20200619 ATTACHMENT J.2 Bid Form IFB_72044020B00001 BH IM2.pdf
PDF 89 KB Posted
- Attached to
- Update#3 to Draft IFB - USAID Second Interim Measures for Dioxin Remediation at Bien Hoa Airbase Area (IM2)
- Solicitation number
- 72044020B00001
About this file
This draft solicitation is for a firm fixed price construction contract to perform the USAID Second Interim Measures for Dioxin Remediation at Bien Hoa Airbase Area in Vietnam. The estimated value of the base bid is between $12-18 million. The period of performance is approximately 20 months from award.
The solicitation is being issued by the United States Agency for International Development in Vietnam. Both US and Vietnamese firms are eligible to compete. The work includes clearing and removal of vegetation, excavation and removal of contaminated soil and sediment, backfilling and compaction, road construction and repairs, fencing installation, and treatment of water from excavation dewatering. The pre-bid conference is tentatively scheduled for August with questions due by a certain date. Bids are due in September with award anticipated shortly after. Attendance at the mandatory pre-bid conference is required to submit a bid.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM
DIOXIN REMEDIATION AT BIEN HOA AIRBASE AREA PROJECT
SECOND INTERIM MEASURES (IM2)
Bid Item No.
Bid Item Description Units Quantity Unit Price Total Amount
00.01 Mobilization (Maximum of 5% of the Subtotal) LS 1
00.02 Temporary Erosion and Sediment Control LS 1
00.03 Environmental Monitoring and Mitigation LS 1
00.04 Health and Safety Including PPE and Blood Monitoring LS 1
00.05 Traffic Control LS 1
00.06 Decontamination LS 1
10.01 Temporary Fencing LS 1
10.02 Clearing and Removal of Vegetation m2 92,331
10.03 Remove and Stockpile Topsoil m2 88,150
10.04 General Excavation, Fill, and Compaction m3 15,504
10.05 Fill and Compact Base with Imported Soil m3 67,256
10.06 Fill and Compact Enbankment with Imported Soil m3 26,377
10.07 Geotextile Fabric m2 40,050
10.08 HDPE Liner m2 30,400
10.09 Cast in Place Concrete, Including Reinforcing for Berm Lining LM 1,060
10.10 Cast in Place Concrete, Including Reinforcing for Ditch Lining (A) LM 490
10.11 Cast in Place Concrete, Including Reinforcing for Ditch Lining (B) LM 180
10.12 Precast Concrete Anchors LS 1
10.13 Precast Concrete Drainage Structures LS 1
10.14 Rip Rap for Toe of Berm LM 1,090
10.15 Monitoring Wells EA 4
10.16 Pumping Tests LS 1
10.17 Security Fencing LM 1,250
10.18 Control Gate LS 1
10.19 Concrete Access Road, Including Subgrade Compaction, Subbase, and Base LM 53
10.20 Temporary Access Road LM 250
10.21 Field Office LS 1
20.01 Temporary Fencing LS 1
20.02 Prepare Existing Storage Area Base LS 1
20.03 Cut Existing Berm for Leveling m3 75
20.04 Fill Portions of Existing Berm m3 225
20.05 Fill for Drainage Grading m3 110
20.06 Cast in Place Concrete Berm Leveling m3 60
20.07 Precast Concrete Blocks LS 1
20.08 HDPE Liner m2 8,700
20.09 Cable System for Anchoring HDPE Liner LS 1
20.10 Monitoring Wells EA 2
20.11 Pumping Tests LS 1
00 GENERAL
10 LONG TERM STORAGE AREA (LTSA)
20 HIGH CONCENTRATION TEMPORARY STORAGE (HCTS)
SECOND INTERIM MEASURES (IM2)
DIOXIN REMEDIATION AT BIEN HOA AIRBASE AREA PROJECT BID FORM
Bid Item No.
Bid Item Description Units Quantity Unit Price Total Amount
30.01 Temporary Fencing LS 1
30.02 Removal of Structures and Obstructions, Including Transport and Disposal LS 1
30.03 Clearing and Removal of Vegetation m2 76,089
30.04 Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement of Low Concentration Soil m3 40,813
30.05 Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement of Low Concentration Sediment m3 1,771
30.06 Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement of High Concentration Soil m3 14,371
30.07 Backfilling and Compaction m3 71,739
30.08 Topsoil m2 33,334
30.09 Seeding and Mulching m2 76,089
30.10 Roadway Subgrade Compaction m2 3,118
30.11 Roadway Subbase m3 804
30.12 Roadway Base m3 804
30.13 Roadway Asphalt m2 3,118
30.14 Plastic Pavement Striping (4" width) (Thermoplastic 90 Mil) LS 1
30.15 Permanent Pavement Markings for Speed Reduction (Rumble Strips) LS 1
30.16 Hauling Road Maintenance, Patching, Passing Areas, Widening LS 1
40.01 Off-base Fencing LM 1,567
40.02 Off-base Gates EA 4
50.01 Removal, Transport, and Disposal of Road Base and Surface LS 1
50.02 Roadway Subgrade Compaction m2 3,220
50.03 Roadway Subbase and Compaction m3 644
50.04 Roadway Base and Compaction m3 644
50.05 Roadway Asphalt m2 3,220
50.06 Plastic Pavement Striping (4" width) (Thermoplastic 90 Mil) LS 1
50.07 Permanent Pavement Markings for Speed Reduction (Rumble Strips) LS 1
60.01 $500,000.00
70.01 Treatment of Water from Excavation Dewatering m3
5,000
70.02 Treatment of Water from Soil and Sediment Dewatering m3 20,000
SUBTOTAL
60 DAY WORK
Total Day Works
TOTAL BASE BID (SUBTOTAL + DAY WORK)
70 SUPPLEMENTARY BID ITEMS
30 DIG AND HAUL
40 FENCING
50 ACCESS ROAD
SECOND INTERIM MEASURES (IM2)
DIOXIN REMEDIATION AT BIEN HOA AIRBASE AREA PROJECT BID FORM