2016.08.01 TMA - Mitigation Plan.pdf
PDF 15 MB Posted
- Solicitation number
- 37700
- Issued by
- Fairfield County, Connecticut
About this file
This is a mitigation plan document prepared for The Maritime Aquarium at Norwalk, Connecticut, developed in response to the Connecticut Department of Transportation's Walk Bridge replacement project. The plan was commissioned by TMA and prepared by Cambridge Seven Associates, Inc., the architecture and exhibit design firm responsible for previous aquarium renovations. The mitigation plan addresses the immediate impacts of the bridge construction scheduled to begin in 2018, which will disrupt access to the IMAX Theater, eliminate outdoor exhibit spaces, and expose sensitive animal species to harmful noise and vibrations. The comprehensive master plan recommends a phased approach to expansion and renovation, with the highest priority given to protecting the health and well-being of the seals and meerkats by relocating and enclosing their exhibits prior to construction commencement.
The proposed improvements include increasing the total building square footage from 123,678 to 154,280 square feet (a 25 percent increase) and dramatically expanding water volume from 230,448 gallons to 821,827 gallons (a 356 percent increase). Major capital additions recommended include a new two-story seal tank (180,000 gallons), expanded shark tanks (320,000 gallons total), new turtle exhibit (63,868 gallons), penguin exhibit (8,407 gallons), coral reef exhibit (47,932 gallons), and Stellwagen Banks exhibit (42,000 gallons), along with replacement of the IMAX Theater with a new 4D theater, a new event space accommodating up to 500 people, and enhanced visitor circulation and lobby facilities. The plan is organized into four construction phases prioritized to maintain public access during implementation, with Phase 1a addressing the most urgent animal welfare concerns related to bridge construction, and subsequent phases introducing new exhibits themed around the "Currents" concept linking Long Island Sound to global conservation issues.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Walk Bridge Mitigation Plan August 1, 2016
1Mitigation Plan
Table of Contents Executive Summary
Analysis
Design Concepts
Summary
This Mitigation Plan has been developed with the contributions and support of the following individuals.
The Maritime Aquarium
Dr. Brian Davis, President & CEO
Prisco DeMercurio, CPA, Chief Financial Officer
Dave Truedson, Director of Operations
John Lenzycki, Curator of Animals
Thomas Frankie, Exhibit Manager
Cambridge Seven Associates, Inc.
Peter Kuttner, FAIA, President
Penny J. Sander, Project Manager
Paul Herbert, Designer
Steven Colson, Designer
Acknowledgements
3Mitigation Plan
Executive Summary
4 Mitigation Plan
The Maritime Aquarium
Executive Summary
Mission
The Maritime Aquarium inspires people of all ages to appreciate and protect the Long Island Sound ecosystem and the global environment through living exhibits, marine science, and environmental education.
The Maritime Aquarium is the sole aquarium that focuses on Long Island Sound. From this core, the institution explores animals and related conservation issues from around the world. Its exhibits, admired for their quality and dramatic elegance, are carefully designed to give people of all ages entertaining, educational, and emotional experiences with animals in order to instill a sense of wonder in the diversity of nature.
A constantly evolving facility, The Maritime Aquarium offers visitors personal interactions with animals and interpretation by knowledgeable staff and volunteers. With its welcoming atmosphere, focus on service to visitors, and outstanding amenities, The Maritime Aquarium is the premiere family destination in the region, attracting large numbers of return visitors. As it has grown, The Maritime Aquarium has retained its intimate scale and remains a beloved institution with deep ties to its community.
Vision
Anchored by its collection, The Maritime Aquarium offers preeminent visitor experiences and education programs widely admired for their depth and innovation. The Maritime Aquarium supports an active collaborative research program on species and natural systems related to its collections. It is a regional forum for the dissemination of information related to Long Island Sound and the oceans.
The Maritime Aquarium’s ultimate goal is to help people recognize that Long Island Sound enriches the quality of their lives and must be protected.
5Mitigation Plan
Executive Summary
Introduction The Maritime Aquarium (TMA), located on the site of a former 1860s iron works factory, opened its doors to the public in July 1988. Since then, TMA has been the anchor for the revitalization of South Norwalk, an area that now bustles with boutiques, nightclubs, acclaimed restaurants, and cinemas. TMA’s annual attendance averages 450,000 visitors, making it one of the largest attractions in Connecticut. Over the years, TMA has expanded with new classrooms, gift shop, food service, and a new entrance in 2001, and a major refurbishment in 2012 that focused on expanding the story of Long Island Sound through new exhibits, including a large Long Island Sound map, the interactive exhibit, “Found in the Sound,” and a new shark and ray touch pool.
Looking ahead to the near future, TMA must address the imminent impact of the Walk Bridge replacement project that is being undertaken by the Connecticut Department of Transportation (CTDOT). The bridge, which stands between TMA’s Maritime Hall and its IMAX Theater, carries four tracks of Metro- North Railroad, Amtrak, and freight service.
The three- to five-year construction period, scheduled to begin in 2018, will cut off access to the IMAX Theater from Maritime Hall, and it will impinge on TMA’s outdoor spaces. The Go Fish, Meerkats, and Dragons exhibits will need to be removed and relocated, as the tent structure will need to be removed, and most importantly, the noise and vibrations from the bridge construction will harm the well-being of several species in the facility, most notably the
Harbor Seals and Meerkats, unless immediate action is taken.
This master plan looks at expanding TMA’s storyline to link visitors’ personal engagement with Long Island Sound with global conservation issues, including climate change and ocean rise, through the theme of “Currents.” This will allow the addition of new, exotic animals, including more jellyfish, corals, and penguins. The plan also looks at how TMA turns the Walk Bridge replacement project to its advantage by re-imagining some of the institution’s key animal exhibits and exploring some of the newest types of theater experiences. Lastly, the master plan looks towards the future with ways to increase earned income through unique rental offerings and premium experiences.
The Planning Process The Maritime Aquarium commissioned Cambridge Seven Associates, Inc. (C7A), to develop the mitigation plan. C7A is the architecture and exhibit design firm that transformed Newman’s Own Hall and developed the Sharks & Rays Gallery in 2012.
The master planning process went through several stages, starting with an analysis phase, and followed by an alternatives phase, and finally the synthesis phase.
During the Analysis Phase, the current status of TMA exhibits, programs, the site, and the building itself were evaluated, with additional input from the TMA core team. In addition, the impact of the Walk Bridge replacement program was one of the primary drivers of the plan, due to its looming eventuality. The health of the animals was the main priority. The team ultimately organized its investigation into twenty program areas: eight focus on existing macro alternatives focused on the Event and Currents gallery off of Maritime Hall, while two schemes focused on the Shark, Jelly, and Otter experiences in the aquarium wing. The team discussed the pros and cons of each scheme, before choosing a direction. The design team then further developed several conceptual alternatives with more details associated with back-of-house spaces, adjacencies, visitor experiences, and phasing recommendations for the exhibit galleries, lobby, and theater that had been previously analyzed.
At the beginning of the Synthesis Phase, the team evaluated all of the individual alternatives for each program area, and prioritized their selections. The team then looked at how the various elements could be grouped and constructed while TMA remains open to the public.
www.walkbridgect.com
Replacement of the Walk Bridge Project
The Walk Bridge replacement project exhibits and spaces; six reflect the impact of the bridge, and six present the vision for the future of TMA.
The analysis helped the team develop groups of specific program areas that could be further developed on a macro and a micro level. The largest elements involved a new “Currents” gallery, new event space, and additions to the Shark, Jellies, and Otter exhibits. Several alternatives were developed to show the large-scale changes that could occur. Two
6 Mitigation Plan
The Maritime AquariumThe Maritime Aquarium
Recommendations The final recommended plans can be found on pages 56 through 59, followed by detailed charts of program areas, tank volumes, and recommended construction phases.
While the total square footage of TMA increases only 25% from 123,678 to 154,280, the water volume of the facility increases 356% from 230,448 gallons to 821,827 gallons.
The additional 30,600 square feet is reflected in the replacement of the Go Fish/Meerkat/ Dragon tent with a new two-story space, the replacement of the IMAX Theater with a new 4D Theater, expansion of the Otter gallery, and a new Lobby/Entry. The increase in water volume is due mostly the addition of a second Shark tank, a new, larger Turtle tank, a new, two-story Seal tank, and new Otter, Stellwagen, Chandelier/Schooling Fish, Coral Reef, and Penguin tanks.
Additions The orange areas indicate the building additions that are proposed as part of this master plan.
A
E
Renovations The gold areas indicate the interior renovations that are proposed as part of this master plan.
Existing Areas The gray areas indicate the existing spaces that will remain throughout the duration of the phased construction periods.
R
Level 2
Level 1
7Mitigation Plan
Analysis The Analysis Phase focuses on documenting and prioritizing the current conditions of The Maritime Aquarium. During several site visits, the C7A team toured the building to under-stand its existing conditions, reviewed TMA’s educational program goals and operational issues, and met with TMA’s core team of administrators and staff representing animal husbandry, visitor services, and exhibits to understand the mission and future vision of the institution.
The team paid particular attention to the major disruptions that will be caused by the impending construction of a new railroad bridge adjacent to TMA. The health and well-being of TMA’s animals—specifically its seals, meerkats, and species in the current “Go Fish” tank—were thoroughly addressed.
The end result of this phase is a compilation of the findings of the different search efforts, along with an approximation of the eventual program area requirements, and phasing recommendations.
9Mitigation Plan
Analysis
Map data ©2016 Google 100 ft
P
IMAX
Walk Bridge
Amtrak & Metro-North To Bridgeport
To Danbury
Garage Entry
Old Entry
Future Bridge Staging
Site Analysis
Riverwalk Pavilion
Existing Entry
Norwalk River
Car approach
Car approach
The Maritime Aquarium is located on a unique and interesting, yet challenging, site near the center of South Norwalk (SoNo). It is highly visible from the Amtrak and Metro-North train as it crosses the Walk Bridge, which unfortunately passes between two parts of the building. The complex suffers from multiple apparent front doors, which can be confusing to visitors. The IMAX entry on the south fronts roughly towards Washington Street, the vehicular bridge to Norwalk, and the CBD for SoNo. Other approaching traffic coming from routes 95 and 15 are guided to a different current main entry to the north. A third earlier entry on the west side, directly facing the Aquarium parking garage entry, is currently closed.
The main museum is a conglomerate of existing industrial buildings joined with a few new additions, arranged along the Norwalk River on a narrow and constrained site. While the buildings abut the river, the visitor experience turns its back on the water vista. One opportunity to go outdoors is adjacent to the seal exhibit, with a nice outdoor picnic area, but the view to the east is mostly obscured by the building.
There is a Riverwalk under development in the area, with a covered pavilion where Ann Street meets the river. At present, the Riverwalk does not embrace the Aquarium, as it is blocked by the IMAX extending to the water’s edge.
Also, existing services to this side of the river are enclosed with a fence, further confusing the public areas from the paid zone along the water’s edge.
Picnic Area
Service
The Maritime Aquarium is situated on a highly visible site in downtown South Norwalk.
To Stamford
10 Mitigation Plan
Analysis
LEVEL DEPARTMENT
EXISTING
AREA (SF)
PROPOSED
AREA (SF) Delta
1 ADMIN 1004 1700 696
1 BOH 1928 1928 0
1 CIRCULATION 3874 3808 -66
1 EDUCATION 2189 2189 0
1 EXHIBIT GALLERY 13713 14940 1227
1 LOBBY 7532 16000 8468
1 LSS 3612 7355 3743
1 MECH 1047 1830 783
1 RESEARCH 493 1860 1367
1 STORAGE 6465 5700 -765
1 TANK 2929 7880 4951
1 THEATER 8759 2700 -6059
1 VISITOR SERVICES 3959 4530 571
2 ADMIN 2353 2870 517
2 BOH 2436 2436 0
2 CAFÉ 3384 3384 0
2 CIRCULATION 5492 6813 1321
2 EVENT SPACE 0 8030 8030
2 EVENT PATIO 0 2200 2200
2 EVENT KITCHEN 0 500 500
2 EXHIBIT GALLERY 10946 13367 2421
2 LSS 1720 5664 3944
2 MECH. 1385 1350 -35
2 STORAGE 329 859 530
2 TANKS 1190 5657 4467
2 THEATER 8759 0 -8759
2 VISITOR SERVICES 392 942 550
3 ADMIN 6092 6092 0
3 BOH 4931 4931 0
3 CIRCULATION 5350 5350 0
3 EDUCATION 1270 1270 0
3 LSS 3972 3972 0
3 MECH. 5271 5271 0
3 STORAGE 902 902 0
SUBTOTAL: 57,504
TOTAL MUSEUM (SF): 123,678
SUBTOTAL: 38,386
SUBTOTAL: 27,788
Building Analysis
The Maritime Aquarium is comprised of several old warehouse structures and a few newer additions. The team toured TMA’s public areas, administrative offices, back-of house facilities, and storage rooms to see how the spaces in the building are currently being used and to evaluate their condition. The impending loss of the IMAX Theater and the tent where Go Fish and the Meerkats are housed, was also noted.
The total area of TMA is 123,678 square feet.
11Mitigation Plan
Analysis
Existing Space Use
The Maritime Aquarium has all of its public spaces on levels 1 and 2, while the bulk of the administrative offices are located on level 3.
Other back-of-house areas are found on much of level 3 and in a few areas on level 1. Much space is given to circulation down the long corridors of each wing. The gift shop is near the entry/exit, while the café is on level 2. The IMAX Theater is accessible at the southern entry or down a long hallway at the far end of Maritime Hall.
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - PROGRAM
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2 PROGRAM
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 Level 3 Floor Plan - Program
IMAXMeerkats
Jiggle JellyBehind the Scenes
Ray Touch Tank
Long Island Sound Map
Go Fish
Seals
Storage
Jellies
Turtles
Gift Shop Classrooms
LSS
Level 1
Level 2
Level 3
Ocean Play SpaceReptiles
Administration
CafeKitchen
Salt Marsh
Otters
Schooling Fish Sharks
AdministrationLSS
LSS / BOH
Administration
Circulation
Exhibits
Events
Education
LSS / BOH
Theater
Cafe
Admin
Visitor Services
Research
12 Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 FLOOR PLAN
Admin
Visitor Experience
Research
Level 1
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 Level 3 Floor Plan
IMAX
Meerkats
Jiggle JellyBehind the Scenes
Ray Touch Tank
Long Island Sound Map
Go Fish
Seals
Storage
Jellies
Turtles
Gift Shop
Classrooms
LSS
LSS
LSS / BOH
Administration
Administration
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2
Ocean Play SpaceReptiles
Administration
CafeKitchen
Otters Sharks Salt
Marsh
Schooling Fish
Level 3
Level 2
Existing Circulation
Circulation through TMA is circuitous and sometimes confusing to visitors. With ticketing at the far north end of the building, visitors walk through the first long hallway, past the gift shop, with little else to see before they arrive at Newman’s Own Hall at the heart of the building on Level 1. From this point, they decide either to continue on Level 1 to Maritime Hall or take the elevator up to Level 2 and follow the Long Island Sound storyline through the Aquarium wing of the building.
While the length of Maritime Hall is a given, the exhibits along its length diminish greatly after the Ray Touch Tank. Additionally, the elevator to Level 2 in Maritime Hall is centrally located;
therefore, visitors often miss the exhibits at the far end of the Hall. New exhibits will help animate this space and extend the length of visits. The second level of Maritime Hall has a few ship models before visitors reach the Play Area and Reptile Exhibit.
In the Aquarium wing, the circulation is a one-way path through the Salt Marsh, Otters, Schooling Fish, and Shark Tank, which leads visitors back down to Level 1. At this point, however, the organization of the Turtles and Jellies exhibits is not clear, and visitors can easily miss the Jellies exhibits if they head straight to the Turtles.
The IMAX Theater entry at the south end of the building adds further confusion to the circulation path.
13Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2 TANK PLAN
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 Level 3 Floor Plan
Meerkats
Jiggle JellyBehind the Scenes
Ray Touch Tank
Long Island Sound Map
Go Fish
Seals
Storage
Jellies
Turtles
Gift Shop
Classrooms
LSS
Level 1
Level 2
Level 3
Ocean Play SpaceReptiles
Administration
CafeKitchen
Salt Marsh
Otters
Schooling Fish Sharks
Administration
LSS
LSS / BOH
Administration
Existing Aquarium Tanks
The Maritime Aquarium ‐ Tank Schedule
EXISTING
GALLONS
LEVEL 1
SHARK TANK 110,000
SHARK RAMP TANKS 561
TURTLE TANK 19,635
JIGGLE A JELLY 583
RESEARCH TANKS 479
EXOTICS
JELLY LSS TANKS 449
JELLY GALLERY TANKS 3,863
SEAL TANK 19,000
SEAL HOLDING TANK 2,431
RAY TOUCH TANK 5,640
CAMOUFLAGE TANK 247
EGG TANKS (2) 90
PYRAMID TANK 284
CORAL REEF TANKS 314
GO FISH TANK/STELLWAGEN 26,704
CHANDELIER TANK
PENGUIN TANK
TOTAL LEVEL 1 190,280
LEVEL 2
SCHOOLING TANK 1,555.84
TOUCH TANK 561.00
WALL TANK 598.40
SEMI‐CIRCULAR FISH TANKS (5) 8,078.40
OTTER TANK 2,992
FISH TANK (ADJ TO OTTERS) 673
COLUMN TANKS / SALT MARSH 505
TURTLE TANK (ADJ TO COLUMNS) 90
TOTAL LEVEL 2 15,054
LSS / Holding (approximate) 25,115
TOTAL 230,448
14 Mitigation Plan
Analysis
1,955,000 gal 2,906,000 gal 396,000 gal
1,997,000 gal
2,008,000 gal
502,000 gal 608,000 gal 640,000 gal 642,000 gal
7,600
2,400
1,997,000 gal
2,008,000 gal 7,600
Aquarium Comparative Size StudyWater Volume
The Maritime Aquarium’s total water volume of 230,000 gallons is on the low side, if TMA wants to compete with major aquariums in the USA and around the world. Except for the 110,000 Shark Tank and the five largest tanks that total approximately 75,000 gallons, the remaining tanks on view are relatively small in volume, and thus have limited impact.
The Maritime Aquarium Norwalk, Connecticut, USA Total Water Volume: 870 m3 = 230,000 gallons
M
ASTER
PLAN
PH
ASE
25 FEBR
U
AR
Y 2016
1" = 50'-0"
LEVEL 1 - TAN
K PLAN
14 Mitigation Plan
15Mitigation Plan
Analysis
Aquarium Comparative Size Study
Cambridge Seven Associates, Inc. Attraction and Museum Data
Attractions Economics Area Fee Mgmnt Animals and Water Notes
Name Location Opening Date
Stabilized Annual Attendance
Adult Ticket Price
(USD)
Child Ticket Price
(USD)
Annual Budget
Building Area (Sq.
Feet)
Building Area (Meters)
$ Cost % Director Total Water Volume (Gallons)
Total Water Volume (Cubic Meters)
Largest Exhibit Volume (Gallons)
Largest Exhibit Volume (Cubic Meters)
Total Number of Specimens
Special Features
New England Aquarium Boston, MA 1969 1,300,000 8.50 77,822 7,233 642,127 2,430 186,824 707 10,000
National Aquarium Baltimore, MD 1981 1,450,000* 11.50 $23,569,000* 209,077 19,431 1,997,729 7,560 1,298,524 4,914 8,560 2006 added Australia exhibit
Ring of Fire Aquarium Osaka, Japan 1990 3,400,000 19.50 289,979 26,950 2,906,749 11,000 1,368,550 5,179 39,900
Tennessee Aquarium Chattanooga, TN 1992 886,744* 8.75 $13,914,000* 130,049 12,086 499,432 1,890 137,938 522 8,600 2006 New 600,000 gallon Ocean Tank
Genoa Aquarium Genoa, Italy 1992 1,230,000 14.00 $ 10,000,000 187,000 17,379
Oceanarium Lisbon, Portugal 1998 1,000,000 8.00 214,847 19,967 1,997,729 7,560 1,248,581 4,725 7,750
The Scientific Center Kuwait City, Kuwait 2000
American National Fish & Wildlife Museum
Springfield, MO 2001 251,822* $3,718,000* 92,000 8,550 500,000 1,892 220,000 833 1,000
Monterey Bay Aquarium Monterey, California 1984 1,750,000 11.75 217,280 20,193 799,355 3,025 334,540 1,266 124,000
Lobbecke Aquazoo Museum
Dusseldorf, Germany 1987 560,000 6.75 44,724 4,157 162,514 615 60,778 230 800
Aquarium of the Americas New Orleans, Louisiana 1990 1,500,000 9.50 110,007 10,224 998,865 3,780 399,546 1,512 4,355
Nausicaa Boulogne, France 1991 620,000 10.00 161,459 15,005 369,950 1,400 158,550 600 6,000
L'Aquarium Barcelona, Spain 1995 1,200,000 10.85 146,927 13,655 1,215,550 4,600 977,725 3,700 3,000
Mystic Aquarium Mystic, Connecticut 700,000 141,500 13,146 2,370,000 8,971
New York Aquarium Brooklyn, New York 506,044 160,441 14,905 1,770,000 6,700
The Maritime Aquarium Norwalk, Connecticut 230,500 8701988 22.95 123,678 11,490 110,000 416450,000
16 Mitigation Plan
Analysis
17Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 FLOOR PLAN
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 Level 3 Floor Plan
The team identified twenty specific program areas that were then analyzed. They have been further organized into three subsets of Existing Conditions and Spaces, Walk Bridge Project Impact, and the Future Vision for the facility.
1 9
Level 1
Level 2
Level 3
14 11 12
Temporary
Existing Exhibits and Spaces
| 1. | Sharks |
| 2. | Turtles |
| 3. | Otters |
| 4. | Oyster Hall (Classrooms) |
| 5. | Green Screen - Photos |
| 6. | Jellies |
| 7. | Reptiles / Play Space |
| 8. | Existing Storage Bldgs |
Walk Bridge Project Impact
| 9. | Seals |
| 10. | Newman’s Own Lobby |
| 11. | Go Fish Exhibit |
| 12. | Meerkats |
| 13. | IMAX |
| 14. | 4D Theater/Lobby |
Future Vision
| 15. | Coral Reef |
| 16. | Penguins |
| 17. | Event Space |
| 18. | Quarantine / Volunteer |
| 19. | Research |
| 20. | Future Lobby / Entry |
Circulation
Exhibits
Events
Education
LSS / BOH
Theater
Cafe
Admin
Visitor Services
Program Areas
18 Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 Level 3 Floor Plan
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2 TANK PLAN
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Diver Lockers Sharks1
Level 3
Level 2
Possible Natural Light Available
Level 1
Shark Tank
Fish of the Caribbean
Shark Tank
Existing Conditions
�� The existing shark tank contains approximately 110,000 gallons
�� There is only one view into the tank.
�� The ramp is dark.
�� There is limited seating for functions in the viewing area.
�� There is minimal space for diver prep.
Suggested Improvements
�� Enlarge shark tank to 310,000 gallons.
�� Add some natural light to the exhibit.
�� Increase the number of species in the tank.
�� Create new “family tube” experiences.
�� Make the experience more immersive.
�� Provide “premium” and behind-the-scenes experiences.
�� Improve the quality of the diver support space.
�� Create a way to separate the shark and turtle experiences, in order to create additional rental spaces.
Several of the existing exhibits at TMA are in need of improvement. Several, such as the shark and otter tanks, appear to be too small for the animal collections, while others, such as the turtle tank, lack a realistic habitat. Enlarging and improving the habitats of most of the these exhibits will enhance the visitor experience.
Existing Exhibits and Spaces
19Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Shark Exhibit
Turtle LSS
Turtles2
Turtle Tank
Potential Natural Light
Existing Conditions
�� The existing tank is approximately 5 feet deep with a 25’-6” diameter and contains approximately 19,700 gallons.
�� The tank currently houses 3 turtles.
�� There is no natural light.
�� The pipe-and-panel graphic display is outdated.
�� The circulation is confusing: visitors head here straight from the shark tank, and they miss the jellies exhibit.
Improvements
�� Provide exhibit with more natural light.
�� Goal is to enlarge tank to 100,000 gallons.
�� New tank should be deeper and larger to allow turtles to grow.
�� Create a more immersive environment.
�� Create more underwater views.
�� Update and refresh the surrounding graphics.
�� The intention is to increase the collection to twelve turtles.
�� Create a way to separate the shark and turtle experiences in order to create additional rental spaces.
Potential Natural Light
Jellies
Turtle Exhibit
20 Mitigation Plan
Analysis
Otters3
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2 TANK PLAN
Otter Exhibit
Otter LSS
Otter Tank
Existing Conditions
�� This is a very small exhibit, and it looks cramped.
�� There is no natural light.
�� Visitors have expressed concerns that the otters don’t seem to have enough room.
Improvements
�� This exhibit needs to be enlarged for enrichment purposes.
�� Consider creating an outdoor exhibit space with exposure to natural light.
�� Interest has been expressed in combining a new outdoor exhibit area with the existing indoor area.
�� AZA requires a minimum of 2,369 sf for four (4) River Otters (1,830 sf of land surface plus 539 sf of water surface).
Touch Tank
21Mitigation Plan
Analysis
Oyster Hall Classrooms
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 FLOOR PLAN
Examples of themed classrooms that can be used as exhibit spaces or classroom spaces
Existing Classrooms
Existing Conditions
�� Direct connections to the exterior and to the lobby allow for easy access by school groups.
�� This is a very dark space.
�� The picnic table arrangement is not flexible.
�� The color scheme is depressing.
�� There’s no connection between this classroom and the exhibits.
Improvements
�� Create connections between existing classrooms and the exhibit galleries via graphics, mobile exhibits, permanent aquarium tanks, or programs.
�� Interiors of the classroom spaces need to be refreshed with new color schemes, graphics, and flexible seating.
�� Create a clear connection between the classrooms and their context within the aquarium.
Oyster Hall Classrooms
Ticketing / Entry
Exterior
22 Mitigation Plan
Analysis
Green Screen/ Photos
Existing Conditions
�� The location is in the middle of the visitor trip through the building.
Improvements
�� Create a more consistent location of the green screen/photo process.
�� Integrate the green screen process at the entry point of the circulation path.
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Green Screen Photos
Lobby Newman’s Own
Turtle LSS
Turtle Tank
Turtle Exhibit
23Mitigation Plan
Analysis
Jellies
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Jellies
Turtle Tank
Existing Conditions
�� Visitors often miss this exhibit, because it is off the main circulation path.
�� The backlit graphic elements are faded and dull.
�� This is another dark area.
�� The exhibit is not immersive.
�� The existing Kreisel tank is damaged and needs to be repaired or replaced.
Improvements
�� Expand the size of this exhibit area.
�� Increase the number of species on display.
�� Repair or replace the damaged Kreisel tank.
�� Create a walk-through kreisel tank similar to Seattle Aquarium’s.
�� Add mirrors to make tank appear to continue to infinity (left and right).
�� Expose visitors to the entire growing process of jellyfish, including successes and failures.
�� Create a jellyfish research lab area (possibly convert the existing turtle tank area).
�� Add an octopus exhibit to this area.
to Sharks
Loading Dock
24 Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2
Reptiles & Play Space
Reptiles
Fill in Floor
Fill in Floor
Toddler Play Area
Elev.
Boat Models
Existing Conditions
�� These are two small exhibits, and they could be vastly improved by expanding their size.
Improvements
�� Expand the reptile exhibit.
�� Expand the toddler play space.
�� Fill in the floor above the ray tank to increase the size of the reptile exhibit.
�� Create visual/theme connections between the reptile gallery and the toddler play space.
�� Provde an interactive discovery place for children where they can leard through play and role play.
25Mitigation Plan
Analysis
Existing Storage Buildings
Existing Conditions
�� These storage buildings behind the aquarium wing are in extremely poor condition and should probably be demolished.
�� They block views and natural light from the exhibits.
26 Mitigation Plan
Analysis
Seals
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Seal Tank
Seal
LSS
Newman’s Own Lobby
Ray Touch Tank
Existing Conditions
�� The seal tank needs to be enclosed because of the noises from the impending railroad bridge construction project.
�� The seal tank currently contains approximately 19,000 gallons.
�� Visitors have expressed concern that the seal tank doesn’t appear to be large enough for the animals.
�� The current size restricts the ability to add more seals to the exhibit.
�� Existing sand filters in the LSS area were retrofitted in 2012.
�� The holding tank adjacent to LSS room is used for both seals and turtles.
�� An adjacent haul out area and a operating room are missing.
Improvements
�� Increase depth for animals to dive and more water column to explore.
�� Provide enclosure for entire exhibit and new haul out area.
�� Create new trainer location at the enlarged portion of the tank.
�� Modify recessed seating to create a center aisle and seating with cushions.
�� Provide glass rail at back of seating.
�� Provide food prep area.
�� Provide vet space adjacent to haul out area.
The impending bridge improvement project is going to have a direct impact on TMA.
The seals and meerkats must be shielded from the noise and vibrations of the bridge construction. The Go Fish, Meerkat, and Dragon exhibits will need to be relocated, and because the IMAX theater is on the proposed staging area for the bridgework, its operations will not be feasible.
Walk Bridge Project Impact
27Mitigation Plan
Analysis
Newman’s Own Hall
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Newman’s Own Hall
Chandelier Fish Tank
Future Go Fish
Future Seal Exhibit
Seal Tank
Ray Touch Tank
Existing and Planned Conditions
�� This is a grand space that has the potential to provide a unique “WOW!” experience.
�� Long Island Sound Map will become a digital screen.
�� Concern has been expressed about reflections in the adjacent acrylic viewing windows.
Improvements
�� TMA has expressed interest in creating an overhead visual experience that is made up of schooling fish.
�� Existing structure will need to be analyzed regarding its capacity to support any additional exhibit loads.
�� Add view to a new Stellwagen tank in the future.
28 Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Go Fish
Go Fish Exhibit
Temporary Tent Building
Existing Conditions
�� The current Go Fish exhibits needs to move because of the impending railroad bridge construction.
�� The current tank has a 30-foot diameter and is 5 feet deep.
�� The windows into this tank are relatively small.
Improvements
�� The new tank should have 8’ tall viewing windows
�� The focus of the new tank should be on Stellwagen Banks.
�� The new habitat could have rockwork seen from one viewing window and a shipwreck seen from the other.
�� The new tank would be approximately 42,000 gallons.
�� This will be a diver-supported tank. Animals need to be hand fed because they are too aggressive or they fight over the food too much.
�� As a diver-supported exhibit, the tank will need a step-down platform.
Go Fish Tank
Touch Tank
29Mitigation Plan
Analysis
Meerkats
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 - TANK PLAN
Meerkat/ Dragon Exhibit
Existing Conditions
�� This exhibit has to be moved because of the railroad bridge construction. The animals are sensitive will not tolerate the noise and vibration in the present location.
�� This is a very popular exhibit.
�� Current exhibit is 3-sided and has a pop-up bubble that kids can crawl into.
�� Exhibit is 350 square feet with 16 inches of sand.
Improvements
�� The new exhibit will need to double in size, because current AZA standards require an area of 700 square feet, a minimum of a 2-foot depth of sand, and a concrete bottom.
�� Whether meerkats can tolerate the noise and vibration if moved to Mariner’s Hall is not known.
�� The new design will need to be flexible, in case the meerkats—moved to a new location—still cannot tolerate the noise and vibrations from the bridge construction.
�� This exhibit may temporarily need to be changed to an alligator exhibit.
�� AZA requires a minimum of 854 sf for six (6) meerkats.
Meerkat Habitat
Go Fish Tank
Go Fish Exhibit
30 Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 FLOOR PLAN
IMAX Theater
IMAX
Existing Conditions
�� The IMAX needs to be addressed because of the impending railroad bridge construction project.
�� During construction, the noise level will prohibit any enjoyable experiences here.
�� Aquarium-relevant content for IMAX films is limited.
�� The space is not flexible for lectures or events.
�� Its location is far from the main entry of the Aquarium and requires a duplicate ticketing desk and front door.
�� The IMAX building interferes with the Riverwalk.
Improvements
�� Build a new theater in a more easily accessed location, away from the railroad construction.
Level 1
Corridor to Museum
Railroad Bridge Above
Recessed Tunnel
31Mitigation Plan
Analysis
4D Theater / Lobby
Level 1
Level 2
Existing Conditions
�� The IMAX Theater should be replaced.
Improvements
�� The length of a 4D show would be 12-14 minutes versus 45 minutes of the current IMAX films.
�� 4D theater should be a multi-purpose space that can also be used for presentations.
�� The proposed design has a tall, 2-story wall in the lobby.
�� Theater could have a series of sliding panels that reveal the river and provide natural light and a more eloquent space for lectures.
�� A concession stand can easily turn into a bar for evening functions.
�� The stage area can be created with risers on the flat area of the 4D theater.
�� The 4D theater could be moved further north to make more room for office space.
32 Mitigation Plan
Analysis
Coral Reef 15 16
New Exhibit
�� Expands the LIS storyline to global ecosystems via ocean currents.
�� Coral reef would be a new, immersive, brilliantly colored reef ecosystem.
�� Adjacent graphics can highlight the impact of climate change on fragile ecosystems.
�� Potentially an 80,000-gallon exhibit.
New Exhibit
�� Expands the LIS storyline to global ecosystems via ocean currents.
�� Can be a single or multi-species exhibit.
�� Adjacent graphics can highlight the impact of climate change on fragile ecosystems.
�� An opportunity to add pop-up domes and crawl tubes in the exhibit to make it more immersive.
�� Provide a space for penguin encounters/ premium programs.
�� A possible opportunity for a penguin breeding program.
�� Potentially a 20,000-gallon exhibit
�� For King/Emperor Species: AZA requires a minimum of 27 sf and 1,620 gallons per bird for the first six birds and an additional 14 sf and 156 gallons for each additional bird.
�� For All other Species: AZA requires a minimum of 12 sf and 540 gallons per bird for the first six birds and an additional 6 sf and 45 gallons for each additional bird.
Penguins
TMA’s future vision is to expand the local Long Island Sound storyline with the global story of connectiveness through a new “Currents” gallery. The addition of a new wing housing immersive Penguin, Coral Reef, and Turtle exhibits will significantly extend the visit. The new wing also provides a second level for a crucially important Event Space, which can improve TMA’s bottom line.
Future Vision
33Mitigation Plan
Analysis
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 LEVEL 1 FLOOR PLAN
MASTER PLAN PHASE
25 FEBRUARY 2016
1" = 50'-0"1 MASTER PLAN LEVEL 2
Event Space 17Event Space
300200
Specifications for New Event Space
�� Space to accommodate sit-down dinners for 500 (the Red Apple Event). This translates into 7,500 square feet.
�� Seating for 300 people with tables and chairs needs a minimum of 4,500 sf (code required 15sf/person).
�� Note: Newman’s Own Lobby can accommodate 190 people for a sit-down dinner.
�� A 3rd-floor event space would have an outdoor view that is above the railroad tracks
�� Events and overnights could work concurrently.
�� To be located above the Coral Reef exhibit, possibly with a glass or acrylic floor over the top of the exhibit.
�� This would be a multi-purpose space.
�� Design should present a one-of-a-kind experience that will attract a broader base of clients.
�� Provide a view to the Seal Tank.
Seal Tank
34 Mitigation Plan
Analysis
Quarantine & Volunteers
Specifications for New Space
�� Quarantine space for holding newly acquired fish and mammals is needed.
�� Space for holding animals requiring treatment is also needed.
�� An exam room and surgical area are needed.
�� The animal-related space could be off-site with a loading dock and crane, or it could perhaps be added to the back of the building.
�� Volunteers need an area to store their belongings, rest, and meet.
Research
Future Requirements
�� Provide space for two research scientists who can update visitors on their research.
�� This component should be part of the overall TMA storyline.
�� Provide two rooms for penguin encounters, a premium program.
35Mitigation Plan
Analysis
Future Lobby / Entry
Vision for Future Entry
�� The future entry will be in the center of the building, across the street from the parking garage entrance.
�� It will include a large view into the new “Stellwagen Banks” habitat (pre-ticketing).
�� A water feature will animate the accessible ramp, next to the stairs.
�� An overhead, interactive digital ocean scene can turn the entry into a “Wow!”
experience.
37Mitigation Plan
Design Concepts
38 Mitigation Plan
Design Concepts
Level 1 - Aquarium Wing
Future Entry
4D Theater
Stellwagen
Future Entry �� A new enclosed entry lobby will replace the main ticketing area.
�� New visual and physical connections are made from the lobby to the retail on level 1 and the cafe on level 2.
4D Theater �� A new 4D theater is a multi-purpose space that can also be used for presentations.
�� The concession stand easily turns into a bar for evening functions.
Sharks �� The existing shark tank remains as is
(110,000 gallons).
�� A new 210,000-gallon tank is added to the exhibit.
�� The walls of the new tank will be curved in a way to enforce a figure eight shaped swim pattern.
Stellwagen �� An additional glimpse into the Stellwagen
Tank can be created for visitors in the main lobby.
Jellies & Exotics �� The existing jellies exhibit remains as is and is to be expanded to include a research lab area where the turtle tank currently exists.
�� The jiggle-a-jelly attraction is relocated to this gallery.
Retail
Sharks
Sharks
Exotics
39Mitigation Plan
Design Concepts
Level 1 - Maritime Wing
Currents Gallery �� The visitors are given a choice to enter any of the three exhibits within the Currents Gallery.
�� The LSS and BOH areas in the center of the exhibit gallery allow access to the projector and other AV equipment for the digital system featured in the Event Space above.
Penguin �� The Penguin Exhibit, located along the exterior wall, allows natural light into the habitat as well as offers views of the river to visitors.
�� The new tank contains 8,400 gallons.
Coral Reef �� The Coral Reef Exhibit is a new, immersive
47,600-gallon tank in a dark, light contolled gallery.
Turtles �� The Turtle Exhibit is a dark, light controlled, immersive experience.
�� The new turtle tank is 63,800 gallons.
Turtles
Penguin
Coral
Newman’s Own Hall
Seals
LSS
LSS
Currents Gallery
40 Mitigation Plan
Design Concepts
Level 2 - Aquarium Wing
Sharks
Sharks
Sharks �� The circulation along “The Race” is modified to become a back of house/LSS space. The circulation path is re-routed around the new tank.
Otters �� The Seal Viewing bridge has been lowered to the same level as the Otter area.
�� The habitat has the large dry exhibit area adjacent to the main lobby.
�� The rock work is designed in a way to create a water feature that creates a slide down into the tank.
Salt Marsh �� The Salt Marsh exhibit, screened by a series of fabricated trees, shares the space with the Otter Exhibit.
Stellwagen �� The habitat in the new Stellwagen tank shows rockwork when seen from one viewing window and a shipwreck when seen from the other.
�� As a diver-supported exhibit, the tank has a stepdown platform.
Chandelier Tank �� This tank is an overhead visual experience that is comprised of schooling fish.
Otters
Stellwagen
Chandelier Tank
LSS
Seals
41Mitigation Plan
Design Concepts
Level 2 - Maritime Wing
Events �� Event Space (400 seats shown - tables and chairs only) also has a patio on level 2.
�� A large digital screen system is mounted in the floor. This provides a flexible solution to simulate views into a tank below.
�� The plan allows views from the Event Space to the upper level of the Seal Exhibit.
Seals �� The depth is increased to 16’ at the deepest point and the overall gallons are increased to +/-180,000.
�� A new LSS area at level 1 and a haul out area at level 2 are provided.
�� A new above water viewing is created at level 2.
Meerkats �� The circulation path through the exhibit separates the Meerkats from the Play area.
Reptiles �� The Reptiles exhibit has a dedicated entry.
�� The Reptile and Meerkat areas share LSS and BOH areas.
Play �� The play area is themed to mimic the actions and the physical environment of the adjacent Meerkat exhibit.
Events
Seals
LSS
Deck
Glass Elevator
Play
MeerkatsReptilesNewman’s Own Hall
Otters
42 Mitigation Plan
Design Concepts
Shark Tank & Gallery
�� The existing 110,000-gallon shark tank remains in place.
�� The circulation through the Sound exhibit remains as it exists.
�� The circulation along “The Race” is modified to become a back-of-house/LSS space.
�� The circulation path is re-routed around the new shark tank.
�� An acrylic tunnel through the new shark tank provides long views into the tank.
�� Two smaller viewing areas protrude into the side of the tank.
�� The acrylic viewing window on the north wall of the new tank is curved into the tank.
�� The walls of the tank are curved in a way to enforce a figure-eight shaped swim path.
�� The loading dock below will be moved because of the location of the new tank.
�� The LSS services the tank from above and below.
�� This tank location allows for separate foundations, and it can be built as a separate structure from the existing building.
�� Rockwork will be used to block views of fellow visitors on opposite sides of the tank.
�� The drawings show an additional tank of approximately 210,000 gallons.
Existing Tank + Expansion
Section
Plan
LSS
Curved Acrylic
Window
Shark Tank
Ramp to Level 1
Shark Tank
BOH / LSS BEYOND
LSS
L3 (35.78’)
L2 (23.6’)
L1 (12.12’)
43Mitigation Plan
Design Concepts
BOH / LSS
Otter Exhibit
�� The Otter Exhibit is relocated to the space adjacent to the lobby so that it is the first experience along the visitor’s path on level 2.
�� The habitat has the large dry exhibit area adjacent to the main lobby. The rock work is designed in a way to create a water feature that creates a slide down into the tank.
�� Visitors are exposed to both dry and wet portions of the exhibit.
�� The Atlas buildings are replaced with a new structure to provide space for storage on level 1 and to house the BOH and LSS systems on level 2 behind the otter habitat.
This location is also adjacent to the BOH and LSS spaces for the proposed Seal expansion.
�� The Salt Marsh exhibit shares the space with the Otter Exhibit and it is screened by a series of fabricated trees.
�� The Salt Marsh exhibit contains the relocated existing tanks and a large sectional exhibit of the tides that move in and out of the marshes.
�� The BOH area will be lowered enough to allow some natural light to come into the otter habitat along the top of the rock work.
Interior Circulation
Otter Exhibit
Salt Marsh
Otter Exhibit
Salt Marsh
BOH
Plan
Section
Seal LSS
44 Mitigation Plan
Design Concepts
Jellies Exhibit Jellies
Lab
Exotics
LSS
Jiggle A Jelly Walk-Through Kreisel
Octopus Tank Jelly Tubes
Jellies & Exotics Exhibits Existing Tanks + Expansion
�� The existing jellies exhibit remains as is and is expanded to include a research lab area where the turtle tank currently exists.
�� A large walk-through kreisel tank is added at the main entry.
�� The jiggle-a-jelly attraction is relocated to this gallery.
�� Additional kreisel tanks with varying species are installed throughout the expanded portion of the gallery.
�� Possible Species: Moon Jellies, Black Sea Nettles, Box Jellies, Blubber Jellies, Comb Jellies, Crown Jellies, Lions Mane Jelly.
�� The circulation paths are individual loops into and through each major gallery.
�� A new gallery of exotics is added and the anchor exhibit is the octopus tank.
�� Possible Species in the Exotics Exhibit: Sea Horse, Sea Dragon, Garden Eels, Skeleton Shrimp.
�� The entry at each of the exhibits has its own marquee.
�� The entries at the Jellies and the Exotics control the light to make sure these areas are dark, immersive environments.
45Mitigation Plan
Design Concepts
PlanMeerkats and Play Interior Perspective Reptiles Meerkats
Play
Section
Event Space
LSS
Two Loops Reptiles / Meerkats / Play
ReptilesMeerkats
�� The Reptiles exhibit has a dedicated entry.
�� The circulation path through the exhibit areas is shielded from the circulation path at the elevator.
�� The existing windows have the ability to provide natural light to the interior of the Meerkat exhibit.
�� The Play Gallery is visually and acoustically connected to the Meerkats exhibit (This may cause disruption for the Meerkats).
�� The Play area is themed to mimic the actions and the physical environment of the Meerkats.
�� The Reptile and Meerkat areas share LSS and BOH areas.
46 Mitigation Plan
Design Concepts The Maritime AquariumProposed Seal Tank Expansion
LOBBY
NEW LSS
SEAL
TANK
EXISTING
LSS
NOT TO SCALE
EXISTING
STAIR
N
EXISTING
LSS
16’ DEEP
8’ DEEP
INTERIOR
VIEWS
EXTERIOR
VIEWS
SECTION A
SECTION A
SECTION BSECTION B
The Maritime AquariumProposed Seal Tank Expansion
LOBBY
NEW LSS AND
HAUL OUT
SEAL
TANK
NOT TO SCALE
EXISTING
STAIR
N
16’ DEEP
8’ DEEP
INTERIOR
VIEWS
EXTERIOR
VIEWS
6” DEEP
2’ DEEP
(AVG)
SECTION A
SECTION BSECTION B
SECTION A
Level 2Level 1
�� Provides an enclosure for a two-story exhibit.
�� Increases depth to 16’ at deepest point and gallons to +/-180,000.
�� Provides a new LSS area at level 1 and haul out area at level 2.
�� Creates a new trainer location at the enlarged portion of the tank.
�� Connects the existing second-floor bridge to level 2 in a new addition that passes through the seal tank.
�� Creates an underwater view at level 1 in Newman’s Own Lobby.
�� Creates a second, immersive underwater viewing window at level 1 in new enclosed space.
�� Creates above-water viewing at level 2.
Seal Exhibit Expanded Two-Story Tank
47Mitigation Plan
Design Concepts
The Maritime AquariumProposed Seal Tank Expansion
NOT TO SCALE
N
16’ DEEP
INTERIOR
VIEWS
SECTION A
SECTION B
12’ FLR TO FLR
LSS BEYOND
16’ DEEP
INTERIOR
VIEWS
LSS AND
HAUL OUT
LSS
The Maritime AquariumProposed Seal Tank Expansion
Seal Exhibit Expanded Two-Story Tank
The Maritime AquariumProposed Seal Tank Expansion
NOT TO SCALE
N
16’ DEEP
INTERIOR
VIEWS
SECTION A
SECTION B
12’ FLR TO FLR
LSS BEYOND
16’ DEEP
INTERIOR
VIEWS
LSS AND
HAUL OUT
LSS
SECTION A
SECTION B
48 Mitigation Plan
Design Concepts
Currents Gallery Continuous Loop
�� The visitors are given a choice to enter any of the three exhibitis within the Currents Gallery. Once they enter, the circulation is a loop that will take them through all three exhibits and back to where they started.
�� The Penguin Exhibit is located along the exterior wall to allow in natural light. The orientation allows natural light into the habitat as well as offers views of the river to the visitors.
�� The Turtle Exhibit and the Coral Reef Exhibit are dark, light controlled, immersive experiences.
�� The LSS and BOH areas are in the center of the exhibit gallery. Any service equipment or new animal transfers will need to happen across the visitor path.
�� The centralized LSS space will allow access to the projector and other AV equipment for the digital system featured in the Event Space above.
Turtle Tank
Mech./LSS
M
W
New Elevator Location Option 2 Shown
Penguins
Coral Reef
StorageLSS Turtle Play
Turtle Rehab
Penguin Play
Live Coral
Plan
Section
Events
Penguins
LSS
Views to River
49Mitigation Plan
Design Concepts
Event Space
�� Event Space (400 seats shown - tables and chairs only)
�� A patio is shown at Level 2
�� Large digital screen system is mounted in the floor and provides a flexible solution to simulate views into a tank below.
�� The perspective below shows digital screens in the ceiling showing an underwater coral reef scene and small tanks at the end wall that display small coral exhibits.
�� The exhibit plan below shows the corresponding exhibit layout that allows access to the projector and other AV equipment that will need to be in the LSS space below the Event Space.
�� New Restrooms are show adjacent to the vertical circulation.
Plan
Patio
Kitchen
Views to Seals
Event Space
View Down to Penguins
River View with Patio
L1 - Related Exhibit Plan
Patio Section
Mech.
M
W
New Elevator Location Option 2 Shown
Digital Screen System (Floor Mounted)
50 Mitigation Plan
Design Concepts
Event Space Connection to Seal Exhibit
Views to Seals
Seal Tank
Curtain wall allows views from the Event Space to the upper level of the Seal Exhibit.
Elev: 24.4’ Elev: 26.5’
M
W
Storage
Glass Elevator
New restrooms are added on level 1 (shown) and on level 2 adjacent to the circulation and adjacent to the event space.
Maritime Wing Elevator
51Mitigation Plan
Design Concepts
Stellwagen Exhibit Two-Sided Tank and Chandelier Tank
The Maritime Aquarium Proposed Freshwater Fish Exhibit and Lobby
LOBBY
TICKETING / INFO
MAIN
ENTRY
ENTRYEXIT
TANK
BRIDGE +
HUSBANDRY
ABOVE
GIFT SHOP
& CAFE
SEA TURTLES
SEALS
NEWMAN’S OWN
LOBBY
SUSPENDED
TANK ABOVE
N
RAMP WATER
FEATURE
’-0
’-0
25’-0”75’-0”
SCALE: 1/16” = 1’-0”
�� The new tank has 8’ tall viewing windows
�� The habitat in the new Stellwagen tank will have rockwork seen from one viewing window and a shipwreck seen from the other
�� The new tank is approximately 42,000 gallons.
�� This is a diver-supported tank. Animals need to be hand fed because they are aggressive or they fight over the food too much.
�� The tank will need a step-down platform.
�� TMA has expressed interest in creating an overhead visual experience that is made up of schooling fish.
�� The existing structure needs to be analyzed regarding its capacity to support any additional exhibit loads.
7' -6
- 8
'-0
Chandelier Tank Stellwagen Tank
52 Mitigation Plan
Design Concepts
4D Theater With 175 Seats
The Maritime AquariumProposed Lobby and Theater - Level 1
NN
LOBBY
CON-
TROL
AREA
MAIN ENTRY
EXIT
PRE-SHOW
B A
C K
O F
H O
U S
E
CONCESSIONS
MENS
W O
M E
N S
T
IC
K E
T
IN
G
4D
THEATER
(PRE-FUNCTION)
ENTRY
NEW
PLAZA
(183
SEATS)
ENTRY ICON
SIGNAGE
LOGO
ART
EXIT
SCALE: 1/16” = 1’-0”
EMERGENCY
EXIT
KITCHEN
GLASSES
WASHING
AREA
STORAGE
/ BOH
O
FF
IC
E
O
FF
IC
E
VESTIBULE
OUTDOOR SEATING
The Maritime AquariumProposed Offices at Second Floor
NN
SCALE: 1/16” = 1’-0”
KITCHEN
RECEPTION OFFICE
CONF. OFFICE
OFFICE
M / W
K
IT
C H
E N
Level 1
Level 2
The Maritime AquariumProposed Lobby and Theater
SCALE: 1/16” = 1’-0”
N
LOBBY
4D THEATER
CONCESSIONS
OFFICE
NEW PLAZA
EXISTING MUSEUM
Section
�� The length of a 4D show is 12-14 minutes versus 45 minutes of the current IMAX films.
�� 4D theater is space that can also be used for presentations.
�� The proposed design has a tall – 2-story wall in the lobby.
�� Theater has a series of sliding panels that reveal the river and provide natural light and a more eloquent space for lectures.
�� Concession stand can easily turn into a bar for evening functions.
�� A…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .