| File | Type | Posted |
|---|---|---|
| Maroon_Creek_TBR-SOW 6-17-2020.docx | DOCX document | |
| 20200616MaroonBellsPreBidQA.DOCX | DOCX document | |
| Bid_Bond_SF24.pdf | ||
| Payment_Bond_SF25A-16a.pdf | ||
| Performance_Bond_SF25-16a.pdf | ||
| Experience_Questionnaire (1).doc | DOC document | |
| 20190710MaroonCrTBR-Specs (1).doc | DOC document | |
| Maroon_Creek_TBR-SOW 5-27-2020.docx | DOCX document | |
| DirectionsToMaroonBellsWelcomeStation.pdf | ||
| wage decision CO20200013.pdf | ||
| SF 1442 5-27-2020.pdf | ||
| 20190720MaroonScenicPlansSIGNED (1).pdf | ||
| 20190710MaroonCrTBR-FirePlanWRNF (1).docx | DOCX document | |
| 20190718WMPLTBplansSIGNED (2).pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| STANDARD SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND TRAIL | |||
| BRIDGES ON FOREST SERVICE PROJECTS | |||
| Specification List | |||
| Project Name: Maroon Scenic Bridge Replacement, White River National Forest | Title | Trail Number | |
| Specification Number: | 2197 | 1982.1A | |
| 900 | General Requirements | X | X |
| 901 | Terms, Format, Abbreviations, and Definitions | X | X |
| 902 | Intent of Contract | X | X |
| 903 | Control of Work | X | X |
| 904 | Control of materials | X | X |
| 905 | Quality Assurance and Quantity of Measurement | X | X |
| 906 | Measurement and Payment | X | X |
| 907 | Mobilization | X | X |
| 908 | Construction Survey, Staking, Flagging and Cleanup | X | X |
| 909 | Maintenance for Traffic and Temporary Construction Access | X | X |
| 910 | Trailway | X | X |
| 911 | Tread and Prism | X | X |
| 912 | Clearing Limits | X | X |
| 913 | Surfacing | X | |
| 918 | Foundations | X | X |
| 964 | Prefabricated Steel Trail Bridges | X | X |
| 965 | Trail Bridge Substructures | X | X |
| 971 | Riprap for Streambanks and Foundation Protection | X | X |
| 983 | Removal of Structures and Obstructions | X | X |
| 989 | Soil Erosion, Sediment Control and Pollution Prevention | X | X |
| 990 | Materials | X | X |
| 991 | Rock, Grid Pavement Units, Aggregate and Asphalt | X | X |
| 994 | Geosynthetics | X | X |
| FP-14 Section 101 | Terms, Format, and Definitions | X | X |
| FP-14 Section 107 | Legal Relations and Responsibility to the Public | X | X |
| FP-14 Section 552 | Structural Concrete | X | X |
| FP-14 Section 554 | Reinforcing Steel | X | X |
| FP-14 Section 555 | Steel Structures | X | X |
| FP-14 Section 717 | Structural Metal | X | X |
| Note: All of the specifications cited are applicable to this project. The other specifications are within the 2014 Standard | |||
| Specifications for Construction of Roads and Bridges on Federal Highway Projects. Other specifications referred to | |||
| within these specifications (even though not specifically listed herein) are also fully applicable to this project. |