2020-017675 IFQ Package - no plans.pdf
PDF 1 MB Posted
- Solicitation number
- IFB 410 2020-017675 2
- Issued by
- Palm Beach County, Florida
About this file
Summary
This Invitation for Quote/Bid (IFQ/B) document is issued by Palm Beach County's Capital Improvements Division for work under the county's Annual Contract for Overhead Door Replacement. The project involves repair, replacement, and reconditioning of existing doors at the PBC Convention Center's Exhibit Hall, located at 650 Okeechobee Blvd, West Palm Beach, Florida. The scope of work includes replacing crash bars, notification micro switches, hinges, tracks, hangers, rollers, safety edge wiring, motors, controls, sweeps/weather stripping, photocells, paint, signs, ADA warning strobes, and safety edges; additionally, the contractor must level panels, adjust splice plates, and conduct operational testing with the owner present. A mandatory pre-bid meeting is scheduled for April 6, 2021 at 9:00 AM at the Convention Center's Security Office at the Loading Dock. Bids are due May 13, 2021 by 2:00 PM to the Capital Improvements Division at 2633 Vista Parkway, West Palm Beach, Florida 33411. The contractor must be qualified under the Annual Contract for Overhead Door Replacement, with qualification applications due at least 10 days before the bid due date. Substantial completion is required within 120 calendar days from permit issuance, with liquidated damages of $80 per day for failure to meet this deadline. A 12-month warranty on all equipment, materials, and labor is required.
Bid security and a public construction bond of 5 percent and 100 percent of the bid amount, respectively, are required for bids of $200,000 or more. The contractor must comply with Palm Beach County's Equal Business Opportunity (EBO) Program, including the submission of completed EBO Schedules 1 and 2 detailing subcontractor participation. The contract includes two applicable Affirmative Procurement Initiatives: SBE Sheltered Market for Small Construction Contracts (reserving work orders of $100,000 or below for certified Small Business Enterprises when at least 3 SBEs are qualified) and SBE Price Preference for Single Trade Construction (awarding to a certified SBE if their bid is within 10 percent of the lowest non-SBE bid). The contractor must be registered with and utilize the E-Verify System to verify employment eligibility of all newly hired workers as required by Florida Statutes Section 448.095. All bids remain valid for 120 calendar days from the bid opening date, with the county anticipating award and written notice to proceed within 90 calendar days of notification, absent a timely bid protest.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2020-017675 Addendum One.pdf | ||
| 2020-017675 Advertisement for Project Quotes under Annual Contract -NonFederal Rev122320.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR QUOTE/BID
ANNUAL CONTRACT
DATE: March 24, 2021
SENT TO: Qualified Contractors
On the Annual Contract – Overhead Door Replacement
SENT FROM: Capital Improvements Division
SENDER: Clark Woods
PHONE: 561-233-2054
PROJECT NAME: PBC Convention Center - Exhibit Hall Door Reconditioning
PROJECT NUMBER: 2020-017675
Mandatory Pre-Bid Conference. There will be a Mandatory Pre-Bid Meeting at Palm Beach County Convention Center (meet at Security Office at Loading
Dock), located at 650 Okeechobee Blvd., West Palm Beach, FL at 9:00 AM on
April 6, 2021. The purpose of this pre-bid meeting will be to review the requirements for the project described in this Invitation for Quote/Bid. The work is to be done under the terms and conditions of Palm Beach County’s
Annual Contract – Overhead Door Replacement as supplemented by this
Invitation for Quote/Bid. You must attend this meeting if you intend to bid this work.
Questions must be e-mailed to FDO-CID-Bids@pbcgov.org
Only questions received in writing will be responded to regarding this
Invitation for Quote/Bid.
Form Rev. 2/5/21 Invitation for Quote/Bid – Nonfederal
Dave Kerner, Mayor
Robert S. Weinroth, Vice Mayor
Maria G. Marino
Gregg K. Weiss
Maria Sachs
Melissa McKinlay
Mack Bernard
Submitting the Quote/Bid Package
The Quote/Bid Package shall be enclosed in a sealed opaque envelope. The envelope shall be addressed as follows:
Project Name: PBC Convention Center - Exhibit Hall Door Reconditioning
Project Number: 2020-017675
Capital Improvements Division
2633 Vista Parkway
West Palm Beach, Florida 33411
Attention: Bid Submissions
No responsibility will be attached to the Owner for premature opening of or failure to open a quote/bid not properly identified. If the quote/bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing with the notation "SEALED QUOTE/BID ENCLOSED" on the face thereof.
PROJECT NO.: 2020-017675
DUE: May 13, 2021 by 2:00 PM
RETURN TO: Capital Improvements Division
2633 Vista Parkway
West Palm Beach, FL 33411
Qualification of Contractors. In order to submit a quote/bid in response to this IFQ/B, a contractor must be qualified under the Annual Contract –Overhead Door Replacement. A contractor may obtain a Qualification Application for this Annual Contract by sending an email with the Project # in the subject line to: FDO-CID-Bids@pbcgov.org or call (561) 233-
0261. Qualification applications may also be downloaded from the County’s on-line Vendor
Self-Service (VSS) system at https://pbcvssp.co.palm-beach.fl.us/webapp/vssp/AltSelfService. The contractor must submit the Qualification
Application at least 10 days before the Quote/Bid Due Date in order for its quote/bid to be considered.
mailto:FDO-CID-Bids@pbcgov.org https://pbcvssp.co.palm-beach.fl.us/webapp/vssp/AltSelfService https://pbcvssp.co.palm-beach.fl.us/webapp/vssp/AltSelfService
1. SCOPE OF WORK: This Quote/Bid is to furnish all material, labor, supervision, permits and supplies necessary and reasonably incidental to repair, replace and/or recondition the existing doors per the specifications provided by Capital Improvements Division in the Invitation for Quote/Bid at Attachment
“C” and/or available at the pre-bid meeting held on April 6, 2021. Work is to be done under the terms and conditions of Palm Beach County’s Annual Contract – Overhead Door Replacement, and pursuant to the conditions of the Work Order, both of which are incorporated into the Contract
Documents by reference.
2. SCHEDULE OF TIME FOR COMPLETION. The time of completion for this Project will be as follows: The Contractor shall substantially complete the work within one hundred twenty (120) calendar days from permit issuance.
3. LIQUIDATED DAMAGES. Liquidated Damages are $80/day for failure to achieve certification of
Substantial Completion within the Work Order time or approved extension thereof.
4. BID SECURITY AND PUBLIC CONSTRUCTION BOND. Bid Security and Public Construction
Bond are required for this Project in accordance with Section 5.2 of the Instructions to Bidders of the Annual
Contract as follows:
Bid Security. If Bid is $200,000 or over, this Bid shall be accompanied by a Bid Security (in the form of, at Bidder's option, cashier's check, certified check, money order or Bid Bond in favor of the County) in the amount of at least five percent (5%) of the bid price, see Section 5.2.2 of the
Instructions to Bidders of the Annual Contract for detailed requirements regarding Bid Security.
Public Construction Bond. If Bid is $200,000 or over (or if cumulative open work orders are
$200,000 or over), then prior to execution of a Work Order, and not later than fourteen (14) calendar days after notification from Owner, the successful Bidder shall furnish a Public
Construction Bond in the amount of 100% of the Work Order and Guarantee, see Section 5.2.3 of the Instructions to Bidders of the Annual Contract for detailed requirements regarding the Public
Construction Bond and Guarantee.
5. Equal Business Opportunity Program. Section 5.3 of the Instruction to Bidders of the Annual Contract sets out the requirements of the County’s Equal Business Opportunity Program. All Bidders are required to submit with their bid the appropriate EBO Program schedules in order to be deemed responsive to this
Invitation for Quote/Bid. EBO Schedules to be submitted with the quote/bid are as follows:
a) Schedule 1 - List of All Proposed Subcontractors, including S/M/WBE Participation. A completed Schedule 1 shall list the names of all subcontractors, including S/M/WBE subcontractors, intended to be used in performance of the Work Order, if awarded. This schedule shall also be used if an S/M/WBE prime bidder is performing any work and/or using any subcontractors.
b) Schedule(s) 2 - Letter(s) of Intent to Perform as a Subcontractor, including S/M/WBE Subcontractors. A Schedule 2 for each subcontractor, including each S/M/WBE subcontractor, listed on Schedule 1, shall be completed and executed by the proposed subcontractor. The type of Work to be performed by each subcontractor and the dollar value or percentage shall also be specified. Additional copies may be made as needed. A completed Schedule 2 is a binding agreement between the prime contractor and the subcontractor and should be treated as such.
Attachment “A” identifies the affirmative procurement initiatives (APIs) applicable to this Invitation for Quote/Bid.
If Bidder is unable to comply with the API requirements (Attachment “A” hereto), such Bidder shall submit a request for a waiver or partial waiver at least (7) days prior to the quote/bid due date If
Bidder requests a waiver from an API from the Office of EBO at least 7 days prior to the quote/bid due date, then the quote/bid due date will be extended pending the outcome of a waiver request.
Additionally, if the waiver is granted, the solicitation will be amended accordingly and the due date extended again.
6. Failure to Provide the Required Documents after Notification of Award. If after Notification of award from the County, the successful Bidder does not provide within 14 Days of Notification the signed
Work Order, the Public Construction Bond and Guarantee (when required), and the required certificates of insurance, the County may: 1. Call in the bid security when provided; 2. Cancel the notification of recommended award and award the project to the next responsive, responsible low bidder; 3. Terminate this Annual Contract for cause; 4. Suspend or debar the Bidder from bidding on future projects for a period of two (2) years, in accordance with the Palm Beach County Purchasing Ordinance; and/or 5. Pursue any and all remedies available against the Bidder for damages resulting from its failure to enter into a Work
Order and provide all required documents within 14 Days after notification.
7. CONTRACT AMENDMENTS. The Annual Contract is amended as follows:
The Insurance Coverage & Limit Table of General Condition 31.15 to the Contract is amended and modified as follows:
Worker’s Compensation and Employer’s Liability
Coverage not less than statutory
Employer’s Liability Limits $500,000/$500,000/$500,000
The following General Condition is added to the General Conditions:
GC 83 E-VERIFY - EMPLOYMENT ELIGIBILITY
83.1 Contractor warrants and represents that it is in compliance with section 448.095, Florida Statutes, as may be amended, and that it: (1) is registered with the E-Verify System
(E-Verify.gov), and beginning January 1, 2021, uses the E-Verify System to electronically verify the employment eligibility of all newly hired workers; and (2) has verified that all of the Contractor’s subcontractors performing any duties and obligations under this Contract are registered with the E-Verify System and beginning January 1, 2021, use the E-Verify
System to electronically verify the employment eligibility of all newly hired workers.
83.2 Contractor shall obtain from each of its subcontractors an affidavit stating that the subcontractor does not employ, contract with, or subcontract with an Unauthorized Alien, as that term is defined in section 448.095(1)(k), Florida Statutes, as may be amended.
Contractor shall maintain a copy of any such affidavit from a subcontractor for, at a minimum, the duration of the subcontract and any extension thereof. This provision shall not supersede any provision of this Contract which requires a longer retention period.
83.3 Owner shall terminate this Contract if it has a good faith belief that Contractor has knowingly violated Section 448.09(1), Florida Statutes as may be amended.
83.3.1 If Owner has a good faith belief that Contractor’s subcontractor has knowingly violated Section 448.09(1), Florida Statutes, as may be amended, Owner shall notify Contractor to terminate its contract with the subcontractor and
Contractor shall immediately terminate its contract with the subcontractor.
83.4 If Owner terminates this Contract pursuant to the above, Contractor shall be barred from being awarded a future contract by Owner for a period of one (1) year from the date on which this Contract was terminated. In the event of such contract termination, Contractor shall also be liable for any additional costs incurred by Owner as a result of the termination.
Form Rev. 2/5/21 Bid Form - NonFederal
BID FORM
PROJECT NAME: PBC Convention Center - Exhibit Hall Door Reconditioning
IN ORDER TO BE DEEMED RESPONSIVE TO THIS INVITATION FOR QUOTE/BID,
THE QUOTE/BID PACKAGE MUST CONTAIN:
a) This Quote/Bid Form completed and executed.
b) EBO Schedules 1 and 2 completed and executed.
c) Bid Security. (If the bid is $200,000 or more).
d) Signed Addenda, if any issued
THE FOLLOWING MUST BE COMPLETED AND SIGNED BY CONTRACTOR
1. TOTAL QUOTE/BID AMOUNT $ ____________
Written amount ____________
2. Bidder commits to achieving the APIs applicable to this solicitation as designated on Attachment
A and as submitted on its EBO Schedules 1 and 2.
3. Is the Bidder a Palm Beach County certified S/M/WBE? Yes_____ No_____
4. Commercial Non-Discrimination Certification. The undersigned Bidder hereby certifies and agrees that the following information is correct: In preparing its response to this Solicitation, the
Bidder has considered all proposals submitted from qualified, potential Subcontractors and suppliers, and has not engaged in "discrimination" as defined in the County’s Commercial
Nondiscrimination Policy as set forth in Resolution 2017-1770 as amended, to wit: discrimination in the solicitation, selection or commercial treatment of any Subcontractor, vendor, supplier or commercial customer on the basis of race, color, national origin, religion, ancestry, sex, age, marital status, familial status, sexual orientation, gender identity or expression, disability, or genetic information, or on the basis of any otherwise unlawful use of characteristics regarding the vendor's, supplier's or commercial customer's employees or owners; provided that nothing in this policy shall be construed to prohibit or limit otherwise lawful efforts to remedy the effects of discrimination that have occurred or are occurring in the County’s relevant marketplace of Palm
Beach County. Without limiting the foregoing, "discrimination" also includes retaliating against any person or other entity for reporting any incident of "discrimination." Without limiting any other provision of the solicitation, it is understood and agreed that, if this certification is false, such false certification will constitute grounds for the County to reject the bid submitted by the Bidder for this Solicitation, and to terminate any contract awarded based on the response. As part of its bid, the Bidder shall provide to the County a list of all instances within the immediate past four (4) years where there has been a final adjudicated determination in a legal or administrative proceeding in the State of Florida that the Bidder discriminated against its Subcontractors, vendors, suppliers or commercial customers, and a description of the status or resolution of that complaint, including any remedial action taken. As a condition of submitting a bid to the County, the Bidder agrees to
Form Rev. 2/5/21 Bid Form - NonFederal comply with the County’s Commercial Nondiscrimination Policy as described in Resolution 2017-
1770 as amended.
5. The Bidder shall be bound by the terms of its Bid for a period of one hundred twenty (120) calendar Days from the date of the bid opening and may not withdraw its Bid within that time period. If the County issues a Notification from Owner within the above 120-Day period, then the
Bidder will be bound by the Bid as submitted. If the County fails to issue a Notification from
Owner to the successful Bidder within the above identified 120-Day period, the successful bidder will not be required to honor its bid unless otherwise agreed to by both parties. County anticipates, but does not guarantee, the award of a Work Order and written notice to proceed within ninety (90) calendar Days of Notification from Owner, absent the filing of a timely bid protest.
6. It is agreed that the undersigned has received all addenda complete as issued by the County and that related costs are included in the bid submitted. The undersigned acknowledges receipt of said addenda as follows:
Addendum # dated Addendum# dated
Addendum # dated Addendum# dated
The undersigned has included the signed addenda, if issued, in its bid package.
7. The undersigned does hereby declare that the Bid covers all expenses of every kind incidental to the completion of said Work in accordance with the Contract Documents, including all claims that may arise through damages or other causes whatsoever. The undersigned does hereby declare that it shall make no claim on account of any variation from any estimate in the quantities of Work to be done, nor on account of any misunderstanding or misconception of the nature of the Work to be done or the grounds, subsurface conditions, or place where the Work is to be done.
QUOTE/BID PROVIDED BY:
Contractor Name
Date Signature
Print Name and Title
Quote/Bid Must Contain Original Signatures. No Copies or Emailed/Faxed Quotes/Bids Will
Be Accepted
REVISED 02/28/2019
OEBO SCHEDULE 1
LIST OF PROPOSED CONTRACTOR/CONSULTANT AND SUBCONTRACTOR/SUBCONSULTANT PARTICIPATION
SOLICITATION/PROJECT/BID NAME: _________________________________________ SOLICITATION/PROJECT/BID No.: ______________________________________
NAME OF PRIME RESPONDENT/BIDDER: ADDRESS: _________________________________________________________
CONTACT PERSON: _______________________________________________________ PHONE NO.: ___________________________ E-MAIL:______________________
SOLICITATION OPENING/SUBMITTAL DATE: ___________________________________ DEPARTMENT: ______________________________________________________
PLEASE LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY THE PRIME CONTRACTOR/CONSULTANT ON THIS PROJECT.
PLEASE ALSO LIST THE DOLLAR AMOUNT OR PERCENTAGE OF WORK TO BE COMPLETED BY ALL SUBCONTRACTORS/SUBCONSULTANTS ON THE
PROJECT.
(Check all Applicable Categories) Non-SBE M/WBE SBE DOLLAR AMOUNT OR PERCENTAGE OF WORK
Name, Address and Phone Number Minority/Women Small
Business Business Black Hispanic Women Caucasian Other (Please Specify)
1.
2.
3.
4.
5.
(Please use additional sheets if necessary) Total ___ _____ __ ______ _________ _________ _________
Total Bid Price $________________________________________ Total SBE - M/WBE Participation _____________
I hereby certify that the above information is accurate to the best of my knowledge: ____________________________________________________________ ______________________________________ Signature Title
Note: 1. The amount listed on this form for a Subcontractor/subconsultant must be supported by price or percentage listed on the properly executed Schedule 2 or attached signed proposal.
2. Firms may be certified by Palm Beach County as an SBE and/or an M/WBE. If firms are certified as both an SBE and/or M/WBE, please indicate the dollar amount under the appropriate category.
3. Modification of this form is not permitted and will be rejected upon submittal.
Prime:
Subcontractor(s) if any:
THearn Highlight
OEBO LETTER OF INTENT – SCHEDULE 2
Revised 09/17/2019
A completed Schedule 2 is a binding document between the Prime Contractor/consultant and a Subcontractor/subconsultant (for any tier) and should be treated as such. The Schedule 2 shall contain bolded language indicating that by signing the Schedule 2, both parties recognize this Schedule as a binding document. All Subcontractors/subconsultants, including any tiered Subcontractors/subconsultants, must properly execute this document. Each properly executed Schedule 2 must be submitted with the bid/proposal.
SOLICITATION/PROJECT NUMBER: ________________________________________________________________________________
SOLICITATION/PROJECT NAME: __________________________________________________________________________________
Prime Contractor: ___________________________________________Subcontractor:______________________________________ (Check box(s) that apply) � SBE � WBE � MBE � M/WBE � Non-S/M/WBE Date of Palm Beach County Certification (if applicable):_______________.
The undersigned affirms they are the following (select one from each column if applicable):
Column 1 Column 2 Column 3
� Male � Female � African-American/Black � Asian American � Caucasian American � Supplier � Hispanic American � Native American
S/M/WBE PARTICIPATION – S/M/WBE Primes must document all work to be performed by their own work force on this form. Failure to submit a properly executed Schedule 2 for any S/M/WBE participation may result in that participation not being counted. Specify in detail, the scope of work to be performed or items supplied with the dollar amount and/or percentage for each work item. S/M/WBE credit will only be given for the areas in which the S/M/WBE is certified. A detailed proposal may be attached to a properly executed Schedule 2.
Line Item
Item Description Unit Price Quantity/ Units
Contingencies/ Allowances
Total Price/Percentage
The undersigned Subcontractor/subconsultant is prepared to self-perform the above-described work in conjunction with the aforementioned project at the following total price or percentage:
Print Name of Prime Print Name of Subcontractor/subconsultant
By: _____________________________________________ By: ________________________________________________
Authorized Signature Authorized Signature
Print Name Print Name
Title Title
Date: ___________________________________________ Date: ______________________________________________
If the undersigned intends to subcontract any portion of this work to another Subcontractor/subconsultant, please list the business name and the amount below accompanied by a separate properly executed Schedule 2.
Price or Percentage:
Name of 2nd/3rd tier Subcontractor/subconsultant
THearn Highlight
IFQ/B ATTACHMENT “A”
Affirmative Procurement Initiatives (“APIs”) (for Fire Alarm, IAQ Remediation, Overhead Doors, Plumbing, Sportslighting Install)
AFFIRMATIVE PROCUREMENT INITIATIVES FOR CONSTRUCTION
PROCUREMENT (“API”s)
The API(s) approved for this project are selected below by ☒. Any bid that fails to comply with the API requirements after the period allowed for waiver requests has lapsed shall be deemed non-responsive. Fillable pdfs of all EBO forms can be found on the OEBO website at http://discover.pbcgov.org/oebo/Pages/Compliance-Programs.aspx. Also, see the EBO Ordinance and
Countywide PPM CW-O-043 for further information on APIs.
____ Waiver
The Office of EBO has granted a waiver of the EBO Program API(s) for this Work Order.
__X__ SBE Sheltered Market for Small Construction Contracts
When at least 3 SBEs are qualified under this contract, Work Orders $100,000 and below are reserved for competition among only certified SBEs. Small prime construction contracts (single trade or multi-trade) valued at or below $100,000 may be reserved for sheltered market competition where only certified
SBEs are eligible to submit bids or quotes.
____ SBE Subcontracting Program
A minimum mandatory goal of 20% SBE participation is established for this contract. The EBO Office shall reduce or waive this goal when there is inadequate availability of SBE prime and / or subcontractor firms. Respondents/bidders may request such waivers at least seven (7) days prior to bid opening based on submission of adequate Good Faith Efforts documentation.
__X__ SBE Price Preference For Single Trade Construction
The work orders under this contract shall be awarded to the lowest, responsive, responsible bidder unless a certified SBE’s bid is within ten percent (10%) of the lowest non-SBE bid, in which case the award shall be made to the certified SBE bidder. Construction contracts where there are no opportunities for subcontracting (i.e. single trade), may include a provision requiring awards of the contract to be made to the lowest responsive, responsible respondent or bidder unless a certified SBE’s bid is within ten (10) percent of the lowest non-small business bid, in which case the award shall be made to the certified small business bidder submitting the lowest responsive, responsible bid at the price that it bid.
____ M/WBE Subcontracting Goal*
_______% (Up to 40%) of this Contract shall be subcontracted to certified M/WBEs owned by African
American, Hispanic American, Asian American, Native American, or non-minority women persons.
The EBO Office shall reduce or waive this goal when there is inadequate availability of M/WBE prime and
/ or subcontractor firms. Respondents/bidders may request such waivers at least seven (7) days prior to bid opening based on submission of adequate Good Faith Efforts documentation. In the absence of a waiver granted by the Office of EBO, a respondent/bidder who does not commit to satisfying the M/WBE subcontracting goal shall be considered non-Responsive.
____ M/WBE Segmented Subcontracting Goals*
___________% of the M/WBE subcontracting goal shall be achieved through the utilization of certified M/WBEs owned by ☐ African American, ☐ Hispanic American, ☐ Asian American, ☐
Native American, and ☐ non-minority women persons (check applicable). M/WBE Segmented http://discover.pbcgov.org/oebo/Pages/Compliance-Programs.aspx
Subcontracting Goals are established on an individual County contract wherein an overall combined
M/WBE goal is accompanied by subsets of one or more smaller goals that specifically target the participation of a particular segment of Minority Group Member segments or the WBE segment based upon that segment’s relative availability. Such segmented goals shall specifically target the participation of a particular segment of business enterprises owned and controlled by women or certain Minority Group
Members (e.g., African-Americans, Hispanic-Americans, Asian-Americans, or Native Americans) based upon relative availability, as well as the existence of consistently and significantly greater patterns of underutilization and disparity within an industry as compared to other gender and Minority Group Member categories of M/WBEs. (For example, if an overall M/WBE subcontracting goal is set at 38% on a given contract, the segmented subcontracting goal may require that at least 23% of that 38% shall be satisfied through the utilization of African American and Hispanic subcontractors.) The EBO Office shall reduce or waive this goal when there is inadequate availability of M/WBE prime and / or subcontractor firms.
Respondents/bidders may request such waivers at least seven (7) days prior to bid opening based on submission of adequate Good Faith Efforts documentation. In the absence of a waiver granted by the
Office of EBO, a respondent/bidder who does not commit to satisfying the M/WBE segmented subcontracting goals shall be considered non-Responsive.
____ M/WBE Joint Venture/Partnership/Teaming Incentive for Contracts greater than $2.5 million
_______ (Up to 20%) evaluation points out of 100 are reserved for qualifying M/WBE joint ventures.
See, Exhibit “Z” for joint venture/partnership teaming incentive program requirements. Incentives are established to promote joint ventures, partnerships, or teaming arrangements between larger established firms and M/WBE firms, or between and among SBE and M/WBE firms. For RFPs, the incentive may be for up to twenty percent (20%) of one hundred evaluation points to be reserved for qualifying M/WBE joint ventures where the certified M/WBE joint venture partner owns 50% or greater, and performs 50% or greater of the work, of the overall joint venture. Proportionately fewer evaluation preference points would be awarded to the joint venture based upon lesser percentages of ownership by the M/WBE partner.
_____ M/WBE Evaluation Preference for RFPs for Prime M/WBE firms
_________ (Up to 15%) of the evaluation points are reserved as a preference for proposals submitted by certified M/WBE firms. Evaluation panels shall assign point preferences equal to up to 15% of the total points assigned for the evaluation, scoring and ranking of construction-related proposals submitted by those certified M/WBE firms. An M/WBE awarded a prime contract may not subcontract more than 49% of the contract value to a non-M/WBE firm.
*FINDINGS OF THE GOAL SETTING COMMITTEE FOR RACE-CONSCIOUS APIs:
Form Rev. 2/5/20 Bid Bond - NonFederal
IFQ/B ATTACHMENT B
Include Attachment B if bid is $200,000 or more
DATE:
BID BOND
STATE OF FLORIDA
COUNTY OF PALM BEACH
KNOW ALL MEN BY THESE PRESENTS: That we, (hereinafter called "Principal"), and
(hereinafter called "Surety") are held and firmly bound unto Palm Beach County, a Political Subdivision in the State of Florida, by and through its Board of
County Commissioners, (hereinafter called "County") in the sum of
Dollars,($ ), (which sum is at least 5% of the bid price), lawful money of the United States of America, for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly be these presents;
WHEREAS, the "Principal" contemplates submitting or has submitted a bid to the Board of County
Commissioners, Palm Beach County, Florida, for furnishing and paying for all necessary labor materials, equipment, machinery, tools, apparatus, services, all state workmen's compensation and unemployment compensation taxes incurred in the performance of the Contract, means of transportation for and complete
Construction of: PBC Convention Center - Exhibit Hall Door Reconditioning, Project Number 2020-
017675, in the County of Palm Beach, State of Florida; and
WHEREAS, it was a condition precedent to the submission of said bid that a certified check cashier's check, money order or bid bond in the amount of five percent (5%) of the base bid be submitted with said bid as a guarantee that the bidder would, if given a Notification from Owner, enter into a written contract with the
County, and furnish a public construction bond in an amount equal to one hundred (100%) of the total
Contract, within fourteen (14) consecutive calendar days after the County issues the Notification from
Owner.
NOW THEREFORE, THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, if the bid of the "Principal" herein is accepted and said "Principal", within fourteen (14) consecutive calendar days after written notice being given of such acceptance, (i) enter into a written contract with the County and (ii) furnishes a public construction contract bond in the amount equal to one hundred percent (100%) of the total contract amount and in a form satisfactory to the County, then this obligation shall be void. If the
Principal fails to complete (i) and (ii) above, the sum herein stated shall be due and payable to the "County", and the "Surety" herein agrees to pay said sum immediately upon demand of the "County", in good and lawful money of the United States of America, as liquidated damages for failure of said "Principal".
Bid Bond Must Contain Original Signatures. No Copies Will Be Accepted.
Form Rev. 2/5/20 Bid Bond - NonFederal
DATE:
IN WITNESS WHEREOF, the said as "Principal" herein, has caused these presents to be signed in its name, by its
, and attested by its under the corporate seal, and the said as "Surety" herein, has caused these presents to be signed in its name, by its
, and attested by its corporate Seal, this day of , A.D., 20 .
ATTEST:
Print Name
TITLE:
(SEAL)
(Contractor Name)
By:
(Signature)
Print Name and Title:
ATTEST:
Print Name
TITLE:
(SEAL)
(Surety Name)
By:
(Signature)
Print Name and Title:
Bid Bond Must Contain Original Signatures. No Copies Will Be Accepted.
IFQ/B ATTACHMENT C
PROJECT REQUIREMENTS
Annual Contract – Overhead Door Replacement
Contact: Clark Woods, Capital Improvements Division Phone: (561) 233-2054 Project Title: PBC Convention Center - Exhibit Hall Door Reconditioning Project #: 2020-017675 Project Location: 650 Okeechobee Blvd, West Palm Beach, FL
1. GENERAL
a. The work covered by this Request for Quote consists of, but is not limited to, the furnishing of all labor, equipment, devices, tools, materials, transportation, professional services, supervision, drawings, permitting and all miscellaneous requirements to perform all operations necessary to accomplish the work set forth below and shall be considered part of the Scope of Work.
b. Please reference the Annual Contract – Overhead Door for additional requirements.
c. Work to be completed during the hours of 7:30 am to 5:00 pm, Monday through
Friday. Special accommodations for additional hours will need to be coordinated with staff. All work will be conducted around the Convention Center’s schedule.
The general contractor and subcontractor shall be responsible for coordination of their work with the schedule of events held at the Convention Center, other crafts and contractors working on the same job, and with the Management Company or owner.
d. Contractor shall contact the Project Manager, within seventy-two (72) hours of
Notice to Proceed to establish scheduling etc. required for project implementation.
e. Work to be completed within one hundred twenty (120) days from permit issuance.
Permit application or receipt of materials, if required, is the responsibility of the Contractor and is to be submitted within five (5) days after Notice to Proceed, order within five (5) days after approval and due diligence exercised to address all Building Department comments.
f. Liquidated damages will accrue in the amount of $80 per day.
g. Contractor is responsible for obtaining all measurements during the site inspection.
2. SCOPE OF WORK
a. Scope consists of the repair, replacement and/or reconditioning of the existing doors (Saino model 1010 sliding fire door(s) with a 2-hour fire rating, Model F1900- PLC, and with electric motor and automation kit. Automatic close system with thermal heat detectors and heavy-duty hardware). Refer to Exhibits “1” and “2”.
1. Replace all crash bars on man doors.
2. Replace all door notification micro switches & brackets.
3. Replace all hinges on man doors with self-closing hinges compatible with Series 888 hardware.
4. Replace all door tracks and hangars with 12 gauge box track and hardware.
5. Replace all rollers and roller brackets to match above.
6. Replace all looped safety edge wiring with retractable reels.
7. Replace all motors (automation kit), controls, emergency stop and automation capabilities as indicated below:
a) Automation kit - Shall be listed and labeled under UL325, UL228 and
UL924. Supply voltage shall be 120 volt A.C., single phase, with a 24 volt control circuit. Motor shall be a 90 volt, ½ HP D.C. permanent magnet type with a right angle gearhead reduction. Proximately switches for controlling door position will be furnished and shall mount on a continuous track for infinite adjustment. A pneumatic reversing edge shall also be furnished.
b) Controls – Control box will be mounted separately on the wall for access from the floor. Two ceiling pull cord switches will be furnished for door actuation. The control circuit will allow for initial or for future addition of various options including time delay, warning bell or lights, interlock and partial open from a separate actuator.
c) Emergency Stop - Upon power failure or emergency signal from a heat detector (or fire alarm system if required), the door will begin to move to the closed position within 10 seconds (time delay must be adjusted during start-
up) and emit an audible alert until the door has closed. If, while closing the door meets an obstruction, the reversing edge will signal the operator to stop, delay for not more than 10 second, then try to close again. Any non-powered actuator (such as a push button station) that opens the door under normal conditions will also open the door under emergency mode, as along as the signal is maintained and the heat on either side of the opening has not reach 500 square feet. When the signal is released, the door will begin to close within 10 seconds. The door will not open under battery if the heat on the either of the opening rise above 500 degrees Fahrenheit. When signal from the heat detectors is restored and the power is returned, the door will function as normal.
d) Automation Capabilities – Motor control shall be accomplished using an electronic control package providing electronic braking for smooth stopping and reversing. The control circuit will allow for two speed operation with the opening and closing speeds independently and infinitely adjustable and will have the diagnostics for easy setup and servicing. The door can open at one speed and close at another speed up to the maximum run speed of 24″ per second (48″ per second for center parting door). The door will slow down and creep into both the open and closed positions.
8. Replace all sweeps/weather stripping & vertical strip/gasket.
9. Replace all safety photocells.
10. Junction boxes on every door to be hard wired.
11. Paint all doors (interior & exterior) of doors. Prime coated with Pro Industrial Procryl Universal Metal Primer (B66-310 Series), or PBC approved equal, and finish coated with Pro Industrial Waterbased Alkyd Urethane Enamel Semi-gloss (B53-1150 Series), or PBC approved equal.
12. Replace all signs with equal to match existing.
13. Replace ADA warning strobe/horn.
14. Replace electric Safety edge (front & back).
15. Level panel & adjust splice plates and replace all bolts.
16. Test operation with Owner present.
3. SUBMITTALS
All submittals shall be sent to the Project Manager for approval. This includes, but is not limited to, products to be used, methods of installation and requests for information and/or clarification. All submittals must be made by the Contractor and must include all details necessary for the Project Manager and Palm Beach County to make any necessary determinations. A transmittal form must be included which clearly requests data or information and deviations from the contract requirements for which approval is being requested. Failure to provide sufficient information will result in the rejection of the submittal. Where the specifications do not specify a brand name product or where a substitution of a product is not specifically prohibited, the Contractor shall submit their selected products for approval by the Project Manager. Such submittals shall include as much detail, and in a format, as required by the Project Manager, so as to allow the Project Manager to evaluate the proposed substitution.
4. MATERIALS
a. All material shall meet or exceed Florida Building Code at the time of the original door installation and product submittals shall be reviewed and approved by the Owner’s Representative prior to ordering.
b. Materials shall be delivered in their original, unopened packages, and protected from exposure to the elements. Damaged or deteriorated materials shall not be used.
5. TEMPORARY PROTECTION
The Contractor shall protect all workers, staff and the general public from injury. The Contractor shall coordinate and schedule all work with the Project Manager.
6. PROJECT CONDITIONS
Contractor is to coordinate all space and security requirements with the Project Manager. A construction schedule shall be submitted for review and approval prior to pre-construction meeting, including a start date, substantial completion date, and work plan defining which openings will be scheduled on what day. The Contractor shall conduct all work so as to cause the least interference possible with the normal activities of the operations of the facility and surrounding areas. Work can be performed during normal operating hours, but coordinated around event schedules and may not interfere with any scheduled events. Any damage caused by Contractor (including landscaping and irrigation) shall be the responsibility of the Contractor to repair and return to its original state.
7. PREPARATION
It shall be the responsibility of the Contractor to prep the site at the construction locations.
8. EXAMINATION
Report to the Project Manager, in writing, any imperfections, unacceptable conditions and/or corrections required to be made before commencing work. Any items not identified, documented and reported to PBC in writing, will become part of the contractors’ scope. All other items identified in writing, if approved, shall result in a change order.
9. INSTALLATION
All materials shall be installed in strict accordance with Manufacturer’s written instructions and recommendations. All work shall be done in conformance with applicable Federal, State and Local codes, and established standards.
10. WARRANTY
Contractor warrants all equipment, materials and labor furnished or performed against defects in design, materials and workmanship for a period of twelve (12) months from substantial completion.
11. CLEAN UP
Remove all waste materials, tools and equipment from job site daily. Thoroughly clean the entire job area prior to requesting final inspection.
12. SECURITY
This project is subject to: [ ] Critical Facilities Background Check
[ ] CJI Facilities Background Check [X] No Background Check
Exhibit "1" 7 pages
Exhibit “2”
Confidential floor plan may be obtained by contacting FDO-CID-Bids@pbcgov.org or calling
(561) 233-0261.
mailto:FDO-CID-Bids@pbcgov.org
| 2020-017675 Invitation for Quote - Annual Contract - Non-Federal Rev 020521 LETTERHEAD |
| 2020-017675 Attachment C Project Requirements |
| 2020-017675 Exhibit 1 |
| 2020-017675 Exhibit 2 - No Plans |
| NAME OF PRIME RESPONDENTBIDDER: |
| Total Bid Price: |
| Text2: 2020-017675 |
| Text3: |
| Text4: |
| Text5: |
| Text6: |
| Text7: |
| Text8: |
| Text10: |
| 0: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| 1: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| 2: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| 3: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| 4: |
| 1: |
| 2: |
| 3: |
| 4: |
| 0: |
| 0: |
| 1: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| Check Box1: |
| 0: |
| 0: Off |
| 1: Off |
| 2: Off |
| 1: |
| 0: Off |
| 1: Off |
| 2: Off |
| 2: |
| 0: Off |
| 1: Off |
| 2: Off |
| 3: |
| 0: Off |
| 1: Off |
| 2: Off |
| 4: |
| 0: Off |
| 1: Off |
| 2: Off |
| Text9: |
| 0: |
| 1: |
| 2: |
| 3: |
| 4: |
| Text15: |
| Text16: |
| Project Name: PBC Convention Center - Exhibit Hall Door Reconditioning |
| SOLICITATIONPROJECT NUMBER: 2020-017675 |
| SOLICITATIONPROJECT NAME: PBC Convention Center - Exhibit Hall Door Reconditioning |
| Prime Contractor: |
| Subcontractor: |
| Date of Palm Beach County Certification if applicable: |
| Line ItemRow1: |
| Item DescriptionRow1: |
| Unit PriceRow1: |
| Quantity UnitsRow1: |
| Contingencies AllowancesRow1: |
| Total PricePercentageRow1: |
| Line ItemRow2: |
| Item DescriptionRow2: |
| Unit PriceRow2: |
| Quantity UnitsRow2: |
| Contingencies AllowancesRow2: |
| Total PricePercentageRow2: |
| Line ItemRow3: |
| Item DescriptionRow3: |
| Unit PriceRow3: |
| Quantity UnitsRow3: |
| Contingencies AllowancesRow3: |
| Total PricePercentageRow3: |
| Line ItemRow4: |
| Item DescriptionRow4: |
| Unit PriceRow4: |
| Quantity UnitsRow4: |
| Contingencies AllowancesRow4: |
| Total PricePercentageRow4: |
| Line ItemRow5: |
| Item DescriptionRow5: |
| Unit PriceRow5: |
| Quantity UnitsRow5: |
| Contingencies AllowancesRow5: |
| Total PricePercentageRow5: |
| Line ItemRow6: |
| Item DescriptionRow6: |
| Unit PriceRow6: |
| Quantity UnitsRow6: |
| Contingencies AllowancesRow6: |
| Total PricePercentageRow6: |
| at the following total price or percentage: |
| Name of 2nd3rd tier Subcontractorsubconsultant: |
| Print Name of Prime: |
| By: |
| Print Name: |
| Title: |
| Date: |
| Price or Percentage: |
| Print Name of Subcontractorsubconsultant: |
| By_2: |
| Print Name_2: |
| Title_2: |
| Date_2: |