Questions and Answers Recieved Against 20201222038.pdf
PDF 464 KB Posted
- Attached to
- Mercedes Infrastructure Cabling Upgrade
- Solicitation number
- 20201222038
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pricing Sheet.xlsx | XLSX spreadsheet | |
| Applicable Clauses and Provisions.pdf | ||
| Wage Determination 2015-5245 Rev 11 06272020.pdf | ||
| SoW Mercedes Infrastructurer Upgrade 061220.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions Received Against 20201222038 Mercedes Infrastructure Cabling Upgrade
1. Are there any current plans or drawings reflecting where the Cat6 cables are to be installed in each building?
No current plans or drawings exist however, we do provide photos in the Scope and have pictures from the last site survey (see end of SOW). There are also narratives provided within the scope that explains that each workstation location will need two sets of cables (data/voip). The recommended site visit should accurately reveal all locations.
2. How many cables will be at each location? Single, Dual?
If this is related to the Data/VOIP jack connections, there will be two at each work station one for data and one for VoIP
3. Are there any drawings that show the conduit pathways between buildings?
No, the scope of work does include an image where the conduit pathways are most likely to be. The site visit recommended within the Scope will reveal exact locations.
4. What size conduit currently runs between the buildings?
Unknown, however the site visit recommended by the Scope will reveal the conduit size.
5. Is the Gov’t open to suggestions in regard to the wall mountable cabinets for the warehouse and personnel buildings? The amount of equipment specified for those cabinets will exceed the RU’s available in the models listed in the SOW.
The government is acceptable to these changes if power and cooling is considered (no AC in the area where the current equipment is kept).
Question 1: Admin building in main IT Comm Room behind IT Rack
Question 1: Personnel building Comm room
Question 1: Warehouse building IT room
Admin fiber access
Admin building IT comm room
Personnel building fiber access
Warehouse fiber access