old tank will be disposed of properly by contractor.

8. SECURITY

Contractor will be responsible for equipment and contents while in their care and custody to include theft, vandalism, or any other damage. An Air Force Form 1297 Will be signed by the contractor for each individual unit being serviced. AF FORM 1297 will be relinquished when the unit specified on the receipt is returned / inspected.

9. POINT OF CONTACT

106th Contracting Office 631-723-7562.

1. SCOPE OF WORK
2. AREA OF WORK
3. DESCRIPTION OF WORK
4. PERIOD OF PERFORMANCE
5. MATERIALS
6. GOVERNMENT WORKING HOURS
7. DISPOSAL OF MATERIALS AND CLEANUP
8. SECURITY
9. POINT OF CONTACT

File details come from the government source that posted it. Updated .